run 2b schedule status
DESCRIPTION
Run 2b Schedule Status. Schedule process status Upcoming Major Purchases Major equipment expenditures in FY03 Labor and equipment funding for CY03 Conclusions. Schedule Status Mechanics. Started monthly schedule progress reporting 1st report: status as of Nov. 20 2 week process - PowerPoint PPT PresentationTRANSCRIPT
V. O’Dell, D0 PMG 10-Dec-02 1
Run 2b Schedule Status
Schedule process status
Upcoming Major Purchases Major equipment expenditures in FY03
Labor and equipment funding for CY03
Conclusions
V. O’Dell, D0 PMG 10-Dec-02 2
Schedule Status Mechanics
Started monthly schedule progress reporting 1st report: status as of Nov. 20 2 week process
– 1st week L3 managers give status and monthly reports to L2 mangers. L2 managers status schedule w/ Bill, Vivian
– 2nd week project office digests information and reports back to the project
Dates aligned with effort reports/DOE reporting Next status will be just after the holidays
aligns with effort reporting to allow EV reporting Project reporting to “aggressive” schedule
project completion data 9/2005 (EIR date 5/2006) Reporting on % complete method only
still working on EV/COBRA reporting
V. O’Dell, D0 PMG 10-Dec-02 3
Shifted silicon milestones
ID WBS Task Name
15 1.1.1.1.3 Sensor Probing Equipment Setup And Certification Complete
33 1.1.1.2.4 Choose L0 Silicon Sensor Technology
69 1.1.1.3.4 Choose L1 Silicon Sensor Technology
91 1.1.1.4.2.2.2 L2-L5 Silicon Sensors Released For Production
38 1.1.1.2.5.4 L0 Silicon Sensors Released For Production
70 1.1.1.3.5 L1 Silicon Sensors Released For Production
846 1.1.5.2.2 Silicon Cylinders Released for Production
996 1.1.7.4.1.7 Release Silicon Unpacking And Translation Packages
800 1.1.4.22.2.3 Successful Fabrication of an Electrical-grade Pre-production Silicon Stave
679 1.1.4.9.3 Begin 20cm Gang Production
41 1.1.1.2.5.7 1st L0 Silicon Sensor Delivered
71 1.1.1.3.6 1st L1 Silicon Sensor Delivered
1001 1.1.7.4.2.4 Release Silicon Examine Package
97 1.1.1.4.3 25% L2-L5 Silicon Sensors Delivered And Tested
587 1.1.3.14.2.7 Stave Shells For South Silicon Complete
42 1.1.1.2.6 All L0 Silicon Sensors Delivered And Tested
72 1.1.1.3.7 All L1 Silicon Sensors Delivered And Tested
590 1.1.3.14.2.10 Stave Shells For North Silicon Complete
98 1.1.1.4.4 50% L2-L5 Silicon Sensors Delivered And Tested
1017 1.1.7.6.9 Release Silicon Calibration Code Package With Documentation
573 1.1.3.13.2 Stave Cores For South Silicon Complete
958 1.1.6.2.2.8 Decide On Final Radiation Monitoring System
1023 1.1.7.7.5 Release Silicon Monitoring Code Package With Documentation
577 1.1.3.13.6 Stave Cores For North Silicon Complete
99 1.1.1.4.5 75% L2-L5 Silicon Sensors Delivered And Tested
100 1.1.1.4.6 All L2-L5 Silicon Sensors Delivered And Tested
105 1.1.1.5 All Silicon Sensors Delivered And Tested
962 1.1.6.2.2.12 Radiation Monitoring System Ready For Installation
878 1.1.5.2.7 Silicon Cylinders Ready for Barrel Assembly
11/2711/6 11/27
1/312/5 1/31
1/312/5 1/31
3/122/11 3/12
4/114/16 4/11
4/114/16 4/11
6/106/17 6/10
7/234/30 7/23
8/157/17 8/15
8/257/25 8/25
9/39/8 9/3
9/39/8 9/3
9/46/12 9/4
10/139/12 10/13
11/1010/10 11/10
11/2612/3 11/26
11/2612/3 11/26
1/1612/9 1/16
2/212/23 2/2
2/511/3 2/5
2/231/23 2/23
3/181/22 3/18
4/151/26 4/15
4/263/26 4/26
5/104/9 5/10
8/187/20 8/18
8/187/28 8/18
9/77/12 9/7
2/243/3 2/24
Qtr 1 Qtr 2 Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 42003 2004 2005
These are milestones that have shifted earlier or later compared to Lehman
Open - LehmanClosed - Reported
V. O’Dell, D0 PMG 10-Dec-02 4
Milestone Status for Silicon
The Good News (milestones completed early) 1.1.3
Mechanical Stave prototype (1.1.3.11.4 MS) on or maybe even ahead of schedule! (12/16/02)
– Should be finished this week
1.1.5 Silicon Barrel Assembly 1.1.5.2.2 prototype silicon cylinders released for
production – 1 week ahead of schedule due to prototype z=0
membrane finishing ahead of schedule
V. O’Dell, D0 PMG 10-Dec-02 5
Delayed silicon milestones
ID WBS Task Name
15 1.1.1.1.3 Sensor Probing Equipment Setup And Certification Complete
91 1.1.1.4.2.2.2 L2-L5 Silicon Sensors Released For Production
996 1.1.7.4.1.7 Release Silicon Unpacking And Translation Packages
800 1.1.4.22.2.3 Successful Fabrication of an Electrical-grade Pre-production Silicon Stave
679 1.1.4.9.3 Begin 20cm Gang Production
1001 1.1.7.4.2.4 Release Silicon Examine Package
97 1.1.1.4.3 25% L2-L5 Silicon Sensors Delivered And Tested
587 1.1.3.14.2.7 Stave Shells For South Silicon Complete
590 1.1.3.14.2.10 Stave Shells For North Silicon Complete
98 1.1.1.4.4 50% L2-L5 Silicon Sensors Delivered And Tested
1017 1.1.7.6.9 Release Silicon Calibration Code Package With Documentation
573 1.1.3.13.2 Stave Cores For South Silicon Complete
958 1.1.6.2.2.8 Decide On Final Radiation Monitoring System
1023 1.1.7.7.5 Release Silicon Monitoring Code Package With Documentation
577 1.1.3.13.6 Stave Cores For North Silicon Complete
99 1.1.1.4.5 75% L2-L5 Silicon Sensors Delivered And Tested
100 1.1.1.4.6 All L2-L5 Silicon Sensors Delivered And Tested
105 1.1.1.5 All Silicon Sensors Delivered And Tested
962 1.1.6.2.2.12 Radiation Monitoring System Ready For Installation
11/2711/6 11/27
3/122/11 3/12
7/234/30 7/23
8/157/17 8/15
8/257/25 8/25
9/46/12 9/4
10/139/12 10/13
11/1010/10 11/10
1/1612/9 1/16
2/212/23 2/2
2/511/3 2/5
2/231/23 2/23
3/181/22 3/18
4/151/26 4/15
4/263/26 4/26
5/104/9 5/10
8/187/20 8/18
8/187/28 8/18
9/77/12 9/7
Qtr 1 Qtr 2 Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 4 Qtr 1 Qtr 22003 2004 2005
These are milestones that have shifted later compared to Lehman
Open Diamonds- LehmanClosed Diamonds- after status reporting
V. O’Dell, D0 PMG 10-Dec-02 6
Milestone Status for Silicon
Milestones on our watchlist 1.1.1 Sensors
L2-L5 sensor production slipped by 1 month due to extra time taken to procure preproduction sensors (1.1.1.4.1.2).
– Delay in procurement understood (mainly communication)
– Addressing this by having a procurement expeditor watch over large or schedule sensitive procurements
This caused delay of 3 weeks in Milestone 1.1.1.5 - All Silicon sensors delivered
– (7/28/04 -> 8/18/04) (some slack in schedule)
1.1.2 Readout electronics SVX4 remains critical path to final detector
completion 2nd prototype submission 1/16/03 - on critical path
V. O’Dell, D0 PMG 10-Dec-02 7
Milestone Status for Silicon
Milestones on our watchlist 1.1.3
L0/L1 structures design (1.1.3.2/1.1.3.3) is behind in % complete but we don’t have an updated projected finish date for the tasks, so it’s hard to understand the impact. This will be fixed in the next month.
Final stave shells and core milestones slipped by 4-5 weeks due to 1.1.4.20.3 - design initial C-channel attachment fixtures taking 1 month longer than expected (now completed)
1.1.4 Detector Production and Testing 1.1.4.9.3 Begin 20cm gang production slipped by 1
month due to silicon sensor procurement slippage
V. O’Dell, D0 PMG 10-Dec-02 8
Milestone Status for Silicon
Milestones on our watchlist 1.1.6 Monitoring
Radiation monitoring system slipped nearly 2 months (7/12/04 -> 9/7/04)-
– Slip due design delay– Non-critical system
Note that the temperature monitoring system is on schedule
V. O’Dell, D0 PMG 10-Dec-02 9
Milestone Status for Silicon
Milestones on our watchlist 1.1.7 - Software and Simulation
1.1.7.4.1.7 Release Silicon Unpacking and Translation Packages slipped by 3 months (4/30/03 -> 7/23/03) because no one is working on it (modifying run2a code for data unpacking)
– This impacts the multi hybrid full chain test 10/23/03 1.1.7.4.2.4 Release Silicon Examine Package slipped
by 3 months (6/12/03 ->9/4/03) for the same reason 1.1.7.6.9 Release Si Calibration Code slipped by the
same 3 months (1/26/04 -> 4/15/04) 1.1.7.7.5 Release Si Monitoring Code slipped same 3
months (1/25/04 -> 4/15/04) Going to collaboration with this to recruit effort
V. O’Dell, D0 PMG 10-Dec-02 10
FY03 Equipment Purchases over $100k
07/03/03167Analog Cables
09/04/03382L2-L5 Production Hybrids
07/11/03475SVX4 Production Chips
04/14/03155L1 Sensors
04/14/03161L0 Sensors
04/03/03263L2-L5 Digital Jumper Cables
03/13/031,453L2-L5 Sensors
Production Start Date
Cost(FY02
k$)
Item
Costs do not include contingency, G&A, or escalation.
Labor not included.All FY03 procurements over $100k in silicon
subproject only.
All scheduled FY03 equipment purchases
over $100k through Sep ’03
V. O’Dell, D0 PMG 10-Dec-02 11
FNAL Equipment Labor/M&S for Silicon
Run2b_Silicon_Schedule_For_Nov02_StatusedCost EQU Quarter10/1/2002 1/1/2003 4/1/2003 7/1/2003 10/1/2003 ROW_TOTAL
F Labor AdminAsstF $0.00 $7,644.00 $12,544.00 $12,544.00 $11,368.00 $44,100.00F Labor CMMOperatorSF $0.00 $595.20 $9,920.00 $15,822.40 $19,368.80 $45,706.40F Labor CMMProgrammerSF $0.00 $2,707.20 $3,684.80 $3,647.20 $12,144.80 $22,184.00F Labor CompProfF $0.00 $0.00 $1,654.40 $2,105.60 $4,466.88 $8,226.88F Labor DesignerF $0.00 $21,489.60 $62,480.00 $80,129.28 $59,544.32 $223,643.20F Labor ElecEngF $0.00 $528.00 $15,136.00 $79,860.00 $38,038.00 $133,562.00F Labor ElecTechF $0.00 $2,683.20 $18,520.32 $26,214.24 $26,794.56 $74,212.32F Labor ElecTechSF $0.00 $633.60 $1,689.60 $17,476.80 $10,824.00 $30,624.00F Labor MechEngF $0.00 $22,215.60 $65,188.20 $83,911.32 $72,171.12 $243,486.24F Labor MechTechF $0.00 $4,253.20 $10,530.80 $9,590.00 $18,676.00 $43,050.00F Labor MechTechSF $0.00 $7,561.60 $26,139.20 $78,757.60 $77,873.60 $190,332.00F Labor WirebonderSF $0.00 $432.00 $1,425.60 $302.40 $0.00 $2,160.00
MandS $0.00 $519,997.00 $628,938.50 $1,313,704.50 $732,460.00 $3,195,100.00COL_TOTAL $0.00 $590,740.20 $857,851.42 $1,724,065.34 $1,083,730.08 $4,256,387.04
FY03 Total (Fermi Labor) $710,016.96CY03 Total (Fermi Labor) $1,061,287.04
V. O’Dell, D0 PMG 10-Dec-02 12
FNAL R&D Labor/M&S for Silicon
Run2b_Silicon_Schedule_For_Nov02_StatusedCost R & D Quarters10/1/2002 1/1/2003 4/1/2003 7/1/2003 10/1/2003 ROW_TOTAL
F Labor CMMOperatorSF $26,622.80 $20,993.20 $3,100.00 $0.00 $0.00 $50,716.00F Labor CMMProgrammerSF $11,825.20 $14,974.20 $16,816.60 $0.00 $0.00 $43,616.00F Labor CompProfF $5,113.60 $0.00 $0.00 $0.00 $0.00 $5,113.60F Labor DesignerF $82,420.80 $30,187.52 $6,688.00 $0.00 $0.00 $119,296.32F Labor ElecEngF $50,336.00 $58,608.00 $33,880.00 $24,420.00 $880.00 $168,124.00F Labor ElecTechF $10,264.80 $17,191.20 $16,192.80 $4,680.00 $0.00 $48,328.80F Labor ElecTechSF $14,411.76 $29,502.00 $3,524.40 $5,610.00 $0.00 $53,048.16F Labor MechEngF $108,612.49 $47,464.68 $28,692.60 $0.00 $0.00 $184,769.77F Labor MechTechF $0.00 $637.00 $11,123.00 $0.00 $0.00 $11,760.00F Labor MechTechSF $63,651.71 $60,615.20 $13,056.00 $0.00 $0.00 $137,322.91F Labor WirebonderSF $2,192.40 $1,047.60 $1,080.00 $0.00 $0.00 $4,320.00
MandS $361,616.00 $328,317.00 $32,960.00 $0.00 $0.00 $722,893.00COL_TOTAL $737,067.56 $609,537.60 $167,113.40 $34,710.00 $880.00 $1,549,308.56
FY03 Total (Fermi Labor) $825,535.56CY03 Total (Fermi Labor) $450,964.00
V. O’Dell, D0 PMG 10-Dec-02 13
Shifted trigger milestones
ID WBS Task Name
112 1.2.2.2 L1 Trigger Cal-Trk Match R&D MOU (UAZ) Complete
86 1.2.1.7 L1 Calorimeter Trigger TAB/GAB Prototyping Complete
49 1.2.1.3.1.8 L1 Calorimeter Trigger TAB Prototype Complete
67 1.2.1.4.1.6 L1 Calorimeter Trigger GAB Prototype Complete
168 1.2.3.3 Target L1 Central Track Trigger Algorithm Firmware Coded And Simulated With FPGA Simulation Tools
199 1.2.3.6.6 L1 Central Track Trigger DFEA Prototype Tested At Fermilab
221 1.2.3.7.7 L1 Central Track Trigger Production And Testing Complete
222 1.2.9 L1 Trigger Upgrade Production and Testing Complete
11/1 12/16
7/165/2
5/16 4/18
7/165/2
7/17 7/11
4/16 4/12
3/16 3/10
3/16 3/10
Qtr 1 Qtr 2 Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 42003 2004 2005
V. O’Dell, D0 PMG 10-Dec-02 14
Milestone Status for Trigger
Executive summary: managing to aggressive schedule (complete 2/28/05) delays in some milestones, but project on schedule
1.2.1 L1 Calorimeter Trigger ADC/Digital Filter board now critical path item due to
prototype ADF design taking longer than estimated (1.2.1.1.1.1) (new end data 1/24/03)
– design more complicated than originally thought– extra engineering added to ensure schedule does not
slip further 1.2.1.1.5 Prototype L1 Cal Trig ADF shipped to FNAL
– delayed by nearly 2 months (5/2/03->6/23/03) 1.2.1.1.3 L1 Cal Trigger ADF Production Complete
– delayed by 2 months (12/8/05 - 2/7/05)
V. O’Dell, D0 PMG 10-Dec-02 15
Milestone Status for Trigger
1.2.1 L1 Calorimeter Trigger (continued) 1.2.1.2.1.5 Cal Trigger ADF+Crate Prototype Complete
– delayed by 3 months - delay in starting backplane design
– Design engineer focussing on ADF
– Conscious priority choice - this is not a critical path item Trigger Algorithm Board design delay, but final prototype
still on schedule (1.2.1.3.1.8)– delay incurred due to rewriting entire suite of sliding
windows firmware to allow better simulation
– Increased ability to simulate firmware before prototype fabrication means less time needed for prototype testing
1.2.1.8 L1 Calorimeter Trigger TAB/GAB Production and Testing Complete delayed by 6 weeks (due to ADF delay)
No upcoming major purchases 1st Major purchase Jan 2004 (ADF parts) $160k
V. O’Dell, D0 PMG 10-Dec-02 16
FNAL Equipment Labor/M&S for Trigger
Upgrade
Run2b_Trigger_Schedule_For_Nov02_StatusedCost EQU Quarter10/1/2002 1/1/2003 4/1/2003 7/1/2003 10/1/2003 ROW_TOTAL
F Labor ElecEngF $0.00 $0.00 $440.00 $0.00 $0.00 $440.00F Labor ElecTechF $0.00 $468.00 $156.00 $16,567.20 $14,352.00 $31,543.20
MandS $0.00 $144,146.69 $134,773.61 $123,228.86 $73,077.04 $475,226.20COL_TOTAL $0.00 $144,614.69 $135,369.61 $139,796.06 $87,429.04 $507,209.40
FY03 Total (Fermi Labor) $17,631.20CY03 Total (Fermi Labor) $31,983.20
V. O’Dell, D0 PMG 10-Dec-02 17
Milestone Status for Online
1.3.2.4.3.5 RAID Array Active delayed by 1 week due to dealy in
commissioning Fiber Channel SAN array (10/18/02 -> 1/22/03).
Note that most of the slack was taken up in reducing testing time for the array.
ID WBS Task Name
106 1.3.2.4.3.5 RAID Array Active 7/16 7/21Qtr 1 Qtr 2 Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 42003 2004 2005
V. O’Dell, D0 PMG 10-Dec-02 18
FNAL Equipment Labor/M&S for Online
Upgrade
No upcoming major purchases.
Run2b_Online_Schedule_For_Nov02_StatusedCost EQU Quarter10/1/2002 1/1/2003 4/1/2003 7/1/2003 10/1/2003 ROW_TOTAL
F Labor CompProfF $0.00 $2,613.20 $2,406.40 $2,481.60 $4,700.00 $12,201.20MandS $0.00 $0.00 $20,000.00 $20,000.00 $20,000.00 $60,000.00COL_TOTAL $0.00 $2,613.20 $22,406.40 $22,481.60 $24,700.00 $72,201.20
FY03 Total (Fermi Labor) $7,501.20CY03 Total (Fermi Labor) $12,201.20
V. O’Dell, D0 PMG 10-Dec-02 19
Project Administration
Costs for project administration (s/w licenses, travel, budget officer, admin, scheduler)
Run2b_Project_Administration_For_Nov02Cost EQU Quarter10/1/2002 1/1/2003 4/1/2003 7/1/2003 10/1/2003 ROW_TOTAL
F Labor AdminAsstF $0.00 $11,480.00 $17,920.00 $17,920.00 $16,240.00 $63,560.00F Labor BudgetOfficerF $0.00 $12,792.00 $19,968.00 $19,968.00 $18,096.00 $70,824.00F Labor SchedulerF $0.00 $18,696.00 $29,184.00 $29,184.00 $26,448.00 $103,512.00
MandS $0.00 $31,000.00 $0.00 $0.00 $29,000.00 $60,000.00COL_TOTAL $0.00 $73,968.00 $67,072.00 $67,072.00 $89,784.00 $297,896.00
FY03 Total (Fermi Labor) $177,112.00CY03 Total (Fermi Labor) $237,896.00
V. O’Dell, D0 PMG 10-Dec-02 20
Conclusions
Project completion dates have NOT changed intermediate milestones have moved in both
directions delays understood and addressed
Managing to “aggressive” schedule completion date Sept 05 EIR/DOE schedule finish May 06
Using the project status information understand impact of shifting tasks anticipate needs
shaking out the bugs to make this exercise as productive as possible
Flagging schedule changes Working on Earned Value analysis (via COBRA)