risk assessment and disaster management...

22
M/s. OCL India Limited Risk Assessment and Disaster Management Plan Proposed Cement Plant (Dalmia DSP Unit) - Clinker (3.0 MTPA), Cement (2.25 MTPA), WHRS (15 MW) and D.G. Set (1000 KVA) At Village & Tehsil: Rajgangpur, District: Sundergarh (Odisha)

Upload: buinhan

Post on 09-Mar-2018

219 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: Risk Assessment and Disaster Management Planenvironmentclearance.nic.in/writereaddata/online/RiskAssessment/... · the hot raw meal gets jammed in the chute and screw conveyors. During

M/s. OCL India Limited

Risk Assessment and

Disaster

Management Plan

Proposed Cement Plant (Dalmia DSP Unit) - Clinker

(3.0 MTPA), Cement (2.25 MTPA), WHRS (15 MW) and

D.G. Set (1000 KVA)

At

Village & Tehsil: Rajgangpur, District: Sundergarh

(Odisha)

Page 2: Risk Assessment and Disaster Management Planenvironmentclearance.nic.in/writereaddata/online/RiskAssessment/... · the hot raw meal gets jammed in the chute and screw conveyors. During

Proposed Cement Plant (Dalmia DSP Unit) - Clinker (3.0 MTPA), Cement (2.25 MTPA), WHRS (15 MW) and D.G. Set (1000 KVA) At Village & Tehsil: Rajgangpur, District: Sundergarh (Odisha)

RISK ASSESSMENT AND DISASTER MANAGEMENT PLAN

M/s. OCL India Limited 1 JM EnviroNet Pvt. Ltd.

RISK ASSESSMENT AND DISASTER MANAGEMENT PLAN

1.1 RISK ASSESSMENT AND DISASTER MANAGEMENT PLAN

1.1.1 Risk Assessment and Damage Control

Risk assessment is the determination of quantitative or qualitative value of risk related to a

concrete situation and a recognized threat.

Accidental risk involves the occurrence or potential occurrence of some accident consisting of

an event or sequence of events resulting into fire, explosion or toxic hazards to human health

and environment.

Activities requiring assessment of risk due to occurrence of most probable instances of hazard

and incident are both onsite and off-site.

1.1.2 Hazard Identification & Risk Assessment (HIRA) for Integrated Cement Project

The cement manufacturing industry is labor intensive and uses large scale and potentially

hazardous manufacturing processes. The industry experiences incident rates that are high

compared with some other manufacturing industries. Cement industries experiences risk of a

number of hazards inherent to the cement production process. Following hazards may occur:

� Exposure to High temperatures;

� Physical Hazards;

� Events pertaining to Manufacturing Process;

� Fire;

� Explosion;

� Electrocution;

� Natural & Manmade hazards

� Noise and Vibration

These mainly impact on those working within the industry, although health hazards can also

impact on local communities. The potential hazardous areas and the likely incidents with the

concerned area have been enlisted below in Table - 7.1.

Page 3: Risk Assessment and Disaster Management Planenvironmentclearance.nic.in/writereaddata/online/RiskAssessment/... · the hot raw meal gets jammed in the chute and screw conveyors. During

Proposed Cement Plant (Dalmia DSP Unit) - Clinker (3.0 MTPA), Cement (2.25 MTPA), WHRS (15 MW) and D.G. Set (1000 KVA) At Village & Tehsil: Rajgangpur, District: Sundergarh (Odisha)

RISK ASSESSMENT AND DISASTER MANAGEMENT PLAN

M/s. OCL India Limited 2 JM EnviroNet Pvt. Ltd.

Table - 7.1

Possible Hazardous Locations on site

S. No. Hazardous Area Likely Incident

1. Kiln Area Hot Zones

2. Electrical rooms Fire and electrocution

3. Transformer area Fire and electrocution

4. Cable tunnel Fire and electrocution

5. Storage yard Sliding and fire

6. Crushing and grinding unit Nip Hazard, Noise

7. Chimney Height

8 Coal / fuel storage area Fire and spillage

1.1.2.1 Exposure to High Temperature

The principal exposures to heat in this sector occur during handling of hot raw meal (Powdered

limestone, laterite additives etc. heated in a pre-heater cyclone), hot clinker and operation &

maintenance of kilns or other hot equipment. Recommended prevention and control

techniques include the following:

� Shielding surfaces where workers proximity and close contact with hot equipment is

expected,

� Using personal protective equipment (PPE), as needed (e.g. insulated gloves and shoes);

� Minimizing the work time required in high temperature environments by implementing

shorter shifts at these locations.

1.1.2.2 Physical Hazards

Injuries during Project operation are typically related to slips, trips, and falls; contact with

falling / moving objects; and lifting / over-exertion. Other injuries may occur due to contact

with, or capture in, moving machinery (e.g. dump trucks, front loaders, forklifts). Activities

related to maintenance of equipment, including crushers, mills, mill separators, fans, coolers,

and belt conveyors, represent a significant source of exposure to physical hazards. Such

hazards may include the following:

� Falling / impact with objects

� Hot surface burns

� Transportation

� Contact with allergic substances.

Following measures will be adopted to prevent the physical hazards in the plant-

Page 4: Risk Assessment and Disaster Management Planenvironmentclearance.nic.in/writereaddata/online/RiskAssessment/... · the hot raw meal gets jammed in the chute and screw conveyors. During

Proposed Cement Plant (Dalmia DSP Unit) - Clinker (3.0 MTPA), Cement (2.25 MTPA), WHRS (15 MW) and D.G. Set (1000 KVA) At Village & Tehsil: Rajgangpur, District: Sundergarh (Odisha)

RISK ASSESSMENT AND DISASTER MANAGEMENT PLAN

M/s. OCL India Limited 3 JM EnviroNet Pvt. Ltd.

• Any person working on equipment with moving parts personally ensures the equipment is

de-energized, isolated and locked/tagged out.

• Any person working from a position with the potential risk for a fall from height uses fall

protection.

• Any person doing flame welding, cutting or brazing in the proximity of any flammable

material wears PPE.

• Safety helmets are used to protect workers below against falling material.

• Barriers like a toe boards or mesh guards are provided to prevent items from slipping or

being knocked off the edge of a structure.

• An exclusion zone will be created beneath areas where work will take place.

• Danger areas are clearly marked with suitable safety signs indicating that access will be

restricted to essential personnel wearing hard hats while the work is in progress.

• In case of any accident immediate and proper medical care will be provided at the plant

site.

1.1.2.3 Events pertaining to the manufacturing process

The following areas are identified as hazard prone in case of Integrated Cement Plant where

Disaster management plan is required.

(i) Handling of Coal

1. The coal will be received and stored in Stockpile. The possible hazards are envisaged due

to the slipping of wagon during unloading.

2. Stockpile will be made in a way so that the wind strikes the width of the stockpile and not

the length.

3. Freshly mined coal will not be piled over the old coal and the old coal will be used first.

4. Stacking- layer by layer (each of 1 to 1.5 m height) with compaction of each layer will be

done.

5. Stacking in small heaps will be done and compacted in trapezoidal shape.

6. Each stockpile should be segregated into various segments for first- in-first-out practice.

7. During summer season, there is chance of coal catching fire due to spontaneous heating.

8. Effective sprinkling systems should be provided all round the coal storage yards.

Page 5: Risk Assessment and Disaster Management Planenvironmentclearance.nic.in/writereaddata/online/RiskAssessment/... · the hot raw meal gets jammed in the chute and screw conveyors. During

Proposed Cement Plant (Dalmia DSP Unit) - Clinker (3.0 MTPA), Cement (2.25 MTPA), WHRS (15 MW) and D.G. Set (1000 KVA) At Village & Tehsil: Rajgangpur, District: Sundergarh (Odisha)

RISK ASSESSMENT AND DISASTER MANAGEMENT PLAN

M/s. OCL India Limited 4 JM EnviroNet Pvt. Ltd.

(ii) Handling of fine dust

The hot raw meal (Powdered limestone, powered coal, laterite additives etc. will be heated in

a multi - stage pre-heater cyclone) will be stored in the raw meal silos. It is very common that

the hot raw meal gets jammed in the chute and screw conveyors. During the maintenance

process, the operator generally works in the pre-heater cyclone and other areas. Though, the

operation of the pyro is in close circuit, there is a less possibility of the risk associated with the

exposure to hot material. The relevant PPEs are being provided during cleaning to the workers

with sufficient care during the maintenance operations.

(iii) Handling of Hot Clinker

The hot clinker will be transported by deep pan conveyors to the top of the silo or closed stock

pile for storage. During this operation, there is a possibility of spill out of hot clinker. Proper

care for the conveyor system and the bund wall for the clinker stock pile shall be the part of

design criteria.

(iv) Handling of Cement

Cement is the fine dust which is being conveyed in a closed circuit (mechanical and/or

pneumatic or combination of both) to avoid any health and environment risk.

1.1.2.4 Fire

Fire can be observed in the boiler area, Coal storage yard, Fuel spillage, Electrical rooms,

Transformer area etc. due to incidental failure scenario. Fire detection, alarm and control

system helps for early detection as well as control measures.

Table - 7.2

Anticipated Hazard Scenarios

S. No. Area/ Activity Hazard Impact

1. HSD Fire may occur due to leakage in the tank which may lead to pool fire in contact with an ignition source.

Fire may propagate towards nearby sheds and buildings

2. LDO Storage Fire may occur due to leakage in the tank which may lead to pool fire in the contact with an ignition source.

Fire may propagate towards nearby sheds and buildings.

3. Furnace Oil Bulk Storage capacity

Fire may occur due to leakage in the tank which may lead to pool fire in contact with an ignition source.

Fire may propagate to nearby sheds.

4. Transformer Oil stored in Conservator

Fire may occur due to leakage in tank or blowing of rupture disk which may

Fire may propagate towards nearby sheds and buildings.

Page 6: Risk Assessment and Disaster Management Planenvironmentclearance.nic.in/writereaddata/online/RiskAssessment/... · the hot raw meal gets jammed in the chute and screw conveyors. During

Proposed Cement Plant (Dalmia DSP Unit) - Clinker (3.0 MTPA), Cement (2.25 MTPA), WHRS (15 MW) and D.G. Set (1000 KVA) At Village & Tehsil: Rajgangpur, District: Sundergarh (Odisha)

RISK ASSESSMENT AND DISASTER MANAGEMENT PLAN

M/s. OCL India Limited 5 JM EnviroNet Pvt. Ltd.

S. No. Area/ Activity Hazard Impact

lead to pool fire in contact with an ignition source

5. Storage of Coal in Coal Storage Yards

Fire may occur due to spontaneous ignition of coal.

Fires will propagate within the coal storage yard.

6. Storage and handling of ground coal

Dust explosion may occur during storage and handling of ground coal

Fire may occur in the ground coal storage and handling system affecting other areas as well.

1.1.2.5 Explosion

Explosion may lead to release of heat energy & Pressure waves. Table - 7.3 shows tentative list

of damages envisaged due to different heat loads.

Table - 7.3

List of Damages Envisaged at Various Heat Loads

S. No. Heat loads (kW/m²)

Type of Damage Intensity

Damage to Equipment Damage to People

1 37.5 Damage to process equipment 100% lethality in 1 min. 1% lethality in 10 sec

2 25.0 Minimum energy required to ignite wood 50% Lethality in 1 min. Significant injury in 10 sec

3 19.0 Maximum thermal radiation intensity allowed on thermally unprotected equipment

--

4 12.5 Minimum energy required to melt plastic tubing

1% lethality in 1 min

5 4.0 -- First degree burns, causes pain for exposure longer than 10 sec

6 1.6 -- Causes no discomfort on long exposures

Source: World Bank (1988). Technical Report No. 55: Techniques for Assessing Industrial Hazard., Washington, D.C: The

World Bank.

1.1.2.6 Electrocution

Fatal Incident due to carelessness during working hours may lead to electrocution.

1.1.2.7 Management measures to prevent the physical hazards in the plant

� Any person working on equipment with moving parts will personally ensure the

equipment is de-energized, isolated and locked/tagged out.

� Any person working from a position with the potential risk for a fall from height will use

fall protection.

Page 7: Risk Assessment and Disaster Management Planenvironmentclearance.nic.in/writereaddata/online/RiskAssessment/... · the hot raw meal gets jammed in the chute and screw conveyors. During

Proposed Cement Plant (Dalmia DSP Unit) - Clinker (3.0 MTPA), Cement (2.25 MTPA), WHRS (15 MW) and D.G. Set (1000 KVA) At Village & Tehsil: Rajgangpur, District: Sundergarh (Odisha)

RISK ASSESSMENT AND DISASTER MANAGEMENT PLAN

M/s. OCL India Limited 6 JM EnviroNet Pvt. Ltd.

� Any person doing flame welding, cutting or brazing in the proximity of any flammable

material will obtain PPE.

� Safety helmets to be used to protect workers below against falling material.

� Barriers like a toe boards or mesh guards is to be provided to prevent items from slipping

or being knocked off the edge of a structure.

� An exclusion zone is to be created beneath areas where work is taking place.

� Danger areas are to be clearly marked with suitable safety signs indicating that access is

restricted to essential personnel wearing hard hats while the work is in progress.

� In case of any incident immediate & proper medical care shall be provided at the plant

site.

1.1.2.8 Natural and Manmade Calamities which can lead to Emergency

(a) Earthquake

Earthquake cannot usually be forecasted and therefore precautions immediately prior to such

event are not usually possible. Apart from some of the counter-measures will be taken in

foreseeable cases, emergency recovery plan has been considered by the emergency

management team as per the situation and site conditions as follows:

Step Activity Action By

Preparedness • Identify and constitute Emergency Response

Team

• Identify ECC, if the identified ones are damaged

• Control centers to be equipped with

� Communication facilities

� Emergency vehicles/ equipment

� List of emergency contacts and suppliers

� Medical facilities

Plant Key Person

Action during

effective period

• Do not panic. Raise alarm

• Avoid standing near to windows, external walls

• Stand near the columns or duck under sturdy

furniture.

• Assemble at emergency assembly point as there

may be aftershocks

Individual (s)

Action after effective

Period (Establish

Emergency Control

Center. Site Main

• Take head count

• Activate emergency plan as situation demands

• Assess situation and initiate shut down of plants

(if required)

Site Incident Controller Site Main Controller Coordinators – Fire and Security, Safety,

Page 8: Risk Assessment and Disaster Management Planenvironmentclearance.nic.in/writereaddata/online/RiskAssessment/... · the hot raw meal gets jammed in the chute and screw conveyors. During

Proposed Cement Plant (Dalmia DSP Unit) - Clinker (3.0 MTPA), Cement (2.25 MTPA), WHRS (15 MW) and D.G. Set (1000 KVA) At Village & Tehsil: Rajgangpur, District: Sundergarh (Odisha)

RISK ASSESSMENT AND DISASTER MANAGEMENT PLAN

M/s. OCL India Limited 7 JM EnviroNet Pvt. Ltd.

Controller to direct

all activities)

• Initiate search and rescue (if required)

• Provide first aid to victims. Remove casualties

• Key persons to report to site

• Assess damage

• Undertake

Material, Medical, and Plant Key Person

(b) Storm

The contingency actions during storm will be based on the weather forecasts obtained from

meteorological stations and the local meteorological department. Some of the important

actions that will be carried out are as follows:

Prior to Storm

� Establish regular contact with the local meteorological department.

� Establish distances from storm in order to execute preparatory actions in a shorter time.

� Appraise the factory operations / installations and consider the consequences that the

emergency might have on operations and personnel.

� Check the availability of tools, batteries, non-perishable foods and other materials that

might be required.

� Review all operations carefully to ensure that systems in jeopardy are taken care of or

shut down.

� Ensure the readiness of first aiders, emergency vehicles, medical centre, medicines etc.

� Metallic sheets, loose materials, empty drums and other light objects will be properly

secured.

� Flush the drainage systems.

During Storm

� Remain calm.

� Do not go outdoors.

� Do not seal the office completely as the suction created by the difference in atmospheric

pressure inside and outside can rip open a window or door by breaking window glass

panes.

After the Storm

� Do not touch electric lines.

� Stay away from the disaster area.

� Take special precautions in driving vehicles since the under-pavement could cave in due to

the weight of automobile.

Page 9: Risk Assessment and Disaster Management Planenvironmentclearance.nic.in/writereaddata/online/RiskAssessment/... · the hot raw meal gets jammed in the chute and screw conveyors. During

Proposed Cement Plant (Dalmia DSP Unit) - Clinker (3.0 MTPA), Cement (2.25 MTPA), WHRS (15 MW) and D.G. Set (1000 KVA) At Village & Tehsil: Rajgangpur, District: Sundergarh (Odisha)

RISK ASSESSMENT AND DISASTER MANAGEMENT PLAN

M/s. OCL India Limited 8 JM EnviroNet Pvt. Ltd.

(c) Air Raid

Air raid warning would be obtained from the District Emergency Authority or Defense

Authorities, during which total blackout of the entire complex will be considered. Some of the

contingency actions that will be considered during an air raid are as follows:

� The Aviation Lights installed on highest point inside the factory will be switched off.

� All the lighting on the Streets will be put off.

� All the plant lighting will be put off.

� Brown curtains will be provided for all windows inside the building.

� Other emergency actions will be followed in addition as per the general procedure.

(d) High Risk Categories and Preventive Measures

High Risk Categories and Preventive Measures are given in Table - 7.4.

Table - 7.4

High Risk Categories and Preventive Measures

High Risk Categories Prevention

Contractors Contractor Safety Management

Young/Temporary Employees Special Safety Induction Training

Direct Causes

Traffic & Mobile Plant Driver Training

Falls from Heights, Objects falling from Heights Safety Procedures for Work at Heights,

Overhead Protection, In-house training

Caught in Starting/Moving Equipment Plant Isolation Procedures, Machine Guarding

1.1.2.10 Measures for occupational Health Hazards

� Dust Exposure level of shop floor workers is to be appropriately monitored.

� Check of the effectiveness of preventive and control measures on regular basis.

� Adequate supplies of potable drinking water is to be provided. Water supplied to areas

of Plant food preparation or for the purpose of personal hygiene (washing or bathing)

are too according to drinking water quality standards

� Where there is potential for exposure to harmful dusts by ingestion arrangements are to

be made for clean eating areas, where workers are not exposed to the hazardous or

noxious substances

Page 10: Risk Assessment and Disaster Management Planenvironmentclearance.nic.in/writereaddata/online/RiskAssessment/... · the hot raw meal gets jammed in the chute and screw conveyors. During

Proposed Cement Plant (Dalmia DSP Unit) - Clinker (3.0 MTPA), Cement (2.25 MTPA), WHRS (15 MW) and D.G. Set (1000 KVA) At Village & Tehsil: Rajgangpur, District: Sundergarh (Odisha)

RISK ASSESSMENT AND DISASTER MANAGEMENT PLAN

M/s. OCL India Limited 9 JM EnviroNet Pvt. Ltd.

� Periodic medical hearing checks are to be performed on workers exposed to high noise

levels

� Provisions are to be made to provide OHS orientation training to all new employees to

ensure they are apprised of the basic site rules of work at / on the site and of personal

protection and preventing injury to fellow employees

� Contractors that have the technical capability to manage the occupational health and

safety issues of their employees are to be hired, extending the application of the hazard

management activities through formal procurement agreements

� Ambulances and First aid treatment facilities are made available for any emergency

situation.

1.2.1 Disaster Management Plan

1.2.1.1 Definition

A major emergency in a work is one, which has the potential to cause serious injury or loss of

life. It may cause extensive damage to property and serious disruption both inside and outside

the work. It would normally require the assistance of emergency services to handle it

effectively.

1.2.1.2 Scope

The aim of hazard control and disaster management is concerned with preventing incidents

through good design, operation, maintenance and inspection, by which it is possible to reduce

the risk of an incident, but it is not possible to eliminate it. Since, absolute safety is not

achievable; an essential part of major hazard control must also include mitigating the effects

of a major incident.

An important element of mitigation is emergency planning, i.e. recognizing incidents as soon

as possible, assessing the consequences of such incidents and deciding on the emergency

procedures, both on-site and off-site, that would need to be implemented in the event of an

emergency.

1.2.1.3 Objective

The overall objectives of the emergency plan will be:

a) To localize the emergency and, if possible eliminate it; and

b) To minimize the effects of the incident on people and property.

c) Restore normalcy at minimum possible time

Page 11: Risk Assessment and Disaster Management Planenvironmentclearance.nic.in/writereaddata/online/RiskAssessment/... · the hot raw meal gets jammed in the chute and screw conveyors. During

Proposed Cement Plant (Dalmia DSP Unit) - Clinker (3.0 MTPA), Cement (2.25 MTPA), WHRS (15 MW) and D.G. Set (1000 KVA) At Village & Tehsil: Rajgangpur, District: Sundergarh (Odisha)

RISK ASSESSMENT AND DISASTER MANAGEMENT PLAN

M/s. OCL India Limited 10 JM EnviroNet Pvt. Ltd.

Elimination will require prompt action by operations and works emergency staff using, for

example, fire-fighting equipment, water sprays etc. Minimizing the effects may include rescue,

first aid, evacuation, rehabilitation and giving information promptly to people living nearby.

To deal with the above emergencies, the Emergency Plan is prepared.

1.2.1.4 Disaster control Management system

Disaster Management group plays an important role in combating emergency in a systematic

manner. In addition; the implementation of an Emergency Response Plan relies on a number

of response functions, which deal with different aspects of emergency, with the most

important ones being:

� Communication and Co-ordination

� Fire and Rescue (Emergency Mitigation) Emergency Control Team at Incident Site

� Medical Services

� Security

� Administration (Logistics and Welfare)

� Co-ordination with external agencies.

1.2.1.4.2 Emergency Control Centre (ECC)

An Emergency Control Centre (ECC) will be established from which emergency operations are

directed and co-ordinated. Centre will be activated as soon as on-site emergency is declared.

The ECC will consist of one room, located in an area that offers minimal risk being directly

exposed to possible incidents. During an emergency, the Emergency Management Staff,

including the main controller will gather in the ECC. Therefore, the ECC will be equipped with

adequate communication systems in the form of telephones and other equipment’s to allow

unhampered organization and other nearby facility personnel. Action Plan for On- Site

Emergency Plan are as:

Page 12: Risk Assessment and Disaster Management Planenvironmentclearance.nic.in/writereaddata/online/RiskAssessment/... · the hot raw meal gets jammed in the chute and screw conveyors. During

Proposed Cement Plant (Dalmia DSP Unit) - Clinker (3.0 MTPA), Cement (2.25 MTPA), WHRS (15 MW) and D.G. Set (1000 KVA) At Village & Tehsil: Rajgangpur, District: Sundergarh (Odisha)

RISK ASSESSMENT AND DISASTER MANAGEMENT PLAN

M/s. OCL India Limited 11 JM EnviroNet Pvt. Ltd.

Table 7.5: Emergency command Structure

S. No. Initiator Action to be taken

1. Combat

team leader

• Inform Site Incident Controller (SIC) through common dialling system and rush to

spot for combating the situation. Take charge of the situation, arrange for

evacuation of people not directly concerned.

• To organise for trained personnel equipped with firefighting appliances and call

for tender at the place of fire.

• To start combating, shutdown equipments and take steps to extinguish fire with

fire fighting facilities

• To find out the root cause of fire and to take necessary actions for prevention of

fire.

2. Site Incident

Controller

• Inform Works Main Controller (WMC) and rush to site. In case of failure of

electronic communication system, the standby available provision for runner with

bike will be there to pass on the command as advised.

• Discuss with combat team leader, assess the situation and call the rescue team

leader and Auxiliary Team Leader.

• Inform to the Rescue Team Leader, Auxiliary Team Leader to send the rescue

team to the site.

• Arrange to evacuate the unwanted persons and call for additional help.

• Feeding the information to Works main Controller about situation at site.

3. Works Main

Controller

• Rush to Emergency Site and observe the ongoing Activities.

• Take stock of the situation in consultation with SIC.

• Move to Emergency Control Room

• Take decision on declaration of emergency and ask for emergency wailing siren.

• Advise Auxiliary Team Leader to inform the statutory authorities and seek help

of mutual aid if required.

• Decide on normalcy of emergency after combating the situation.

• Ensure that the emergency operations are recorded chronologically.

Page 13: Risk Assessment and Disaster Management Planenvironmentclearance.nic.in/writereaddata/online/RiskAssessment/... · the hot raw meal gets jammed in the chute and screw conveyors. During

Proposed Cement Plant (Dalmia DSP Unit) - Clinker (3.0 MTPA), Cement (2.25 MTPA), WHRS (15 MW) and D.G. Set (1000 KVA) At Village & Tehsil: Rajgangpur, District: Sundergarh (Odisha)

RISK ASSESSMENT AND DISASTER MANAGEMENT PLAN

M/s. OCL India Limited 12 JM EnviroNet Pvt. Ltd.

S. No. Initiator Action to be taken

4. Rescue

Team

Leader

• Consult with Site Incident Controller (SIC) and rush to emergency site through

safe route along with team members and start the rescuing work.

• Shift the injured persons to hospital by ambulance after providing necessary first

aid.

• To inform the Auxiliary Team Leader for necessary help from Mutual Aid

Partners.

5. Auxiliary

Team

Leader

• On being directed by the Works Main Controller (WMC) inform about the

emergency to statutory authorities depending upon the situation.

• Seek help of the Mutual Aid partners to render their service if required.

• To take role call to find out the missing persons if any.

• Arrange to inform the relatives of casualties.

• Take care of visit of the authorities to the Emergency Site.

6. Team

Members

• Each of the team members should follow the instruction of concerned team

leader to mitigate the emergency.

The ECC will provide shelter to its occupants against the most common incidents; in addition,

the ECC’s communication systems will be protected from possible shutdown. The ECC will have

its own emergency lighting arrangement and electric communication systems operation. The

ECC will always be ready for operation and provided with the equipment and supplies necessary

during the emergency such as:

� Hazard identification chart, All Emergency response plans; Emergency Command Structure

as given below in Figure 7.1.

� Internal telephone connections and External telephone connections

� A list of key personnel, with addresses, telephone numbers, etc.

� Hotline connection to district collector, police control room, fire brigade, Hospital etc.

� Public address system (PAS)

� MSDS of all the materials used in Plant site

� List of dispensaries and registered medical practitioners around factory

� Area map of surrounding villages

� Note pads and ball pens to record message received and instructions

� The blown-up copy of Layout plan showing areas where incident has occurred

Page 14: Risk Assessment and Disaster Management Planenvironmentclearance.nic.in/writereaddata/online/RiskAssessment/... · the hot raw meal gets jammed in the chute and screw conveyors. During

Proposed Cement Plant (Dalmia DSP Unit) - Clinker (3.0 MTPA), Cement (2.25 MTPA), WHRS (15 MW) and D.G. Set (1000 KVA) At Village & Tehsil: Rajgangpur, District: Sundergarh (Odisha)

RISK ASSESSMENT AND DISASTER MANAGEMENT PLAN

M/s. OCL India Limited 13 JM EnviroNet Pvt. Ltd.

� Undated copies of the On-site Disaster Management Plan

� Emergency telephone numbers

� The names, phone number, and address of external agencies, response organizations and

neighbouring facilities

� The adequate number of telephone

� Emergency lights

� List of fire extinguishers with their type no. and location, capacity, etc

� Personal protective equipment(PPE)

� Safety helmets

� Clock

� Material safety data sheets for chemicals handled at the facility

� Several maps of the facility including drainage system for surrounding area showing:

� Areas where hazardous materials are stored

� Plant layout

� Plot plans of storage tanks, routes of pipelines, all water permanent lines etc.

� The locations where personal protective equipments are stored.

� The position of pumping stations and other water sources.

� Roads and plant entrances

� Assembly areas

� Lay out of Hydrant lines.

Figure 7.1: Emergency Command Structure

Works Main Controller (Organizational Head / Director)

Site Incident Controller (SIC) (Process Head/ Engg. Head)

Coordinator (SAFETY)

Combat Team Leader (CTL)

Auxiliary Team Leader (ATL)

Rescue Team Leader (RTL)

Members Members Members

Page 15: Risk Assessment and Disaster Management Planenvironmentclearance.nic.in/writereaddata/online/RiskAssessment/... · the hot raw meal gets jammed in the chute and screw conveyors. During

Proposed Cement Plant (Dalmia DSP Unit) - Clinker (3.0 MTPA), Cement (2.25 MTPA), WHRS (15 MW) and D.G. Set (1000 KVA) At Village & Tehsil: Rajgangpur, District: Sundergarh (Odisha)

RISK ASSESSMENT AND DISASTER MANAGEMENT PLAN

M/s. OCL India Limited 14 JM EnviroNet Pvt. Ltd.

1.2.1.4.3 Emergency Communication

The views of the possible hazards that can arise out of the daily operations in the plant various

measures will be adopted to prevent the occurrence of a major incident. This comprises of:

a) Built in safety measures, alarms, trips and interlocks etc.

b) Standard safe operating and maintenance procedures permit system etc.

c) Training of all the involved staff in normal and emergency operating procedures.

d) Training of all employees in safety, firefighting and first aid.

However, in spite of these precautions, it is required to foresee situation of major incident and

plan for taking timely action to minimize the effects of such incident on the safety and health

of persons working in the plant as well as those situated around the premises. Hence the

present plant will be drawn up to serve as the manual of handling major emergencies.

Internal telephone systems are provided at work places. Shift In charge at site and other In

charge also given on call handset (Walkie-Talkie) for immediate communication to all

concerned. Emergency Command Structure to be followed during emergency is as given below

in Figure 7.1.

In case of devastating fire / major incident or hazard, immediate information will be given as

per need to following through telephone operators who will be available round the clock over

phone.

1.2.1.4.4 Onsite emergency planning for cement plant

Following onsite measures will be taken to avoid/ minimize the risk of incidents & other hazards

in cement plant and power plant:

(i) Alarm and Communication Systems

Communication is crucial factor in handling an emergency. It is the practice at many plants that

any employee can raise an emergency alarm, so allowing the earliest possible action to be

taken to control the situation.

Alarm systems vary and will depend on the size of the plant. There should be an adequate

number of points from an audible warning, or indirectly, viz. a signal or message to a

permanently manned location. The alarm should alert the people to implement appropriate

emergency procedures. In areas where a high level of noise; it may be necessary to install more

than one audible alarm transmitter or flashing lights. Automatic alarms may be appropriate on

some sites.

Page 16: Risk Assessment and Disaster Management Planenvironmentclearance.nic.in/writereaddata/online/RiskAssessment/... · the hot raw meal gets jammed in the chute and screw conveyors. During

Proposed Cement Plant (Dalmia DSP Unit) - Clinker (3.0 MTPA), Cement (2.25 MTPA), WHRS (15 MW) and D.G. Set (1000 KVA) At Village & Tehsil: Rajgangpur, District: Sundergarh (Odisha)

RISK ASSESSMENT AND DISASTER MANAGEMENT PLAN

M/s. OCL India Limited 15 JM EnviroNet Pvt. Ltd.

There should be a reliable system for informing the emergency services as soon as the alarm is

raised on site. The details of the communication arrangements should be agreed locally; in

some cases it may be advisable to have a direct line to the fire bridge. Predetermined code

works to indicate the scale and type of the emergency may be valuable.

(ii) Fire-fighting System

In view of vulnerability to fire, effective measures will be taken to minimize fire hazard. Fire

protection is envisaged through hydrant and sprinkler system, designed as per the

recommendation of Tariff Advisory Committee of Insurance Association of India. The following

areas in the power station are mainly susceptible to fire:

� Cable galleries

� Electrical switchgear/ MCC room

� Coal handling areas: Conveyors, transfer points, tunnels and storage yard.

� Transformers and turbine oil tank

For containment of fire and preventing it from spreading in cable galleries, section wise fire

barriers with self - closing fire resistant doors will be provided. The ventilation systems, if any,

provided in cable galleries will be interlocked with the fire alarm system, so that in event of a

fire, the ventilation system will be automatically switched off. In order to avoid spreading of

fire all cable entries opening in cable galleries, tunnels, channels, floors, barriers etc will be

sealed with non-inflammable/Fire resistant sealing materials.

For detection and protection of the plant against fire hazard, any one or a combination of the

following systems will protect susceptible areas:

� Hydrant system

� Automatic high velocity spray system

� Medium velocity spray system

� Portable fire extinguishers

� Fire alarm systems

Fire hydrant points will be provided throughout the premises. Automatic high velocity spray

system will be provided for protection of transformers and cable galleries. Manual medium

velocity spray system will be provided for protection of fuel oil and turbine oil storage tanks

and coal conveyor galleries.

Water for hydrant, spray and sprinkler system will be supplied from the firewater pumps

located in firewater pump house adjacent to Raw Water Reservoir. Adequate number of

portable and mobile chemical fire extinguishers will be provided at strategic locations

Page 17: Risk Assessment and Disaster Management Planenvironmentclearance.nic.in/writereaddata/online/RiskAssessment/... · the hot raw meal gets jammed in the chute and screw conveyors. During

Proposed Cement Plant (Dalmia DSP Unit) - Clinker (3.0 MTPA), Cement (2.25 MTPA), WHRS (15 MW) and D.G. Set (1000 KVA) At Village & Tehsil: Rajgangpur, District: Sundergarh (Odisha)

RISK ASSESSMENT AND DISASTER MANAGEMENT PLAN

M/s. OCL India Limited 16 JM EnviroNet Pvt. Ltd.

throughout the plant. Fire detection and alarm system will be provided at strategic locations

throughout the plant. Fire detection and alarm system will be provided to detect fire/ smoke

in vulnerable areas of the plant through smoke / heat detectors. Table - 7.6 & Table - 7.7 enlist

case & Site-specific Fire extinguishers respectively.

Table - 7.6

List of Extinguisher to be used as case specific

S. No. Chemical Name Type of Extinguisher

1 Pet Coke Use: Water fog, CO2, Foam, Dry Chemical

2 Fuel Oil Use: Water spray, foam, dry powder or carbon dioxide

Do Not Use: water jet as an extinguisher, as this will spread the

fire

3 HSD Use: Foam, Carbon dioxide, Dry Chemical Powder. Water may be

used to cool fire-exposed containers

4 LDO Use: water fog, foam, dry chemical or carbon dioxide (CO2) to

extinguish flames

5 Fly Ash Non-Flammable

6 Gypsum Non-Flammable

7 Laterite Non-Flammable

8 Metal dust Certified class D Extinguishing agent

TABLE - 7.7

List of Extinguisher to be used as Site specific

S. No. Name of site Type of Extinguisher

1 Cable galleries CO2 & Foam type, Dry chemical powder

2 High voltage panel CO2 & Foam type, Dry chemical powder

3 Control rooms CO2 & Foam type, Dry chemical powder

4 MCC rooms CO2 & Foam type, Dry chemical powder

5 Pump Houses CO2 & Foam type, Dry chemical powder

6 Guest houses and offices Dry chemical powder, foam type

7 Godowns Foam type

8 Bunkers, Silo, enclosed dust collector

CO2 type, N2 type, automatic sprinkler, fixed spray nozzle (unless water reactive)

Page 18: Risk Assessment and Disaster Management Planenvironmentclearance.nic.in/writereaddata/online/RiskAssessment/... · the hot raw meal gets jammed in the chute and screw conveyors. During

Proposed Cement Plant (Dalmia DSP Unit) - Clinker (3.0 MTPA), Cement (2.25 MTPA), WHRS (15 MW) and D.G. Set (1000 KVA) At Village & Tehsil: Rajgangpur, District: Sundergarh (Odisha)

RISK ASSESSMENT AND DISASTER MANAGEMENT PLAN

M/s. OCL India Limited 17 JM EnviroNet Pvt. Ltd.

(iii) Evacuation Procedure

As the major hazard is only due to fire, which has more or less localized impact no mass

evacuation, procedures are required. Evacuation would involve only the people working very

close to the fire area.

(iv) First Aid

A first aid center with adequate facilities shall be provided. It shall be maintained round the

clock by a compounder cum dresser and a doctor. An auxiliary first aid squad shall be identified,

the members of which shall be spread in each shift in different departments. In the event of an

emergency this squad will augment medical services. An Ambulance which is available with

plant shall also be used at site to carry affected people to hospital. Assistance of these

hospitals will be taken in case of any necessity.

(v) Safety

The safety wing led by Plant Safety Head will meet the requirement of emergencies round the

clock. The required safety appliances shall be distributed at different locations of the plant to

meet any eventualities. Poster/placards reflecting safety awareness will be placed at different

locations in the plant area.

(vi) Emergency Drills

The emergency response plans and emergency preparedness level would be tested through

the following drills:

a. Table-top exercise (TTE)

b. Functional exercise (FE)

c. Full-scale exercise (FSE)

All elements/procedures of the On-Site Emergency Plan would be first tested through TTE and

perfected to the extent possible. The Plan then would be modified/ updated. Functional

Exercises basically to ensure proper functioning of various equipment such as the fire-fighting

equipment and the fire hydrant system. The Full-Scale Drill would be conducted to know the

level of preparedness of all teams. Initially, TTE and FE would be conducted periodically.

The following drills are conducted periodically:

a. Plant Emergency Drill for fire

b. Fire Drills at offices and admin building

c. Plant Emergency Drills (fire scenario involving evacuation)

Page 19: Risk Assessment and Disaster Management Planenvironmentclearance.nic.in/writereaddata/online/RiskAssessment/... · the hot raw meal gets jammed in the chute and screw conveyors. During

Proposed Cement Plant (Dalmia DSP Unit) - Clinker (3.0 MTPA), Cement (2.25 MTPA), WHRS (15 MW) and D.G. Set (1000 KVA) At Village & Tehsil: Rajgangpur, District: Sundergarh (Odisha)

RISK ASSESSMENT AND DISASTER MANAGEMENT PLAN

M/s. OCL India Limited 18 JM EnviroNet Pvt. Ltd.

(vii) Personal Protective Equipment’s (PPEs)

Personal protective equipment’s play a vital role in overcoming major disastrous situation

saving life during onsite emergency. List of recommended Personal Protective equipment

(PPE) is given below in Table - 7.8.

TABLE - 7.8

Summary of Recommended Personal Protective Equipment according to hazard onsite

Objective Workplace Hazards Suggested PPE

Eye and face protection

Flying particles, molten metal, liquid chemicals, gases or vapors, light radiation

Safety glasses with side-shields, protective shades, etc.

Head protection

Falling objects, inadequate height clearance, and overhead power cords

Plastic helmets with top and side impact protection

Hearing protection

Noise, ultra-sound Hearing protectors (ear plugs or ear muffs)

Foot protection

Failing or rolling objects, points objects. Corrosive or hot liquids

Safety shoes and boots for protection against moving and failing objects, liquids and chemicals

Hand protection

Hazardous materials, cuts or lacerations, vibrations, extreme temperatures

Gloves made of rubber or synthetic material (Neoprene), leather, steel, insulation materials, etc.

Respiratory protection

Dust, fogs, fumes, mists, gases, smokes, vapors

Facemasks with appropriate filters for dust removal and air purification (chemical, mists, vapors and gases). Single or multi-gas personal monitors, if available

Oxygen deficiency Portable or supplied air (fixed lines). Onsite rescue equipment

Body / leg protection

Extreme temperatures, hazardous materials, biological agents, cutting and laceration

Insulating clothing, body suits, aprons etc. of appropriate materials

Apart from this, all the employees are provided with helmets and safety shoes. It is statutory

on the part of the company employees to wear the appropriate safety gear given while

attending duty in the factory.

1.3.1 Off-Site Emergency Planning

The off-site emergency plan is an integral part of any hazard control system. It is based on those

incidents identified by the works management, which could affect people and the environment

outside the works. Thus, the off-site plan follows logically from the analysis that took place to

provide the basis for the on-site plan and the two plans therefore complement each other. The

roles of the various parties that may be involved in the implementation of an off-site plan are

Page 20: Risk Assessment and Disaster Management Planenvironmentclearance.nic.in/writereaddata/online/RiskAssessment/... · the hot raw meal gets jammed in the chute and screw conveyors. During

Proposed Cement Plant (Dalmia DSP Unit) - Clinker (3.0 MTPA), Cement (2.25 MTPA), WHRS (15 MW) and D.G. Set (1000 KVA) At Village & Tehsil: Rajgangpur, District: Sundergarh (Odisha)

RISK ASSESSMENT AND DISASTER MANAGEMENT PLAN

M/s. OCL India Limited 19 JM EnviroNet Pvt. Ltd.

described below. The responsibility for the off-site plan will be likely to rest either with the

works management or with the local authority.

Either way, the plan must identify an emergency coordinating officer who would take overall

command of the off-site activities. Consideration of evacuation may include the following

factors:

� In the case of a major fire but without explosion risk (e.g. an oil storage tank), only houses

close to the fire are likely to need evacuation

� If fire is escalating very fast it is necessary to evacuate people nearby as soon as possible.

� In acute emergency people are advised to stay indoors and shield themselves from the fire.

1.3.1.1 Organization

Organizational details of command structure, warning systems, implementation procedures,

emergency control centres include name and appointments of incident controller, site main

controller, their deputies and other key personnel involved during emergency.

1.3.1.2 Communications

Identification of personnel involved, communication centre, call signs, network, list of

telephone numbers.

1.3.1.3 Special Emergency Equipment

Details of availability and location of heavy lifting gear, specified fire-fighting equipment,

fireboats etc.

1.3.1.4 Voluntary Organizations

Details of Voluntary organizations, telephone numbers nearby of hospitals, Emergency

helpline, resources etc are to be available with chief authorities.

1.3.1.5 Non-government Organizations (NGO)

NGO’s could provide a valuable source of expertise and information to support emergency

response efforts. Members of NGOs could assist response personnel by performing specified

tasks, as planned during the emergency planning process.

� Evacuation of personnel from the affected area

� Arrangements at rallying posts and parking yards

� Rehabilitation of evacuated persons.

Page 21: Risk Assessment and Disaster Management Planenvironmentclearance.nic.in/writereaddata/online/RiskAssessment/... · the hot raw meal gets jammed in the chute and screw conveyors. During

Proposed Cement Plant (Dalmia DSP Unit) - Clinker (3.0 MTPA), Cement (2.25 MTPA), WHRS (15 MW) and D.G. Set (1000 KVA) At Village & Tehsil: Rajgangpur, District: Sundergarh (Odisha)

RISK ASSESSMENT AND DISASTER MANAGEMENT PLAN

M/s. OCL India Limited 20 JM EnviroNet Pvt. Ltd.

1.3.1.6 Chemical information

Details of the hazardous substances (MSDS information) and a summary of the risks associated

with them are to be made available at respective site.

1.3.1.7 Meteorological information

There is to be arrangements for obtaining details of weather conditions prevailing at r before

the time of incident and weather forecasts updates.

1.3.1.8 Humanitarian Arrangements

Transport, evacuation centres, emergency feeding, treatment of injured, first aid, ambulances,

temporary mortuaries.

1.3.1.9 Public Information

� Dealing with the media-press office

� Informing relatives, etc.

1.3.1.10 Assessment

� Collecting information on the causes of the emergency

� Reviewing the efficiency and effectiveness of all aspects of the emergency plan.

1.3.1.11 Role of local authority

Local Authorities like Panchayat, Sabha, Samity, municipalities can help in combating

emergency situation after assessing the impact scenario in rescue phase.

1.3.1.12 Role of police

The police is to assist in controlling of the incident site, organizing evacuation and removing of

any seriously injured people to hospitals.

� Co-ordination with the transport authorities, civil defence and home guards

� Co-ordination with army, navy, air force and state fire services

� Arrange for post mortem of dead bodies

� Establish communication centre with easy contact with ECC

1.3.1.13 Role of Fire Brigade

The fire brigade is to be organized to put out fires and provide assistance as required during

emergency.

Page 22: Risk Assessment and Disaster Management Planenvironmentclearance.nic.in/writereaddata/online/RiskAssessment/... · the hot raw meal gets jammed in the chute and screw conveyors. During

Proposed Cement Plant (Dalmia DSP Unit) - Clinker (3.0 MTPA), Cement (2.25 MTPA), WHRS (15 MW) and D.G. Set (1000 KVA) At Village & Tehsil: Rajgangpur, District: Sundergarh (Odisha)

RISK ASSESSMENT AND DISASTER MANAGEMENT PLAN

M/s. OCL India Limited 21 JM EnviroNet Pvt. Ltd.

1.3.1.14 Media

� The media is to have ready and continuous access to designated officials with relevant

information, as well as to other sources in order to provide essential and accurate

information to public throughout the emergency and to avoid commotion and confusion.

� Efforts are made to check the clarity and reliability of information as it becomes available,

and before it is communicated to public.

� Public health authorities are consulted when issuing statements to the media concerning

health aspects of chemical incidents.

� Members of the media are to facilitate response efforts by providing means for informing

the public with credible information about incidents involving hazardous substances.

1.3.1.15 Role of health care authorities

� Hospitals and doctors must be ready to treat all type of injuries to causalities during

emergency.

� Co-ordinate the activities of Primary Health Centres and Municipal Dispensaries to ensure

required quantities of drugs and equipments.

� Securing assistance of medical and paramedical personnel from nearby

hospitals/institutions.

� Temporary mortuary and identification of dead bodies.

1.4.1 Conclusion

It has concluded that there will be no major risk involved due to proposed project activity.

Suitable Risk Control Measures with respect to Risk Assessment shall be implemented to

minimize the risk to an acceptable level. Regular Training, Implementation of SOPs and

compliance of relevant Personal Protective Equipment’s (PPEs) shall help to minimize the

health hazards and incidental casualties. So, it is safe to say that there will be no major risk

involved due to the proposed project activity.