running scrum on a non-agile environment - tales from a past experience" by nuno caneco
TRANSCRIPT
Bio
Nuno Caneco
● Software Engineer for 13+ years● Scrum Practitioner since 2008● Scrum Master since 2009● Leading Software Projects since 2006
How it started
● Fixed scope
● Fixed delivery date(based on high level estimations)
● Waterfall-based Project Management
Project Management Foundations
Schedule
Scope Budget
Quality
ResourcesRisk
Contract
Managed by Contractor (PM)
Agile & Contracts
Schedule
Scope Budget
Quality
ResourcesRisk
Fixed Contract:
● Fixed Budget ● Fixed Scope● Fixed Schedule
Waterfall Project Management
The Agile way:
● Flexible Scope● Flexible Schedule
Flexible Budget
Internal Agile - The Opportunity
Using Agile would hopefully:
● Improve the flexibility within the
Team
● Improve resource and time
management
● Steady and frequent checkpoints
● Small and frequent victories
Façades
SupplierCustomer
Sponsor
PM
Sponsor
PM / PO ScrumMaster
TTTeam
Waterfall AgileWaterfall & Agile
Combining Waterfall with Agile
Requirements
Design
Implementation
Verification
Waterfall Façade Agile Façade Activities
● Close high level specs with Customer● Epic Backlog● Initial Product Backlog
● Refine Product Backlog● Initial Mockups● Sprint 0 - project structure and first lines of code
● Sprints● Backlog Grooming● Internal QA & Demos
● Acceptance tests with customer● Bug fixes
Preparing the Backlogs
Functional Specification● Modules
○ Features
User Acceptance Tests● High level UAT
(not that much detailed at this point)
Waterfall Façade Agile Façade
Epic Backlog
Product Backlog
Modules mapped to Epics
Features mapped to User Stories
UAT mapped to Acceptance Criteria
Epic Backlog Prioritizing
Prioritize on Epics based on the following criteria:
1. Dependency to other Epics/Stories○ Foundational epics go first○ Epics that are dependencies to other epics go first
2. Risk & Impact○ High risk + High Impact Epics are likely to go first○ "Bread and butter" epics are likely to go last
At the End of Requirements Phase
The Team had:
● A Functional Specification approved by the customer● A high level UAT document approved by the customer
and
● A detailed and prioritized Epic Backlog ○ T-Shirt size estimation
● A Product Backlog with:○ Detailed functional description ○ High level Acceptance Criteria○ No User Story estimation
Invariants
● Setup the Team
○ Front-end Engineers ; Back-end Engineers ; Lead Architect
● 2-week Sprints
○ Starting on Monday ; Ending on Friday (by agreement with the Team)
● Recurring appointments on the agenda:
○ Sprint Planning
○ Daily meetings
○ Sprint Demo
○ Sprint Retrospective
Sprint Loop
Day 1 Day 2 Day 3 Day 4 Day 5 Day 6 Day 7 Day 8 Day 9 Day 10
Sprint Planning[Team + SM]
Backlog Grooming (Mid/long term)[SM + PO ; Team(optional)]
Mock-ups & User Store detail grooming [PO + SM]
Backlog Grooming (Sprint n+1)[Team + SM + PO]
Sprint Demo[Team + SM + PO + PM]
Sprint Retrospective[Team + SM]
Sprint n
Sprint Planning
Product Backlog Sprint Backlog
● Stories are split into Tasks
● Each Task:○ Gets estimated in hours
(Estimation > 12h → Split the task)○ Is pre-assigned to a Team Member
● Tax Tasks:○ Backlog Grooming○ Daily meetings○ Sprint Demos○ (...)● Story ID
● Description● Estimation [Story Points]● Mock ups
● Task ID● Story ID● Task Type● Description● Assignee● Estimation [h]● Time tracking
Definition of Done
Examples:
● Code on Source Control must compile and run by hitting F5
● Tests must be implemented and passing
● Database project must be updated
Time to Adapt!
● Identify the user stories that become critical for the BETA
● Enter Kanban mode for 2 sprints to:a. Finish the featuresb. Install the system @ PROD
Sprint #1 Sprint #2 Sprint #3 Sprint #4 Sprint #5 Sprint #6 Sprint #7 Sprint #8 (...)
Scrum Scrum Scrum Scrum Scrum Kanban Kanban Scrum (...)
Adding a QA to the Team
At some point, we decided to bring in a QA into the team:
● Iterate towards the final UAT document
● Test the outcome of Previous Sprint according to UAT document
● Report bugs
QA loop
Sprint n
QA: Test fixed bugs
QA: Run UAT tests on new storiesTeam: Fix issues reported by QA (within saved capacity)
QA: Iterate on UAT document
The QA Loop was integrated with the Team Loop
Some numbers
● 17x 2-week Sprints
● 5 software engineers (backend and frontend)
● 1 QA (non-permanent)
● ~210.000 lines of code
○ From which 37.000 are tests (~12%)
● 4 software applications + 1 common library
Pros
● Guided and steady workflow
● Regular sense of completion at the end of each Sprint
● Quickly respond to change
● Pre-align epics to Sprints
● Waterfall Status Reports became really easy○ Just use the data from Sprint Demos
● Deallocations and inefficiencies become visible
● Improved the Team buy-in on the Project
Cons
● A bit of Management overhead ○ Map Scrum <--> Waterfall
● Higher allocation of QA Team Members○ Early allocation to the Project
Lessons Learned
● It's easier to run Internal Scrum if the Management buys the strategy○ And our Management did support this strategy
● Using Kanban for stability Sprints○ Improved the flexibility to fix issues and implement quick-but-needed features
● If properly aligned, the Waterfall artifacts can be mapped to/from Agile
artifacts with minimal effort○ Technical Specification → Epic Backlog and Product Backlog
○ Sprint Demos & Sprint Backlog → Status Reports
○ Acceptance Criteria → User Acceptance Test
But most important
Always remember that the customer did NOT buy Agile
Keep
the
FaçadeKeep the fixed scope and time to the customer
Allow some internal
flexibility