    THE BAHRAIN PETROLEUMCOMPANY B.S.C (C)

    WASTE WATER TREATMENT PLANTPROJECT (WWTPP)

    RISK ASSESSMENT

    FOR

    Demolition & making of new pump foundation spent

    caustic tank area

    Plant No.: 386

    Material Class: A

    Equipment Nos.: N/A

    P.O. No.: GS/BAPCO/008

    REV Date Page Description

    Preprd Chkd Appd

    MCSCGS E&C

    CM

    GS E&C

    SMBAPCO

    A 11/07/2012 34Risk

    Assessment

    B 15/07/2012 26Risk

    assessment

  • 7/27/2019 RISK ASSESSMENT Demolation and Making of New Pump Foundation B

    2/33

    THE BAHRAIN PETROLEUMCOMPANY B.S.C (C)

    WASTE WATER TREATMENT PLANTPROJECT (WWTPP)

    Job

    Code100210

    BAPCO

    Doc. No.RP- 052046

    GS E&C

    Doc. No.100210-HSE-RA-043 Page No. Page 1 of 26 Rev. B

  • 7/27/2019 RISK ASSESSMENT Demolation and Making of New Pump Foundation B

    3/33

    WASTE WATER TREATEMENT PROJECTHazard Identification, Risk Assessment & Risk Control Register

    RISK ASSESSMENT FORDemolition & making of new pump foundation spent caustictank

    Sl. No Process

    Activity

    Potential

    HazardsRisk Involved

    INITIAL

    Risk Control Measure

    RESIDUAL

    Probability

    1-5

    Severity

    1-5

    RiskLevel

    1-25 P

    robability

    1-5

    Severity

    1-5

    RiskLevel

    1-25

    01. Demolition of old pumpfoundationUsing of jackhammer&compressor

    Usage of jackhammer

    Rigging of soilembeddedfoundations

    Injury & hearingloses

    Injury & equipmentdamage

    3

    4

    2

    2

    6

    8

    Obtain adequate permit for jackhammering.Earth connection to be provided for

    jack hammer. Whip check arrestershall be provided to secure allhose connections. Use face shield& ear plugs in addition to generalPPECompressed air shall not be usedto clean dust from body.

    All safety precaution ofexcavations shall be strictly

    followed.Remove all soil from the side of

    3

    4

    1

    1

    3

    4

    THE BAHRAIN PETROLEUM COMPANY B.S.C. (CLOSED)

    WASTE WATER TREATMENT PLANT PROJECT (WWTPP) BAPCO Doc. No.: 052046 Revision: B

    RISK ASSESSMENT FOR

    Demolition & making of new pump foundation spentcaustic tank area

    Doc. No.: 100210-HSE-RA- 043Page 3 of 26

  • 7/27/2019 RISK ASSESSMENT Demolation and Making of New Pump Foundation B

    4/33

    WASTE WATER TREATEMENT PROJECTHazard Identification, Risk Assessment & Risk Control Register

    RISK ASSESSMENT FORDemolition & making of new pump foundation spent caustictank

    Sl. No Process

    Activity

    Potential

    HazardsRisk Involved

    INITIAL

    Risk Control Measure

    RESIDUAL

    Probability

    1-5

    Severity

    1-5

    RiskLevel

    1-25 P

    robability

    1-5

    Severity

    1-5

    RiskLevel

    1-25

    foundations before attempt to lift.Make sure that all the holding boltsare un boltedIf crane shows any additional loadthan expected, dont attempt to liftfurther which may lead to sudden

    jerk of load.The air compressor shall bealways attended durationoperation.

    All joints of compressed air hosefitted with whip check arrester.

    Compressed air must never bedirected at any individual

    THE BAHRAIN PETROLEUM COMPANY B.S.C. (CLOSED)

    WASTE WATER TREATMENT PLANT PROJECT (WWTPP) BAPCO Doc. No.: 052046 Revision: B

    RISK ASSESSMENT FOR

    Demolition & making of new pump foundation spentcaustic tank area

    Doc. No.: 100210-HSE-RA- 043Page 4 of 26

  • 7/27/2019 RISK ASSESSMENT Demolation and Making of New Pump Foundation B

    5/33

    WASTE WATER TREATEMENT PROJECTHazard Identification, Risk Assessment & Risk Control Register

    RISK ASSESSMENT FORDemolition & making of new pump foundation spent caustictank

    Sl. No Process

    Activity

    Potential

    HazardsRisk Involved

    INITIAL

    Risk Control Measure

    RESIDUAL

    Probability

    1-5

    Severity

    1-5

    RiskLevel

    1-25 P

    robability

    1-5

    Severity

    1-5

    RiskLevel

    1-25

    compressed air shall not be usedfor cleaning of clothing or PPE.Compressor shall be kept awayfrom excavation and existingequipment .

    02. Excavation for foundation

    Damage of UGservices

    InjuryElectric shock,Fire,Gas Leak,Environmentpollution

    4 4 16 Any Excavation must be done only

    after getting the excavation permit,

    confirming the presence and

    location of any underground

    services.

    In the presence of utility or productlines, excavation should be done

    1 4 4

    THE BAHRAIN PETROLEUM COMPANY B.S.C. (CLOSED)

    WASTE WATER TREATMENT PLANT PROJECT (WWTPP) BAPCO Doc. No.: 052046 Revision: B

    RISK ASSESSMENT FOR

    Demolition & making of new pump foundation spentcaustic tank area

    Doc. No.: 100210-HSE-RA- 043Page 5 of 26

  • 7/27/2019 RISK ASSESSMENT Demolation and Making of New Pump Foundation B

    6/33

    WASTE WATER TREATEMENT PROJECTHazard Identification, Risk Assessment & Risk Control Register

    RISK ASSESSMENT FORDemolition & making of new pump foundation spent caustictank

    Sl. No Process

    Activity

    Potential

    HazardsRisk Involved

    INITIAL

    Risk Control Measure

    RESIDUAL

    Probability

    1-5

    Severity

    1-5

    RiskLevel

    1-25 P

    robability

    1-5

    Severity

    1-5

    RiskLevel

    1-25

    by hand tools only; these lines are

    identified by existing drawings or

    by excavating, trail pits.

    Incase of damage / discovery of a

    service line the client shall be

    informed immediately (Emergency

    Response Plan As Per Situation)

    and the work should be suspended

    until further notice from

    GSE&C/BAPCO.Extra care shall be taken during

    jack hammer operation that not todamage / disturb any existing

    THE BAHRAIN PETROLEUM COMPANY B.S.C. (CLOSED)

    WASTE WATER TREATMENT PLANT PROJECT (WWTPP) BAPCO Doc. No.: 052046 Revision: B

    RISK ASSESSMENT FOR

    Demolition & making of new pump foundation spentcaustic tank area

    Doc. No.: 100210-HSE-RA- 043Page 6 of 26

  • 7/27/2019 RISK ASSESSMENT Demolation and Making of New Pump Foundation B

    7/33

    WASTE WATER TREATEMENT PROJECTHazard Identification, Risk Assessment & Risk Control Register

    RISK ASSESSMENT FORDemolition & making of new pump foundation spent caustictank

    Sl. No Process

    Activity

    Potential

    HazardsRisk Involved

    INITIAL

    Risk Control Measure

    RESIDUAL

    Probability

    1-5

    Severity

    1-5

    RiskLevel

    1-25 P

    robability

    1-5

    Severity

    1-5

    RiskLevel

    1-25

    Collapse ofexcavation walls

    Injury/ PropertyDamage

    3 4 12

    equipment or its foundations.All jackhammers shall be earthedto ground.Full time Supervision shall beavailable.Job Watcher shall be available ateach location.

    Provide adequate supports forexisting facilities if anyShoring/ Sloping or stepping

    should be provided for deepexcavation to prevent from its wall

    1 4 4

    THE BAHRAIN PETROLEUM COMPANY B.S.C. (CLOSED)

    WASTE WATER TREATMENT PLANT PROJECT (WWTPP) BAPCO Doc. No.: 052046 Revision: B

    RISK ASSESSMENT FOR

    Demolition & making of new pump foundation spentcaustic tank area

    Doc. No.: 100210-HSE-RA- 043Page 7 of 26

  • 7/27/2019 RISK ASSESSMENT Demolation and Making of New Pump Foundation B

    8/33

    WASTE WATER TREATEMENT PROJECTHazard Identification, Risk Assessment & Risk Control Register

    RISK ASSESSMENT FORDemolition & making of new pump foundation spent caustictank

    Sl. No Process

    Activity

    Potential

    HazardsRisk Involved

    INITIAL

    Risk Control Measure

    RESIDUAL

    Probability

    1-5

    Severity

    1-5

    RiskLevel

    1-25 P

    robability

    1-5

    Severity

    1-5

    RiskLevel

    1-25

    collapse.Dewatering shall be carried out tocontrol ground water. Whereverground water is observed.

    All construction materials andexcavated soil should be stored atleast one meter away from theexcavation edge.Heavy and other equipment whichgenerates the vibration should notbe used near by the excavationedge and existing equipment. Safe

    distance shall be maintained.Daily inspection shall be carried

    THE BAHRAIN PETROLEUM COMPANY B.S.C. (CLOSED)

    WASTE WATER TREATMENT PLANT PROJECT (WWTPP) BAPCO Doc. No.: 052046 Revision: B

    RISK ASSESSMENT FOR

    Demolition & making of new pump foundation spentcaustic tank area

    Doc. No.: 100210-HSE-RA- 043Page 8 of 26

  • 7/27/2019 RISK ASSESSMENT Demolation and Making of New Pump Foundation B

    9/33

    WASTE WATER TREATEMENT PROJECTHazard Identification, Risk Assessment & Risk Control Register

    RISK ASSESSMENT FORDemolition & making of new pump foundation spent caustictank

    Sl. No Process

    Activity

    Potential

    HazardsRisk Involved

    INITIAL

    Risk Control Measure

    RESIDUAL

    Probability

    1-5

    Severity

    1-5

    RiskLevel

    1-25 P

    robability

    1-5

    Severity

    1-5

    RiskLevel

    1-25

    People falling intoexcavation

    Injury 4 3 12

    out of all deep excavations toobserve any sign of collapses.

    All excavations shall have warningsigns and shall be barricadedadequatelyWhere excavations are locatedadjacent to pedestrian or vehicleaccess ways, warning lights mustbe provided at darkness hours.Workers shouldnt be allowed towork or walk near by theexcavation edge proper access

    and cross over bridges shall beprovided.

    1 3 3

    THE BAHRAIN PETROLEUM COMPANY B.S.C. (CLOSED)

    WASTE WATER TREATMENT PLANT PROJECT (WWTPP) BAPCO Doc. No.: 052046 Revision: B

    RISK ASSESSMENT FOR

    Demolition & making of new pump foundation spentcaustic tank area

    Doc. No.: 100210-HSE-RA- 043Page 9 of 26

  • 7/27/2019 RISK ASSESSMENT Demolation and Making of New Pump Foundation B

    10/33

  • 7/27/2019 RISK ASSESSMENT Demolation and Making of New Pump Foundation B

    11/33

    WASTE WATER TREATEMENT PROJECTHazard Identification, Risk Assessment & Risk Control Register

    RISK ASSESSMENT FORDemolition & making of new pump foundation spent caustictank

    Sl. No Process

    Activity

    Potential

    HazardsRisk Involved

    INITIAL

    Risk Control Measure

    RESIDUAL

    Probability

    1-5

    Severity

    1-5

    RiskLevel

    1-25 P

    robability

    1-5

    Severity

    1-5

    RiskLevel

    1-25

    reported to BAPCO/ GS E&C.Continues gas monitoring shall becarried out by using calibratedportable gas monitor if requestedby approving authority.

    All the workers should wearpersonal gas monitor and carryescape mask while working in H2Sdesignated areas. Only workerswho attained H2S training areallowed to work in H2S designatedareas.

    Proper traffic movement shall beensure while working on or near by

    THE BAHRAIN PETROLEUM COMPANY B.S.C. (CLOSED)

    WASTE WATER TREATMENT PLANT PROJECT (WWTPP) BAPCO Doc. No.: 052046 Revision: B

    RISK ASSESSMENT FOR

    Demolition & making of new pump foundation spentcaustic tank area

    Doc. No.: 100210-HSE-RA- 043Page 11 of 26

  • 7/27/2019 RISK ASSESSMENT Demolation and Making of New Pump Foundation B

    12/33

    WASTE WATER TREATEMENT PROJECTHazard Identification, Risk Assessment & Risk Control Register

    RISK ASSESSMENT FORDemolition & making of new pump foundation spent caustictank

    Sl. No Process

    Activity

    Potential

    HazardsRisk Involved

    INITIAL

    Risk Control Measure

    RESIDUAL

    Probability

    1-5

    Severity

    1-5

    RiskLevel

    1-25 P

    robability

    1-5

    Severity

    1-5

    RiskLevel

    1-25

    Traffic movement/Road closure

    Collision withworkers and othervehicles / injury/property damage

    2 4 8

    the road.Warning signs & warning lightsmust be placed at least 50 metersbefore any excavation jobs doneon any road or close to the road.

    Road plates shall be providedwhile making excavation on theroad and area shall be cleared assoon as possible.Signal mans shall be appointed toguide the vehicles while working

    on the road.Warning signs, diversion signs

    1 4 4

    THE BAHRAIN PETROLEUM COMPANY B.S.C. (CLOSED)

    WASTE WATER TREATMENT PLANT PROJECT (WWTPP) BAPCO Doc. No.: 052046 Revision: B

    RISK ASSESSMENT FOR

    Demolition & making of new pump foundation spentcaustic tank area

    Doc. No.: 100210-HSE-RA- 043Page 12 of 26

  • 7/27/2019 RISK ASSESSMENT Demolation and Making of New Pump Foundation B

    13/33

    WASTE WATER TREATEMENT PROJECTHazard Identification, Risk Assessment & Risk Control Register

    RISK ASSESSMENT FORDemolition & making of new pump foundation spent caustictank

    Sl. No Process

    Activity

    Potential

    HazardsRisk Involved

    INITIAL

    Risk Control Measure

    RESIDUAL

    Probability

    1-5

    Severity

    1-5

    RiskLevel

    1-25 P

    robability

    1-5

    Severity

    1-5

    RiskLevel

    1-25

    Heavy equipmentmovement

    Collision, collapse/injury/ PropertyDamage

    3 4 12

    must be used to warn the visitorsor public.

    Appropriate Road Closer permitshall be obtained prior to close theroad.

    All workers must wear reflectivejackets.

    All heavy equipment shall haveaudible reverse alarm.

    All heavy equipment shall be

    operated only in the presence of abanks man.

    1 4 4

    THE BAHRAIN PETROLEUM COMPANY B.S.C. (CLOSED)

    WASTE WATER TREATMENT PLANT PROJECT (WWTPP) BAPCO Doc. No.: 052046 Revision: B

    RISK ASSESSMENT FOR

    Demolition & making of new pump foundation spentcaustic tank area

    Doc. No.: 100210-HSE-RA- 043Page 13 of 26

  • 7/27/2019 RISK ASSESSMENT Demolation and Making of New Pump Foundation B

    14/33

  • 7/27/2019 RISK ASSESSMENT Demolation and Making of New Pump Foundation B

    15/33

    WASTE WATER TREATEMENT PROJECTHazard Identification, Risk Assessment & Risk Control Register

    RISK ASSESSMENT FORDemolition & making of new pump foundation spent caustictank

    Sl. No Process

    Activity

    Potential

    HazardsRisk Involved

    INITIAL

    Risk Control Measure

    RESIDUAL

    Probability

    1-5

    Severity

    1-5

    RiskLevel

    1-25 P

    robability

    1-5

    Severity

    1-5

    RiskLevel

    1-25

    Equipment servicing shall becarried out on a regular basis toavoid unnecessary brake downs.

    THE BAHRAIN PETROLEUM COMPANY B.S.C. (CLOSED)

    WASTE WATER TREATMENT PLANT PROJECT (WWTPP) BAPCO Doc. No.: 052046 Revision: B

    RISK ASSESSMENT FOR

    Demolition & making of new pump foundation spentcaustic tank area

    Doc. No.: 100210-HSE-RA- 043Page 15 of 26

  • 7/27/2019 RISK ASSESSMENT Demolation and Making of New Pump Foundation B

    16/33

    WASTE WATER TREATEMENT PROJECTHazard Identification, Risk Assessment & Risk Control Register

    RISK ASSESSMENT FORDemolition & making of new pump foundation spent caustictank

    Sl. No Process

    Activity

    Potential

    HazardsRisk Involved

    INITIAL

    Risk Control Measure

    RESIDUAL

    Probability

    1-5

    Severity

    1-5

    RiskLevel

    1-25 P

    robability

    1-5

    Severity

    1-5

    RiskLevel

    1-25

    03. Shuttering,rebar cutting,bending, andfixing

    Unsafe stacking,

    Sharp edgesElectrical shock

    Injuries

    InjuryFatal. Seriousinjuries

    3

    3

    3

    4

    9

    12

    All steel rebar shall be stored on afirm level base area and onlyrequired quantity shall be broughtto the job site for cutting andbending.Hand gloves must be used whilehandling any rebar.Use heavy duty hand gloves.Use double insulated or properlygrounded equipment.Ensure all electrical equipmentsare tested and tagged by client

    requirements.

    1

    1

    3

    4

    3

    4

    THE BAHRAIN PETROLEUM COMPANY B.S.C. (CLOSED)

    WASTE WATER TREATMENT PLANT PROJECT (WWTPP) BAPCO Doc. No.: 052046 Revision: B

    RISK ASSESSMENT FOR

    Demolition & making of new pump foundation spentcaustic tank area

    Doc. No.: 100210-HSE-RA- 043Page 16 of 26

  • 7/27/2019 RISK ASSESSMENT Demolation and Making of New Pump Foundation B

    17/33

    WASTE WATER TREATEMENT PROJECTHazard Identification, Risk Assessment & Risk Control Register

    RISK ASSESSMENT FORDemolition & making of new pump foundation spent caustictank

    Sl. No Process

    Activity

    Potential

    HazardsRisk Involved

    INITIAL

    Risk Control Measure

    RESIDUAL

    Probability

    1-5

    Severity

    1-5

    RiskLevel

    1-25 P

    robability

    1-5

    Severity

    1-5

    RiskLevel

    1-25

    04. Concreting Concrete

    High pressure

    Injury

    Damage to crew

    3

    4

    4

    3

    12

    12

    Before pouring concrete ensure allformworks are adequatelysupported and structure is securedwith jacks and locking devices.Crew must always wear the PPEand supervisor must ensure thatthe face shield is used whilepouring concrete and the visor isclear and clean.Crew must wear rubber boots withsteel toes while working inconcrete.

    While working on steel bear place

    1

    1

    4

    3

    4

    3

    THE BAHRAIN PETROLEUM COMPANY B.S.C. (CLOSED)

    WASTE WATER TREATMENT PLANT PROJECT (WWTPP) BAPCO Doc. No.: 052046 Revision: B

    RISK ASSESSMENT FOR

    Demolition & making of new pump foundation spentcaustic tank area

    Doc. No.: 100210-HSE-RA- 043Page 17 of 26

  • 7/27/2019 RISK ASSESSMENT Demolation and Making of New Pump Foundation B

    18/33

    WASTE WATER TREATEMENT PROJECTHazard Identification, Risk Assessment & Risk Control Register

    RISK ASSESSMENT FORDemolition & making of new pump foundation spent caustictank

    Sl. No Process

    Activity

    Potential

    HazardsRisk Involved

    INITIAL

    Risk Control Measure

    RESIDUAL

    Probability

    1-5

    Severity

    1-5

    RiskLevel

    1-25 P

    robability

    1-5

    Severity

    1-5

    RiskLevel

    1-25

    pump

    vibrators

    Chemicals

    and plant.

    Repetitive handinjury

    Chemical burns

    3

    3

    3

    3

    9

    9

    planks to distribute the load.

    Use hand gloves. Rotate crewwhile using vibrators.Use well maintained equipment.The truck mounted concretepumps must be treated as liftingequipment and all safety rules andregulations are applicable to it aswould be for a crane.

    Only essential personnel shall beinvolved in the pumping operation

    1

    1

    3

    3

    3

    3

    THE BAHRAIN PETROLEUM COMPANY B.S.C. (CLOSED)

    WASTE WATER TREATMENT PLANT PROJECT (WWTPP) BAPCO Doc. No.: 052046 Revision: B

    RISK ASSESSMENT FOR

    Demolition & making of new pump foundation spentcaustic tank area

    Doc. No.: 100210-HSE-RA- 043Page 18 of 26

  • 7/27/2019 RISK ASSESSMENT Demolation and Making of New Pump Foundation B

    19/33

    WASTE WATER TREATEMENT PROJECTHazard Identification, Risk Assessment & Risk Control Register

    RISK ASSESSMENT FORDemolition & making of new pump foundation spent caustictank

    Sl. No Process

    Activity

    Potential

    HazardsRisk Involved

    INITIAL

    Risk Control Measure

    RESIDUAL

    Probability

    1-5

    Severity

    1-5

    RiskLevel

    1-25 P

    robability

    1-5

    Severity

    1-5

    RiskLevel

    1-25

    crew members shall not standunder the direct flow of concretebeing pumped. Note: manyinjuries are caused when the pumpboom is shifted from one locationto another due to residual concretein the line.Use a rope securely tied to thepump delivery hose to direct theflow of concrete.Rotate the crew when continuousconcrete pouring is carried out.

    All chemicals use d in the processmust be accompanied with the

    THE BAHRAIN PETROLEUM COMPANY B.S.C. (CLOSED)

    WASTE WATER TREATMENT PLANT PROJECT (WWTPP) BAPCO Doc. No.: 052046 Revision: B

    RISK ASSESSMENT FOR

    Demolition & making of new pump foundation spentcaustic tank area

    Doc. No.: 100210-HSE-RA- 043Page 19 of 26

  • 7/27/2019 RISK ASSESSMENT Demolation and Making of New Pump Foundation B

    20/33

    WASTE WATER TREATEMENT PROJECTHazard Identification, Risk Assessment & Risk Control Register

    RISK ASSESSMENT FORDemolition & making of new pump foundation spent caustictank

    Sl. No Process

    Activity

    Potential

    HazardsRisk Involved

    INITIAL

    Risk Control Measure

    RESIDUAL

    Probability

    1-5

    Severity

    1-5

    RiskLevel

    1-25 P

    robability

    1-5

    Severity

    1-5

    RiskLevel

    1-25

    Movement ofheavy vehicle

    Collision 3 4 12

    material safety data sheet and alladditional precautions must betaken as per the in formationsprovided within. Proper PPE shallbe used as required.

    All heavy vehicles shall be driveslowly in the construction are andfollow the rules of clients exit andentry routes.

    All equipment shall maintain a safedistance from each other or from

    any excavation.A banks man shall signal the

    1 2 2

    THE BAHRAIN PETROLEUM COMPANY B.S.C. (CLOSED)

    WASTE WATER TREATMENT PLANT PROJECT (WWTPP) BAPCO Doc. No.: 052046 Revision: B

    RISK ASSESSMENT FOR

    Demolition & making of new pump foundation spentcaustic tank area

    Doc. No.: 100210-HSE-RA- 043Page 20 of 26

  • 7/27/2019 RISK ASSESSMENT Demolation and Making of New Pump Foundation B

    21/33

    WASTE WATER TREATEMENT PROJECTHazard Identification, Risk Assessment & Risk Control Register

    RISK ASSESSMENT FORDemolition & making of new pump foundation spent caustictank

    Sl. No Process

    Activity

    Potential

    HazardsRisk Involved

    INITIAL

    Risk Control Measure

    RESIDUAL

    Probability

    1-5

    Severity

    1-5

    RiskLevel

    1-25 P

    robability

    1-5

    Severity

    1-5

    RiskLevel

    1-25

    heavy trucks to and for the pouringarea. All proper warning lights andhorns shall be used whileoperating the plant and equipment.

    05. Removal of shuttering(Dismantling)

    Pinch point injury 3 3 9 Maintain correct body positioning.Always give extra attention whileremoval of shuttering.Hold only on safe areas ofshuttering to avoid hand injury.

    1 3 3

    THE BAHRAIN PETROLEUM COMPANY B.S.C. (CLOSED)

    WASTE WATER TREATMENT PLANT PROJECT (WWTPP) BAPCO Doc. No.: 052046 Revision: B

    RISK ASSESSMENT FOR

    Demolition & making of new pump foundation spentcaustic tank area

    Doc. No.: 100210-HSE-RA- 043Page 21 of 26

  • 7/27/2019 RISK ASSESSMENT Demolation and Making of New Pump Foundation B

    22/33

    WASTE WATER TREATEMENT PROJECTHazard Identification, Risk Assessment & Risk Control Register

    RISK ASSESSMENT FORDemolition & making of new pump foundation spent caustictank

    Sl. No Process

    Activity

    Potential

    HazardsRisk Involved

    INITIAL

    Risk Control Measure

    RESIDUAL

    Probability

    1-5

    Severity

    1-5

    RiskLevel

    1-25 P

    robability

    1-5

    Severity

    1-5

    RiskLevel

    1-25

    06. Back Fillingand compactionaroundfoundation area

    Use of compactor Injury 3 3 9 Use inspected and well maintainedcompactors.Trained and capable person tooperate Jumping or roller compactor.The compactor shall be in neutralwhile starting to avoid unexpectedmovement.Dont leave the compactor runningwithout operator.

    Operator and crew shall wear

    hearing protection while operatingcompactors.

    1 3 3

    THE BAHRAIN PETROLEUM COMPANY B.S.C. (CLOSED)

    WASTE WATER TREATMENT PLANT PROJECT (WWTPP) BAPCO Doc. No.: 052046 Revision: B

    RISK ASSESSMENT FOR

    Demolition & making of new pump foundation spentcaustic tank area

    Doc. No.: 100210-HSE-RA- 043Page 22 of 26

  • 7/27/2019 RISK ASSESSMENT Demolation and Making of New Pump Foundation B

    23/33

    WASTE WATER TREATEMENT PROJECTHazard Identification, Risk Assessment & Risk Control Register

    RISK ASSESSMENT FORDemolition & making of new pump foundation spent caustictank

    Sl. No Process

    Activity

    Potential

    HazardsRisk Involved

    INITIAL

    Risk Control Measure

    RESIDUAL

    Probability

    1-5

    Severity

    1-5

    RiskLevel

    1-25 P

    robability

    1-5

    Severity

    1-5

    RiskLevel

    1-25

    Wear appropriate PPE.

    07. ManualHandling

    Frequent, Forcedor AwkwardMovement of thebody

    Back Injuries,Severe pains inthe hands, wrist,arm or neck

    3 3 9 Install anchor points and usemechanical devices like pulleyblocks, etc to minimize manualload on crewUse correct lifting technique toavoid any strain on the back; donot lift a load if you doubt its weight

    or adequacy of the equipment.Ensure there are enough crew

    1 3 3

    THE BAHRAIN PETROLEUM COMPANY B.S.C. (CLOSED)

    WASTE WATER TREATMENT PLANT PROJECT (WWTPP) BAPCO Doc. No.: 052046 Revision: B

    RISK ASSESSMENT FOR

    Demolition & making of new pump foundation spentcaustic tank area

    Doc. No.: 100210-HSE-RA- 043Page 23 of 26

  • 7/27/2019 RISK ASSESSMENT Demolation and Making of New Pump Foundation B

    24/33

    WASTE WATER TREATEMENT PROJECTHazard Identification, Risk Assessment & Risk Control Register

    RISK ASSESSMENT FORDemolition & making of new pump foundation spent caustictank

    Sl. No Process

    Activity

    Potential

    HazardsRisk Involved

    INITIAL

    Risk Control Measure

    RESIDUAL

    Probability

    1-5

    Severity

    1-5

    RiskLevel

    1-25 P

    robability

    1-5

    Severity

    1-5

    RiskLevel

    1-25

    members before lifting the load.

    Use the following technique whilelifting manually:Check for any obstructions beforelifting.Check out the area where the loadwill be placed before lifting theload.Place feet apart, leading legforward.Bend your legs and not your back

    to lift any load.Keep a firm grip and keep load as

    THE BAHRAIN PETROLEUM COMPANY B.S.C. (CLOSED)

    WASTE WATER TREATMENT PLANT PROJECT (WWTPP) BAPCO Doc. No.: 052046 Revision: B

    RISK ASSESSMENT FOR

    Demolition & making of new pump foundation spentcaustic tank area

    Doc. No.: 100210-HSE-RA- 043Page 24 of 26

  • 7/27/2019 RISK ASSESSMENT Demolation and Making of New Pump Foundation B

    25/33

    WASTE WATER TREATEMENT PROJECTHazard Identification, Risk Assessment & Risk Control Register

    RISK ASSESSMENT FORDemolition & making of new pump foundation spent caustictank

    Sl. No Process

    Activity

    Potential

    HazardsRisk Involved

    INITIAL

    Risk Control Measure

    RESIDUAL

    Probability

    1-5

    Severity

    1-5

    RiskLevel

    1-25 P

    robability

    1-5

    Severity

    1-5

    RiskLevel

    1-25

    close to the body.Dont jerk or make any awkwardmovements.Keep the load down and thenadjust as necessary.

    08 Lifting & Rigging Failure of SlingsLifting gear.

    Failure of wireropes. Hydraulicsystem

    Injury to crewDamage to plantand equipment

    Injury to crew,Damage to plantand equipment

    4

    3

    3

    3

    12

    12

    Rigging study must be done priorto lifting activityUse only certified and competentqualified personnel.Use inspected and tagged cables,slings, and shackles (lifting gear).Color codedPlace warning signs and barricadethe area off limits.

    1

    1

    3

    3

    3

    3

    THE BAHRAIN PETROLEUM COMPANY B.S.C. (CLOSED)

    WASTE WATER TREATMENT PLANT PROJECT (WWTPP) BAPCO Doc. No.: 052046 Revision: B

    RISK ASSESSMENT FOR

    Demolition & making of new pump foundation spentcaustic tank area

    Doc. No.: 100210-HSE-RA- 043Page 25 of 26

  • 7/27/2019 RISK ASSESSMENT Demolation and Making of New Pump Foundation B

    26/33

    WASTE WATER TREATEMENT PROJECTHazard Identification, Risk Assessment & Risk Control Register

    RISK ASSESSMENT FORDemolition & making of new pump foundation spent caustictank

    Sl. No Process

    Activity

    Potential

    HazardsRisk Involved

    INITIAL

    Risk Control Measure

    RESIDUAL

    Probability

    1-5

    Severity

    1-5

    RiskLevel

    1-25 P

    robability

    1-5

    Severity

    1-5

    RiskLevel

    1-25

    Unstable erection

    Insecure loadduring lifting

    Injury to crewDamage to plantand equipment

    Injuries, damage toplant and

    4

    4

    3

    3

    12

    12

    Check the working load and type ofsling required.

    All cranes and Boom trucks will

    have their load test certificates and

    Client approval certificates as

    necessary. (All certificates must be

    kept in the operators cabin).

    Conduct visual inspections beforeand after operations.Carry out periodical maintenance.

    Only a competent person shallcarry out maintenance.

    1

    1

    3

    3

    3

    3

    THE BAHRAIN PETROLEUM COMPANY B.S.C. (CLOSED)

    WASTE WATER TREATMENT PLANT PROJECT (WWTPP) BAPCO Doc. No.: 052046 Revision: B

    RISK ASSESSMENT FOR

    Demolition & making of new pump foundation spentcaustic tank area

    Doc. No.: 100210-HSE-RA- 043Page 26 of 26

  • 7/27/2019 RISK ASSESSMENT Demolation and Making of New Pump Foundation B

    27/33

    WASTE WATER TREATEMENT PROJECTHazard Identification, Risk Assessment & Risk Control Register

    RISK ASSESSMENT FORDemolition & making of new pump foundation spent caustictank

    Sl. No Process

    Activity

    Potential

    HazardsRisk Involved

    INITIAL

    Risk Control Measure

    RESIDUAL

    Probability

    1-5

    Severity

    1-5

    RiskLevel

    1-25 P

    robability

    1-5

    Severity

    1-5

    RiskLevel

    1-25

    operations

    Incorrect operation

    equipment

    Damage to plant,equipment, injuries

    3 3 9

    Dont lift during heavy windconditions.Lift or lower a load slowly withoutany sudden acceleration or suddenstopping.Ensure outriggers fully extended,the ground is compacted, and levelsurface is firm. Always useblocking under outrigger pad.

    Check for any unsecured materialson the load to be lifted.

    Make sure the load is properlyattached to the lifting equipment

    1 3 3

    THE BAHRAIN PETROLEUM COMPANY B.S.C. (CLOSED)

    WASTE WATER TREATMENT PLANT PROJECT (WWTPP) BAPCO Doc. No.: 052046 Revision: B

    RISK ASSESSMENT FOR

    Demolition & making of new pump foundation spentcaustic tank area

    Doc. No.: 100210-HSE-RA- 043Page 27 of 26

  • 7/27/2019 RISK ASSESSMENT Demolation and Making of New Pump Foundation B

    28/33

    WASTE WATER TREATEMENT PROJECTHazard Identification, Risk Assessment & Risk Control Register

    RISK ASSESSMENT FORDemolition & making of new pump foundation spent caustictank

    Sl. No Process

    Activity

    Potential

    HazardsRisk Involved

    INITIAL

    Risk Control Measure

    RESIDUAL

    Probability

    1-5

    Severity

    1-5

    RiskLevel

    1-25 P

    robability

    1-5

    Severity

    1-5

    RiskLevel

    1-25

    Overhead andundergroundservices

    Damage to plant,equipment, highinjuries

    4 3 12 and there is a guideline attached toload.Never pound the slings understress and never force the chokedsling eye down close to the load.Check for the stability of the loadas soon as it is lifted. If there is avariation more than 5 degree thenthe load is not balanced and the liftmust be stopped.Never pull or tug a load, Cranesare used only to lift a load. Lift or

    lower a load slowly without anysudden acceleration or sudden

    1 3 3

    THE BAHRAIN PETROLEUM COMPANY B.S.C. (CLOSED)

    WASTE WATER TREATMENT PLANT PROJECT (WWTPP) BAPCO Doc. No.: 052046 Revision: B

    RISK ASSESSMENT FOR

    Demolition & making of new pump foundation spentcaustic tank area

    Doc. No.: 100210-HSE-RA- 043Page 28 of 26

  • 7/27/2019 RISK ASSESSMENT Demolation and Making of New Pump Foundation B

    29/33

    WASTE WATER TREATEMENT PROJECTHazard Identification, Risk Assessment & Risk Control Register

    RISK ASSESSMENT FORDemolition & making of new pump foundation spent caustictank

    Sl. No Process

    Activity

    Potential

    HazardsRisk Involved

    INITIAL

    Risk Control Measure

    RESIDUAL

    Probability

    1-5

    Severity

    1-5

    RiskLevel

    1-25 P

    robability

    1-5

    Severity

    1-5

    RiskLevel

    1-25

    stopping.Swing a load slowly as a rapidswing causes side loading and cancause the load to swing out.Cranes should keep safe distancefrom each other and from livefacilities.Operator should not leave thecabin with suspended load.

    All lifting equipment shall maintainsafe distance while operating nearservice lines. Cranes shall not be

    erected near or on any buriedservice line.

    THE BAHRAIN PETROLEUM COMPANY B.S.C. (CLOSED)

    WASTE WATER TREATMENT PLANT PROJECT (WWTPP) BAPCO Doc. No.: 052046 Revision: B

    RISK ASSESSMENT FOR

    Demolition & making of new pump foundation spentcaustic tank area

    Doc. No.: 100210-HSE-RA- 043Page 29 of 26

  • 7/27/2019 RISK ASSESSMENT Demolation and Making of New Pump Foundation B

    30/33

    WASTE WATER TREATEMENT PROJECTHazard Identification, Risk Assessment & Risk Control Register

    RISK ASSESSMENT FORDemolition & making of new pump foundation spent caustictank

    Sl. No Process

    Activity

    Potential

    HazardsRisk Involved

    INITIAL

    Risk Control Measure

    RESIDUAL

    Probability

    1-5

    Severity

    1-5

    RiskLevel

    1-25 P

    robability

    1-5

    Severity

    1-5

    RiskLevel

    1-25

    Operator shall ensure that theboom/ hook is not traveling nearany overhead service lines.

    Correct sling length shall be used

    so that the minimum operating

    level of the boom shall be

    maintained.In case of any emergency, theequipment shall be switched off.The operator shall leave hisoperating cabin only after the

    service line has been isolated andconfirmed by service operators.

    THE BAHRAIN PETROLEUM COMPANY B.S.C. (CLOSED)

    WASTE WATER TREATMENT PLANT PROJECT (WWTPP) BAPCO Doc. No.: 052046 Revision: B

    RISK ASSESSMENT FOR

    Demolition & making of new pump foundation spentcaustic tank area

    Doc. No.: 100210-HSE-RA- 043Page 30 of 26

  • 7/27/2019 RISK ASSESSMENT Demolation and Making of New Pump Foundation B

    31/33

    WASTE WATER TREATEMENT PROJECTHazard Identification, Risk Assessment & Risk Control Register

    RISK ASSESSMENT FORDemolition & making of new pump foundation spent caustictank

    Notes:

    1. Full time Safety and Supervisory coverage shall be ensured at site.

    2. All the required permits shall be obtained before starting the job.

    3. All issued work permits and copies of Risk Assessment shall be kept in a Permit Box at site.

    4. The Supervisor shall conduct Tool Box Talk & explain the risks and control measures to all crew members.

    5. Before leaving the work site on completion of each days work, the area shall be checked for proper house-keeping, elimination of all

    possible sources of fire, shutdown of all construction equipment, proper storage of tools and tackles etc

    6. All employees must know the emergency procedures of BAPCO /GS

    7. Attendance sheet of Toolbox Talk shall be available for audit; subsequently it must be submitted to GS.

    8. Provide portable toilet, proper barricading of the work area with signage.

    9. Cool down shelter and drinking water shall be available at site.

    10. Ensure the work / resting area, shall be kept neat and clean and all rubbish is put into the waste and shall be disposed on regular

    basis.

    THE BAHRAIN PETROLEUM COMPANY B.S.C. (CLOSED)

    WASTE WATER TREATMENT PLANT PROJECT (WWTPP) BAPCO Doc. No.: 052046 Revision: B

    RISK ASSESSMENT FOR

    Demolition & making of new pump foundation spentcaustic tank area

    Doc. No.: 100210-HSE-RA- 043Page 31 of 26

  • 7/27/2019 RISK ASSESSMENT Demolation and Making of New Pump Foundation B

    32/33

    WASTE WATER TREATEMENT PROJECTHazard Identification, Risk Assessment & Risk Control Register

    RISK ASSESSMENT FORDemolition & making of new pump foundation spent caustictank

    Prepared By Approved By Approved By Approved By

    Waseem Tanoli Paul Edward C.G. Sudhakaran

    Site HSE Officer GS E&C Civil HSE Manager F H&S Specialist

    MCSC GS E&C GS E&C BAPC

    THE BAHRAIN PETROLEUM COMPANY B.S.C. (CLOSED)

    WASTE WATER TREATMENT PLANT PROJECT (WWTPP) BAPCO Doc. No.: 052046 Revision: B

    RISK ASSESSMENT FOR

    Demolition & making of new pump foundation spentcaustic tank area

    Doc. No.: 100210-HSE-RA- 043Page 32 of 26