RSRDC. UNIT- II, AJMER. ORGANISATION CHART OF RSRDC UNIT-II, AJMER. P.K.Arora. Vacant (Addl. Charge to Sh. Sunil jain. ARE. Sh. Lokesh Gupte Sh. Lalit Sharma. 3. Sh. Ashish Sharma 4. Sh. Harsh Rai. Financial Work Load in Unit. Rs. In Lacs. - PowerPoint PPT PresentationTRANSCRIPT
RSRDC
UNIT- II, AJMER
ORGANISATION CHART OF RSRDC UNIT-II, AJMER
P.K.Arora
ARE1. Sh. Lokesh Gupte
2. Sh. Lalit Sharma
3. Sh. Ashish Sharma
4. Sh. Harsh Rai
Vacant(Addl. Charge to Sh. Sunil jain
Financial Work Load in UnitS.
No. Name of Work Client Deptt. A& F Sanction Expenditure till date
Balance Work
ARE – I Sh. Lokesh Gupta
1 Construction of ROB with approaches (Excluding railway portion) on Dholpur-Rajakhera road Km-3 on SH-2
PWD 1000.00 579.43 420.57
2 Construction of ROB with approaches at LC No. 472 (1305/6-8 Mania-Marena road) Jhansi-Agra Section.
PWD 1000.00 0.03 999.97
ARE – II Sh. Lalit Sharma
1 Construction of 2 lane ROB with approaches (excluding Railway portion) at MDR 37-A on Nagour-Basni Road in lieu of LC No. 63-C (On NH-89)
PWD 1300.00
ARE – II 600.00 191.45 408.55
ARE - IV 700.00 197.41 502.59
Rs. In Lacs
S. No. Name of Work Client
Deptt.A& F
SanctionExpenditure
till dateBalance
Work
ARE – III Sh. Ashish Sharma
1 Construction of ROB & approaches on Bhilwara -Chittorgarh BG Track at Bhilwara. (UIT Work)
UIT Bhilwara
2086.00 1327.31+
385.00(Rly.)
373.69
ARE – IV Sh. Harsh Rai
1 Construction of ROB & approaches on Phalodi-Mandal-Bhilwara road in lieu of LC No. 63-C
PWD 1000.00 870.32 129.68
2 Construction of ROB on Manglana - Makrana road in lieu of LC No. 36 Kuchaman city Makrana section SH-2B
PWD 1000.00 305.16 694.84
ARE – V Sh. Brijesh Mathur of Unit-I,Ajmer
1 Construction of ROB in Km. 70 of Kishangarh -Roopangarh road SH-07 in lieu of LC No. 28 NWR.
PWD 1000.00 843.67 156.33
2 Construction of ROB (excluding Railway portion) and approaches on Ajmer-Beawer road in lieu of LC No. 5A/2E
PWD 1000.00 783.28 216.72
Regional Pollution Control Board office, Bhilwara
Completion Cost – Rs. 23.97 lacs
Important Works Completed during last 5 years
Construction of ROB at Kishangarh, Ajmer
Total Cost : Rs. 10.00 Crores
Location : Kishangarh, Ajmer
Date of Start : 18.03.2007
Stipulated Date of Completion : 17.01.2008
Expenditure till Date : Rs. 843.96 Lacs
Likely Completion date : 30.6.2010 (Depends on Railway work)
Bottlenecks if any : Two nos span and finishing dependant on railway work
Status of railway work : Sub structure work completed. Idle since last six months due to finalisation of drawing & design of super structure.
Construction of ROB at Saradhna, Ajmer
Total Cost : Rs. 10.00 Crores
Location : Beawar road, Ajmer
Date of Start : 17.07.2007
Stipulated Date of Completion : 16.06.2008
Expenditure till Date : Rs. 783.56 Lacs
Likely Completion date : 31.12.2010 (Depends on Railway work)
Bottlenecks if any : Gap slab connecting rly. portion and finishing dependant on railway work
Status of railway work : Lay out & shifting of cable work in progress.
Construction of ROB at Bhilwara(UIT Work)
Total Cost : Rs. 20.86 Crores
Location : Bhilwara
Date of Start : 18.03.2007
Stipulated Date of Completion : 17.11.2007Expenditure till Date : Rs. 1327.31 lacs + Rs385.00 lacs (Rly.)Likely Completion date : 31.05.2010 (Depends on Railway work)
Bottlenecks if any : Two nos span and finishing dependant on railway work
Status of railway work : Sub structure work completed.
Super structure work in progress.
Construction of ROB at Mandal (Bhilwara)
Total Cost : Rs. 10.00 Crores
Location : Mandal, Bhilwara
Date of Start : 19.07.2007
Stipulated Date of Completion : 18.06.2008Expenditure till Date : Rs. 870.46 LacsLikely Completion date : 30.06.2010 (Depends on Railway work)
Bottlenecks if any : Two nos span and finishing dependant on railway work
Status of railway work : Sub structure work in progress.
Construction of ROB at Makrana Distt. - Nagour)
Total Cost : Rs. 10.00 Crores
Location : Makrana, (Distt.-Nagour)
Date of Start : 23.08.2008
Stipulated Date of Completion : 22.07.2009Expenditure till Date : Rs. 390.67 lacs.Likely Completion date : 30.09.2010 (Depends on Railway work)
Bottlenecks if any : Shifting of electric lines & encroachments.
Status of railway work : Work order placed. Work yet not started.
Construction of ROB at Nagour
Total Cost : Rs. 13.00 Crores
Location : Nagour
Date of Start : 21.08.2008
Stipulated Date of Completion : 20.07.2009Expenditure till Date : Rs. 405.45 lacs.Likely Completion date : 30.09.2010 (Depends on Railway work)
Bottlenecks if any : -
Status of railway work : Work order issued. Work yet not started.
Construction of ROB at Dholpur
Total Cost : Rs. 10.00 Crores
Location : Dholpur
Date of Start : 17.11.2007
Stipulated Date of Completion : 16.10.2008Expenditure till Date : Rs. 609.36 lacs.Likely Completion date : 30.09.2010 (Depends on Railway work)
Bottlenecks if any : -
Status of railway work : Work order issued. Work yet not started.
Construction of ROB at Mania-Marena Road
Total Cost : Rs. 10.00 Crores
Location : Mania, Dholpur
Date of Start : -
Stipulated Date of Completion : -Expenditure till Date : Rs. 0.03 lacs.Likely Completion date :
Bottlenecks if any : The present LC No. 472 is a part of Bye pass for ROB at LC No. 463. Hence traffic is to be bye passed at LC No. 473 which requires interlocking. Railway has agreed for interlocking & up gradation. Which shall be completed by Feb-2010. Revised A&F required amounting to Rs. 16.15 Crore Estimate Submitted to CE PWD through ACE Zone Bharatpur
Status of railway work : Revised GAD pending at Railway part for approval, likely to be received in Dec. 2009’
Proposed New WorksS. No. Name of Work Client Deptt. Mode Estimated Cost
1 Construction of Academic block at MLV Textile & Engineering College, Bhilwara
MLVT, Bhilwara Actual plus Rs. 350.00 lacs
2 Construction of Urban Co Operative bank at Shastri Nagar Bhilwara
BUCB Bhilwara Actual plus Rs. 50.00 Lacs