Risk Category Cause Risk Effect Project Management The Unique hardware is a new development They may not be delivered on time Forcing schedule delay and potential deviation from design control approach A Site during Erection or Construction Improper or inadequate soil assessment May result in unplanned sub-soil standard Causing a delay in the commencement of construction and re-planning required for construction Planning Lack of proper planning and coordination between the home and site office May result in equipment already dispatched from the sub-supplier’s works, with access to the site not properly established Causing a delay in the equipment reaching the site and consequently causing project schedule slippage Faulty Planning May result in the out-of-sequence receipt of materials at the site Leading to a delay in the site project schedule Faulty Planning Political Pressure Local politicos, unruly elements, etc. May cause access to site to be denied or challenged Resulting in delay in the start of construction, leading to slippage in the project schedule Improper packing and handling May cause damage during storage Resulting in breakage of equipment, necessitating repair or replacement Security Improper provision of May result in theft Causing a time and cost increase for

Upload: tauseefkhan

Post on 11-Nov-2015

3 views

Category:

Documents


0 download

DESCRIPTION

risk

TRANSCRIPT

Risk CategoryCauseRiskEffect

Project ManagementThe Unique hardware is a new developmentThey may not be delivered on timeForcing schedule delay and potential deviation from design control approach

A Site during Erection or ConstructionImproper or inadequate soil assessmentMay result in unplanned sub-soil standardCausing a delay in the commencement of construction and re-planning required for construction

PlanningLack of proper planning and coordination between the home and site officeMay result in equipment already dispatched from the sub-suppliers works, with access to the site not properly established Causing a delay in the equipment reaching the site and consequently causing project schedule slippage

Faulty PlanningMay result in the out-of-sequence receipt of materials at the siteLeading to a delay in the site project schedule

Faulty Planning

Political PressureLocal politicos, unruly elements, etc.May cause access to site to be denied or challenged

Resulting in delay in the start of construction, leading to slippage in the project schedule

Improper packing and handlingMay cause damage during storageResulting in breakage of equipment, necessitating repair or replacement

SecurityImproper provision of security at siteMay result in theftCausing a time and cost increase for the project

DesignImproper engineering design discovered during the construction of the main deckMay cause design problems and errors such as equipment out of dimension and not fitting rightResulting in the work needing to be down, generating additional risks as well as cost

HRUntrained or improperly trained workforce/ unskilled workersMay lead to defective workmanshipResulting in rework

SupplierThe inefficiency of the supplierMay cause payment disputes between supplier and his employeesLeading to a delay in the project schedule

ContractMisinterpretation of the contractMay cause a delay due to the dispute between the client and the customer regarding paymentLeading to a delay in the project implementation

CommunicationCommunication problems between the home and site officesMay result in non-receipt of design drawingsLeading to a slip in the project schedule