THE BAHRAIN PETROLEUMCOMPANY B.S.C (C)
WASTE WATER TREATMENT PLANTPROJECT (WWTPP)
RISK ASSESSMENT
FOR
Demolition & making of new pump foundation spent
caustic tank area
Plant No.: 386
Material Class: A
Equipment Nos.: N/A
P.O. No.: GS/BAPCO/008
REV Date Page Description
Preprd Chkd Appd
MCSCGS E&C
CM
GS E&C
SMBAPCO
A 11/07/2012 34Risk
Assessment
B 15/07/2012 26Risk
assessment
-
7/27/2019 RISK ASSESSMENT Demolation and Making of New Pump Foundation B
2/33
THE BAHRAIN PETROLEUMCOMPANY B.S.C (C)
WASTE WATER TREATMENT PLANTPROJECT (WWTPP)
Job
Code100210
BAPCO
Doc. No.RP- 052046
GS E&C
Doc. No.100210-HSE-RA-043 Page No. Page 1 of 26 Rev. B
-
7/27/2019 RISK ASSESSMENT Demolation and Making of New Pump Foundation B
3/33
WASTE WATER TREATEMENT PROJECTHazard Identification, Risk Assessment & Risk Control Register
RISK ASSESSMENT FORDemolition & making of new pump foundation spent caustictank
Sl. No Process
Activity
Potential
HazardsRisk Involved
INITIAL
Risk Control Measure
RESIDUAL
Probability
1-5
Severity
1-5
RiskLevel
1-25 P
robability
1-5
Severity
1-5
RiskLevel
1-25
01. Demolition of old pumpfoundationUsing of jackhammer&compressor
Usage of jackhammer
Rigging of soilembeddedfoundations
Injury & hearingloses
Injury & equipmentdamage
3
4
2
2
6
8
Obtain adequate permit for jackhammering.Earth connection to be provided for
jack hammer. Whip check arrestershall be provided to secure allhose connections. Use face shield& ear plugs in addition to generalPPECompressed air shall not be usedto clean dust from body.
All safety precaution ofexcavations shall be strictly
followed.Remove all soil from the side of
3
4
1
1
3
4
THE BAHRAIN PETROLEUM COMPANY B.S.C. (CLOSED)
WASTE WATER TREATMENT PLANT PROJECT (WWTPP) BAPCO Doc. No.: 052046 Revision: B
RISK ASSESSMENT FOR
Demolition & making of new pump foundation spentcaustic tank area
Doc. No.: 100210-HSE-RA- 043Page 3 of 26
-
7/27/2019 RISK ASSESSMENT Demolation and Making of New Pump Foundation B
4/33
WASTE WATER TREATEMENT PROJECTHazard Identification, Risk Assessment & Risk Control Register
RISK ASSESSMENT FORDemolition & making of new pump foundation spent caustictank
Sl. No Process
Activity
Potential
HazardsRisk Involved
INITIAL
Risk Control Measure
RESIDUAL
Probability
1-5
Severity
1-5
RiskLevel
1-25 P
robability
1-5
Severity
1-5
RiskLevel
1-25
foundations before attempt to lift.Make sure that all the holding boltsare un boltedIf crane shows any additional loadthan expected, dont attempt to liftfurther which may lead to sudden
jerk of load.The air compressor shall bealways attended durationoperation.
All joints of compressed air hosefitted with whip check arrester.
Compressed air must never bedirected at any individual
THE BAHRAIN PETROLEUM COMPANY B.S.C. (CLOSED)
WASTE WATER TREATMENT PLANT PROJECT (WWTPP) BAPCO Doc. No.: 052046 Revision: B
RISK ASSESSMENT FOR
Demolition & making of new pump foundation spentcaustic tank area
Doc. No.: 100210-HSE-RA- 043Page 4 of 26
-
7/27/2019 RISK ASSESSMENT Demolation and Making of New Pump Foundation B
5/33
WASTE WATER TREATEMENT PROJECTHazard Identification, Risk Assessment & Risk Control Register
RISK ASSESSMENT FORDemolition & making of new pump foundation spent caustictank
Sl. No Process
Activity
Potential
HazardsRisk Involved
INITIAL
Risk Control Measure
RESIDUAL
Probability
1-5
Severity
1-5
RiskLevel
1-25 P
robability
1-5
Severity
1-5
RiskLevel
1-25
compressed air shall not be usedfor cleaning of clothing or PPE.Compressor shall be kept awayfrom excavation and existingequipment .
02. Excavation for foundation
Damage of UGservices
InjuryElectric shock,Fire,Gas Leak,Environmentpollution
4 4 16 Any Excavation must be done only
after getting the excavation permit,
confirming the presence and
location of any underground
services.
In the presence of utility or productlines, excavation should be done
1 4 4
THE BAHRAIN PETROLEUM COMPANY B.S.C. (CLOSED)
WASTE WATER TREATMENT PLANT PROJECT (WWTPP) BAPCO Doc. No.: 052046 Revision: B
RISK ASSESSMENT FOR
Demolition & making of new pump foundation spentcaustic tank area
Doc. No.: 100210-HSE-RA- 043Page 5 of 26
-
7/27/2019 RISK ASSESSMENT Demolation and Making of New Pump Foundation B
6/33
WASTE WATER TREATEMENT PROJECTHazard Identification, Risk Assessment & Risk Control Register
RISK ASSESSMENT FORDemolition & making of new pump foundation spent caustictank
Sl. No Process
Activity
Potential
HazardsRisk Involved
INITIAL
Risk Control Measure
RESIDUAL
Probability
1-5
Severity
1-5
RiskLevel
1-25 P
robability
1-5
Severity
1-5
RiskLevel
1-25
by hand tools only; these lines are
identified by existing drawings or
by excavating, trail pits.
Incase of damage / discovery of a
service line the client shall be
informed immediately (Emergency
Response Plan As Per Situation)
and the work should be suspended
until further notice from
GSE&C/BAPCO.Extra care shall be taken during
jack hammer operation that not todamage / disturb any existing
THE BAHRAIN PETROLEUM COMPANY B.S.C. (CLOSED)
WASTE WATER TREATMENT PLANT PROJECT (WWTPP) BAPCO Doc. No.: 052046 Revision: B
RISK ASSESSMENT FOR
Demolition & making of new pump foundation spentcaustic tank area
Doc. No.: 100210-HSE-RA- 043Page 6 of 26
-
7/27/2019 RISK ASSESSMENT Demolation and Making of New Pump Foundation B
7/33
WASTE WATER TREATEMENT PROJECTHazard Identification, Risk Assessment & Risk Control Register
RISK ASSESSMENT FORDemolition & making of new pump foundation spent caustictank
Sl. No Process
Activity
Potential
HazardsRisk Involved
INITIAL
Risk Control Measure
RESIDUAL
Probability
1-5
Severity
1-5
RiskLevel
1-25 P
robability
1-5
Severity
1-5
RiskLevel
1-25
Collapse ofexcavation walls
Injury/ PropertyDamage
3 4 12
equipment or its foundations.All jackhammers shall be earthedto ground.Full time Supervision shall beavailable.Job Watcher shall be available ateach location.
Provide adequate supports forexisting facilities if anyShoring/ Sloping or stepping
should be provided for deepexcavation to prevent from its wall
1 4 4
THE BAHRAIN PETROLEUM COMPANY B.S.C. (CLOSED)
WASTE WATER TREATMENT PLANT PROJECT (WWTPP) BAPCO Doc. No.: 052046 Revision: B
RISK ASSESSMENT FOR
Demolition & making of new pump foundation spentcaustic tank area
Doc. No.: 100210-HSE-RA- 043Page 7 of 26
-
7/27/2019 RISK ASSESSMENT Demolation and Making of New Pump Foundation B
8/33
WASTE WATER TREATEMENT PROJECTHazard Identification, Risk Assessment & Risk Control Register
RISK ASSESSMENT FORDemolition & making of new pump foundation spent caustictank
Sl. No Process
Activity
Potential
HazardsRisk Involved
INITIAL
Risk Control Measure
RESIDUAL
Probability
1-5
Severity
1-5
RiskLevel
1-25 P
robability
1-5
Severity
1-5
RiskLevel
1-25
collapse.Dewatering shall be carried out tocontrol ground water. Whereverground water is observed.
All construction materials andexcavated soil should be stored atleast one meter away from theexcavation edge.Heavy and other equipment whichgenerates the vibration should notbe used near by the excavationedge and existing equipment. Safe
distance shall be maintained.Daily inspection shall be carried
THE BAHRAIN PETROLEUM COMPANY B.S.C. (CLOSED)
WASTE WATER TREATMENT PLANT PROJECT (WWTPP) BAPCO Doc. No.: 052046 Revision: B
RISK ASSESSMENT FOR
Demolition & making of new pump foundation spentcaustic tank area
Doc. No.: 100210-HSE-RA- 043Page 8 of 26
-
7/27/2019 RISK ASSESSMENT Demolation and Making of New Pump Foundation B
9/33
WASTE WATER TREATEMENT PROJECTHazard Identification, Risk Assessment & Risk Control Register
RISK ASSESSMENT FORDemolition & making of new pump foundation spent caustictank
Sl. No Process
Activity
Potential
HazardsRisk Involved
INITIAL
Risk Control Measure
RESIDUAL
Probability
1-5
Severity
1-5
RiskLevel
1-25 P
robability
1-5
Severity
1-5
RiskLevel
1-25
People falling intoexcavation
Injury 4 3 12
out of all deep excavations toobserve any sign of collapses.
All excavations shall have warningsigns and shall be barricadedadequatelyWhere excavations are locatedadjacent to pedestrian or vehicleaccess ways, warning lights mustbe provided at darkness hours.Workers shouldnt be allowed towork or walk near by theexcavation edge proper access
and cross over bridges shall beprovided.
1 3 3
THE BAHRAIN PETROLEUM COMPANY B.S.C. (CLOSED)
WASTE WATER TREATMENT PLANT PROJECT (WWTPP) BAPCO Doc. No.: 052046 Revision: B
RISK ASSESSMENT FOR
Demolition & making of new pump foundation spentcaustic tank area
Doc. No.: 100210-HSE-RA- 043Page 9 of 26
-
7/27/2019 RISK ASSESSMENT Demolation and Making of New Pump Foundation B
10/33
-
7/27/2019 RISK ASSESSMENT Demolation and Making of New Pump Foundation B
11/33
WASTE WATER TREATEMENT PROJECTHazard Identification, Risk Assessment & Risk Control Register
RISK ASSESSMENT FORDemolition & making of new pump foundation spent caustictank
Sl. No Process
Activity
Potential
HazardsRisk Involved
INITIAL
Risk Control Measure
RESIDUAL
Probability
1-5
Severity
1-5
RiskLevel
1-25 P
robability
1-5
Severity
1-5
RiskLevel
1-25
reported to BAPCO/ GS E&C.Continues gas monitoring shall becarried out by using calibratedportable gas monitor if requestedby approving authority.
All the workers should wearpersonal gas monitor and carryescape mask while working in H2Sdesignated areas. Only workerswho attained H2S training areallowed to work in H2S designatedareas.
Proper traffic movement shall beensure while working on or near by
THE BAHRAIN PETROLEUM COMPANY B.S.C. (CLOSED)
WASTE WATER TREATMENT PLANT PROJECT (WWTPP) BAPCO Doc. No.: 052046 Revision: B
RISK ASSESSMENT FOR
Demolition & making of new pump foundation spentcaustic tank area
Doc. No.: 100210-HSE-RA- 043Page 11 of 26
-
7/27/2019 RISK ASSESSMENT Demolation and Making of New Pump Foundation B
12/33
WASTE WATER TREATEMENT PROJECTHazard Identification, Risk Assessment & Risk Control Register
RISK ASSESSMENT FORDemolition & making of new pump foundation spent caustictank
Sl. No Process
Activity
Potential
HazardsRisk Involved
INITIAL
Risk Control Measure
RESIDUAL
Probability
1-5
Severity
1-5
RiskLevel
1-25 P
robability
1-5
Severity
1-5
RiskLevel
1-25
Traffic movement/Road closure
Collision withworkers and othervehicles / injury/property damage
2 4 8
the road.Warning signs & warning lightsmust be placed at least 50 metersbefore any excavation jobs doneon any road or close to the road.
Road plates shall be providedwhile making excavation on theroad and area shall be cleared assoon as possible.Signal mans shall be appointed toguide the vehicles while working
on the road.Warning signs, diversion signs
1 4 4
THE BAHRAIN PETROLEUM COMPANY B.S.C. (CLOSED)
WASTE WATER TREATMENT PLANT PROJECT (WWTPP) BAPCO Doc. No.: 052046 Revision: B
RISK ASSESSMENT FOR
Demolition & making of new pump foundation spentcaustic tank area
Doc. No.: 100210-HSE-RA- 043Page 12 of 26
-
7/27/2019 RISK ASSESSMENT Demolation and Making of New Pump Foundation B
13/33
WASTE WATER TREATEMENT PROJECTHazard Identification, Risk Assessment & Risk Control Register
RISK ASSESSMENT FORDemolition & making of new pump foundation spent caustictank
Sl. No Process
Activity
Potential
HazardsRisk Involved
INITIAL
Risk Control Measure
RESIDUAL
Probability
1-5
Severity
1-5
RiskLevel
1-25 P
robability
1-5
Severity
1-5
RiskLevel
1-25
Heavy equipmentmovement
Collision, collapse/injury/ PropertyDamage
3 4 12
must be used to warn the visitorsor public.
Appropriate Road Closer permitshall be obtained prior to close theroad.
All workers must wear reflectivejackets.
All heavy equipment shall haveaudible reverse alarm.
All heavy equipment shall be
operated only in the presence of abanks man.
1 4 4
THE BAHRAIN PETROLEUM COMPANY B.S.C. (CLOSED)
WASTE WATER TREATMENT PLANT PROJECT (WWTPP) BAPCO Doc. No.: 052046 Revision: B
RISK ASSESSMENT FOR
Demolition & making of new pump foundation spentcaustic tank area
Doc. No.: 100210-HSE-RA- 043Page 13 of 26
-
7/27/2019 RISK ASSESSMENT Demolation and Making of New Pump Foundation B
14/33
-
7/27/2019 RISK ASSESSMENT Demolation and Making of New Pump Foundation B
15/33
WASTE WATER TREATEMENT PROJECTHazard Identification, Risk Assessment & Risk Control Register
RISK ASSESSMENT FORDemolition & making of new pump foundation spent caustictank
Sl. No Process
Activity
Potential
HazardsRisk Involved
INITIAL
Risk Control Measure
RESIDUAL
Probability
1-5
Severity
1-5
RiskLevel
1-25 P
robability
1-5
Severity
1-5
RiskLevel
1-25
Equipment servicing shall becarried out on a regular basis toavoid unnecessary brake downs.
THE BAHRAIN PETROLEUM COMPANY B.S.C. (CLOSED)
WASTE WATER TREATMENT PLANT PROJECT (WWTPP) BAPCO Doc. No.: 052046 Revision: B
RISK ASSESSMENT FOR
Demolition & making of new pump foundation spentcaustic tank area
Doc. No.: 100210-HSE-RA- 043Page 15 of 26
-
7/27/2019 RISK ASSESSMENT Demolation and Making of New Pump Foundation B
16/33
WASTE WATER TREATEMENT PROJECTHazard Identification, Risk Assessment & Risk Control Register
RISK ASSESSMENT FORDemolition & making of new pump foundation spent caustictank
Sl. No Process
Activity
Potential
HazardsRisk Involved
INITIAL
Risk Control Measure
RESIDUAL
Probability
1-5
Severity
1-5
RiskLevel
1-25 P
robability
1-5
Severity
1-5
RiskLevel
1-25
03. Shuttering,rebar cutting,bending, andfixing
Unsafe stacking,
Sharp edgesElectrical shock
Injuries
InjuryFatal. Seriousinjuries
3
3
3
4
9
12
All steel rebar shall be stored on afirm level base area and onlyrequired quantity shall be broughtto the job site for cutting andbending.Hand gloves must be used whilehandling any rebar.Use heavy duty hand gloves.Use double insulated or properlygrounded equipment.Ensure all electrical equipmentsare tested and tagged by client
requirements.
1
1
3
4
3
4
THE BAHRAIN PETROLEUM COMPANY B.S.C. (CLOSED)
WASTE WATER TREATMENT PLANT PROJECT (WWTPP) BAPCO Doc. No.: 052046 Revision: B
RISK ASSESSMENT FOR
Demolition & making of new pump foundation spentcaustic tank area
Doc. No.: 100210-HSE-RA- 043Page 16 of 26
-
7/27/2019 RISK ASSESSMENT Demolation and Making of New Pump Foundation B
17/33
WASTE WATER TREATEMENT PROJECTHazard Identification, Risk Assessment & Risk Control Register
RISK ASSESSMENT FORDemolition & making of new pump foundation spent caustictank
Sl. No Process
Activity
Potential
HazardsRisk Involved
INITIAL
Risk Control Measure
RESIDUAL
Probability
1-5
Severity
1-5
RiskLevel
1-25 P
robability
1-5
Severity
1-5
RiskLevel
1-25
04. Concreting Concrete
High pressure
Injury
Damage to crew
3
4
4
3
12
12
Before pouring concrete ensure allformworks are adequatelysupported and structure is securedwith jacks and locking devices.Crew must always wear the PPEand supervisor must ensure thatthe face shield is used whilepouring concrete and the visor isclear and clean.Crew must wear rubber boots withsteel toes while working inconcrete.
While working on steel bear place
1
1
4
3
4
3
THE BAHRAIN PETROLEUM COMPANY B.S.C. (CLOSED)
WASTE WATER TREATMENT PLANT PROJECT (WWTPP) BAPCO Doc. No.: 052046 Revision: B
RISK ASSESSMENT FOR
Demolition & making of new pump foundation spentcaustic tank area
Doc. No.: 100210-HSE-RA- 043Page 17 of 26
-
7/27/2019 RISK ASSESSMENT Demolation and Making of New Pump Foundation B
18/33
WASTE WATER TREATEMENT PROJECTHazard Identification, Risk Assessment & Risk Control Register
RISK ASSESSMENT FORDemolition & making of new pump foundation spent caustictank
Sl. No Process
Activity
Potential
HazardsRisk Involved
INITIAL
Risk Control Measure
RESIDUAL
Probability
1-5
Severity
1-5
RiskLevel
1-25 P
robability
1-5
Severity
1-5
RiskLevel
1-25
pump
vibrators
Chemicals
and plant.
Repetitive handinjury
Chemical burns
3
3
3
3
9
9
planks to distribute the load.
Use hand gloves. Rotate crewwhile using vibrators.Use well maintained equipment.The truck mounted concretepumps must be treated as liftingequipment and all safety rules andregulations are applicable to it aswould be for a crane.
Only essential personnel shall beinvolved in the pumping operation
1
1
3
3
3
3
THE BAHRAIN PETROLEUM COMPANY B.S.C. (CLOSED)
WASTE WATER TREATMENT PLANT PROJECT (WWTPP) BAPCO Doc. No.: 052046 Revision: B
RISK ASSESSMENT FOR
Demolition & making of new pump foundation spentcaustic tank area
Doc. No.: 100210-HSE-RA- 043Page 18 of 26
-
7/27/2019 RISK ASSESSMENT Demolation and Making of New Pump Foundation B
19/33
WASTE WATER TREATEMENT PROJECTHazard Identification, Risk Assessment & Risk Control Register
RISK ASSESSMENT FORDemolition & making of new pump foundation spent caustictank
Sl. No Process
Activity
Potential
HazardsRisk Involved
INITIAL
Risk Control Measure
RESIDUAL
Probability
1-5
Severity
1-5
RiskLevel
1-25 P
robability
1-5
Severity
1-5
RiskLevel
1-25
crew members shall not standunder the direct flow of concretebeing pumped. Note: manyinjuries are caused when the pumpboom is shifted from one locationto another due to residual concretein the line.Use a rope securely tied to thepump delivery hose to direct theflow of concrete.Rotate the crew when continuousconcrete pouring is carried out.
All chemicals use d in the processmust be accompanied with the
THE BAHRAIN PETROLEUM COMPANY B.S.C. (CLOSED)
WASTE WATER TREATMENT PLANT PROJECT (WWTPP) BAPCO Doc. No.: 052046 Revision: B
RISK ASSESSMENT FOR
Demolition & making of new pump foundation spentcaustic tank area
Doc. No.: 100210-HSE-RA- 043Page 19 of 26
-
7/27/2019 RISK ASSESSMENT Demolation and Making of New Pump Foundation B
20/33
WASTE WATER TREATEMENT PROJECTHazard Identification, Risk Assessment & Risk Control Register
RISK ASSESSMENT FORDemolition & making of new pump foundation spent caustictank
Sl. No Process
Activity
Potential
HazardsRisk Involved
INITIAL
Risk Control Measure
RESIDUAL
Probability
1-5
Severity
1-5
RiskLevel
1-25 P
robability
1-5
Severity
1-5
RiskLevel
1-25
Movement ofheavy vehicle
Collision 3 4 12
material safety data sheet and alladditional precautions must betaken as per the in formationsprovided within. Proper PPE shallbe used as required.
All heavy vehicles shall be driveslowly in the construction are andfollow the rules of clients exit andentry routes.
All equipment shall maintain a safedistance from each other or from
any excavation.A banks man shall signal the
1 2 2
THE BAHRAIN PETROLEUM COMPANY B.S.C. (CLOSED)
WASTE WATER TREATMENT PLANT PROJECT (WWTPP) BAPCO Doc. No.: 052046 Revision: B
RISK ASSESSMENT FOR
Demolition & making of new pump foundation spentcaustic tank area
Doc. No.: 100210-HSE-RA- 043Page 20 of 26
-
7/27/2019 RISK ASSESSMENT Demolation and Making of New Pump Foundation B
21/33
WASTE WATER TREATEMENT PROJECTHazard Identification, Risk Assessment & Risk Control Register
RISK ASSESSMENT FORDemolition & making of new pump foundation spent caustictank
Sl. No Process
Activity
Potential
HazardsRisk Involved
INITIAL
Risk Control Measure
RESIDUAL
Probability
1-5
Severity
1-5
RiskLevel
1-25 P
robability
1-5
Severity
1-5
RiskLevel
1-25
heavy trucks to and for the pouringarea. All proper warning lights andhorns shall be used whileoperating the plant and equipment.
05. Removal of shuttering(Dismantling)
Pinch point injury 3 3 9 Maintain correct body positioning.Always give extra attention whileremoval of shuttering.Hold only on safe areas ofshuttering to avoid hand injury.
1 3 3
THE BAHRAIN PETROLEUM COMPANY B.S.C. (CLOSED)
WASTE WATER TREATMENT PLANT PROJECT (WWTPP) BAPCO Doc. No.: 052046 Revision: B
RISK ASSESSMENT FOR
Demolition & making of new pump foundation spentcaustic tank area
Doc. No.: 100210-HSE-RA- 043Page 21 of 26
-
7/27/2019 RISK ASSESSMENT Demolation and Making of New Pump Foundation B
22/33
WASTE WATER TREATEMENT PROJECTHazard Identification, Risk Assessment & Risk Control Register
RISK ASSESSMENT FORDemolition & making of new pump foundation spent caustictank
Sl. No Process
Activity
Potential
HazardsRisk Involved
INITIAL
Risk Control Measure
RESIDUAL
Probability
1-5
Severity
1-5
RiskLevel
1-25 P
robability
1-5
Severity
1-5
RiskLevel
1-25
06. Back Fillingand compactionaroundfoundation area
Use of compactor Injury 3 3 9 Use inspected and well maintainedcompactors.Trained and capable person tooperate Jumping or roller compactor.The compactor shall be in neutralwhile starting to avoid unexpectedmovement.Dont leave the compactor runningwithout operator.
Operator and crew shall wear
hearing protection while operatingcompactors.
1 3 3
THE BAHRAIN PETROLEUM COMPANY B.S.C. (CLOSED)
WASTE WATER TREATMENT PLANT PROJECT (WWTPP) BAPCO Doc. No.: 052046 Revision: B
RISK ASSESSMENT FOR
Demolition & making of new pump foundation spentcaustic tank area
Doc. No.: 100210-HSE-RA- 043Page 22 of 26
-
7/27/2019 RISK ASSESSMENT Demolation and Making of New Pump Foundation B
23/33
WASTE WATER TREATEMENT PROJECTHazard Identification, Risk Assessment & Risk Control Register
RISK ASSESSMENT FORDemolition & making of new pump foundation spent caustictank
Sl. No Process
Activity
Potential
HazardsRisk Involved
INITIAL
Risk Control Measure
RESIDUAL
Probability
1-5
Severity
1-5
RiskLevel
1-25 P
robability
1-5
Severity
1-5
RiskLevel
1-25
Wear appropriate PPE.
07. ManualHandling
Frequent, Forcedor AwkwardMovement of thebody
Back Injuries,Severe pains inthe hands, wrist,arm or neck
3 3 9 Install anchor points and usemechanical devices like pulleyblocks, etc to minimize manualload on crewUse correct lifting technique toavoid any strain on the back; donot lift a load if you doubt its weight
or adequacy of the equipment.Ensure there are enough crew
1 3 3
THE BAHRAIN PETROLEUM COMPANY B.S.C. (CLOSED)
WASTE WATER TREATMENT PLANT PROJECT (WWTPP) BAPCO Doc. No.: 052046 Revision: B
RISK ASSESSMENT FOR
Demolition & making of new pump foundation spentcaustic tank area
Doc. No.: 100210-HSE-RA- 043Page 23 of 26
-
7/27/2019 RISK ASSESSMENT Demolation and Making of New Pump Foundation B
24/33
WASTE WATER TREATEMENT PROJECTHazard Identification, Risk Assessment & Risk Control Register
RISK ASSESSMENT FORDemolition & making of new pump foundation spent caustictank
Sl. No Process
Activity
Potential
HazardsRisk Involved
INITIAL
Risk Control Measure
RESIDUAL
Probability
1-5
Severity
1-5
RiskLevel
1-25 P
robability
1-5
Severity
1-5
RiskLevel
1-25
members before lifting the load.
Use the following technique whilelifting manually:Check for any obstructions beforelifting.Check out the area where the loadwill be placed before lifting theload.Place feet apart, leading legforward.Bend your legs and not your back
to lift any load.Keep a firm grip and keep load as
THE BAHRAIN PETROLEUM COMPANY B.S.C. (CLOSED)
WASTE WATER TREATMENT PLANT PROJECT (WWTPP) BAPCO Doc. No.: 052046 Revision: B
RISK ASSESSMENT FOR
Demolition & making of new pump foundation spentcaustic tank area
Doc. No.: 100210-HSE-RA- 043Page 24 of 26
-
7/27/2019 RISK ASSESSMENT Demolation and Making of New Pump Foundation B
25/33
WASTE WATER TREATEMENT PROJECTHazard Identification, Risk Assessment & Risk Control Register
RISK ASSESSMENT FORDemolition & making of new pump foundation spent caustictank
Sl. No Process
Activity
Potential
HazardsRisk Involved
INITIAL
Risk Control Measure
RESIDUAL
Probability
1-5
Severity
1-5
RiskLevel
1-25 P
robability
1-5
Severity
1-5
RiskLevel
1-25
close to the body.Dont jerk or make any awkwardmovements.Keep the load down and thenadjust as necessary.
08 Lifting & Rigging Failure of SlingsLifting gear.
Failure of wireropes. Hydraulicsystem
Injury to crewDamage to plantand equipment
Injury to crew,Damage to plantand equipment
4
3
3
3
12
12
Rigging study must be done priorto lifting activityUse only certified and competentqualified personnel.Use inspected and tagged cables,slings, and shackles (lifting gear).Color codedPlace warning signs and barricadethe area off limits.
1
1
3
3
3
3
THE BAHRAIN PETROLEUM COMPANY B.S.C. (CLOSED)
WASTE WATER TREATMENT PLANT PROJECT (WWTPP) BAPCO Doc. No.: 052046 Revision: B
RISK ASSESSMENT FOR
Demolition & making of new pump foundation spentcaustic tank area
Doc. No.: 100210-HSE-RA- 043Page 25 of 26
-
7/27/2019 RISK ASSESSMENT Demolation and Making of New Pump Foundation B
26/33
WASTE WATER TREATEMENT PROJECTHazard Identification, Risk Assessment & Risk Control Register
RISK ASSESSMENT FORDemolition & making of new pump foundation spent caustictank
Sl. No Process
Activity
Potential
HazardsRisk Involved
INITIAL
Risk Control Measure
RESIDUAL
Probability
1-5
Severity
1-5
RiskLevel
1-25 P
robability
1-5
Severity
1-5
RiskLevel
1-25
Unstable erection
Insecure loadduring lifting
Injury to crewDamage to plantand equipment
Injuries, damage toplant and
4
4
3
3
12
12
Check the working load and type ofsling required.
All cranes and Boom trucks will
have their load test certificates and
Client approval certificates as
necessary. (All certificates must be
kept in the operators cabin).
Conduct visual inspections beforeand after operations.Carry out periodical maintenance.
Only a competent person shallcarry out maintenance.
1
1
3
3
3
3
THE BAHRAIN PETROLEUM COMPANY B.S.C. (CLOSED)
WASTE WATER TREATMENT PLANT PROJECT (WWTPP) BAPCO Doc. No.: 052046 Revision: B
RISK ASSESSMENT FOR
Demolition & making of new pump foundation spentcaustic tank area
Doc. No.: 100210-HSE-RA- 043Page 26 of 26
-
7/27/2019 RISK ASSESSMENT Demolation and Making of New Pump Foundation B
27/33
WASTE WATER TREATEMENT PROJECTHazard Identification, Risk Assessment & Risk Control Register
RISK ASSESSMENT FORDemolition & making of new pump foundation spent caustictank
Sl. No Process
Activity
Potential
HazardsRisk Involved
INITIAL
Risk Control Measure
RESIDUAL
Probability
1-5
Severity
1-5
RiskLevel
1-25 P
robability
1-5
Severity
1-5
RiskLevel
1-25
operations
Incorrect operation
equipment
Damage to plant,equipment, injuries
3 3 9
Dont lift during heavy windconditions.Lift or lower a load slowly withoutany sudden acceleration or suddenstopping.Ensure outriggers fully extended,the ground is compacted, and levelsurface is firm. Always useblocking under outrigger pad.
Check for any unsecured materialson the load to be lifted.
Make sure the load is properlyattached to the lifting equipment
1 3 3
THE BAHRAIN PETROLEUM COMPANY B.S.C. (CLOSED)
WASTE WATER TREATMENT PLANT PROJECT (WWTPP) BAPCO Doc. No.: 052046 Revision: B
RISK ASSESSMENT FOR
Demolition & making of new pump foundation spentcaustic tank area
Doc. No.: 100210-HSE-RA- 043Page 27 of 26
-
7/27/2019 RISK ASSESSMENT Demolation and Making of New Pump Foundation B
28/33
WASTE WATER TREATEMENT PROJECTHazard Identification, Risk Assessment & Risk Control Register
RISK ASSESSMENT FORDemolition & making of new pump foundation spent caustictank
Sl. No Process
Activity
Potential
HazardsRisk Involved
INITIAL
Risk Control Measure
RESIDUAL
Probability
1-5
Severity
1-5
RiskLevel
1-25 P
robability
1-5
Severity
1-5
RiskLevel
1-25
Overhead andundergroundservices
Damage to plant,equipment, highinjuries
4 3 12 and there is a guideline attached toload.Never pound the slings understress and never force the chokedsling eye down close to the load.Check for the stability of the loadas soon as it is lifted. If there is avariation more than 5 degree thenthe load is not balanced and the liftmust be stopped.Never pull or tug a load, Cranesare used only to lift a load. Lift or
lower a load slowly without anysudden acceleration or sudden
1 3 3
THE BAHRAIN PETROLEUM COMPANY B.S.C. (CLOSED)
WASTE WATER TREATMENT PLANT PROJECT (WWTPP) BAPCO Doc. No.: 052046 Revision: B
RISK ASSESSMENT FOR
Demolition & making of new pump foundation spentcaustic tank area
Doc. No.: 100210-HSE-RA- 043Page 28 of 26
-
7/27/2019 RISK ASSESSMENT Demolation and Making of New Pump Foundation B
29/33
WASTE WATER TREATEMENT PROJECTHazard Identification, Risk Assessment & Risk Control Register
RISK ASSESSMENT FORDemolition & making of new pump foundation spent caustictank
Sl. No Process
Activity
Potential
HazardsRisk Involved
INITIAL
Risk Control Measure
RESIDUAL
Probability
1-5
Severity
1-5
RiskLevel
1-25 P
robability
1-5
Severity
1-5
RiskLevel
1-25
stopping.Swing a load slowly as a rapidswing causes side loading and cancause the load to swing out.Cranes should keep safe distancefrom each other and from livefacilities.Operator should not leave thecabin with suspended load.
All lifting equipment shall maintainsafe distance while operating nearservice lines. Cranes shall not be
erected near or on any buriedservice line.
THE BAHRAIN PETROLEUM COMPANY B.S.C. (CLOSED)
WASTE WATER TREATMENT PLANT PROJECT (WWTPP) BAPCO Doc. No.: 052046 Revision: B
RISK ASSESSMENT FOR
Demolition & making of new pump foundation spentcaustic tank area
Doc. No.: 100210-HSE-RA- 043Page 29 of 26
-
7/27/2019 RISK ASSESSMENT Demolation and Making of New Pump Foundation B
30/33
WASTE WATER TREATEMENT PROJECTHazard Identification, Risk Assessment & Risk Control Register
RISK ASSESSMENT FORDemolition & making of new pump foundation spent caustictank
Sl. No Process
Activity
Potential
HazardsRisk Involved
INITIAL
Risk Control Measure
RESIDUAL
Probability
1-5
Severity
1-5
RiskLevel
1-25 P
robability
1-5
Severity
1-5
RiskLevel
1-25
Operator shall ensure that theboom/ hook is not traveling nearany overhead service lines.
Correct sling length shall be used
so that the minimum operating
level of the boom shall be
maintained.In case of any emergency, theequipment shall be switched off.The operator shall leave hisoperating cabin only after the
service line has been isolated andconfirmed by service operators.
THE BAHRAIN PETROLEUM COMPANY B.S.C. (CLOSED)
WASTE WATER TREATMENT PLANT PROJECT (WWTPP) BAPCO Doc. No.: 052046 Revision: B
RISK ASSESSMENT FOR
Demolition & making of new pump foundation spentcaustic tank area
Doc. No.: 100210-HSE-RA- 043Page 30 of 26
-
7/27/2019 RISK ASSESSMENT Demolation and Making of New Pump Foundation B
31/33
WASTE WATER TREATEMENT PROJECTHazard Identification, Risk Assessment & Risk Control Register
RISK ASSESSMENT FORDemolition & making of new pump foundation spent caustictank
Notes:
1. Full time Safety and Supervisory coverage shall be ensured at site.
2. All the required permits shall be obtained before starting the job.
3. All issued work permits and copies of Risk Assessment shall be kept in a Permit Box at site.
4. The Supervisor shall conduct Tool Box Talk & explain the risks and control measures to all crew members.
5. Before leaving the work site on completion of each days work, the area shall be checked for proper house-keeping, elimination of all
possible sources of fire, shutdown of all construction equipment, proper storage of tools and tackles etc
6. All employees must know the emergency procedures of BAPCO /GS
7. Attendance sheet of Toolbox Talk shall be available for audit; subsequently it must be submitted to GS.
8. Provide portable toilet, proper barricading of the work area with signage.
9. Cool down shelter and drinking water shall be available at site.
10. Ensure the work / resting area, shall be kept neat and clean and all rubbish is put into the waste and shall be disposed on regular
basis.
THE BAHRAIN PETROLEUM COMPANY B.S.C. (CLOSED)
WASTE WATER TREATMENT PLANT PROJECT (WWTPP) BAPCO Doc. No.: 052046 Revision: B
RISK ASSESSMENT FOR
Demolition & making of new pump foundation spentcaustic tank area
Doc. No.: 100210-HSE-RA- 043Page 31 of 26
-
7/27/2019 RISK ASSESSMENT Demolation and Making of New Pump Foundation B
32/33
WASTE WATER TREATEMENT PROJECTHazard Identification, Risk Assessment & Risk Control Register
RISK ASSESSMENT FORDemolition & making of new pump foundation spent caustictank
Prepared By Approved By Approved By Approved By
Waseem Tanoli Paul Edward C.G. Sudhakaran
Site HSE Officer GS E&C Civil HSE Manager F H&S Specialist
MCSC GS E&C GS E&C BAPC
THE BAHRAIN PETROLEUM COMPANY B.S.C. (CLOSED)
WASTE WATER TREATMENT PLANT PROJECT (WWTPP) BAPCO Doc. No.: 052046 Revision: B
RISK ASSESSMENT FOR
Demolition & making of new pump foundation spentcaustic tank area
Doc. No.: 100210-HSE-RA- 043Page 32 of 26
-