rob at koratty in lieu of lc no.54 progress as on 3.6.2011
TRANSCRIPT
![Page 1: ROB at Koratty in lieu of LC No.54 Progress as on 3.6.2011](https://reader036.vdocument.in/reader036/viewer/2022070401/56649f1a5503460f94c2f8ba/html5/thumbnails/1.jpg)
ROB at Koratty in lieu of LC No.54
Progress as on 3.6.2011
www.rbdck.com
![Page 2: ROB at Koratty in lieu of LC No.54 Progress as on 3.6.2011](https://reader036.vdocument.in/reader036/viewer/2022070401/56649f1a5503460f94c2f8ba/html5/thumbnails/2.jpg)
Project Details
2
Total Length-423m
Carriage way width -7.5m
Foot path-1.5m wide on one side only
Railway span-42m (ie 11.27+21+10.53)
Approach span-134m(26+4x27)
Solid ramp portion
Pulikkakadavu side-107m,RE wall-71.65m
NH side -140m,RE wall-76m
Site Engineer :Santhosh G ,KITCO Manager :Jemymathew, RBDCK ,9447078783
![Page 3: ROB at Koratty in lieu of LC No.54 Progress as on 3.6.2011](https://reader036.vdocument.in/reader036/viewer/2022070401/56649f1a5503460f94c2f8ba/html5/thumbnails/3.jpg)
3
•Consultant: KITCO Ltd
•Contractor : Cherian Varkey Construction Company Pvt Ltd
Manager in Charge RBDCK: JemyMathew, Contact No.
9447078783
Project Engineer KITCO :Santhosh G Contact
No:9447384217
Site Engineer CVCC: Shaji.M ,Contact No:9747004340
Site Engineer :Santhosh G ,KITCO Manager :Jemymathew, RBDCK ,9447078783
![Page 4: ROB at Koratty in lieu of LC No.54 Progress as on 3.6.2011](https://reader036.vdocument.in/reader036/viewer/2022070401/56649f1a5503460f94c2f8ba/html5/thumbnails/4.jpg)
Progress graph as on 3.6.2011
![Page 5: ROB at Koratty in lieu of LC No.54 Progress as on 3.6.2011](https://reader036.vdocument.in/reader036/viewer/2022070401/56649f1a5503460f94c2f8ba/html5/thumbnails/5.jpg)
5
SlNoActivity -Description
Total Quantity
Cumulative progress up to this week(1)
Balance work(2)
Cumulative delay in weeks afterSpplagmnt(3)
Work planned during the week(4)
Actual work done during the last week(5)
Short fall in the last week (6)
Work Planned for next week(7)
No of days remaing for completion as per the weekly plan
Remarks
1 Re wall towards NH side 100% 34 66 27 RR work 0 0 0 19 .
3Approach Span 5 4 1 33 - - - -
4 Pier cap 2no 1 3 36 0 0 0 0 18
5Pile (Rly)pulikakadavu side
4 4 5 55 0 0 0 0 02
6 Pile (Rly)Nh side 4 4 5 55 0 0 0 0 02
7 Piers (Rly) 2No 1 3 46 0 0 0 0
2nd lift of pier concreting at p1 completed
![Page 6: ROB at Koratty in lieu of LC No.54 Progress as on 3.6.2011](https://reader036.vdocument.in/reader036/viewer/2022070401/56649f1a5503460f94c2f8ba/html5/thumbnails/6.jpg)
SlNoActivity -Description
Total Quantity
Cumulative progress up to this week(1)
Balance work(2)
Cumulative delay in weeks afterSpplagmnt(3)
Work planned during the week(4)
Actual work done during the last week(5)
Short fall in the last week (6)
Work Planned for next week(7)
No of days remaing for completion as per the weekly plan
Remarks
8R0AD WORK{WBM} towards pulikkakadavu side
100% 90% 0
9GIRDER(LAND SPAN)P2-P3 span
3 3 1 1 0 0 41 1st stage stressing over
10 P2-P3 span Shuttering of deck slab
Concreting of deck slab P2-P3
shuttering work of the deck slab of P2-P3 in progress
Concreting of deck slab on 10-6-2011
Heavy rain hampering the work in P2-P3 Span
11 Diaphram wall(P2-P3)
Reinforcement work completed
Concreting of end diaphragms
Concreting of two end diaphragms completed successfully
Work completed as planned
12RR work in the approach portion of Nh side
50
Re wall ,Kerb and hand rail towards Pulikkakadavu side completed
![Page 7: ROB at Koratty in lieu of LC No.54 Progress as on 3.6.2011](https://reader036.vdocument.in/reader036/viewer/2022070401/56649f1a5503460f94c2f8ba/html5/thumbnails/7.jpg)
Activities which cannot be completed without caution
1 Pile 10Nos Pier -2Nos
Pier Cap-2 Nos
Deck -3slab
![Page 8: ROB at Koratty in lieu of LC No.54 Progress as on 3.6.2011](https://reader036.vdocument.in/reader036/viewer/2022070401/56649f1a5503460f94c2f8ba/html5/thumbnails/8.jpg)
RR MASONRY WORK IN THE APPROACH PORTION IN THE N.H SIDE COMPLETED UPTO 50%.
THE BALANCE WORK IS PLANNED IN THE NEXT WEEK.
![Page 9: ROB at Koratty in lieu of LC No.54 Progress as on 3.6.2011](https://reader036.vdocument.in/reader036/viewer/2022070401/56649f1a5503460f94c2f8ba/html5/thumbnails/9.jpg)
Material Stocking StatusCoarse Aggreagate (m3) 12 30 Remarks Fine Aggreagate(m3) 13 20 . Cement(bag) 25 34 Steel(MT) 7 11
Utility shifting Utilities to be shifted Status Remarks BSNL KSEB no hindrance KWA .
Others No hindrance i
![Page 10: ROB at Koratty in lieu of LC No.54 Progress as on 3.6.2011](https://reader036.vdocument.in/reader036/viewer/2022070401/56649f1a5503460f94c2f8ba/html5/thumbnails/10.jpg)
10Site Engineer :Santhosh .G KITCO Manager :Jemymathew,
RBDCK ,9447078783
DATE 28-5-2011 30-5-2011 31-5-2011 01-06-2011 02-06-2011 03-06-2011
Weather hot Hot sunny RAINY RAINY RAINY
Climate
Labour Details
Date Labours
RR work at P1
Span P2-P3
Beam work
Mechanic and operators
Pier reinforcement
Total
28-05-2011 0 0 11 4 0 15
30-5-2011 0 0 12 4 0 16
31-5-2011 0 0 11 4 0 16
01-6-2011 0 6 12 3 0 21
02-6-.2011 0 6 12 3 0 21
03-6-2011 0 6 12 3 0 21
![Page 11: ROB at Koratty in lieu of LC No.54 Progress as on 3.6.2011](https://reader036.vdocument.in/reader036/viewer/2022070401/56649f1a5503460f94c2f8ba/html5/thumbnails/11.jpg)
zSl.No
Date Activity
1 28-5-2011 1.Concreting of 1st end diaphragm of span P2-P3 2.Shuttering work of deck slab of span P2-P3
2 30-5-2011 1.Concreting of 2nd end diaphragm of span P2-P3 2.Shuttering work of deck slab of span P2-P3
3 31-5-.2011
1.Shuttering work of deck slab of span P2-P3
4 01-06-2011 1.Shuttering and reinforcement work of deck slab of span P2-P3
2. RR masonry work near P1 location.
5
6
02-6-2011
3-6-2011
1.Shuttering and reinforcement work of deck slab of span P2-P3 2. RR masonry work near P1 location.
.
1.Shuttering and reinforcement work of deck slab of span P2-P3 2. RR masonry work near P1 location.
Daily Activity Report
![Page 12: ROB at Koratty in lieu of LC No.54 Progress as on 3.6.2011](https://reader036.vdocument.in/reader036/viewer/2022070401/56649f1a5503460f94c2f8ba/html5/thumbnails/12.jpg)
Work Done during last monthSl No Activity
Week 1 up to 6.6.2011
3rd Girder of P3-P2 span concreting
Week 2 up to 13.6.2011
1)Concreting of Pier P1 Ist lift (Approximately 2m) done.2)Premix bituminous work Ist layer completed at Pulikkakadavu side at the approach portion.
Week 3 up to 20.6.2011
1) 1st stage stressing completed for all three beams of the span P2-P3
2)Reinforcement and shuttering work of Cross beam or end diaphragm of the span P2-P3
3)Grouting of the ducts of all the beams in the span P2-P3.
Week 4 up to 27.5.2011
RR work and 2nd lift of Pier P1
Week 5 up to 3.6.2011
Diaphram wall concreting and RR work,Stagging work of deck slab
![Page 13: ROB at Koratty in lieu of LC No.54 Progress as on 3.6.2011](https://reader036.vdocument.in/reader036/viewer/2022070401/56649f1a5503460f94c2f8ba/html5/thumbnails/13.jpg)
SHUTTERING OF DECK SLAB AT P2-P3
![Page 14: ROB at Koratty in lieu of LC No.54 Progress as on 3.6.2011](https://reader036.vdocument.in/reader036/viewer/2022070401/56649f1a5503460f94c2f8ba/html5/thumbnails/14.jpg)
END DIAPHRAGM CONCRETE P2-P3 SPAN
![Page 15: ROB at Koratty in lieu of LC No.54 Progress as on 3.6.2011](https://reader036.vdocument.in/reader036/viewer/2022070401/56649f1a5503460f94c2f8ba/html5/thumbnails/15.jpg)
SHUTTERING WORK OF DECK SLAB P2-P3 SPAN
![Page 16: ROB at Koratty in lieu of LC No.54 Progress as on 3.6.2011](https://reader036.vdocument.in/reader036/viewer/2022070401/56649f1a5503460f94c2f8ba/html5/thumbnails/16.jpg)
HEAVY RAIN AT KORATTY
![Page 17: ROB at Koratty in lieu of LC No.54 Progress as on 3.6.2011](https://reader036.vdocument.in/reader036/viewer/2022070401/56649f1a5503460f94c2f8ba/html5/thumbnails/17.jpg)
RR MASONRY AT P1-1.6.2011
![Page 18: ROB at Koratty in lieu of LC No.54 Progress as on 3.6.2011](https://reader036.vdocument.in/reader036/viewer/2022070401/56649f1a5503460f94c2f8ba/html5/thumbnails/18.jpg)
RR MASONRY AT P1 2.6.2011
![Page 19: ROB at Koratty in lieu of LC No.54 Progress as on 3.6.2011](https://reader036.vdocument.in/reader036/viewer/2022070401/56649f1a5503460f94c2f8ba/html5/thumbnails/19.jpg)
SHUTTERING OF DECK SLAB AT P2-P3
![Page 20: ROB at Koratty in lieu of LC No.54 Progress as on 3.6.2011](https://reader036.vdocument.in/reader036/viewer/2022070401/56649f1a5503460f94c2f8ba/html5/thumbnails/20.jpg)
SHUTTERING OF DECK SLAB AT P2-P3
![Page 21: ROB at Koratty in lieu of LC No.54 Progress as on 3.6.2011](https://reader036.vdocument.in/reader036/viewer/2022070401/56649f1a5503460f94c2f8ba/html5/thumbnails/21.jpg)
• Thank you