  • 8/12/2019 Risk Profile Redesigned

    1/31

  • 8/12/2019 Risk Profile Redesigned

    2/31

    Environmental IssuesDelay in completion of:

    Dry ash evacuation system

    Effluent Disposal SystemAmbient air Quality

    Reasons:

    Delay in material supply

    Non performance by agency

  • 8/12/2019 Risk Profile Redesigned

    3/31

    Environmental IssuesAction for mitigation of risk:

    Direct procurement of critical material from Sub

    vendors, Intervention to get the agency to get work done

    through different working agencies at site,

    Continuous monitoring and follow up with agencies.

  • 8/12/2019 Risk Profile Redesigned

    4/31

    COAL SHORTAGEIssues with

    Coal Tie up and availability

    Coal UnloadingReasons

    Delays in development of linked mines

    Delay in Development of Indian Railway Network Delay in Development of Wagon Tippler

    commissioning

  • 8/12/2019 Risk Profile Redesigned

    5/31

    COAL SHORTAGEAction for mitigation of risk:

    Getting coal through E-auction

    Use of imported coal Outsourcing of mining operations

    Issue taken up at CM(Bihar) level for environmentalclearance

  • 8/12/2019 Risk Profile Redesigned

    6/31

    Water ShortageIssues with

    Raw water availability

    Reasons Delay in construction of Intake Well/Raw Water pump

    house

    Seasonal shortage of water

    Excessive siltation and change in river course

  • 8/12/2019 Risk Profile Redesigned

    7/31

    Water ShortageAction for mitigation of Risk

    Intake well sinking completed

    Raw water commissioning expected by June 15 Course of Ganga being controlled by Dredging

  • 8/12/2019 Risk Profile Redesigned

    8/31

    SCHEDULE GENERATIONIssues with

    Variable Charges, Merit Order

    Reasons Unavailability of coal from linked coal mine

    Site compelled to procure costly coal through e-auction

    Large distance from mines

  • 8/12/2019 Risk Profile Redesigned

    9/31

    SCHEDULE GENERATIONAction for mitigation of Risk

    Regular follow up for expediting the development of

    linked mines

    Regular follow up with railways for early completion oforiginal rail transportation route envisaged in FR.

  • 8/12/2019 Risk Profile Redesigned

    10/31

    Delay in execution by agenciesIssue

    Delay w.r.t L2 network

    Reasons

    Financial problems of agencies Inadequate mobilization by agency

    Shortage of skilled labor

    Law and order issues

  • 8/12/2019 Risk Profile Redesigned

    11/31

    Delay in execution by agencies

    Action for mitigation of risk

    Termination notice to be served to TPE

    Enlistment of vendors with proven track recordsAward of erection contract is planned after

    termination notice is served to TPE

    Training and recruitment of ITI graduates is being

    done.

  • 8/12/2019 Risk Profile Redesigned

    12/31

    RISK PROFILE OF

    NORTH KARANPURAPOWER PROJECT

  • 8/12/2019 Risk Profile Redesigned

    13/31

    Problem in Land Availability

    Reason Delay in finalization of R&R package

    Delay in physical possession of land

    Poor land record with state governmentAction for mitigation of risk

    Physical possession started with disbursement of R&Rcompensation and barricading by Chain link fencing

    of Main Plant

  • 8/12/2019 Risk Profile Redesigned

    14/31

    Problem in transporting materials to the site

    Reason Difficulty in receiving materials due to rail and road

    connectivity problem

    Action for mitigation of Risk

    RCD, Govt. of Jharkhand is entrusted toconstruct/strengthen road of 110 km and Rs 250 crs

    advance money deposited to RCD, GoJ.

  • 8/12/2019 Risk Profile Redesigned

    15/31

    Water Shortage expected

    Reason Delay in readiness of water system

    Action taken for mitigation of risk

    Govt. of Jharkhand is to construct the dam such thatwater is available by March 2017.

  • 8/12/2019 Risk Profile Redesigned

    16/31

    Delay in availability of Construction

    PowerSupply line to be constructed by DVC on deposit basis

    Reason for Delay

    Forest clearance is yet to be obtained by DVC Sub agency of DVC has raised certain claims due to

    delay which is under negotiation.

  • 8/12/2019 Risk Profile Redesigned

    17/31

    RISK PROFILE OFKAHALGAON

    STATION

  • 8/12/2019 Risk Profile Redesigned

    18/31

    Less efficiency w.r.t normative parameters

    Reasons:

    Frequent tripping due to backing down

    Higher Heat Rate

    Higher APC

    Action for mitigation of Risk Reduce Specific Oil Consumption by start up time

    reduction

    Activities like Oxygen Optimization, BFP catridge

    replacement, Flue gas duct repair and condenser waterbox cleaning being taken up to improve HR

  • 8/12/2019 Risk Profile Redesigned

    19/31

    Less efficiency w.r.t normative parameters

    Action for mitigation of Risk

    Coal feeding to bunkers through reclamation to avoidbunker choking

    Reduction of APC by improving utilization factor ofCHP, Stage I units Feed Regulating Stations.

    Differential Pressure optimization and ID fan margin

    improvement.

  • 8/12/2019 Risk Profile Redesigned

    20/31

    Lower PLFReasons

    High partial loading due to equipment problem

    Coal shortage

    Lower merit order

  • 8/12/2019 Risk Profile Redesigned

    21/31

    Lower PLF

    Action for mitigation of risk Preventive and predictive maintenance planning

    More coal being lifted with proactive persuasion with

    CIL Optimization of ECR by discouraging high specific

    cost coal, use of MGR/RJ coal with restricted blending,raniganj coal of G6 grade to be preferred instead of

    G5/G4/G3 coal as there is steep rise in price.

  • 8/12/2019 Risk Profile Redesigned

    22/31

    Under recovery of O&M Charges

    Reasons

    Higher repair and maintenance cost

    Higher employee cost excluding PRP

    Higher CC expenses

  • 8/12/2019 Risk Profile Redesigned

    23/31

    ANNEXURE II

    DESCRIPTION2012-13 2013-14

    MOU Actual MOU Actual Variation Reason for Deviation

    EMPLOYEE COST 14519 16203 15423 19400 -3977

    Increase in 44 No. of employees,resulting in increase in Sal

    & wages by Rs. 4.6 crs. Increase in winter Liveries &

    uniform exps by Rs. 1.78 crs, Contribution to Pension

    Scheme Rs.28.41crs.Increase in medical exps Rs.1.27crs.

    REPAIRS &

    MAINT.12707 17089 14751 17943 -3192

    1.BMD: Matls.Rs.1510 lakh:-

    A). Higher consumption of mill spares due to poor quality

    of coal- excess consm.Rs. 1420 Lakh. B). St-I APH tubes:

    Excess consm: Rs.40 Lakh. C). Coal Feeder#6G: Rs.50Lakh.

    2. CHP: Rs. 830 lakh :-

    A). Excess Matls. Cost: Rs.718 Lakh mainly due to

    conv.belts (Rs.550 Lakh, B). Increased services cost: Rs.

    112 lakh.

    3. O&M-CIVIL: Rs. 240 Lakh:- Excess Expenditure due to

    A).Construction of peripheral road from gate no.1 to

    Ekchari gate, B).Paving & Gravelling works for SWYD,C).Roller compacted road from Ekchari gate to Koa nala

    bridge, D).Water-proofing treatment of Admn. Bldg.,

    Canteen bldg., Auditorium roofs, E).FRP Lining in DM Plant,

    F).Checking, testing and repairing of St-II coal bunkers,

    G).Development of Dry ash silo area st-II.

    Detail of BREAK up of O&M Cost

    Detail of BREAK up of O&M Cost ANNEXURE II

  • 8/12/2019 Risk Profile Redesigned

    24/31

    DESCRIPTION 2012-13 2013-14

    MOU Actual MOU ACTUAL Variation

    REPAIRS &

    MAINT.12707 17089 14751 17943 -3192

    4. MGR: Rs 258 Lakh:- i). Excess cost of Loco

    overhauling Rs.125 Lakh, ii). PSC sleepers: Rs.54

    Lakh, iii).Left & right turn out sets : Rs. 60 Lakh

    returned to RITES against past loan, iv). Additional

    job: Trip inspection for RJA rakes: Rs. 19 Lakh.

    5. Ash Brick Manufacturing : Rs 140 Lakh

    6. Dry Ash System Maint. : Rs 120 Lakh

    7. Township : Rs 90 Lakh;- i). Ash /earth filling near

    stadium-Rs.60Lakh, ii). Painting of schools & various

    bldgs. Rs.30 Lakh.

    STATION

    OVERHEAD6509 6960 7215 6948 267

    Total 33735 40252 37389 44292 -6903

    Detail of BREAK up of O&M Cost ANNEXURE II

  • 8/12/2019 Risk Profile Redesigned

    25/31

    Problem in Scheduling of Power

    Reasons Lower merit order

    Action for mitigation of risk

    Efforts being made to reduce ECR by blending, andusing different coal bunkers at different TOD,improving HR/APC/SOC.

  • 8/12/2019 Risk Profile Redesigned

    26/31

    Environmental Problems

    Issues Emission high

    Problem in Ash Utilization

    Reasons

    Design inadequacy of ESP/AGFC

    Less Ash utilization due to location constraints

  • 8/12/2019 Risk Profile Redesigned

    27/31

    Environmental Problems

    Action for mitigation of risk

    Permanent flue gas conditioning system has beeninstalled in U#1 & U#4. For U#2 & U#3 installationwork is under progress

    ESP parameters recorded and corrective actions arebeing taken for deviations

    Checks during O/H:

    Action for mitigation of risk(Ash Utilization initiatives)

  • 8/12/2019 Risk Profile Redesigned

    28/31

    Action for mitigation of risk(Ash Utilization initiatives)

    Initiatives for Fly ash Brick Sector: Presently 25 parties lifting 18000 MT/month of f ly ash from ash silo in free of cost

    for use in Fly ash brick manufacturing against only one party in last year. Fly ash is being issued within 14 days in every case after submission of application

    with proper documents. 25 more parties/persons applied for fly ash in this regard are in pipeline in

    different stage Application format and procedure is made available in BSPCB site for more

    accessibility. Initiatives for Clay ash Brick Sector A Demonstration project for ash utilization in clay-ash brick manufacturing has

    been organized to raise confidence among brick manufacturers for use of ash inbrick manufacturing and to popularise the clay ash brick in place of clay brick. Workshops for Brick kiln owners/ ash brick manufacturers for using ash in

    brick manufacturing. 15000 MT pond Ash is being transported on free of cost to Brick klin.

    Other Initiatives for Maximizing Ash Utilization Dedicated Road for ash transportation is constructed from NTPC gate to

    Ekchari, bypassing Kahalgaon town from May-2013. Wind breaking wall has been constructed and water sprinkling is being done

    on regular basis at Kahalgaon railway siding. Ash transportation in Jumbo bags directly by railway successfully done on

    12.09.2013 on trial basis and now it is streamlined. It is being done by oneparty, Railway is being contacted for other parties. This process iseconomical and environment friendly

    Ash Utilization through low land filling for public utility land, compilation is

    in advance stage. First phase quantity will be 2.5LMT.

  • 8/12/2019 Risk Profile Redesigned

    29/31

    Safety and Security problem

    Reason

    Problem in implementation of safety norms

    Problem in security of installationsof stations

    Action being taken for mitigation of risk Cases investigated, recommendations discussed in

    daily meeting.

    Awareness training programs

    Site visits to check safety norms

  • 8/12/2019 Risk Profile Redesigned

    30/31

    Availability of Ash DykeIssues

    Availability of Land Space

    Inadequate ash utilization

    High Ash Content

    ReasonsWork in Lagoon III D not started due to Local

    Resistance

    Capacity of Lagoon III A/B and C very low

    High Ash Content in Lalmatia coal

  • 8/12/2019 Risk Profile Redesigned

    31/31

    Availability of Ash DykeAction for mitigation of risk

    Possibilities for buttressing is being explored forLagoon II

    Matter of Local resistance taken with Local

    Administration Dry ash extraction system for Unit# 3 & 4 to be

    tendered. Cost estimation under revison.