Risk Factors for PPP: the Case of HZMB Project in GPRD Metropolitan. Yao Yi, Associate Professor Guangzhou Academy of Social Sciences, China. HZMB Background. Hongkong-Zhuhai-Macao Bridge. PPP Development in China. - PowerPoint PPT PresentationTRANSCRIPT
![Page 1: Risk Factors for PPP: the Case of HZMB Project in GPRD Metropolitan](https://reader030.vdocument.in/reader030/viewer/2022032607/56812fd4550346895d954f3d/html5/thumbnails/1.jpg)
Risk Factors for PPP: the Case of HZMB Project in GPRD Metropolitan
Risk Factors for PPP: the Case of HZMB Project in GPRD Metropolitan
Yao Yi, Associate ProfessorGuangzhou Academy of Social Sciences, China
![Page 2: Risk Factors for PPP: the Case of HZMB Project in GPRD Metropolitan](https://reader030.vdocument.in/reader030/viewer/2022032607/56812fd4550346895d954f3d/html5/thumbnails/2.jpg)
HZMB Background
Hongkong-Zhuhai-Macao Bridge
![Page 3: Risk Factors for PPP: the Case of HZMB Project in GPRD Metropolitan](https://reader030.vdocument.in/reader030/viewer/2022032607/56812fd4550346895d954f3d/html5/thumbnails/3.jpg)
![Page 4: Risk Factors for PPP: the Case of HZMB Project in GPRD Metropolitan](https://reader030.vdocument.in/reader030/viewer/2022032607/56812fd4550346895d954f3d/html5/thumbnails/4.jpg)
![Page 5: Risk Factors for PPP: the Case of HZMB Project in GPRD Metropolitan](https://reader030.vdocument.in/reader030/viewer/2022032607/56812fd4550346895d954f3d/html5/thumbnails/5.jpg)
PPP Development in China
• Shajiao Thermal Plant, Shenzhen, 1988• Labin Power Plant, Guangxi, 1995
• National Olympic Stadium, 2003•Beijing Subway No.4 Line, 2005
First Round
Second Round
• No PPP national law or regulation• No PPP control organization Legal FrameworkLegal Framework
![Page 6: Risk Factors for PPP: the Case of HZMB Project in GPRD Metropolitan](https://reader030.vdocument.in/reader030/viewer/2022032607/56812fd4550346895d954f3d/html5/thumbnails/6.jpg)
Financing HZMB
Early 2008
End 2008
1990s
Estimated:
$ 2 billion
Funding Scheme by GD, HK, Macao:
Bridge: $6.3 billion
Overall: $9 billion
COST: Keep Rising
Feasibility Report:
Overall: $11 billion
Feasibility Report:
Overall: $11 billion
![Page 7: Risk Factors for PPP: the Case of HZMB Project in GPRD Metropolitan](https://reader030.vdocument.in/reader030/viewer/2022032607/56812fd4550346895d954f3d/html5/thumbnails/7.jpg)
Funding Model: from BOT to Government Funding
BOT Model
Early 2008:
Private investorGovernment subsidy
Government Funding
End of 2008:
Government capital fund bank loans
![Page 8: Risk Factors for PPP: the Case of HZMB Project in GPRD Metropolitan](https://reader030.vdocument.in/reader030/viewer/2022032607/56812fd4550346895d954f3d/html5/thumbnails/8.jpg)
Stake Holders:
Government 1
Private sector2
public3
![Page 9: Risk Factors for PPP: the Case of HZMB Project in GPRD Metropolitan](https://reader030.vdocument.in/reader030/viewer/2022032607/56812fd4550346895d954f3d/html5/thumbnails/9.jpg)
Stake Holders:
Government
![Page 10: Risk Factors for PPP: the Case of HZMB Project in GPRD Metropolitan](https://reader030.vdocument.in/reader030/viewer/2022032607/56812fd4550346895d954f3d/html5/thumbnails/10.jpg)
Stake Holders:
Private sector: Attitude: active→ less interested
Interests: profit prospect diminished
Public opposition: law case in 2010,
1 year delay & 5% cost rise
![Page 11: Risk Factors for PPP: the Case of HZMB Project in GPRD Metropolitan](https://reader030.vdocument.in/reader030/viewer/2022032607/56812fd4550346895d954f3d/html5/thumbnails/11.jpg)
Barriers for PPP in HZMB Case
Huge investment vs. Low market return
Legal constraints
Project coordination
![Page 12: Risk Factors for PPP: the Case of HZMB Project in GPRD Metropolitan](https://reader030.vdocument.in/reader030/viewer/2022032607/56812fd4550346895d954f3d/html5/thumbnails/12.jpg)
Conclusion: Risk Factors for PPP
Market return risk
Public opposition
Lengthy decision-making process
Loss of project uniqueness
RISK