road construction production output rates
DESCRIPTION
Production Rates for Road Construction Works including Equipment, Manpower, Materials Hauling, etc.)TRANSCRIPT
ESTIMATING GUIDELINE
I. MECHANIZED ASPECT
DOZER
(Horse Power)DENSE OF VEGETATION (No. of Trees per Hectares)
0~50 51~100 101~200 201~250 251 & >120 360 250 190 160 130140 420 290 220 185 150160 480 330 255 210 170180 540 375 285 240 195200 600 420 310 265 215
B.1 - CRANE
TONNAGESCanal Structure Creek
10~15 15 10 1015~20 25 15 1520~25 30 20 2025~30 35 25 25
B.2 - DOZER
Canal Structure120 30 10140 40 15160 50 20180 60 25200 70 30
B.3 - BACKHOE
Canal Structure Creek0.50 20 15 150.75 30 20 201.00 35 25 251.25 40 30 301.50 50 35 35
DOZER LOOSE EXCAVATED MATERIAL
(Horse Power) Common Aggregate Cobble/Boulder140 40 30 10 70160 50 40 15 80180 60 55 20 90200 75 70 25 100
BUCKET
Common Aggregate Couble/Boulder
A) CLEARING & GRUBBINGPRODUCTION (m2/hr)
B) EXCAVATION (COMMON MATERIALS)
CAPABILITY (m3/hr) BANK VOLUME
HORSEPOWER
PRODUCTION (m3/hr) BANK VOLUME)
BUCKET(m3)
PRODUCTION (m3/hr) BANK VOLUME)
C) QUARRYINGPRODUCTION (m3/hr) BANK VOLUME
(m3)
D) LOADINGPRODUCTION (m3/hr) BANK VOLUME
(m3)
1.0~1.5 70 80 301.5~2.0 100 110 402.0~2.5 130 140 502.5~3.0 150 160 60
GRADER(Horse Power) Common Aggregate
80~100 60 70100`125 70 80125~150 90 100150~175 100 110
DOZER(Horse Power)
80~100 35100~125 40125~150 45150~175 55
DOZER(Horse Power)
140 50160 70180 80200 90
DOZER(Horse Power) Vibratory Static
3~5 60 406~10 70 5011~15 80 60
4.00 10 min. 12 min. 15 min.6.00 12 min. 15 min. 17 min.8.00 17 min. 17 min. 20 min.
HAUL DIST. GOOD MAINTAINED POOR MAINTAINED(km) Loaded Unloaded Loaded UnloadedAll 30 kph 40 kph 25 kph 35 kph
(Note: Limit of Free Haul Distance is 200m)
E) SPREADINGPRODUCTION (m3/hr) COMPACTED VOLUME
F) SIDE BORROW (COMMON MATERIAL)
PRODUCTION (m3/hr) COMPACTED VOLUME
G) STRUCTURAL BACKFILL WITH COMPACTION
PRODUCTION (m3/hr) COMPACTED VOLUME
H) EMBANKMENT COMPACTIONPRODUCTION (m3/hr) COMPACTED VOLUME
I) LOADING, SPOT & MANEUVERING, UNLOADING & DELAY TIMEUsed Loader: 1.00m3 bucket
Dump Truck Capacity(m3)
Common Materials
Road Surfacing Materials
Cobbles / Boulders
J) AVERAGE SPEED OF DUMP TRUCK (km/hr)
EQUIPMENTMassive Concrete Slab & Wall
8.00 12.00
EQUIPMENTCAPACITY (m/hr)
Steel Piles Concrete Piles Thick & Thin Concrete Piles
20.00
2.00 4.00
K) DEMOLITION OF CONCRETECAPACITY (m3/day)
160cfm Compressor & 2-Pavement Breaker
L) DRIVING OF PILES
25 Tons Crane with 2 Tons Drop Hammer25 Tons Crane with
7500 kgs-m Pile Hammer
ESTIMATING GUIDELINE
II. MANUAL ASPECT
A.1 - COMMON MATERIAL
DEPTH OF EXCAVATION1.5m 1.6~2.5m 2.6m+
Farm Ditch 3.00 - -Canal 2.50 2.00 1.75Structure 2.00 1.75 1.50Desilting 2.50 2.00 1.75
A.2 - SLIGHTLY HARD MATERIAL
BANK VOLUMECanal 1.00Structure 0.75
Sand & Gravel Common Cobbles Boulders Cement RS Bars Lumber Plywood(bags/hr) (kgs./hr) (bd. ft./hr) (pcs/hr)
4 5 3.5 3 300 6000 4000 250
Sand & Gravel Common Cobbles Boulders Cement RS Bars Lumber Plywood(bags/hr) (kgs./hr) (bd. ft./hr) (pcs/hr)
6 8 5 4 300 7000 4000 250
STRUCTURE
Dam 96 kgs/daySiphon 112 kgs/dayBridge 100 kgs/dayOther 80 kgs/day
MATERIALSSand & Gravel 3.50Cobbles 2.50Boulder 2.00
MATERIALSSlab & Wall 0.40Massice Conc. 0.25
MATERIALSGravel 4.00Sand 6.00
MATERIALSCommon 3.00
A) EXCAVATION
TYPE OF WORK
CAPACITY (m3/day) BANK VOLUME
TYPE OF WORK
CAPACITY (m3/day/man)
B) MANUAL LOADING CAPABILITIES OF FIVE (5) LABORERS
(m3/hr) (m3/hr) (m3/hr) (m3/hr)
C) MANUAL UNLOADING CAPABILITIES OF FIVE (5) LABORERS
(m3/hr) (m3/hr) (m3/hr) (m3/hr)
D) CUT, BEND & PLACE RSB1-Steelman & 1-Helper
with bar cutter
E) QUARRYINGCAPABILITY (m3/day/man)
F) DEMOLITION OF CONCRETECAPABILITY (m3/day/man)
G) SCREENING OF AGGREGATESCAPABILITY (m3/day/man)
H) MANUAL BACKFILLCAPABILITY (m3/day/man)
MATERIALSCobbles 2.00Boulders 1.50
MATERIALS2.50
CREW1-Foreman
6.002-Mason10-LaborerL.E Operator
CREWWith Mixer Without Mixer
1-Foreman
7.505.502-Mason
10-LaborerL.E Operator
Crew: 1-Mason, 2-Laborer
MATERIALSFence Building
4" CHB 14 106" CHB 10 8
CREWWith 1-Bagger Mixer
1-Foreman
4.502-Mason10-LaborerL.E Operator
Crew: 1-Mason, 5-LaborerMATERIALS CAPABILITY (Assy/day)
16x16 ~ 24x24 2above 24x24 1
P.1 - FABRICATION, PLACING & DISMANTLING OF FORMSCrew: 3-Carpenter & 5-Laborer
Crew: 1-Carpenter & 1-Laborer
P.2 - CONCRETING & CURINGP.2a - With Concrete Mixer
CREWClass "A" Class "B" Class "C" Lean Concrete
1-Foreman
3.50 4.50 4.80 6.002-Mason8-Laborer1-L.E Operator
I) LAYING OF MATERIALSCAPABILITY (m3/day/man)
J) SPREADING OF GRAVEL & SAND ON FILTER DRAIN & GRAVEL BLANKETCAPABILITY (m3/day/man)
K) RUBBLE MASONRY (Concreting)CAPABILITY (m3/day)
L) GROUTED RIPRAPCAPABILITY (m3/day)
M) CHB SETTING
CAPABILITY (m2/day)
N) CONCRETE LININGCAPABILITY (m3/day)
O) INSTALLATION OF STEEL GATES
P) CONCRETE WORKS
Cap. = 3.50 m3/day for 3000psi
Cap.= 4.50 m3/day for Canal Lining
CAPABILITY (m3/day)
P.2a - Without Concrete Mixer
CREWClass "A" Class "B" Class "C" Lean Concrete
1-Foreman2.50 3.20 3.50 4.502-Mason
8-Laborer
CREWOne Side Only
2-Mason12.00
2-Laborer
CREWCAPABILITY (pcs/day)
DiameterFabrication Installation
(inch / cm)1-Foreman 12 / 30 15 161-Mason 18 / 46 11 141-Carp./Stlman 24 / 61 9 1212-Laborers 30 / 76 6 10
36 / 91 5 848 / 122 3 6
DIAMETERNo. of Laborer
Minutes per Pc.No. of pcs/trip
(inches) Loading Unloading12 4 3 1 2418 4 4 2 1824 6 5 3 1430 6 7 4 1036 8 12 8 642 10 18 10 4
WORK DESCRIPTION CREW MEMBERS CAPABILITIESInstallation of Ceiling Joist 2-Carpenter & 1-Labourer 100 bd.ft./dayInstallation of Ceiling Board 2-Carpenter & 1-Labourer 15 pcs/dayInstallation of GI Roofing 2-Carpenter & 1-Labourer 150 Lin.Ft./dayInstallation of Panel Door 2-Carpenter & 1-Labourer 4 pcs/dayInstallation of Flush Door 2-Carpenter & 1-Labourer 6 pcs/dayInstallation of Flourescent Bulb 1-Electrician & 1-Laborer 16 pcs/dayInstallation of Incandescent Bulb 1-Electrician & 1-Laborer 32 pcs/dayInstallation of Panel Board 1-Electrician & 1-Laborer 1/2 unit/dayInstallation of Electric Conduit 1-Electrician & 1-Laborer 32 pcs/dayInstallation of # 4 Wire 1-Electrician & 1-Laborer 20 L.M./dayInstallation of # 8 Wire 1-Electrician & 1-Laborer 40 L.M./dayInstallation of # 14 Wire 1-Electrician & 1-Laborer 60 L.M./dayPainting 1-Painter
Tile Setting 1-Mason & 1-LaborerInstallation of GI Flushing 1-Lath. & 1-Laborer 16 pcs/dayInstallation of GI Ridge Roll 1-Lath. & 1-Laborer 16 pcs/dayInstallation of Down Spout 1-Lath. & 1-Laborer 12 pcs/dayInstallation of GI Gutter 1-Lath. & 1-Laborer 8 pcs/dayInstallation of Jalousie & Accs. 1-Carpenter & 1-Laborer
Note:1. Time of mixer per day = Total bags of cement x 10 min. per bag / 60 minutes per hour = ____ hrs/day2. Labor Intensity: 1-Leadman per 10-Laborers
1-Foremen per 4-Leadman1-Watcher per 4-Heavy Equipment1-Mechanic per 4-Heavy Equipment
CAPABILITY (m3/day)
Q) PLASTERING OF CHB WALLCAPABILITY (m2/day)
R) REINFORCED CONCRETE PIPES
w/ 1-bagger mixer
S) MANUAL HANDLING OF RC PIPES
T) BUILDING FACILITIES
24 m2/day
2 m2/day
10 m2/day
ESTIMATING GUIDELINE
III. MATERIAL ASPECT
CLASS STRENGTHMAX. AGGRE. CEMENT SAND GRAVEL BOULDER
(inches)A. Concrete
"A" 211 kgsc 1.50 9.00 0.45 0.90 -"B" 200 kgsc 2.00 7.00 0.50 1.00 -"C" 200 kgsc 3.00 6.50 0.52 1.04 -
Canal Lining 200 kgsc 1.00 7.50 0.48 0.96 -
B. Rubble Concrete211 kgsc 4.50 0.225 0.45 0.95
C. Grouted Riprap 3.50 0.80 0.10 1.00 Plain/Boulder Riprap - - 0.40 1.00
D. Lean Conc. 1000 psi 5.00 0.55 1.10 -
E. Rubber Blanket (ccm) - 0.40 0.60 -
F. Filter Drain (ccm) - 0.60 0.40 -
OTHER MATERIALS
CLASS TYPE OF STRUCTURESTRENGTH F. Lumber 1/2 Plywood Tie Wire Nail
(kgsc)"A" Bridge Flume 211 60 1.00 1.25% RSB 2.25"A" Siphon / Box Culvert 211 25 1.00 1.20% RSB 2.00"A" Other Structure @ MC 211 20 1.25 1.10% RSB 1.75"A" Pther Str. T. Fac. 211 15 1.15 1.10% RSB 1.50"A" Rubble Masonry 211 10 0.10 - 0.25"B" Canal Lining 200 5 - - 0.25"A" Dam 211 20 0.50 1.00% RSB 1.00"B" Dam 200 10 0.10 1.00% RSB 1.00"A" Roads Pavement 211 5 - - 0.20
REINFORCED CONCRETE PIPES
DIAMETERFABRICATION MATERIAL PER PC.
Cement Sand Gravel GI Sheet F. Lumber RSB CW Nails(inches) (bag) (L.F.) (Bd. Ft.) (kgs) (kgs)
12 0.58 0.02 0.05 0.12 0.24 5.28 0.1018 1.22 0.05 0.10 0.19 0.36 7.72 0.2024 1.82 0.08 0.15 0.24 0.48 9.77 0.3030 2.52 0.11 0.21 0.30 0.60 23.22 0.1036 3.33 0.14 0.28 0.34 0.72 50.43 0.5042 4.28 0.18 0.36 0.40 0.84 60.84 0.60
INSTALLATION OF RC PIPES
DIAMETERFABRICATION MATERIAL PER PC.
Cement Sand Gravel F. Lumber RSB CW Nails(inches) (bag) (Bd. Ft.) (kgs) (kgs)
12 0.21 0.01 0.02 2.00 - 0.2018 0.45 0.02 0.04 2.00 3.65 0.2024 0.72 0.03 0.06 3.00 4.52 0.3030 0.93 0.04 0.08 3.00 5.26 0.3036 1.11 0.05 0.10 4.00 6.01 0.4042 1.32 0.06 0.12 4.00 6.79 0.40
PLASTERING OF CHB
SIZESand Cement
4" & 6" 0.034 0.41
(bag/m3) (m3/m3) (m3/m3) (m3/m3)
(bd.ft./m3) (pcs/m3) (kg/m3) (kgs/m3)
(m3) (m3)
(m3) (m3)
MATERIAL PER M2 (Two sides)
LAYING OF CHB
SIZECEMENT SAND
4" 0.55 0.0466" 1.07 0.089
(bag/m2) (m3/m2)
HAULING COST ANALYSIS
1. HAULING OF CEMENTAve. Haul. Dist. = 20 km (from Source to Jobsite)Utilized: 6~7 Tons Cargo Truck with 5-LaborersBase Cost of Cement: UC/bagCapacity of Cargo Truck: 150 bags per trip
CYCLE TIME:With Load: 20km/trip x 60min/hr / 25 km/hr = 48 min/tripWithout Load: 20km/trip x 60min/hr / 30 km/hr = 70 min/tripManual Loading Capability of 5-Laborers, Loading & Unloading = 300 bags/hrLoading: 150bags/trip x 60min/hr / 300bags/hr = 30 min/tripUnloading: 150bags/trip x 60min/hr / 300bags/hr = 30 min/trip
Total Time = 140 min/tripor 2.47 hrs/trip
LABOR COST:Driver: 1 x Rate/day x 2.47hrs/trip / 8hrs/day x 150bags/trip = ____/bagLaborer: 5 x Rate/day x 2.47hrs/trip / 8hrs/day x 150bags/trip = ____/bag
Labor Cost = ____/bag
EQUIPMENTFuel: 10lit/hr x 1.47hrs/trip x UC/lit / 150bags/trip = ____/bagRental: Rate/hr x 2.47hrs/trip / 150 bags/trip = ____/bagSpare Parts: Rate/hr x 2.47hrs/trip / 150bags/trip = ____/bag
(Note: The travel Time on with & without load were only considered and the loading & unloading time were excluded on fuel consumption)
SUMMARY:Base Cost = UC/bagLabor Cost = ____/bagFuel Cost = ____/bagRental Cost = ____/bagSpare Part Cost = ____/bag
Total = ____/bag
HAULING COST ANALYSIS
2. HAULING OF PLYWOOD, 1/2" x 4' x 8'Ave. Haul. Dist. = 25 km (from Source to Jobsite)Utilized: 6~7 Tons Cargo Truck with 5-LaborersBase Cost of Plywood: UC/bagCapacity of Cargo Truck: 250 bags per trip
CYCLE TIME:With Load: 25km/trip x 60min/hr / 25 km/hr = 60 min/tripWithout Load: 25km/trip x 60min/hr / 30 km/hr = 50 min/tripManual Loading Capability of 5-Laborers, Loading & Unloading = 250pcs/hrLoading: 250pcs/trip x 60min/hr / 250pcs/hr = 60 min/tripUnloading: 250pcs/trip x 60min/hr / 250pcs/hr = 60 min/trip
Total Time = 230 min/tripor 3.83 hrs/trip
LABOR COST:Driver: 1 x Rate/day x 3.83hrs/trip / 8hrs/day x 250pcs/trip = ____/pcLaborer: 5 x Rate/day x 3.83hrs/trip / 8hrs/day x 250pcs/trip = ____/pc
Labor Cost = ____/pc
EQUIPMENTFuel: 10lit/hr x 3.83hrs/trip x UC/lit / 250pcs/trip = ____/pcRental: Rate/hr x 3.83hrs/trip / 250pcs/trip = ____/pcSpare Parts: Rate/hr x 3.83hrs/trip / 250pcs/trip = ____/pc
(Note: The travel Time on with & without load were only considered and the loading & unloading time were excluded on fuel consumption)
SUMMARY:Base Cost = UC/pcLabor Cost = ____/pcFuel Cost = ____/pcRental Cost = ____/pcSpare Part Cost = ____/pc
Total = ____/pc
HAULING COST ANALYSIS
3. HAULING OF RS BARS, CW NAILS & TIE WIREAve. Haul. Dist. = 25 km (from Source to Jobsite)Utilized: 6~7 Tons Cargo Truck with 5-LaborersBase Cost of Plywood: RSB=UC/kg, CW Nail=UC/kg, T.Wire=UC/kgCapacity of Cargo Truck: 6,000kg/trip
CYCLE TIME:With Load: 25km/trip x 60min/hr / 25 km/hr = 60 min/tripWithout Load: 25km/trip x 60min/hr / 30 km/hr = 50 min/tripManual Loading Capability of 5-Laborers, Loading=6,000kgs/hr & Unloading=7,000kgs/hrLoading:6000kgs/trip x 60min/hr / 6000pcs/hr = 60 min/tripUnloading:6000kgs/trip x 60min/hr / 7000pcs/hr = 51.4 min/trip
Total Time = 221.40 min/tripor 3.69 hrs/trip
LABOR COST:Driver: 1 x Rate/day x 3.69hrs/trip / 8hrs/day x6000kgs/trip = ____/kgLaborer: 5 x Rate/day x 3.69hrs/trip / 8hrs/day x 6000kgs/trip = ____/kg
Labor Cost = ____/kg
EQUIPMENTFuel: 10lit/hr x 3.69hrs/trip x UC/lit / 6000kgs/trip = ____/kgRental: Rate/hr x 3.69hrs/trip / 6000kgs/trip = ____/kgSpare Parts: Rate/hr x 3.69hrs/trip / 6000kgs/trip = ____/kg
(Note: The travel Time on with & without load were only considered and the loading & unloading time were excluded on fuel consumption)
SUMMARY: RSB CWNBase Cost = UC/kg = UC/kgLabor Cost = ____/kg = ____/kgFuel Cost = ____/kg = ____/kgRental Cost = ____/kg = ____/kgSpare Part Cost = ____/kg = ____/kg
Total = ____/kg = ____/kg
HAULING COST ANALYSIS
4. HAULING OF SAND & GRAVELAve. Haul. Dist. = 10 km (from Source to Jobsite)Utilized: 6~7 Tons Cargo Truck with 5-Laborers
Capacity of Cargo Truck: 250 bags per trip
4a) LOADING COST (MECHANIZED)Utilized: 1~1.50 Loader
LABOR COST:
Labor Cost
EQUIPMENT:
4b) HAULING COST (MECHANIZED)Utilized: 4~6 Dump Trucks
CYCLE TIME:With Load: 10km/trip x 60min/hr / 25 km/hr = 24 min/tripWithout Load: 10km/trip x 60min/hr / 30 km/hr = 20 min/tripLoading, Spot & Manuever, Unloading & Delay = 12 min/trip
Total Time = 56 min/tripor 0.93 hrs/trip
LABOR COST:
Labor Cost
EQUIPMENT
Base Cost of Plywood: UC/m3
Capability of Loader: 80m3/hr
Driver: 1 x Rate/day / 8hrs/day x 80m3/hr = ____/m3
Laborer: 1 x Rate/day / 8hrs/day x 80m3/hr = ____/m3
= ____/m3
Fuel: 10lit/hr x UC/lit / 80m3/hr = ____/m3
Rental: Rate/hr / 80m3/hr = ____/m3
Spare Parts: Rate/hr / 80m3/hr = ____/m3
Capacity of Dump Truck = 4.50m3/trip
Driver: 1 x Rate/day x 0.93hrs/trip / 8hrs/day x 4.50m3/trip = ____/m3
Laborer: 1 x Rate/day x 0.93hrs/trip / 8hrs/day x 4.50m3/trip = ____/m3
= ____/m3
Fuel: 15lit/hr x 0.93hrs/trip x UC/lit / 4.50m3/trip = ____/m3
Rental: Rate/hr x 0.93hrs/trip / 4.50m3/trip = ____/m3
Spare Parts: Rate/hr x 0.93hrs/trip / 4.50m3/trip = ____/m3
SUMMARY:
Base Cost
Labor Cost
Fuel Cost
Rental Cost
Spare Part Cost
Total
= UC/m3
= ____/m3
= ____/m3
= ____/m3
= ____/m3
= ____/m3