Run 16 RHIC Machine/Experiments Meeting 5 Jan 2016 Agenda: Run 16 Schedule (Pile) AuAu Run Plan (Gu) Projections for deuteron-gold energy scan (Liu) STAR (Xu) PHENIX (Jouan) Other READYTALK LOGIN INFO Audio Login Toll-Free (US & Canada): 866.740.1260 Toll: 303.248.0285 Access Code: 8304505 ReadyTalk link https://core.readytalk.com/interface/guest.jsp?host=readytalk&an=8667401260&ac=8304505

Upload: others

Post on 03-Jun-2020

6 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Run 16 RHIC Machine/Experiments Meeting€¦ · Run 16 RHIC Machine/Experiments Meeting 5 Jan 2016 ... Executive Summary Table Run Energy Duration System Goals priority Sequence 16

Run 16 RHIC Machine/Experiments Meeting

5 Jan 2016

Agenda: • Run 16 Schedule (Pile) • AuAu Run Plan (Gu) • Projections for deuteron-gold energy scan (Liu) • STAR (Xu) • PHENIX (Jouan) • Other

READYTALK LOGIN INFO Audio Login Toll-Free (US & Canada): 866.740.1260 Toll: 303.248.0285 Access Code: 8304505 ReadyTalk link https://core.readytalk.com/interface/guest.jsp?host=readytalk&an=8667401260&ac=8304505

Page 2: Run 16 RHIC Machine/Experiments Meeting€¦ · Run 16 RHIC Machine/Experiments Meeting 5 Jan 2016 ... Executive Summary Table Run Energy Duration System Goals priority Sequence 16

http://www.bnl.gov/cad/esfd

Scheduling Physicist: Christie

AGS-Booster-Tandem/Linac/EBIS Startup

RHIC Cryo scrub & Cooldown to 45 deg K

RHIC Cryo Cooldown/Warm-up

RHIC Cryo Operation

RHIC Cryo off

AGS polarized proton studies

RHIC STAR & PHENIX

RHIC Research with s = 200 GeV/n AuAu

RHIC Research with s = 200,62,39,20 GeV/n dAu

CeC POP Experiment E=40 GeV/n Au

Contingency

NSRL (NASA Radiobiology)

NSRL (NASA-Langley)

BLIP (Isotopes)

BLIP (Other)

Shutdown (RHIC)

C-A Operations-FY16

Program Element Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep

FY 2015

5 Jan 16

setup with beams

Sep

concurrent with RHIC

ramp up luminosity

setup as required

16 weeks

10 weeks4.7 physics wks

.4 weeks

12 Oct20 Nov

15C4 April

4 Jan

16A

5.5 weeks

TBD 30 June

19 Jan

planned

20 weeks

7 Jun

16B

27 May

TBD

31 Jul

15 Apr 22 Jan 5 days

1 Apr

21 Mar

19 Oct20 Oct

3 Jun

Page 3: Run 16 RHIC Machine/Experiments Meeting€¦ · Run 16 RHIC Machine/Experiments Meeting 5 Jan 2016 ... Executive Summary Table Run Energy Duration System Goals priority Sequence 16

Run 15 plan based on 20 weeks cryo operation and Fischer et.al. RHIC Collider Projections (FY 2016 – FY 2022), 19 April 2015

today, 5 Jan…

• 19 Jan, Begin cool-down to 4.5K

• 22 Jan, Beam in Blue

• 5 Feb, Begin 10 week √s=200 GeV/n AuAu physics run • 15 April, End 10 week √s=200 GeV/n AuAu physics run

• 19 April, Begin 1.2 week √s=200 GeV/n dAu physics run • 27 April, End 1.2 week √s=200 GeV/n dAu physics run

• 29 April, Begin 1.2 week √s=62 GeV/n dAu physics run • 7 May, End 1.2 week √s=62 GeV/n dAu physics run

• 9 May, Begin 1.2 week √s=39 GeV/n dAu physics run • 17 May, End 1.2 week √s=39 GeV/n dAu physics run

• 19 May, Begin 1.2 week √s=20 GeV/n dAu physics run • 27 May, End 1.2 week √s=20 GeV/n dAu physics run

• 29 May, Begin 5 day E=40 GeV/n Au CEC physics run • 3 June, End 5 day √s=40 GeV/n Au CEC physics run

• 3 June, begin cryo warm-up • 7 June, cryo warm-up complete, 20.0 cryo weeks of operation See http://www.rhichome.bnl.gov/AP/RHIC2016/ for the Run Coordinator’s detailed plan

Note 2 day setup time assumed between energy scan runs, Chuyu assumes 0.5 weeks and scan in ascending order

Page 4: Run 16 RHIC Machine/Experiments Meeting€¦ · Run 16 RHIC Machine/Experiments Meeting 5 Jan 2016 ... Executive Summary Table Run Energy Duration System Goals priority Sequence 16

From Fischer et. al., RHIC Collider Projections (FY 2016 – FY 2022), 19 April 2015

Page 5: Run 16 RHIC Machine/Experiments Meeting€¦ · Run 16 RHIC Machine/Experiments Meeting 5 Jan 2016 ... Executive Summary Table Run Energy Duration System Goals priority Sequence 16

From Fischer et. al., RHIC Collider Projections (FY 2016 – FY 2022), 19 April 2015

PHENIX goals 10 weeks, 1.8 nb-1 with 12 billion MB events recorded within |z|< 10 cm vertex STAR goals 13 weeks 10nb-1 sampled for MTD and 2 billion MB events recorded for HFT, request dynamic b* squeeze

Page 6: Run 16 RHIC Machine/Experiments Meeting€¦ · Run 16 RHIC Machine/Experiments Meeting 5 Jan 2016 ... Executive Summary Table Run Energy Duration System Goals priority Sequence 16

From Fischer et. al., RHIC Collider Projections (FY 2016 – FY 2022), 19 April 2015

----- 11.0 ----- 5.0 ----- 1.5

Chuyu’s latest projections

Page 7: Run 16 RHIC Machine/Experiments Meeting€¦ · Run 16 RHIC Machine/Experiments Meeting 5 Jan 2016 ... Executive Summary Table Run Energy Duration System Goals priority Sequence 16

Balanced Billing for the lab +$148K (ahead) Sep through Nov 2015

Page 8: Run 16 RHIC Machine/Experiments Meeting€¦ · Run 16 RHIC Machine/Experiments Meeting 5 Jan 2016 ... Executive Summary Table Run Energy Duration System Goals priority Sequence 16
Page 9: Run 16 RHIC Machine/Experiments Meeting€¦ · Run 16 RHIC Machine/Experiments Meeting 5 Jan 2016 ... Executive Summary Table Run Energy Duration System Goals priority Sequence 16

Archive

Page 10: Run 16 RHIC Machine/Experiments Meeting€¦ · Run 16 RHIC Machine/Experiments Meeting 5 Jan 2016 ... Executive Summary Table Run Energy Duration System Goals priority Sequence 16

Who’s Who for 2016

RHIC 100 x 100 GeV AuAu: Run Coordinator: Xiaofeng Gu, [email protected] , 631-344-4724 RHIC dAu Energy Scan: Run Coordinator: Chuyu Liu, [email protected] , 631-344-4431 RHIC CeC POP Experiment: Run Coordinator: TBD Scheduling Physicist: Bill Christie, [email protected], 631-344-7137 (x4643 after 29 Jan) Assistant Scheduling Physicists through 29 Jan: Yousef Makdisi, [email protected], 631-344-4932 Phil Pile, [email protected], 631-344-4643 AGS Liaison: Haixin Huang, [email protected] , 631-344-5446

Page 11: Run 16 RHIC Machine/Experiments Meeting€¦ · Run 16 RHIC Machine/Experiments Meeting 5 Jan 2016 ... Executive Summary Table Run Energy Duration System Goals priority Sequence 16
Page 12: Run 16 RHIC Machine/Experiments Meeting€¦ · Run 16 RHIC Machine/Experiments Meeting 5 Jan 2016 ... Executive Summary Table Run Energy Duration System Goals priority Sequence 16
Page 13: Run 16 RHIC Machine/Experiments Meeting€¦ · Run 16 RHIC Machine/Experiments Meeting 5 Jan 2016 ... Executive Summary Table Run Energy Duration System Goals priority Sequence 16
Page 14: Run 16 RHIC Machine/Experiments Meeting€¦ · Run 16 RHIC Machine/Experiments Meeting 5 Jan 2016 ... Executive Summary Table Run Energy Duration System Goals priority Sequence 16
Page 15: Run 16 RHIC Machine/Experiments Meeting€¦ · Run 16 RHIC Machine/Experiments Meeting 5 Jan 2016 ... Executive Summary Table Run Energy Duration System Goals priority Sequence 16
Page 16: Run 16 RHIC Machine/Experiments Meeting€¦ · Run 16 RHIC Machine/Experiments Meeting 5 Jan 2016 ... Executive Summary Table Run Energy Duration System Goals priority Sequence 16

Who’s Who for 2016

RHIC 100 x 100 GeV AuAu: Run Coordinator: Xiaofeng Gu, [email protected] , 631-344-5446 (office) RHIC dAu Energy Scan: Run Coordinator: Chuyu Liu, [email protected] , 631-344-4431 (office) Scheduling Physicist: Bill Christie, [email protected], 631-344-7137 Assistants through 29 Jan: Yousef Makdisi, [email protected], 631-344-4932(office) Phil Pile, [email protected], 631-344-4643 (office), 631-834-2005 (cell) AGS Liaison: Haixin Huang, [email protected] , 631-344-5446 (office)

Page 17: Run 16 RHIC Machine/Experiments Meeting€¦ · Run 16 RHIC Machine/Experiments Meeting 5 Jan 2016 ... Executive Summary Table Run Energy Duration System Goals priority Sequence 16

17

Executive Summary Table

Run Energy Duration System Goals priority Sequence

16 sNN=200 GeV sNN=62 GeV sNN=19.6 GeV

13-wk

4-wk

1-wk

Au+Au Au+Au d+Au

Lc, D v2, RAA, ϒ RAA 10nb-1, 2billion MB 1.5B MB (1B w/ HFT) 100M MB

1 4 4

1 2 3

17 s = 510 GeV sNN=19.6 GeV sNN =200 GeV sNN=200 GeV

11 wk

1-wk 3-wk 3-wk

Transverse p+p p+p Ru+Ru Zr+Zr

AN of W±, g, Drell-Yan, L=360 pb-1, 55% pol 400M MB 1.2billion MB 1.2billion MB

2 4 3

3

1 2 3 4

In each scenario, the data requirements for STAR’s two top

priority scientific goals will be met. In no scenario can all the

data needs for all programs be met in runs 16 and 17

STAR BUR

Page 18: Run 16 RHIC Machine/Experiments Meeting€¦ · Run 16 RHIC Machine/Experiments Meeting 5 Jan 2016 ... Executive Summary Table Run Energy Duration System Goals priority Sequence 16

18

PHENIX Proposal for Run-16

We present a plan assuming 10 week so Au+Au @ 200 GeV The optimum for PHENIX is to run Option A and Option B both