route 1 and harrison road intersection improvements · (540) 903-5253 office/cell...
TRANSCRIPT
![Page 1: Route 1 and Harrison Road Intersection Improvements · (540) 903-5253 office/cell Randall.McKinney@VDOT.Virginia.Gov Kelly Hannon VDOT Communications Manager (540) 374-3344 office](https://reader034.vdocument.in/reader034/viewer/2022050309/5f7130fdb2a16a7d9768160a/html5/thumbnails/1.jpg)
April 27, 2016
Randy McKinney, P.E.
Virginia Department of Transportation,
Fredericksburg District
Area Construction Engineer
Route 1 and Harrison Road
Intersection Improvements
![Page 2: Route 1 and Harrison Road Intersection Improvements · (540) 903-5253 office/cell Randall.McKinney@VDOT.Virginia.Gov Kelly Hannon VDOT Communications Manager (540) 374-3344 office](https://reader034.vdocument.in/reader034/viewer/2022050309/5f7130fdb2a16a7d9768160a/html5/thumbnails/2.jpg)
Route 1 and Harrison Road Spotsylvania County 2
![Page 3: Route 1 and Harrison Road Intersection Improvements · (540) 903-5253 office/cell Randall.McKinney@VDOT.Virginia.Gov Kelly Hannon VDOT Communications Manager (540) 374-3344 office](https://reader034.vdocument.in/reader034/viewer/2022050309/5f7130fdb2a16a7d9768160a/html5/thumbnails/3.jpg)
What will the project do?
• Reduce delay for motorists
• Widen intersection to increase capacity by
adding turn lanes and through lanes
• New pedestrian crossings, traffic signal
equipment and lighting
• New shared-use path and additional sidewalks
• Close frontage road entrances at the
intersection for safety
• Construct raised medians
3
![Page 4: Route 1 and Harrison Road Intersection Improvements · (540) 903-5253 office/cell Randall.McKinney@VDOT.Virginia.Gov Kelly Hannon VDOT Communications Manager (540) 374-3344 office](https://reader034.vdocument.in/reader034/viewer/2022050309/5f7130fdb2a16a7d9768160a/html5/thumbnails/4.jpg)
Fast Facts:
Construction
• Construction begins
May 2, 2016
• Project contractor is
Henderson Construction Co. of
Stafford, Va.
• 24 months of construction
• Project completion May 2018
• Incentive to finish early is
$2,500 a day up to 100 days
ahead of schedule
4
Project Cost
Preliminary Engineering: $2.1 million
Right of Way: $8.1 million
Construction: $12.4 million
TOTAL
$22.7 million
![Page 5: Route 1 and Harrison Road Intersection Improvements · (540) 903-5253 office/cell Randall.McKinney@VDOT.Virginia.Gov Kelly Hannon VDOT Communications Manager (540) 374-3344 office](https://reader034.vdocument.in/reader034/viewer/2022050309/5f7130fdb2a16a7d9768160a/html5/thumbnails/5.jpg)
Harrison Road westbound,
east of Route 1
Existing condition:
• Shared left turn/through lane
• Right turn only lane
After construction:
• Left turn only lane
• Through lane
• Shared through/right turn lane
5
![Page 6: Route 1 and Harrison Road Intersection Improvements · (540) 903-5253 office/cell Randall.McKinney@VDOT.Virginia.Gov Kelly Hannon VDOT Communications Manager (540) 374-3344 office](https://reader034.vdocument.in/reader034/viewer/2022050309/5f7130fdb2a16a7d9768160a/html5/thumbnails/6.jpg)
Harrison Road eastbound,
west of Route 1
Existing condition:
• Shared left turn/through lane
• Right turn only lane
After construction:
• 2 left turn only lanes
• Through lane
• Right turn only lane
6
![Page 7: Route 1 and Harrison Road Intersection Improvements · (540) 903-5253 office/cell Randall.McKinney@VDOT.Virginia.Gov Kelly Hannon VDOT Communications Manager (540) 374-3344 office](https://reader034.vdocument.in/reader034/viewer/2022050309/5f7130fdb2a16a7d9768160a/html5/thumbnails/7.jpg)
Route 1 southbound
Existing condition:
• Left turn only lane
• 2 through lanes
• Right turn only lane
After construction:
• Left turn only lane
• 3 through lanes
• Right turn only lane
7
![Page 8: Route 1 and Harrison Road Intersection Improvements · (540) 903-5253 office/cell Randall.McKinney@VDOT.Virginia.Gov Kelly Hannon VDOT Communications Manager (540) 374-3344 office](https://reader034.vdocument.in/reader034/viewer/2022050309/5f7130fdb2a16a7d9768160a/html5/thumbnails/8.jpg)
Route 1 northbound
Existing condition:
• Left turn only lane
• 2 through lanes
After construction:
• 2 left turn only lanes
• 2 through lanes
• Right turn only lane
8
![Page 9: Route 1 and Harrison Road Intersection Improvements · (540) 903-5253 office/cell Randall.McKinney@VDOT.Virginia.Gov Kelly Hannon VDOT Communications Manager (540) 374-3344 office](https://reader034.vdocument.in/reader034/viewer/2022050309/5f7130fdb2a16a7d9768160a/html5/thumbnails/9.jpg)
Wallace Lane access
Existing condition:
• Wallace Lane access from
frontage road (Loren Drive) at intersection
After construction:
• Loren Drive ends at 4 Mile Fork Business Center
• New connector road to Wallace
Lane built off Harrison Road
• Road built on former Harrison
Road Community Center property
• New entrances built from Route 1 to
access Fleming Street and Extra Space
Storage/Fredericksburg Auto Sales 9
![Page 10: Route 1 and Harrison Road Intersection Improvements · (540) 903-5253 office/cell Randall.McKinney@VDOT.Virginia.Gov Kelly Hannon VDOT Communications Manager (540) 374-3344 office](https://reader034.vdocument.in/reader034/viewer/2022050309/5f7130fdb2a16a7d9768160a/html5/thumbnails/10.jpg)
Lee Street
• Lee Street will end at cul-de-sac east of Route 1
• New Lee Street connector road will intersect with
Mosby Street
• New direct entrance to Mosby Street built from
Route 1 northbound
• Wicker Street ends at Beauregard Street
10
![Page 11: Route 1 and Harrison Road Intersection Improvements · (540) 903-5253 office/cell Randall.McKinney@VDOT.Virginia.Gov Kelly Hannon VDOT Communications Manager (540) 374-3344 office](https://reader034.vdocument.in/reader034/viewer/2022050309/5f7130fdb2a16a7d9768160a/html5/thumbnails/11.jpg)
Estimated Construction
Schedule
Spring-Summer 2016
• Demolition of buildings
• Complete power, gas, phone, and Internet/cable
utility relocation
• Start water line, drainage, and sewer work
• Construction of Wallace Lane connector
• Construction of Lee Street connector
• Open new Route 1 access points
• Close frontage roads
• Construct storm water management basin
11
![Page 12: Route 1 and Harrison Road Intersection Improvements · (540) 903-5253 office/cell Randall.McKinney@VDOT.Virginia.Gov Kelly Hannon VDOT Communications Manager (540) 374-3344 office](https://reader034.vdocument.in/reader034/viewer/2022050309/5f7130fdb2a16a7d9768160a/html5/thumbnails/12.jpg)
Estimated Construction
Schedule
Fall 2016-Winter 2017
• Continue water line, drainage and sewer work
• Start constructing Route 1 and eastbound Harrison
Road lanes
Spring-Summer 2017
• Continue construction of Route 1 lanes
• Continue water line and drainage work, complete
sewer work
• Traffic signal equipment installation
12
![Page 13: Route 1 and Harrison Road Intersection Improvements · (540) 903-5253 office/cell Randall.McKinney@VDOT.Virginia.Gov Kelly Hannon VDOT Communications Manager (540) 374-3344 office](https://reader034.vdocument.in/reader034/viewer/2022050309/5f7130fdb2a16a7d9768160a/html5/thumbnails/13.jpg)
Estimated Construction
Schedule
Fall 2017-Winter 2018
• Construct westbound Harrison Road lanes
• Complete water line and drainage work
• Construct medians
Spring 2018
• Final paving
• Placement of final pavement markings/signs
• Sidewalk, shared-use path completion
13
![Page 14: Route 1 and Harrison Road Intersection Improvements · (540) 903-5253 office/cell Randall.McKinney@VDOT.Virginia.Gov Kelly Hannon VDOT Communications Manager (540) 374-3344 office](https://reader034.vdocument.in/reader034/viewer/2022050309/5f7130fdb2a16a7d9768160a/html5/thumbnails/14.jpg)
How will construction
affect me?
Lane closures
• Most will occur at night and off-peak travel times
Route 1
9 p.m. - 6 a.m. Monday - Friday
10 p.m. - 10 a.m. Saturday and Sunday
Harrison Road, Route 1 to Pine Needle Court
10 p.m. - 5:30 a.m. Monday - Sunday
Harrison Road, West of Pine Needle Court
8 p.m. - 5:30 a.m. Monday – Friday
8 p.m. - 8 a.m. Saturday and Sunday
14
![Page 15: Route 1 and Harrison Road Intersection Improvements · (540) 903-5253 office/cell Randall.McKinney@VDOT.Virginia.Gov Kelly Hannon VDOT Communications Manager (540) 374-3344 office](https://reader034.vdocument.in/reader034/viewer/2022050309/5f7130fdb2a16a7d9768160a/html5/thumbnails/15.jpg)
How will construction
affect me?
Pardon our dust!
• Equipment
• Barrels, cones and workers
• Stay alert for new traffic patterns
• Temporary driving surface may be rough
• New pavement surface placed at end of
project
• 511Virginia.org has real-time work zone
information
15
![Page 16: Route 1 and Harrison Road Intersection Improvements · (540) 903-5253 office/cell Randall.McKinney@VDOT.Virginia.Gov Kelly Hannon VDOT Communications Manager (540) 374-3344 office](https://reader034.vdocument.in/reader034/viewer/2022050309/5f7130fdb2a16a7d9768160a/html5/thumbnails/16.jpg)
16
Who can I contact with
questions?
Randy McKinney, P.E.
Area Construction Engineer
(540) 903-5253 office/cell
Kelly Hannon
VDOT Communications Manager
(540) 374-3344 office
(540) 656-0321 cell
1-800-FOR-ROAD
VDOT Customer Service Center
Open 24 hours a day, 7 days a week
![Page 17: Route 1 and Harrison Road Intersection Improvements · (540) 903-5253 office/cell Randall.McKinney@VDOT.Virginia.Gov Kelly Hannon VDOT Communications Manager (540) 374-3344 office](https://reader034.vdocument.in/reader034/viewer/2022050309/5f7130fdb2a16a7d9768160a/html5/thumbnails/17.jpg)
Thank you! 17