rose water (rs. 0.86 million)
TRANSCRIPT
-
8/21/2019 Rose Water (Rs. 0.86 Million)
1/18
Pre-Feasibility Study
(Rose Water)
Small and Medium Enterprises Development Authority
Ministry of Industries & ProductionGovernment of Pakistan
www.smeda.org.pk
HEAD OFFICE
4th Floor, Building No. 3, Aiwan-e-Iqbal Complex, Egerton Road,Lahore
Tel: (92 42) 111 111 456, Fax: (92 42) 36304926-7
REGIONAL OFFICE
PunjabREGIONAL OFFICE
SindhREGIONAL OFFICE
Khyber PakhtunkhwaREGIONAL OFFICE
Balochistan3rdFloor, Building No. 3,Aiwan-e-Iqbal Complex,
Egerton Road Lahore,
Tel: (042) 111-111-456Fax: (042) 36304926-7
5thFloor, BahriaComplex II, M.T. Khan Road,
Karachi.
Tel: (021) 111-111-456Fax: (021) 35610572
Ground FloorState Life Building
The Mall, Peshawar.
Tel: (091) 111-111-456Fax: (091) 5286908
Bungalow No. 15-AChaman Housing Scheme
Airport Road, Quetta.
Tel: (081) 2831623, 2831702Fax: (081) 2831922
Note: All SMEDA Services / information related to PM's Youth Business Loan areFree of Cost
May, 2014
mailto:[email protected]:[email protected]:[email protected]://../Downloads/[email protected]://../Downloads/[email protected]://../Downloads/[email protected]://../Downloads/[email protected]://../Downloads/[email protected]://../Downloads/[email protected]:[email protected]:[email protected] -
8/21/2019 Rose Water (Rs. 0.86 Million)
2/18
Pre-Feasibility Studies Rose Water Processing Unit (Rs. 0.86 Million)
TABLE OF CONTENTS
1.DISCLAIMER .............................................................................................................. 2
2.PURPOSE OF THE DOCUMENT ................................................................................ 3
3.INTRODUCTION TO SMEDA ...................................................................................... 3
4.INTRODUCTION TO SCHEME ................................................................................... 4
5.EXECUTIVE SUMMARY ............................................................................................. 4
6.BRIEF DESCRIPTION OF PROJECT & PRODUCT ................................................... 4
7.CRITICAL FACTORS .................................................................................................. 5
8.INSTALLED & OPERATIONAL CAPACITIES ............................................................ 5
9.GEOGRAPHICAL POTENTIAL FOR INVESTMENT .................................................. 5
10. POTENTIAL TARGET MARKETS / CITIES ........................................................... 6
11. PRODUCTION PROCESS FLOW .......................................................................... 6
12. PROJECT COST SUMMARY ................................................................................ 712.1. PROJECT ECONOMICS............................................................................................ 712.2. PROJECT FINANCING.............................................................................................. 712.3. PROJECT COST...................................................................................................... 812.4. SPACE REQUIREMENT............................................................................................ 812.5. MACHINERY AND EQUIPMENT.................................................................................. 812.6. FURNITURE,FIXTURE AND EQUIPMENT.................................................................... 912.7. RAW MATERIAL REQUIREMENTS............................................................................ 1012.8. HUMAN RESOURCE REQUIREMENT........................................................................ 1012.9. REVENUE GENERATION........................................................................................ 1112.10. OTHER COSTS.................................................................................................... 11
13. CONTACT DETAILS OF SUPPLIERS, EXPERTS/CONSULTANTS DEV.INSTITUTIONS ..................................................................................................... 11
14. ANNEXURE ......................................................................................................... 12
14.1. INCOME STATEMENT............................................................................................. 1214.2. BALANCE SHEET.................................................................................................. 1314.3. CASH FLOW STATEMENT....................................................................................... 1414.4. USEFUL PROJECT MANAGEMENT TIPS................................................................... 1514.5. USEFUL LINKS...................................................................................................... 16
15. KEY ASSUMPTIONS ........................................................................................... 17
-
8/21/2019 Rose Water (Rs. 0.86 Million)
3/18
Pre-Feasibility Studies Rose Water Processing Unit (Rs. 0.86 Million)
1. DISCLAIMER
This information memorandum is to introduce the subject matter and provide a
general idea and information on the subject. Although, the material included in
this document is based on data / information gathered from various reliable
sources; however, it is based upon certain assumptions which may differ from
case to case. The information has been provided on as is where is basis without
any warranties or assertions as to the correctness or soundness thereof.
Although, due care and diligence has been taken to compile this document, the
contained information may vary due to any change in any of the concerned
factors, and the actual results may differ substantially from the presented
information. SMEDA, its employees or agents do not assume any liability for any
financial or other loss resulting from this memorandum in consequence of
undertaking this activity. The contained information does not preclude any further
professional advice. The prospective user of this memorandum is encouraged tocarry out additional diligence and gather any information which is necessary for
making an informed decision including taking professional advice from a qualified
consultant / technical expert before taking any decision to act upon the
information.
For more information on services offered by SMEDA, please contact our website:www.smeda.org.pk
SMEDA Services / Information related to PMs Youth Business Loan are FREE OF COST - 2
http://www.smeda.org.pk/http://www.smeda.org.pk/http://www.smeda.org.pk/ -
8/21/2019 Rose Water (Rs. 0.86 Million)
4/18
Pre-Feasibility Studies Rose Water Processing Unit (Rs. 0.86 Million)
2. PURPOSE OF THE DOCUMENT
The objective of the pre-feasibility study is primarily to facilitate potential
entrepreneurs in project identification for investment. The project pre-feasibility
may form the basis of an important investment decision and in order to serve this
objective, the document / study covers various aspects of project conceptdevelopment, start-up, production, marketing, finance and business
management.
The purpose of this document is to facilitate potential investors in Rose Water
Processing Unit by providing them with a general understanding of the business
with the intention of supporting potential investors in crucial investment decisions.
The need to come up with pre-feasibility reports for undocumented or minimally
documented sectors attains greater imminence as the research that precedes
such reports reveal certain thumb rules; best practices developed by existing
enterprises by trial and error, and certain industrial norms that become a guidingsource regarding various aspects of business set-up and its successful
management.
Apart from carefully studying the whole document, one must consider critical
aspects provided later on, which form the basis of any investment decision.
3. INTRODUCTION TO SMEDA
The Small and Medium Enterprises Development Authority (SMEDA) was
established in October 1998 with an objective to provide fresh impetus to the
economy through development of Small and Medium Enterprises (SMEs).
With a mission "to assist in employment generation and value addition to the
national income, through development of the SME sector, by helping increase
the number, scale and competitiveness of SMEs", SMEDA has carried out
sectoral research to identify policy, access to finance, business development
services, strategic initiatives and institutional collaboration and networking
initiatives.
Preparation and dissemination of prefeasibility studies in key areas of investment
has been a hallmark of SME facilitation by SMEDA.
Concurrent to the prefeasibility studies, a broad spectrum of business
development services is also offered to SMEs by SMEDA. These services
include identification of experts and consultants and delivery of need based
capacity building programs of different types in addition to business guidance
through help desk services.
SMEDA Services / Information related to PMs Youth Business Loan are FREE OF COST - 3
-
8/21/2019 Rose Water (Rs. 0.86 Million)
5/18
Pre-Feasibility Studies Rose Water Processing Unit (Rs. 0.86 Million)
4. INTRODUCTION TO SCHEME
Prime Ministers Youth Business Loan scheme, for young entrepreneurs, with
an allocated budget of Rs. 5.0 Billion for the year 2013-14, is designed to provide
subsidised financing at 8% mark-up per annum for one hundred thousand
(100,000) beneficiaries, through designated financial institutions, initially by theNational Bank of Pakistan (NBP) and the First Women Bank Ltd. (FWBL).
Loans from Rs. 0.1 million to Rs. 2.0 million with tenure up to 8 years, inclusive of
1 year grace period, and a debt: equity of 90: 10 will be disbursed to SME
beneficiaries across Pakistan, covering; Punjab, Sindh, Khyber Pakhtunkhwa,
Balochistan, Gilgit Baltistan, Azad Jammu & Kashmir and Federally Administered
Tribal Areas (FATA).
5. EXECUTIVE SUMMARY
Cultivation of ornamental flowers including rose flower is concentrated around bigcities such as Rawalpindi, Faisalabad, Lahore, Multan, Hyderabad and Karachi.
Accordingly, these cities present an opportunity for establishment of Rose Water
Processing Unit due to easy sourcing of rose petals.
The proposed project is a small sized simple steam distillation unit which would
take approximately 8 hours to complete a production cycle, from rose petal input
to rose water extraction.
The project will be producing rose water packed in pet bottles of 750 ml and 250
ml with a ratio of 60% and 40% respectively. Total installed production capacity
of rose water is 49,500 liters from 4.95 ton rose petals and 99,000 liters of water.
The total project cost for setting up a Rose Water Processing Unit is estimated at
Rs. 0.86 million out of which Rs. 0.63 million is capital cost and Rs. 0.23 million is
working capital. The project is proposed to be financed through 90% debt and
10% equity. The NPV is projected around Rs. 4.67 million, with an IRR of 57%
and a payback period of 2.51 years. The legal business status of this project is
proposed as a Sole Proprietorship.
6. BRIEF DESCRIPTION OF PROJECT & PRODUCT
This project is about processing rose petals to extract water and its packing in
pet bottles of 750 ml and 250 ml.
The processing unit will have a capacity to process 4.95 tons of rose petals,
extracting 49,500 liters of rose water annually. The plant will operate on 70%
capacity in the first year and achieve maximum capacity utilization of 95% in the
SMEDA Services / Information related to PMs Youth Business Loan are FREE OF COST - 4
-
8/21/2019 Rose Water (Rs. 0.86 Million)
6/18
Pre-Feasibility Studies Rose Water Processing Unit (Rs. 0.86 Million)
6th year. The business will provide employment opportunity to 05 individuals
directly.
Keeping in view the scope and volume of Prime Ministers Youth Business Loan
scheme, the proposed model for processing of rose water is based on purchase
of rose petal from the market instead of self cultivation / harvest of rose plants.
All the expenditures that are required to be incurred for setting up of rose water
processing unit and purchase of raw material for start-up are included in the
capital cost of the project.
7. CRITICAL FACTORS
Following factors play a critical role in the successful execution of the business
operations and impact profitability:
Entrepreneurs background and technical know-how of the business.
Contract sourcing of good quality rose-petals on reasonable prices. Ensure the quality of the finished product.
Effective marketing and distribution of the product particularly to the
wholesale buyers.
8. INSTALLED & OPERATIONAL CAPACITIES
Following table provides details of installed capacities and capacity utilization for
the first year of operations @ of 70%:
Product Unit Installed Capacity First Year Production
750 ml Packing Bottles 39,600 27,720
250 ml Packing Bottles 79,200 55,440
9. GEOGRAPHICAL POTENTIAL FOR INVESTMENT
The industry of growing flowers and other ornamental crops is mainly
concentrated around big cities like Karachi, Hyderabad, Lahore, Rawalpindi,Islamabad, Multan, Faisalabad, and Quetta along with Pattoki, Sahiwal and
Hyderabad.
SMEDA Services / Information related to PMs Youth Business Loan are FREE OF COST - 5
-
8/21/2019 Rose Water (Rs. 0.86 Million)
7/18
Pre-Feasibility Studies Rose Water Processing Unit (Rs. 0.86 Million)
10. POTENTIAL TARGET MARKETS / CITIES
Rose water is used in many medical, cosmetic and culinary products. Large
herbal medicine companies and pharmaceutical businesses are major buyers of
rose water. Additionally, due to traditional consumption of rose water for
household use, there is also a significant consumer market all across Pakistan.
11. PRODUCTION PROCESS FLOW
Raw MaterialSteam
Distillation
Water
Accumulation
Bottling and
Packing
Marketing &
Distribution
SMEDA Services / Information related to PMs Youth Business Loan are FREE OF COST - 6
-
8/21/2019 Rose Water (Rs. 0.86 Million)
8/18
Pre-Feasibility Studies Rose Water Processing Unit (Rs. 0.86 Million)
12. PROJECT COST SUMMARY
A detailed financial model has been developed to analyze the commercial
viability of the Rose Water Processing Unit under the Prime Ministers Youth
Business Loan scheme. Various cost and revenue related assumptions along
with results of the analysis are outlined in this section.The projected Income Statement, Cash Flow Statement and Balance Sheet are
attached as appendix.
12.1. Project Economics
All the figures in this financial model have been calculated for a target production
of 49,500 liters, whereby; 34,650 liters of rose water will be produced in year one
at 70% of capacity.
The following table shows internal rate of return, payback period and Net Present
Value.
Table 1: Project Economics
Description Details
Internal Rate of Return (IRR) 57%
Payback Period (yrs) 2.51
Net Present Value (NPV) Rs. 4,665,191
Returns on the business and its profitability are highly dependent on the
efficiency in sourcing of good quality rose petal for extraction of fine rose water.Rose water distribution is also very important in this regard, adequate marketing
with strong distribution network is required for its sale.
12.2. Project Financing
Following table provides details of the equity required and variables related to
bank loan:
Table 2: Project Financing
Description Details
Total Equity (10%) Rs. 86,518
Bank Loan (90 %.) Rs. 778,659
Markup to the Borrower (%age/annum) 8%
Tenure of the Loan (Years) 8
Grace Period (Year) 1
SMEDA Services / Information related to PMs Youth Business Loan are FREE OF COST - 7
-
8/21/2019 Rose Water (Rs. 0.86 Million)
9/18
Pre-Feasibility Studies Rose Water Processing Unit (Rs. 0.86 Million)
12.3. Project Cost
Following requirements have been identified for operations of the proposed
business:
Table 3: Capital Investment for the Project
Capital Investment Amount (Rs.)Plant and Machinery 253,000
Furniture & Fixture 50,000
Office Equipment 36,000
Office Vehicle 250,000
Pre-operating Cost 46,743
Total Capital Costs 635,743
Working Capital
Equipment Spare Part Inventory 3,163
Raw Material Inventory 16,239
Upfront Building Rent 84,000
Cash 126,031
Total Working Capital 229,433
Total Project Cost 865,176
12.4. Space Requirement
A total of 700 square feet area is required to start this business. Space for the
processing unit has been calculated on the basis of space required for production
area, management building, and store. However, the units operating in the
industry do not follow any set pattern. Following table shows calculations for
project space requirement.
Table 4: Space Requirement
Space Requirement Sq. ft
Production Hall 400
Store 300
Total Area 700
Rental expense for the space required is assumed at Rs. 28,000 per month.
12.5. Machinery and Equipment
Following table provides list of machinery and equipment required for an average
150 liters / shift of rose water.
SMEDA Services / Information related to PMs Youth Business Loan are FREE OF COST - 8
-
8/21/2019 Rose Water (Rs. 0.86 Million)
10/18
Pre-Feasibility Studies Rose Water Processing Unit (Rs. 0.86 Million)
Table 5: List of Machinery and Equipment
DescriptionCapacity
Units/8 HrQuantity Cost
Rs/unitTotalRs.
Plant 150 Liter 1 120,000 120,000
Extraction Pot 150 Liter 1 35,000 35,000
Burner and OtherAccessories
- 1 18,000 18,000
Packing Cone 150 Liter 150 Liter 1 80,000 80,000
Total 253,000
Main equipment for this project is its extraction plant along with its accessories.
This Pre-feasibility study proposes 1 plant, with a capacity to produce 150 liters
of rose water per shift, from 300 liters of water and 15 kg rose petals input.
Extraction plant is locally manufactured and available in the market.
12.6. Furniture, Fixture and Equipment
Following Furniture, Fixture and Office Equipment are proposed to be required to
establish a proper set-up:
Table 6: Furniture and Fixture
Quantity Cost Amount (Rs.)
Furniture set for Office 1 15,000 15,000
UPS (1500 Watts) 1 35,000 35,000
Total 50,000
Table 7: Office Equipment Costs
Quantity Cost Amount (Rs.)
Computer 1 25,000 25,000
Printer 1 10,000 10,000
Telephone and Connection 1 1,000 1,000
Total 36,000
Office vehicle required for the project is as follows:
Table 8: Office Vehicles
Number Cost Amount (Rs.)
3 Wheel Vehicle 1 250,000 250,000
One 3-wheel vehicle with carriage box would be sufficient for distribution of rosewater bottles in the market.
SMEDA Services / Information related to PMs Youth Business Loan are FREE OF COST - 9
-
8/21/2019 Rose Water (Rs. 0.86 Million)
11/18
Pre-Feasibility Studies Rose Water Processing Unit (Rs. 0.86 Million)
12.7. Raw Material Requirements
Following table shows raw material cost per bottle.
Table 9: Cost per Bottle
Unit Unit Cost (Rs.) Qty Cost (Rs.)
750 ml BottleRose Petals Kg 45 0.075 3.375
Pet Bottle No. 10.50 1 10.500
Total 13.875
250 ml Bottle
Rose Petals Kg 45 0.025 1.125
Pet Bottle No. 7.30 1 7.300
Total 8.425
Table 10: Cost of Material
Product BottlesCost (Rs.
/ Unit)
First YearProduction @70% capacityexcl. Finished
Goodsinventory
First YearCost (Rs.)
750 ml Packing 39,600 13.875 27,181 377,136
250 ml Packing 79,200 8.425 54,362 458,000
Total 835,136
12.8. Human Resource Requirement
Table 11: Human Resource Requirement
Description No. of Employees Salary perEmployee per
month
Owner / Manager 1 25,000
Helper 2 10,000
Salesman 1 15,000Security Guard 1 10,000
Total 5
The above table provides details of human resource required to run the proposed
unit. Owner / Manager will look after the financial, marketing and distribution
SMEDA Services / Information related to PMs Youth Business Loan are FREE OF COST - 10
-
8/21/2019 Rose Water (Rs. 0.86 Million)
12/18
Pre-Feasibility Studies Rose Water Processing Unit (Rs. 0.86 Million)
matters. Salesman will distribute rose water in the market under the supervision
of the owner. Salaries of all employees are estimated to increase at 10%
annually.
12.9. Revenue Generation
Table 12: First Year Revenue
Product BottlesSalesPrice
(Rs./Unit)
First YearProduction @70% capacityexcl. Finished
Goodsinventory
First YearSales
Revenue (Rs)
750 ml Packing 39,600 58 27,181 1,576,498
250 ml Packing 79,200 30 54,362 1,630,860
Total Sales Revenue 3,207,358
12.10. Other Costs
An essential cost to be borne by the unit is the marketing and office vehicle
running expenses, which are 10% and 7.5% of sales respectively.
13. CONTACT DETAILS OF SUPPLIERS,
EXPERTS/CONSULTANTS DEV. INSTITUTIONS
University of Agriculture, Horticulture
Department, Faisalabad
www.uaf.edu.pk
Tel: +92-41-9200161-70
Fax: +92-41-9200764
Hanif & Sons, 384 D, Salamat Pura, GT
Road, Lahore. Telephone: 042-
3654006, Fax: 042-36543084
PAMICO Technologies, P-124, Street No. 2,Shahad Colony, Jhang Road, Faisalabad.Tel: 041-2551911Web:www.pamicotechnologies.com
SMEDA Services / Information related to PMs Youth Business Loan are FREE OF COST - 11
http://www.pamicotechnologies.com/http://www.pamicotechnologies.com/http://www.pamicotechnologies.com/http://www.pamicotechnologies.com/ -
8/21/2019 Rose Water (Rs. 0.86 Million)
13/18
Pre-Feasibility Studies Rose Water Processing Unit (Rs.0.86 Million)
14. ANNEXURE
14.1. Income Statement
Calculations SMED
Income Statement
Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7 Year 8 Year 9 Year
Revenue 3,207,358 3,850,063 4,517,773 5,280,526 6,150,650 7,141,995 7,864,243 8,650,667 9,515,734 10,467,
Cost of sales
Cost of goods Sold 835,136 1,002,485 1,176,344 1,374,950 1,601,515 1,859,642 2,047,702 2,252,472 2,477,720 2,725,
Operation costs 1 (direct labor) 240,000 264,000 290,400 319,440 351,384 386,522 425,175 467,692 514,461 565,
Operating costs 2 (machinery maintenance) 12,650 13,915 15,307 16,837 18,521 20,373 22,410 24,651 27,116 29,
Operating costs 3 (Electricity, Gas and Water Expense) 319,200 376,200 441,408 515,896 600,867 697,673 767,440 844,184 928,603 1,021,
Total cost of sales 1,406,986 1,656,600 1,923,458 2,227,123 2,572,286 2,964,211 3,262,727 3,589,000 3,947,900 4,342,
Gross Profit 1,800,372 2,193,463 2,594,315 3,053,402 3,578,364 4,177,784 4,601,515 5,061,667 5,567,834 6,124,
General administration & selling expenses
Administration expense 600,000 660,000 726,000 798,600 878,460 966,306 1,062,937 1,169,230 1,286,153 1,414,
Building rental expense 336,000 369,600 406,560 447,216 491,938 541,131 595,244 654,769 720,246 792,
Office Vehicle Running Expenses 240,552 288,755 338,833 396,039 461,299 535,650 589,818 648,800 713,680 785,
Communications expense (phone, fax, mail, internet, etc.) 30,000 33,000 36,300 39,930 43,923 48,315 53,147 58,462 64,308 70,
Legal & Professional Charges - - - - - - - - -
Office expenses (stat ionary, entertai nment, j anit or ial ser vices, etc. ) 18,000 19,800 21,780 23,958 26,354 28,989 31,888 35,077 38,585 42,
Marketing Expenses 320,736 385,006 451,777 528,053 615,065 714,200 786,424 865,067 951,573 1,046,
Depreciation expense 62,500 62,500 62,500 62,500 62,500 64,489 64,489 64,489 64,489 64,
Amortization of pre-operating costs 9,349 9,349 9,349 9,349 9,349 - - - -
Amortization of legal, licensing, and training costs - - - - - - - - -
Bad debt expense 16,037 19,250 22,589 26,403 30,753 35,710 39,321 43,253 47,579 52,
Subtotal 1,633,173 1,847,260 2,075,688 2,332,047 2,619,640 2,934,790 3,223,269 3,539,147 3,886,613 4,268,
Operating Income 167,199 346,203 518,627 721,355 958,724 1,242,994 1,378,246 1,522,520 1,681,221 1,855,
Gain / (loss) on sale of office equipment - - - - 14,400 - - - -
Earnings Before Interest & Taxes 167,199 346,203 518,627 721,355 973,124 1,242,994 1,378,246 1,522,520 1,681,221 1,855,
Interest expense on long term debt (Project Loan) 64,628 59,168 51,991 44,219 35,801 26,685 16,812 6,119 -
Subtotal 64,628 59,168 51,991 44,219 35,801 26,685 16,812 6,119 -
Earnings Before Tax 102,570 287,035 466,636 677,137 937,323 1,216,310 1,361,435 1,516,401 1,681,221 1,855,
Tax - - 6,664 27,714 63,098 104,946 126,715 150,780 183,744 218,
NET PROFIT/(LOSS) AFTER TAX 102,570 287,035 459,972 649,423 874,225 1,111,363 1,234,720 1,365,621 1,497,477 1,637,
SMEDA Services / Information related to PMs Youth Business Loan are FREE OF COST - 12
-
8/21/2019 Rose Water (Rs. 0.86 Million)
14/18
Pre-Feasibility Studies Rose Water Processing Unit (Rs.0.86 Million)
14.2. Balance Sheet
Calculations SMEDA
Balance Sheet
Year 0 Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7 Year 8 Year 9 Year 10
Current assets
Cash & Bank 126,032 244,052 495,836 907,226 1,496,238 2,296,548 3,315,080 4,444,642 5,690,154 7,200,546 9,223,185
Accounts receivable 26,362 29,003 34,388 40,267 46,977 54,627 61,669 67,869 74,656 82,122
Finished goods inventory 27,901 32,253 37,446 43,355 50,071 57,696 63,442 69,786 76,765 84,441
Equipment spare part inventory 3,163 3,653 4,219 4,873 5,628 6,500 7,508 8,672 10,016 11,568 -
Raw material inventory 16,239 21,442 27,677 35,584 45,593 58,236 70,537 85,350 103,274 124,961 -
Pre-paid building rent 84,000 92,400 101,640 111,804 122,984 135,283 148,811 163,692 180,061 198,068 -
Total Current Assets 229,433 415,809 690,628 1,131,322 1,754,065 2,593,615 3,654,260 4,827,468 6,121,161 7,686,565 9,389,749
Fixed assetsMachinery & equipment 253,000 227,700 202,400 177,100 151,800 126,500 101,200 75,900 50,600 25,300 -
Furniture & fixtures 50,000 45,000 40,000 35,000 30,000 25,000 20,000 15,000 10,000 5,000 -
Office vehicles 250,000 225,000 200,000 175,000 150,000 125,000 100,000 75,000 50,000 25,000 -
Office equipment 36,000 28,800 21,600 14,400 7,200 45,946 36,757 27,568 18,378 9,189 -
Total Fixed Assets 589,000 526,500 464,000 401,500 339,000 322,446 257,957 193,468 128,978 64,489 -
Intangible assets
Pre-operation costs 46,743 37,395 28,046 18,697 9,349 - - - - - -
Legal, licensing, & training costs - - - - - - - - - - -
Total Intangible Assets 46,743 37,395 28,046 18,697 9,349 - - - - - -
TOTAL ASSETS 865,176 979,704 1,182,674 1,551,519 2,102,414 2,916,061 3,912,217 5,020,935 6,250,139 7,751,054 9,389,749
Current liabilities
Accounts payable 11,957 14,360 16,878 19,767 23,079 26,823 29,646 32,745 36,183 37,744
Total Current Liabilities - 11,957 14,360 16,878 19,767 23,079 26,823 29,646 32,745 36,183 37,744
Other liabilities
Deferred tax - - - - - - - - - -
Long term debt (Project Loan) 778,659 778,659 692,190 598,545 497,128 387,292 268,341 139,517 - - -
Total Long Term Liabilities 778,659 778,659 692,190 598,545 497,128 387,292 268,341 139,517 - - -
Shareholders' equity
Paid-up capital 86,518 86,518 86,518 86,518 86,518 132,464 132,464 132,464 132,464 132,464 132,464
Retained earnings 102,570 389,606 849,578 1,499,001 2,373,226 3,484,589 4,719,309 6,084,930 7,582,407 9,219,541
Total Equity 86,518 189,088 476,123 936,096 1,585,519 2,505,690 3,617,053 4,851,773 6,217,394 7,714,871 9,352,004
TOTAL CAPITAL AND LIABILITIES 865,176 979,704 1,182,674 1,551,519 2,102,414 2,916,061 3,912,217 5,020,935 6,250,139 7,751,054 9,389,749
Liabilities & Shareholders' Equity
Assets
SMEDA Services / Information related to PMs Youth Business Loan are FREE OF COST - 13
-
8/21/2019 Rose Water (Rs. 0.86 Million)
15/18
Pre-Feasibility Study Rose Water Processing Unit (Rs. 0.86 Million)
14.3. Cash Flow Statement
Calculations SMEDA
Cash Flow Statement
Year 0 Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Year 7 Year 8 Year 9 Year 10
Operating activities
Net profit 102,570 287,035 459,972 649,423 874,225 1,111,363 1,234,720 1,365,621 1,497,477 1,637,134
Add: depreciation expense 62,500 62,500 62,500 62,500 62,500 64,489 64,489 64,489 64,489 64,489
amortization of pre-operating costs 9,349 9,349 9,349 9,349 9,349 - - - - -
amortization of training costs - - - - - - - - - -
Deferred income tax - - - - - - - - - -
Accounts receivable (26,362) (2,641) (5,385) (5,879) (6,710) (7,650) (7,042) (6,200) (6,787) (7,466)
Finished goods inventory (27,901) (4,353) (5,193) (5,909) (6,716) (7,626) (5,745) (6,344) (6,979) (7,676)
Equipment inventory (3,163) (490) (566) (654) (755) (872) (1,008) (1,164) (1,344) (1,552) 11,568
Raw material inventory (16,239) (5,203) (6,235) (7,908) (10,008) (12,643) (12,302) (14,813) (17,924) (21,687) 124,961
Pre-paid building rent (84,000) (8,400) (9,240) (10,164) (11,180) (12,298) (13,528) (14,881) (16,369) (18,006) 198,068
Accounts payable 11,957 2,403 2,518 2,889 3,312 3,744 2,823 3,100 3,438 1,561
Cash provided by operations (103,401) 118,020 338,252 505,036 690,429 910,145 1,137,483 1,258,387 1,385,029 1,510,392 2,022,639
Financing activities
Project Loan - principal repayment - (86,468) (93,645) (101,418) (109,835) (118,951) (128,824) (139,517) - -
Additions to Project Loan 778,659 - - - - - - - - - -
Issuance of shares 86,518 - - - - 45,946 - - - - -
Cash provided by / (used for) financing activities 865,176 - (86,468) (93,645) (101,418) (63,889) (118,951) (128,824) (139,517) - -
Investing activities
Capital expenditure (635,743) - - - - (45,946) - - - - -
Acquisitions
Cash (used for) / provided by investing activities (635,743) - - - - (45,946) - - - - -
NET CASH 126,032 118,020 251,784 411,390 589,012 800,310 1,018,532 1,129,562 1,245,512 1,510,392 2,022,639
SMEDA Services / Information related to PMs Youth Business Loan are FREE OF COST - 14
-
8/21/2019 Rose Water (Rs. 0.86 Million)
16/18
Pre-Feasibility Study Rose Water Processing Unit (Rs. 0.86 Million)
14.4. Useful Project Management Tips
Technology
Required Spare Parts & Consumables: Suppliers credit agreements and
availability as per schedule of maintenance be ensured before start ofoperations.
Energy Requirement:Should not be overestimated or installed in excess and
alternate source of energy for critical operations are arranged in advance.
Machinery Suppl iers: Training and after sales services should be sought
under the contract with the machinery suppliers.
Quality Assurance Equipment & Standards: Products quality standards
need to be defined on the packaging and a system to check them instituted.
This improves credibility.
Marketing
Product Development & Packaging: Expert's help may be engaged for
product/service and packaging design & development.
Ads & P.O.S. Promotion: Business promotion and dissemination through
banners and launch events is highly recommended. Product brochures from
good quality service providers
Sales & Distribution Network: Expert's advice and distribution agreements
are required with the distribution.
Price - Bulk Discounts, Cost plus Introductory Discounts: Price should
never be allowed to compromise quality. Price during introductory phase may
be lower and used as a promotional tool. Product cost estimates should be
carefully documented before price setting. Government controlled prices
should be displayed, where applicable.
Human Resources
Adequacy & Competencies: Recruitment of skilled and experienced staff.
Performance Based Remuneration:Attempt to manage human resource cost
should be focused through performance measurement and performance based
compensation.
SMEDA Services / Information related to PMs Youth Business Loan are FREE OF COST - 15
-
8/21/2019 Rose Water (Rs. 0.86 Million)
17/18
Pre-Feasibility Study Rose Water Processing Unit (Rs. 0.86 Million)
14.5. Useful Links
Prime Ministers Office,www.pmo.gov.pk
Small and Medium Enterprise Development Authority,www.smeda.org.pk
National Bank of Pakistan (NBP),www.nbp.com.pk
First Women Bank Limited (FWBL),www.fwbl.com.pk
Government of Pakistan, www.pakistan.gov.pk
Ministry of Industries & Production, www.moip.gov.pk
Ministry of Education, Training & Standards in Higher Education,http://moptt.gov.pk
Government of Punjab, www.punjab.gov.pk
Government of Sindh, www.sindh.gov.pk
Government of Khyber Pakhtunkhwa, www.khyberpakhtunkhwa.gov.pk
Government of Balochistan, www.balochistan.gov.pk
Government of Gilgit Baltistan, www.gilgitbaltistan.gov.pk
Government of Azad Jammu & Kashmir, www.ajk.gov.pk
Trade Development Authority of Pakistan (TDAP), www.tdap.gov.pk
Securities and Exchange Commission of Pakistan (SECP),www.secp.gov.pk
Federation of Pakistan Chambers of Commerce and Industry (FPCCI),www.fpcci.com.pk
State Bank of Pakistan (SBP), www.sbp.org.pk
University of Agriculture Faisalabad www.uaf.edu.pk
Barani Agriculture Research Institute, Chakwal, www.barichakwal.org
Pakistan Agricultural Research Council (PARC) www.parc.gov.pk
SMEDA Services / Information related to PMs Youth Business Loan are FREE OF COST - 16
http://www.pmo.gov.pk/http://www.pmo.gov.pk/http://www.pmo.gov.pk/http://www.smeda.org.pk/http://www.smeda.org.pk/http://www.smeda.org.pk/http://www.nbp.com.pk/http://www.nbp.com.pk/http://www.nbp.com.pk/http://www.fwbl.com.pk/http://www.fwbl.com.pk/http://www.fwbl.com.pk/http://www.fwbl.com.pk/http://www.nbp.com.pk/http://www.smeda.org.pk/http://www.pmo.gov.pk/ -
8/21/2019 Rose Water (Rs. 0.86 Million)
18/18
Pre-Feasibility Study Rose Water Processing Unit (Rs. 0.86 Million)
15. KEY ASSUMPTIONS
Table 13: Operating Assumptions
Days Operational per Year (Days) 330
Accounts Payable (Days) 5
Accounts Receivable (Days) 3Raw Material Inventory (Days) 7
Finished Goods Inventory (Days) 7
Table 14: Expense Assumptions
Marketing Expenses 10% of Sales
Vehicle Running Expenses 7.5% of Sales
Bad Debt Expenses 0.50% of Sales
Electricity Expenses @70% capacity (Year 1) Rs. 2,100 per month
Gas Expenses @70% capacity (Year 1) Rs. 21,000 per month
Water Expenses @70% capacity (Year 1) Rs. 3,500 per month
SMEDA Services / Information related to PMs Youth Business Loan are FREE OF COST - 17