  • 8/14/2019 Role of the Consulting Engineer in the Application of Water

    1/23

    Role of the Consulting EngineerRole of the Consulting Engineer

    in the Application of Water Mist Systemsin the Application of Water Mist Systems

    P. J. DiNenno, P.E.P. J. DiNenno, P.E.

    ForFor

    Jack Mawhinney,PEngJack Mawhinney,PEng

  • 8/14/2019 Role of the Consulting Engineer in the Application of Water

    2/23

    Presented atPresented at

    NFPA/IMWA ConferenceNFPA/IMWA Conference

    on Water Mist Fire Suppressionon Water Mist Fire SuppressionSystemsSystems

    Dallas, TXDallas, TX

    May 2003May 2003

  • 8/14/2019 Role of the Consulting Engineer in the Application of Water

    3/23

    Role of the Consulting Engineer Role of the Consulting Engineer

    s Research and development, first principles scienceResearch and development, first principles science

    s Water Mist Design = Performance Based DesignWater Mist Design = Performance Based Design

    s 33rdrd Party Review of Designs by VendorsParty Review of Designs by Vendors

    s Acceptance testingAcceptance testing

    s ConclusionConclusion

  • 8/14/2019 Role of the Consulting Engineer in the Application of Water

    4/23

    Chronology of Water MistChronology of Water Mist

    s NFPA 750, Standard for Water Mist Fire ProtectionNFPA 750, Standard for Water Mist Fire Protection

    SystemsSystemsx Committee formed in 1993 New Technology, NewCommittee formed in 1993 New Technology, New

    StandardStandard

    x Many interested parties: casual to vitalMany interested parties: casual to vital

    x Provided fire protection engineering basis for developmentProvided fire protection engineering basis for development

    s Research Era 1990 to 1998 Research Era 1990 to 1998 s Market Emergence (1995 to present )Market Emergence (1995 to present )

  • 8/14/2019 Role of the Consulting Engineer in the Application of Water

    5/23

    Chronology Chronology

    s NFPA 750, Standard for Water Mist Fire Protection SystemsNFPA 750, Standard for Water Mist Fire Protection Systems

    x Committee formed in 1993 New Technology, New StandardCommittee formed in 1993 New Technology, New Standard

    s Research EraResearch Erax 1990 to 1998 (?) intense research 1 st principles1990 to 1998 (?) intense research 1 st principles

    x Water based fire suppression, efficiency, limits,Water based fire suppression, efficiency, limits,opportunitiesopportunities

    x Manufacturers R & D efforts still on-goingManufacturers R & D efforts still on-going

    x Military special applications still on-goingMilitary special applications still on-going

    s Market Emergence (1995 to present )Market Emergence (1995 to present )

    x Commercial development of technology, invention,Commercial development of technology, invention,

  • 8/14/2019 Role of the Consulting Engineer in the Application of Water

    6/23

    Chronology Chronology

    s NFPA 750, Standard for Water Mist Fire Protection SystemsNFPA 750, Standard for Water Mist Fire Protection Systems

    x Committee formed in 1993 New Technology, New StandardCommittee formed in 1993 New Technology, New Standard

    s Research EraResearch Era

    x

    1990 to 1998 (?) intense research 1 st principles1990 to 1998 (?) intense research 1 st principless Market Emergence (1995 to present )Market Emergence (1995 to present )

    x Commercial development of technology, invention,Commercial development of technology, invention,

    x Marine sector = sprinkler equivalence rapid growthMarine sector = sprinkler equivalence rapid growthOther sectors = halon replacement very slow growth,except inOther sectors = halon replacement very slow growth,except innichesniches

    Standards development (IMO, NFPA 750; CEN TC 191)Standards development (IMO, NFPA 750; CEN TC 191)x Formalized Test ProtocolsFormalized Test Protocols

  • 8/14/2019 Role of the Consulting Engineer in the Application of Water

    7/23

    Chronology Chronology

    s Acceptance Era (2000 to Present)Acceptance Era (2000 to Present) By End UserBy End User - Growing- Growing

    By AHJBy AHJ - Approvals getting easier- Approvals getting easier

    Growth is unevenGrowth is uneven

    --

    Oil fields, Marine, Co-Generation well advancedOil fields, Marine, Co-Generation well advanced

    Land-based, heritage, commercial, computer roomsLand-based, heritage, commercial, computer rooms

    Slow in the US depends on AHJSlow in the US depends on AHJ

    Rapid in Europe Every End User decides for themselvesRapid in Europe Every End User decides for themselves

    s Engineering and Construction Era (2000 + )Engineering and Construction Era (2000 + )

    x Design & approval methods establishedDesign & approval methods established

    x Specifications, Design Drawings, Construction SupervisionSpecifications, Design Drawings, Construction Supervision

  • 8/14/2019 Role of the Consulting Engineer in the Application of Water

    8/23

    Chronology Chronology

    s Acceptance Era (1997 to Present)Acceptance Era (1997 to Present)

    s Engineering and Construction Era (2000 + )Engineering and Construction Era (2000 + )

    Specifications, Design Drawings, Construction SupervisionSpecifications, Design Drawings, Construction Supervision

    Hydraulics; mixtures of gas and water; achieving duration; pistonHydraulics; mixtures of gas and water; achieving duration; piston

    pumps; materials; techniques; trained installerspumps; materials; techniques; trained installers

    Acceptance TestingAcceptance Testing

    Maintenance and ReliabilityMaintenance and Reliability CostsCosts

  • 8/14/2019 Role of the Consulting Engineer in the Application of Water

    9/23

    Performance Based DesignPerformance Based Design

    s NFPA 750 Chapter 5: DesignNFPA 750 Chapter 5: Design

    x Design of a water mist system must be based on results ofDesign of a water mist system must be based on results of

    comprehensive fire tests, conducted by an internationallycomprehensive fire tests, conducted by an internationally

    recognized laboratory.recognized laboratory.

    Comprehensive Test Protocols: Marine machinery spaces;Comprehensive Test Protocols: Marine machinery spaces;

    turbine enclosures; wet benches; marine accommodation andturbine enclosures; wet benches; marine accommodation and

    public spaces; light and ordinary hazard occupancies.public spaces; light and ordinary hazard occupancies.

    x The test protocol seldom exactly matches the applicationThe test protocol seldom exactly matches the application

    x Interpretation is requiredInterpretation is required

  • 8/14/2019 Role of the Consulting Engineer in the Application of Water

    10/23

    Performance Based DesignPerformance Based Design

    s NFPA 750 Chapter 5: DesignNFPA 750 Chapter 5: Design

    x Application of a water mist system to a real spaceApplication of a water mist system to a real space

    Confirm performance objectives of the protocol are appropriate.Confirm performance objectives of the protocol are appropriate.

    E.g. full extinguishment, control for 10-minutes ?E.g. full extinguishment, control for 10-minutes ?

    Confirm compartment size, ventilation, obstructions, fuel quantities, and otherConfirm compartment size, ventilation, obstructions, fuel quantities, and otherfeatures of the application match the assumptions in the test protocolfeatures of the application match the assumptions in the test protocol

    It requires fire protection engineering knowledge to evaluate whether the designIt requires fire protection engineering knowledge to evaluate whether the designmeets the End Users objectives.meets the End Users objectives.

    Major Source of MisapplicationsMajor Source of Misapplications

    Uncertainty transfers riskUncertainty transfers risk

  • 8/14/2019 Role of the Consulting Engineer in the Application of Water

    11/23

    National Gallery of Art Water Mist SystemNational Gallery of Art Water Mist System

    End Users ObjectivesEnd Users Objectivess Extinguish or control fire in combustible ceiling and prevent fire spread toExtinguish or control fire in combustible ceiling and prevent fire spread to

    adjacent galleriesadjacent galleries

    s Control a normal fire at floor level (light hazard)Control a normal fire at floor level (light hazard)

    s Have no water over the collection (preaction system)Have no water over the collection (preaction system)

    s Design to provide capacity for future expansion (pumped system)Design to provide capacity for future expansion (pumped system)

    s Address issues of incomplete listings for equipmentAddress issues of incomplete listings for equipment

    x Specification recognizing pending approvalSpecification recognizing pending approval

    s Ultimately, provide a system that meets NGA performance expectations,Ultimately, provide a system that meets NGA performance expectations,complies with intent of NFPA 750, and is a listed, approved systemcomplies with intent of NFPA 750, and is a listed, approved system

  • 8/14/2019 Role of the Consulting Engineer in the Application of Water

    12/23

    National Gallery of ArtNational Gallery of Art

    s Listing of nozzles essentially appropriateListing of nozzles essentially appropriate

    s Application not exactly conforming to listingApplication not exactly conforming to listing

    s Nozzles listed, but pump unit not listed (pending)Nozzles listed, but pump unit not listed (pending)

    s Specifications drafted to suit installation by fire protectionSpecifications drafted to suit installation by fire protectioncontractor new to high pressure piping and water mistcontractor new to high pressure piping and water mistsystems equipmentsystems equipment

    s Professional responsibility of consultant vs. acceptanceProfessional responsibility of consultant vs. acceptanceby informed End User acting as own AHJby informed End User acting as own AHJ

  • 8/14/2019 Role of the Consulting Engineer in the Application of Water

    13/23

    Engineering ChallengesEngineering Challenges

    s Decision-points arise all the timeDecision-points arise all the time

    x Water mist technology is still under development.Water mist technology is still under development.

    Special invention, adaptation is often encounteredSpecial invention, adaptation is often encountered

    x How do you advise the AHJ or End User about the engineeringHow do you advise the AHJ or End User about the engineeringsuitability of situations encountered for the first time?suitability of situations encountered for the first time?

    x Example:Example:

    Deluge control valves for high pressure systemsDeluge control valves for high pressure systems

    Capacity of largestCapacity of largestlistedlistedvalve is less than required for the systemvalve is less than required for the system

    demanddemand Solution: manifold a series of small capacity sectional valvesSolution: manifold a series of small capacity sectional valves

    Issue: what is the effect on reliability?Issue: what is the effect on reliability?

  • 8/14/2019 Role of the Consulting Engineer in the Application of Water

    14/23

    Consultants Role in Peer ReviewConsultants Role in Peer Review

    x End User or AHJ does not have resources to provide aEnd User or AHJ does not have resources to provide a

    review to the desired level of thoroughness.review to the desired level of thoroughness.

    x Engage a qualified consultant who has the knowledge toEngage a qualified consultant who has the knowledge to

    judge whether a proposed system meets the End Usersjudge whether a proposed system meets the End Users

    needsneeds

  • 8/14/2019 Role of the Consulting Engineer in the Application of Water

    15/23

    Consulting engineer must be able to compareConsulting engineer must be able to compare

    technologiestechnologies

    Low pressure, twin fluid, gas driven (Securiplex)Low pressure, twin fluid, gas driven (Securiplex)

    Intermediate pressure, single fluid, gas drivenIntermediate pressure, single fluid, gas driven

    (Chemetron, Fike)(Chemetron, Fike)

    High pressure, single fluid, gas driven (Marioff,High pressure, single fluid, gas driven (Marioff,

    Fogtec, others ...)Fogtec, others ...)

    High or Low pressure, single fluid, pumped (Marioff,High or Low pressure, single fluid, pumped (Marioff,

    Fogtec, UniFog, Aquamist, )Fogtec, UniFog, Aquamist, )

    Decaying pressure, hybrid gas-water (Marioff)Decaying pressure, hybrid gas-water (Marioff)

    Cycled discharge versus continuous dischargeCycled discharge versus continuous discharge

    (Securiplex, Fike, Chemetron, others )(Securiplex, Fike, Chemetron, others )

  • 8/14/2019 Role of the Consulting Engineer in the Application of Water

    16/23

    Twin Fluid, Low Pressure, Gas drivenTwin Fluid, Low Pressure, Gas driven

    1

    Compressed Gas

    Cylinders(atomizing

    medium)

    Slave Master

    789

    1

    1

    1

    8

    A

    i

    r ControlPanel

    Detectors

    Regulator

    Water

    Reservoir

    Duration of discharge typically10 minutes

    Cycled discharge (on-off)

    Stored water

    High PressureLow Pressure

  • 8/14/2019 Role of the Consulting Engineer in the Application of Water

    17/23

    Single fluid, intermediate pressure, gasSingle fluid, intermediate pressure, gas

    drivendriven

    1

    1

    8

    7

    Detectors

    ControlPanel

    Duration of discharge typically

    10 minutes

    Cycled discharge (on-off)

    Stored water

  • 8/14/2019 Role of the Consulting Engineer in the Application of Water

    18/23

    Pumped system, high or intermediatePumped system, high or intermediate

    pressurepressure

    M

    6

    7

    Q P

    8

    Releasing

    Panel

    Detectors

    Controller

    Filters

    M

    Unloader

    Test Line

    Sectional ControlValves

    Water Supply (potable)

    Gas-driven jockey pump

  • 8/14/2019 Role of the Consulting Engineer in the Application of Water

    19/23

    Consultants Required knowledgeConsultants Required knowledge

    s Compare pros and cons of different types of systemsCompare pros and cons of different types of systems

    s Compare costs of different systemsCompare costs of different systems

    s Understand differences in long term maintenanceUnderstand differences in long term maintenance

    needsneeds

    s Compare reliability to the extent knownCompare reliability to the extent known

    x Equipment is often too new to be able to quantify itsEquipment is often too new to be able to quantify its

    reliabilityreliability

    s Understand Construction and ITM infrastructureUnderstand Construction and ITM infrastructure

  • 8/14/2019 Role of the Consulting Engineer in the Application of Water

    20/23

    Acceptance TestingAcceptance Testing

    s The Vendor should not be the only party in theThe Vendor should not be the only party in the

    room who knows how the system works room who knows how the system works

    To sump

    Water Supply

    27 kW 27 kW

    M M

    M M

    27 kW 27 kW

    To sump

  • 8/14/2019 Role of the Consulting Engineer in the Application of Water

    21/23

    500400300200100 150 250 350 450

    160

    140

    120

    100

    80

    60

    40

    Test Result for 4 motors, 8 pumps.

    4321

    Evaluating High Pressure Pump Performance

    Flow Test Objective

    400 l/min @ 105 bar

    Discharge, L/min

    Flow Test Result

    316 l/min @ 107 bar

    For System: k = 31.749

    328 l/min @ 107 bar

    Calculated demand,

    K = 31.749

  • 8/14/2019 Role of the Consulting Engineer in the Application of Water

    22/23

    Role of the Consulting Engineer Role of the Consulting Engineer

    ConclusionConclusion

    s The increasing acceptance of water mist systemsThe increasing acceptance of water mist systemscreates increased demand for independent expertisecreates increased demand for independent expertise

    s Water mist systems represent a performance basedWater mist systems represent a performance based

    design paradigmdesign paradigm

    s The consulting engineer (3The consulting engineer (3rdrd party reviewer) mustparty reviewer) mustappreciate the pros and cons of all water mistappreciate the pros and cons of all water misttechnologiestechnologies

    s

    Required knowledge for entry is difficult to acquire, butRequired knowledge for entry is difficult to acquire, butis still based on fundamental engineering principles ofis still based on fundamental engineering principles ofhydraulics and systems reliabilityhydraulics and systems reliability

  • 8/14/2019 Role of the Consulting Engineer in the Application of Water

    23/23