rpg meeting 07-18-2008 five year plan extension brad schwarz
TRANSCRIPT
RPG Meeting 07-18-2008
Five Year Plan Extension
Brad Schwarz
RPG Meeting 07-18-2008
Outline
• Goals
• Method
• Other Considerations
• Status
RPG Meeting 07-18-2008
Goals for Five Year Plan Extension
• The 5-Year Plan extension will:– List all topology changes to the 2012 case– Identify projects to meet identified needs for reliability criteria
only
• Ultimate goal is to obtain a case to be used for evaluation of potential RPG projects until the full 5-Year Plan begins later in 2008
RPG Meeting 07-18-2008
Method of Study
• Transmission Topology from the final 2012 Uplan case that contained all reliability and economic projects
• Load level from the latest 2013 SSWG data set B case
• Added generators that had signed Interconnect Agreements as of the first week of June– Added 1878 MW of Natural Gas generation– Added 2919 MW of Wind generation (9102 total
nameplate wind generation)
RPG Meeting 07-18-2008
Method of Study Cont’d
• Identification of Reliability Projects– Eliminate unserved energy using the 2013
SSWG peak load forecast– ERCOT will develop “direct fix” projects and
send to Transmission Owners– Transmission Owners should review “direct
fix” projects and submit alternatives if desired
• Document work on each project added to simplify RPG Independent Review process
RPG Meeting 07-18-2008
Other Considerations
• Currently consider ERCOT category B contingencies– N – 1 contingencies (single circuit, double circuit,
transformer, etc.)– Single generator out plus loss of single transmission
element
• Other tests for reliability– Remove dynamic ratings on lines– No output from hydro units– NERC category C contingencies (Single transformer
out plus loss of single transmission element)
RPG Meeting 07-18-2008
Status
• Currently finished with first round of reliability analysis
• Next Steps– Send out first round of reliability analysis results to
Transmission Owners– Simulate generators out and contingency analysis– Simulate NERC Category C contingencies– Possibly simulate 2 generating unit out
simultaneously
RPG Meeting 07-18-2008
Questions?