river mile 10.9 removal action overview - passaic riverpassaic.sharepointspace.com/public...
TRANSCRIPT
November 13, 2014 CAG Meeting
1
River Mile 10.9 Removal Action Overview River Mile 10.9 Removal Action Overview River Mile 10.9 Removal Action Overview River Mile 10.9 Removal Action Overview
Modified from CPG’s RM10.9 Removal Action Final Design Report dated Nov. 2013
River Mile 10.9 Removal Action Activities River Mile 10.9 Removal Action Activities River Mile 10.9 Removal Action Activities River Mile 10.9 Removal Action Activities
Dredging: Approx. 2 feet of contaminated sediment were removed.
Capping: A cap of approx. 2 feet was placed over the “post –dredge sediment.” The cap consisted of the following layers in ascending order:
• Active material/sand mixture was placed above the post-dredge sediment (remaining contaminated sediment) to prevent contaminants from migrating to the surface of the cap.
• Geotextile was placed over the active material/sand mixture. The geotextile is a fabric layer that keeps the active layer/sand mixture in place and prevents penetration by the armor stones.
• Armor stones, the sizes of which were determined by an engineer, were placed over the geotextile. Placement of the stones happened after the geotextile panels were placed.
• Sand (habitat layer) was placed over the armor stones to fill in voids to help reestablish the mudflat ecosystem. 2
August 17, 2013 August 28, 2013
August 7, 2013 to October 4, 2013: Dredging operations conductedApproximately 2 feet of contaminated sediments were removed.
3
November 13, 2013 – A telebelt (device to convey
material from barge) is depositing the active
material/sand mixture over the post dredge sediment.
November 15, 2013 – Photo shows an area where
active material/sand mixture had been placed.
November to December 2013: Active Material/Sand Mixture Placement
Approximately 10 inches of active material/sand mixture placed over post dredge sediment
4
March 15, 2014
Left Photo: geotextile panel being placed
near the fire deptartment boat launch
Right Photo: armor stone placement
overlying the newly placed down geotextile
panel. CPG’s contractor can be seen trimming
the extra geotextile.
March 2014: Placement of geotextile and armor stone
Geotextile: fabric layer used to keep the
active layer/sand mixture in place and to
prevent penetration.
Armor stones: were placed after the
geotextile panels were laid down.
� Keeps the geotextile in place and also
helps to protect the underlying cap from
erosion due to high river flows and
propeller wash from recreational
boating.
5
April 14, 2014: Photo of armor stones over
recently-placed geotextile panel.
Two different types of armor stone are seen
in this photograph:
Type B (the smaller of the two stones
used) was used when the underlying
substrate was hard pan. Type B armor stones
were placed closer to shoreline where the
flow rate is expected to be lower (less
potential erosion).
Type A (the larger of the two stones used)
were determined by CPG’s engineer to
withstand a 100-year storm event.
April 2014: Placement of geotextile and armor stone
6Photograph taken in area south of “No Dredge Zone”
April 23, 2014
North of the “No Dredge Zone”
Mini excavator is in the background leveling out the
armor stone north of the “No Dredge Zone”
South of the “No Dredge Zone”
Type B stone can be seen here
Exposed geotextile panel is shown here as it extends
beyond the armor stones. When placing the geotextile
panel:
� CPG’s contractor laid the panels out flat to extend
approx. 5-15 feet off the vegetated shoreline,
anchoring it off the trees/brush until the armor stone
could be installed.
� Process resulted in approx. 5 feet excess geotextile in
places beyond where dredging/capping occurred
� CPG’s contractors then trimmed back the geotextile to
the edge of cap. Exposed geotextile is not a result of
erosion
April 2014: Placement of geotextile and armor stone continued
“No Dredge Zone” Area
South
North
7
May 8, 2014: Initial test run of sand being applied via a telebelt
over the armor stone. Area photographed is south of the “No
Dredge Zone.”
May 2014: Sand (habitat layer) placement beganSand layer was applied over the armor stones to fill in voids to help reestablish the mudflat ecosystem.
May 9, 2014: Photo of an area where one layer of sand was
initially applied.
8
May 12, 2014: Photo taken three days after the initial
placement of two sand layers (on May 9th).
May 2014: Sand (habitat layer) placement continued
May 9, 2014: Photo of sand layer 24 hours after initial
test. Two layers of sand have been placed.
9
May 27, 2014:
Background: The telebelt is conveying
first layer of sand in an area just south of
the fire department boat launch.
Foreground: An area that was covered in
the prior week.
The row of exposed armor stone in the
foreground is outside the dredge line and
was not slated to be covered by sand.
� Helps to anchor the extra geotextile
that extends beyond the area
dredged/capped.
� CPG’s contractor cut additional fabric
once the row of armor stone anchoring
the geotextile had been placed.
May 2014: Sand (habitat layer) placement continued
10
May 29, 2014: Photo taken while standing south of “No
Dredge Zone” looking north. The row of armor stone (acting
as an anchor) can be seen on the right side of the photo.
May 29, 2014: Photo taken from the southern most
cap/dredge location and looking north. The final cap
surface post installation can be seen here.
11
May 29, 2014: CPG started to demobilize from RM10.9
� Site visits with EPA, CPG and
members of the boating
community
� EPA and CPG discuss and plan for
an effort to address high spots of
armor stones. EPA and CPG
engage in discussions regarding
placement of buoy markers
� CPG and EPA identify areas of
elevated armor stones and CPG
takes coordinates of the
locations
Photo credit: Harvey Morginstin. Photograph titled “Lyndhurst LT June 24 2014 037.jpg”
and was provided to EPA on 6/24/2014 via email.
June 2014 - August 2014
12
September 2014
� CPG begins effort on Sept. 29th to
move high spots of armor stones
� EPA oversees this effort
September 29, 2014: CPG effort to move high spots of armor stones
13
CPG’s contractor removes high spots of armor stones in areas
closer to the channel. Area is south of “No Dredge Zone.”
Conditions prior to start of work. Row of armor stones anchoring
geotextile seen in foreground. A red buoy marker not placed by
CPG and EPA is seen. Also, a rower passing by.
14
September 30, 2014: CPG effort to move armor stones
CPG’s contractor continues to manually remove high spots of armor stones.
Based on observations that day, it was estimated that approximately 3-4 inches of sediment had accumulated above the sand layer. River level
at low tide was higher than anticipated. As such, work was scheduled to resume the following week.
15
October 6, 2014:
Last day of effort
Area near fire
department
boat launch
CPG’s contractor utilized a
tracked vehicle in effort to
remove armor stones in
area north of “No Dredge
Zone.”
CPG’s contractor manually removes
armor stones near channel in area north
of the “No Dredge Zone.”
16
RM10.9 site visits after CPG’s efforts to remove high spots of armor stones
November 4, 2014: Area north of “No Dredge Zone.” Row of
armor stones anchoring geotextile is in foreground. These stones
are outside the dredged/capped area, line almost the entire
length of the mudflat, and will remain as they help to anchor the
underlying geotextile layer.
October 8, 2014: Area south of “No Dredge Zone.”