runway construction project execution plan

215
Runway Construction Project Execution Plan Details of how a Runway is constructed, and how the progress, safety and quality will be monitored and controlled. Also the measures to ensure that the site is environmentally friendly. David H Moloney 14 th Oct 2016 Brief Description The purpose of this presentation is to give an understanding of the Methods, Plant and Sequence to construct a Runway . This presentation can be used to engage Stakeholders and to get the Site Teams commitment to the programme. Also can be used for Induction Training and as a way to capture and share knowledge. Project Execution Plan (PEP) details how a project will be executed, monitored and controlled. High in Educational Value and easily understood. Recommended for Continuing Professional Development (CPD) This Video Presentation is innovative and has many beneficial uses. http://www.slideshare.net/DavidHMoloney/runway-construction-project-execution-plan Film at https://youtu.be/yCKLPzrDztw © David H Moloney

Upload: david-h-moloney

Post on 21-Apr-2017

3.931 views

Category:

Engineering


78 download

TRANSCRIPT

Page 1: Runway Construction Project Execution Plan

Runway Construction Project Execution Plan Details of how a Runway is constructed, and how the progress, safety and quality will be monitored and controlled. Also the measures to ensure that the site is environmentally friendly.

David H Moloney

14th Oct 2016

Brief Description

The purpose of this presentation is to give an understanding of the Methods, Plant and Sequence to construct a Runway .

This presentation can be used to engage Stakeholders and to get the Site Teams commitment to the programme. Also can be used for Induction Training and as a way to capture and share knowledge.

Project Execution Plan (PEP) details how a project will be executed, monitored and controlled.

High in Educational Value and easily understood. Recommended for Continuing Professional Development (CPD)This Video Presentation is innovative and has many beneficial uses.

http://www.slideshare.net/DavidHMoloney/runway-construction-project-execution-plan

Film at https://youtu.be/yCKLPzrDztw

© David H Moloney

Page 2: Runway Construction Project Execution Plan

Table of Contents

© David H Moloney

Page 3: Runway Construction Project Execution Plan

Runway Construction

© David H Moloney

Page 4: Runway Construction Project Execution Plan

Runway Construction Sequence & MethodsR

oads &

Pavin

gs

© David H Moloney

Page 5: Runway Construction Project Execution Plan

Excavate & Load Tipper Trucks

© David H Moloney

Page 6: Runway Construction Project Execution Plan

Trench Excavation with Stepped Faces

© David H Moloney

Page 7: Runway Construction Project Execution Plan

Trench Excavation with Battered Faces

© David H Moloney

Page 8: Runway Construction Project Execution Plan

Spreading & Compaction Clay fillE

art

hw

ork

s

Page 9: Runway Construction Project Execution Plan

Tipper Trucks Unloading

Page 10: Runway Construction Project Execution Plan

Spreading & Compaction Clay fillE

art

hw

ork

s

Page 11: Runway Construction Project Execution Plan

Backfill TrenchE

art

hw

ork

s

Page 12: Runway Construction Project Execution Plan

Dozer Pushing ClayE

art

hw

ork

s

Page 13: Runway Construction Project Execution Plan

Dozer Ripping GroundE

art

hw

ork

s

Page 14: Runway Construction Project Execution Plan

Excavator with Hydraulic RockbreakerE

art

hw

ork

s

Page 15: Runway Construction Project Execution Plan

Rock - Excavability

The excavability of rock depends mainly on the rock strength and the layer thickness. This diagram shows excavation methods for rock of various strengths and thicknesses, with a free face.

ⓒ David H Moloney

Page 16: Runway Construction Project Execution Plan

CABC ( Crushed aggregate base course )E

art

hw

ork

s

Mixing Plant

Testing Compaction

Site Trial

Page 17: Runway Construction Project Execution Plan

Mixing CABCE

art

hw

ork

s

Page 18: Runway Construction Project Execution Plan

Spreading & Compaction CABC ( Crushed aggregate base course )E

art

hw

ork

s

Page 19: Runway Construction Project Execution Plan

Spreading & Compaction CABC ( Crushed aggregate base course ) E

art

hw

ork

s

Page 20: Runway Construction Project Execution Plan

Spreading & Compaction CABC ( Crushed aggregate base course )E

art

hw

ork

s

Page 21: Runway Construction Project Execution Plan

Runway Asphalt PavementR

oads &

Pavin

gs

Brief Description

Sequence, plant and methods to construct a runway

Page 22: Runway Construction Project Execution Plan

Prime Coat Site TrialsR

oads &

Pavin

gs

Bituminous Prime Coat shall

consist of supplying and applying

bituminous material to a previously

prepared and approved base

course in accordance with the

Specification to ensure a bond

between this surface and the

overlying course.

Page 23: Runway Construction Project Execution Plan

Runway Asphalt Pavement - Prime CoatR

oads &

Pavin

gs

Page 24: Runway Construction Project Execution Plan

Runway Asphalt PavementR

oads &

Pavin

gs

Page 25: Runway Construction Project Execution Plan

Runway Asphalt PavementR

oads &

Pavin

gs

Page 26: Runway Construction Project Execution Plan

Runway Asphalt PavementR

oads &

Pavin

gs

Page 27: Runway Construction Project Execution Plan

Runway Asphalt PavementR

oads &

Pavin

gs

Page 28: Runway Construction Project Execution Plan

Runway Asphalt Pavement - 4 Pavers working togetherR

oads &

Pavin

gs

Page 29: Runway Construction Project Execution Plan

Runway Asphalt Pavement - 4 Pavers working togetherR

oads &

Pavin

gs

Page 30: Runway Construction Project Execution Plan

Cutting JointR

oads &

Pavin

gs

Page 31: Runway Construction Project Execution Plan

Runway Asphalt Pavement - Line & Level R

oads &

Pavin

gs

Checking asphalt level by Dip measurements

String line used for Level & line reference

Page 32: Runway Construction Project Execution Plan

Runway Asphalt PavementR

oads &

Pavin

gs

Page 33: Runway Construction Project Execution Plan

Runway Pavement - MarkingR

oads &

Pavin

gs

Page 34: Runway Construction Project Execution Plan

Runway Pavement – Cleaning surface with rotating water jetsR

oads &

Pavin

gs

Page 35: Runway Construction Project Execution Plan

Runway Pavement – Cleaning surface with rotating water jetsR

oads &

Pavin

gs

Page 36: Runway Construction Project Execution Plan

Runway Pavement – Test for Skid Resistance

Roads &

Pavin

gs

Page 37: Runway Construction Project Execution Plan

Runway Pavement R

oads &

Pavin

gs

Using the Douglas Mu-Meter continuous friction measuring equipment

Page 38: Runway Construction Project Execution Plan

Runway Pavement – Test for Smoothness using Rolling Straight Edge

Roads &

Pavin

gs

Page 39: Runway Construction Project Execution Plan

Runway Pavement – Test for Texture by Sand Patch testR

oads &

Pavin

gs

Page 40: Runway Construction Project Execution Plan

Airfield Ground Lights Ducts & ChambersM

isce

llan

eo

us

Page 41: Runway Construction Project Execution Plan

Airfield Ground Lights M

isce

llan

eo

us

Page 42: Runway Construction Project Execution Plan

Airfield Ground Lights Ducts & ChambersM

isce

llan

eo

us

Page 43: Runway Construction Project Execution Plan

Airfield Ground Lights Excavate Trench in CABCM

isce

llan

eo

us

Page 44: Runway Construction Project Execution Plan

Airfield Ground Lights – Concrete DuctsM

isce

llan

eo

us

Page 45: Runway Construction Project Execution Plan

Airfield Ground Lights – Surface Inset LightsM

isce

llan

eo

us

Page 46: Runway Construction Project Execution Plan

Airfield Ground LightsM

isce

llan

eo

us

Jig to Level Pot

Page 47: Runway Construction Project Execution Plan

Airfield Ground Lights - Core drill for Inset LightM

isce

llan

eo

us

Page 48: Runway Construction Project Execution Plan

Airfield Ground Lights Fit Pot with JigM

isce

llan

eo

us

Page 49: Runway Construction Project Execution Plan

Airfield Ground Lights M

isce

llan

eo

us

Page 50: Runway Construction Project Execution Plan

Precast Yard - Chambers M

isce

llan

eo

us

Page 51: Runway Construction Project Execution Plan

Delivery of Precast Chambers M

isce

llan

eo

us

Page 52: Runway Construction Project Execution Plan

Airfield Ground Lights M

isce

llan

eo

us

Jointing HDPE Ducts Jointing HDPE Ducts

Precast Chamber Grouting Inset Light Pot

Page 53: Runway Construction Project Execution Plan

ILS Localiser Antenna & Approach LightsM

isce

llan

eo

us

Provides lateral radio guidance to an aircraft approaching and landing on a runway

Page 54: Runway Construction Project Execution Plan

Approach LightsM

isce

llan

eo

us

Page 55: Runway Construction Project Execution Plan

Approach LightsM

isce

llan

eo

us

Used by the pilot to align the aircraft visually with the runway centreline.

Page 56: Runway Construction Project Execution Plan

ILS Glide Path AntennaM

isce

llan

eo

us

Provides radio vertical guidance to an aircraft approaching and landing on a runway

Page 57: Runway Construction Project Execution Plan

DVOR Ground StationM

isce

llan

eo

us

Omni Directional Radio Range (VOR) is a radio navigation system for aircrafts, so an aircraft can determine their position and stay on course.

Page 58: Runway Construction Project Execution Plan

Airfield Lights - SubstationM

isce

llan

eo

us

Contains switchgear, protection and control equipment

Page 59: Runway Construction Project Execution Plan

Airfield Lights - SubstationM

isce

llan

eo

us

Contains switchgear, protection and control equipment

Page 60: Runway Construction Project Execution Plan

Airfield Lights – Taxi Guidance SignsM

isce

llan

eo

us

Taxi guidance signs provide direction and information to taxiing aircraft.

Page 61: Runway Construction Project Execution Plan

Concrete Slipform PavingR

oads &

Pavin

gs

Brief Description

Horizontal slip forming for concrete pavement. The process

consists of placing and spreading low slump concrete on the

ground in front of a paver that slips over the concrete and

extrudes strips of slabs.

Slipform Concrete PaverSpreader

Texturing & Curing

Page 62: Runway Construction Project Execution Plan

Concrete Slipform Paving – Texturing MachineR

oads &

Pavin

gs

Page 63: Runway Construction Project Execution Plan

Concrete Slipform Paving - Slipform MachineR

oads &

Pavin

gs

Page 64: Runway Construction Project Execution Plan

Concrete Slipform Paving – Placer / Spreader MachineR

oads &

Pavin

gs

Page 65: Runway Construction Project Execution Plan

Concrete Slipform Paving R

oads &

Pavin

gs

Page 66: Runway Construction Project Execution Plan

Concrete Slipform Paving R

oads &

Pavin

gs

Page 67: Runway Construction Project Execution Plan

Concrete Slipform Paving R

oads &

Pavin

gs

Page 68: Runway Construction Project Execution Plan

Concrete Slipform Paving R

oads &

Pavin

gs

Page 69: Runway Construction Project Execution Plan

Concrete Slipform Paving – Drilling holes for dowelsR

oads &

Pavin

gs

Page 70: Runway Construction Project Execution Plan

Concrete Slipform Paving – Drilling holes for dowelsR

oads &

Pavin

gs

Page 71: Runway Construction Project Execution Plan

Runway Concrete PavementR

oads &

Pavin

gs

Page 72: Runway Construction Project Execution Plan

Milling / Planing MachineR

oads &

Pavin

gs

Used to remove part of the surface of a paved area

Page 73: Runway Construction Project Execution Plan

Cable LayingP

ipe

wo

rk

Brief Description

132 kVa Cable laying .

Page 74: Runway Construction Project Execution Plan

Cable Laying P

ipe

wo

rk

Page 75: Runway Construction Project Execution Plan

Cable Laying P

ipe

wo

rk

Page 76: Runway Construction Project Execution Plan

Cable Laying P

ipe

wo

rk

Page 77: Runway Construction Project Execution Plan

Cable Laying ⓒ David H Moloney

Cable Drum Stand Cable pulled on rollersCable Winch

Cable Drum Unloading Cable on rollers Cable Testing prior to Backfilling

Mis

ce

llan

eo

us

Page 78: Runway Construction Project Execution Plan

Horizontal Directional DrillingP

ipe

wo

rk

Brief Description

Horizontal Directional Drilling under a taxiway.

Process

1. A pilot hole id drilled to the designed profile

2. A reamer is pulled back through the hole to enlarge it

3. A pipe string is pulled into the hole.

Page 79: Runway Construction Project Execution Plan

Horizontal Directional DrillingP

ipe

wo

rk

Page 80: Runway Construction Project Execution Plan

Micro TunnellingT

un

ne

ls

Page 81: Runway Construction Project Execution Plan

Micro Tunnelling Sequence David H Moloney

ⓒ David H Moloney

Tu

nn

els

Page 82: Runway Construction Project Execution Plan

FencingM

isce

llan

eo

us

Brief Description

Fencing.

Sequence of construction;

1. Clear and grade the ground.

2. Fix corner and straining posts.

3. Fix intermediate posts.

4. Fix line wire, chain-link and razor wire.

5. Construct concrete ground beam

Page 83: Runway Construction Project Execution Plan

FencingM

isce

llan

eo

us

Page 84: Runway Construction Project Execution Plan

FencingM

isce

llan

eo

us

Page 85: Runway Construction Project Execution Plan

FencingM

isce

llan

eo

us

Page 86: Runway Construction Project Execution Plan

FencingM

isce

llan

eo

us

Page 87: Runway Construction Project Execution Plan

Fencing DeliveryM

isce

llan

eo

us

Page 88: Runway Construction Project Execution Plan

Article on Muscat Airport Runway Link http://www.ccc.me/pdf/bulletins/bulletin103.pdf

Page 89: Runway Construction Project Execution Plan

Runway Construction Pavement Details & Mixes

Runway Asphalt Runway Ends Concrete

Page 90: Runway Construction Project Execution Plan

Concrete Delivery Order - RecordC

on

cre

te Brief Description

It is important to record orders for

concrete deliveries.

The form can be adapted for

other materials e.g.

reinforcement.

Page 91: Runway Construction Project Execution Plan

Flight CheckTe

sts

Brief Description

Aircraft performing flight checks

on new Instrument Landing

System

Page 92: Runway Construction Project Execution Plan

Concrete

Page 93: Runway Construction Project Execution Plan

Reinforced Wall Construction Sequence

ⓒ David H Moloney

Co

ncre

te

Brief Description

The sequence to construct a reinforced concrete wall is as

follows:

Tie the reinforcement.

Erect stop-ends and the wall shutters.

Pour and vibrate the concrete mix.

Remove the shutters after the concrete has hardened.

.

Cycle Time Pour per Day

Page 94: Runway Construction Project Execution Plan

Reinforced Wall Construction Sequence

ⓒ David H Moloney

Co

ncre

te

Page 95: Runway Construction Project Execution Plan

Culvert ConstructionC

on

cre

te

Brief Description

Sequence to construct culvert

with head walls.

Page 96: Runway Construction Project Execution Plan

Culvert ConstructionC

on

cre

te

Page 97: Runway Construction Project Execution Plan

Oil InterceptorM

isce

llan

eo

us

Used to capture oil / fuel from leaks or spillages that are washed down drains every time it rains.

Page 98: Runway Construction Project Execution Plan

Oil InterceptorC

on

cre

te

Page 99: Runway Construction Project Execution Plan

Excavation for Underground Pump stationE

art

hw

ork

s

Brief Description

Faces of excavation Stepped &

Well-point Dewatering used.

Page 100: Runway Construction Project Execution Plan

Concrete MixG

en

era

l It

em

s

A concrete mix contains 5 major

elements: cement, water, coarse

aggregates, fine aggregates (sand) and

air in different proportion. Additional

elements such as pozzolanic materials (fly

ash, silica fumes or slag) and chemical

admixtures can also be incorporated to

the mix to increase its properties.

Page 101: Runway Construction Project Execution Plan

Vibrating Concrete

ⓒ David H Moloney

Co

ncre

te

Page 102: Runway Construction Project Execution Plan

Airside Restrictions

Page 103: Runway Construction Project Execution Plan

Stakeholders Engagement

Method of Work Plan (MOWP)

A Method of Working Plan (MOWP) is prepared when the normal operation of an aerodrome is

disrupted through aerodrome works and the risk to aircraft operations is increased. Stakeholders

likely to be significantly affected by the proposed works will be given the opportunity to participate

in the planning process.

The MOWP will clearly set out the following: • the scope of work and the stages of carrying out

the work; • how the works are to be carried out and the restrictions on the works organisation; •

how the aircraft operators and pilots will be told, through NOTAM, of the restrictions to aircraft

operations at each stage of the work; • identify any changes necessary to aerodrome markings

and lights as the works progress; • drawings to illustrate work arrangements and changes to

declared distances, taxiing routes, etc.; and • identify persons responsible for the works and those

accountable for ensuring safety of the aerodrome facilities to aircraft operations.

Airport Stakeholders

Operations G.M.

Technical Services G.M

Senior Aviation Manager

Chief Fire Officer

Project Manager

Sr. Maintenance Manager

Operations Reediness Team Leader

Certification & Compliance Manager

Airfield Duty Manager

Airport Duty Manager

HSE Specialist

DGSAS, Director of Airports

DGSAS, Aerodrome Certification

CAA Air Traffic Control –Tower

CAA Chief of Tower

Police

Ground Handling Agent

Airport Refueller Companies

Page 104: Runway Construction Project Execution Plan

Airplane Wingtip ClearanceM

isce

llan

eo

us

Brief Description

Regulation distances shown

for wingtip clearance.

Page 105: Runway Construction Project Execution Plan

Airplane Wingtip ClearanceM

isce

llan

eo

us

Page 106: Runway Construction Project Execution Plan

Taxiway Reconstruction AirsideM

isce

llan

eo

us

Brief Description

Regulations regarding working adjacent to

a live runway.

Page 107: Runway Construction Project Execution Plan

Taxiway Reconstruction AirsideM

isce

llan

eo

us

Page 108: Runway Construction Project Execution Plan

Working Airside to Upgrade Taxiway

Asphalt Pavement Laid on Existing Concrete Pavement Temporary Gate and Fence

Excavation Planing at Runway tie-inFill –Crushed Aggregate Rake sealant out of Joints

Page 109: Runway Construction Project Execution Plan

Taxiway Reconstruction AirsideM

isce

llan

eo

us

Page 110: Runway Construction Project Execution Plan

Contractors Temporary Facilities

Page 111: Runway Construction Project Execution Plan

Temporary Contractors Site Facilities

ⓒ David H Moloney

Brief Description

Site Offices, Camp Accommodation for 1,250 workers, Canteen, Recreation, Fabrication shops, Stores, Plant Yard. In five locations along the route.

Page 112: Runway Construction Project Execution Plan

Welfare Facilities

ⓒ David H Moloney

Ge

ne

ral It

em

s

Toilets – Washing

Canteen, Drying Room, Toilet & Generator

Page 113: Runway Construction Project Execution Plan

Site Hoarding examples

ⓒ David H Moloney

Ge

ne

ral It

em

s

Page 114: Runway Construction Project Execution Plan

Temporary Fence type 1

ⓒ David H Moloney

Ge

ne

ral It

em

s

Brief Description

Examples of temporary security fences that are higher than the usual

Page 115: Runway Construction Project Execution Plan

Temporary Fence type 1

ⓒ David H Moloney

Ge

ne

ral It

em

s

Page 116: Runway Construction Project Execution Plan

Temporary Fence type 2

ⓒ David H Moloney

Ge

ne

ral It

em

s

Brief Description

Temporary fence on precast beam for airport.

Page 117: Runway Construction Project Execution Plan

Temporary Fence type 2

ⓒ David H Moloney

Ge

ne

ral It

em

s

Page 118: Runway Construction Project Execution Plan

Dewatering

ⓒ David H Moloney

Ge

ne

ral It

em

s

Brief Description

Construction dewatering is the removal or drainage of

groundwater and or surface / rain water usually by

pumping to keep the works dry.

Page 119: Runway Construction Project Execution Plan

Dewatering

ⓒ David H Moloney

Ge

ne

ral It

em

s

Brief Description

Construction dewatering is the removal or

drainage of groundwater and or surface /

rain water usually by pumping to keep the

works dry.

Page 120: Runway Construction Project Execution Plan

Dewatering

ⓒ David H Moloney

Ge

ne

ral It

em

s

Page 121: Runway Construction Project Execution Plan

Wheel Wash Drive-through

ⓒ David H Moloney

Ge

ne

ral It

em

s

Page 122: Runway Construction Project Execution Plan

Wheel Wash Drive-throughG

en

era

l It

em

s

Page 123: Runway Construction Project Execution Plan

Temporary Electricity Supply & Tower Lights

ⓒ David H Moloney

Ge

ne

ral It

em

s

Page 124: Runway Construction Project Execution Plan

Asphalt Batching YardG

en

era

l It

em

s

Page 125: Runway Construction Project Execution Plan

Asphalt Batching YardG

en

era

l It

em

s

Page 126: Runway Construction Project Execution Plan

Asphalt Batching YardG

en

era

l It

em

s

Page 127: Runway Construction Project Execution Plan

Concrete Batching Yard 3 Nr MixersG

en

era

l It

em

s

Page 128: Runway Construction Project Execution Plan

Concrete Batching Plant David H Moloney

ⓒ David H Moloney

Concrete batching plant comprises - concrete mixer, control cabin, silos for cement and fly ash, aggregate bins and conveyor belt system to feed the mixer. Also aggregate storage bays and water storage tanks. The mixing is computer controlled and has a dynamic screen display, showing the process. Material storage capacity to match two days concrete production

Page 129: Runway Construction Project Execution Plan

Concrete Batching Yard 3 Nr MixersG

en

era

l It

em

s

Page 130: Runway Construction Project Execution Plan

Crushed Aggregate Batching PlantG

en

era

l It

em

s

Page 131: Runway Construction Project Execution Plan

Crushed Aggregate Batching PlantG

en

era

l It

em

s

Page 132: Runway Construction Project Execution Plan

Quarry & Aggregate ProductionG

en

era

l It

em

s

Page 133: Runway Construction Project Execution Plan

Quarry & Aggregate ProductionG

en

era

l It

em

s

Page 134: Runway Construction Project Execution Plan

Reinforcement Cutting & Bending Yard David H Moloney

ⓒ David H Moloney

Reinforcement in 12 m lengths. Delivery in 3 ton Bundles Reinforcement cut to length by Shearing Machine

Reinforcement Bent to Shape by Bending Machine Reinforcement that is cut and bent is Bundled for delivery to work site

Page 135: Runway Construction Project Execution Plan

Reinforcement Cutting & Bending

ⓒ David H Moloney

Co

ncre

te

Page 136: Runway Construction Project Execution Plan

Setting out & Surveying

Page 137: Runway Construction Project Execution Plan

Setting out & Surveying

Page 138: Runway Construction Project Execution Plan

Setting out & Surveying

Page 139: Runway Construction Project Execution Plan

Safety & Environmental

Page 140: Runway Construction Project Execution Plan

Emergency Phone Numbers & Response

Page 141: Runway Construction Project Execution Plan

HSE Monitoring & Reporting - Dashboard Dashboard is a single page, graphical representation of

current HSE Issues and historical trends

Page 142: Runway Construction Project Execution Plan

Site Safety Posters examples

Page 143: Runway Construction Project Execution Plan

Safety Precautions

Page 144: Runway Construction Project Execution Plan

Personal Protective Equipment (PPE)H

ealth,

Safe

ty &

Envir

onm

ent

Personal protective equipment (PPE) is protective clothing, helmets, goggles, or other garments or equipment designed to protect the wearer from injury or infection

Page 145: Runway Construction Project Execution Plan

Existing Underground Utilities

ⓒ David H Moloney

Ea

rth

wo

rks

Brief Description

Before digging

establish the location

and route of

underground utilities.

Locator to find Utilities

Spray Paint to mark pavement

Page 146: Runway Construction Project Execution Plan

Existing Underground Utilities & Overhead Cables - Safety Measures

ⓒ David H Moloney

Ea

rth

wo

rks

Page 147: Runway Construction Project Execution Plan

Trench - Safety Measures H

ealth,

Safe

ty &

Envir

onm

ent

Page 148: Runway Construction Project Execution Plan

Trench - Safety Measures

ⓒ David H Moloney

Health,

Safe

ty &

Envir

onm

ent

Page 149: Runway Construction Project Execution Plan

Safety Training on Site M

isce

llan

eo

us

The purpose of safety training is to provide the knowledge necessary to

perform a job safely

Page 150: Runway Construction Project Execution Plan

Safety Training Matrix M

isce

llan

eo

us

The purpose of safety training is to provide the knowledge necessary to

perform a job safely

Page 151: Runway Construction Project Execution Plan

Emergency Response Drill H

SE

Drills and exercises are used to rehearse anticipated emergency scenarios

Page 152: Runway Construction Project Execution Plan

Safety DocumentsH

ealth,

Safe

ty &

Envir

onm

ent

Safe System of Work.

To provide a safe system of work is a legal requirement. What this means is that before you ask an employee to do a

job. You ensure that he has received training, has the appropriate personal protective equipment, the work area is safe

and he is unlikely to be injured or cause damage by carrying out the assigned task.

Project Management Plan for Health, Safety, Security and Environment. also Known as (HSSE Plan)

The Project HSSE Management Plan details how safety on site will be managed.

Project Procedures for Health, Safety, Security & Environment

Details the safe way to undertake a task

Methods Statements

Are prepared in advance of starting work, to plan a Safe System of Work on site for all activities that carries a risk. The

contents of a Method Statement, typically include:- Scope & Location of the Works, Programme, Roles & Responsibilities

of Staff. Resources, Work Methodologies and Risk Assessment.

Slide 1 of 2

Page 153: Runway Construction Project Execution Plan

Safety DocumentsH

ealth,

Safe

ty &

Envir

onm

ent

Safety Risk Assessments

Are prepared to identify and evaluate risks, to adopt control measures to reduce or eliminate risks.

COSHH Sheet

The purpose of the Control Of Substances Hazardous to Health sheet is to identify how to prevent or adequately control

workers exposure to hazardous substances.

Permit to Work.

Is a management system used to control high risk activities by ensuring safety measures are in place prior to starting

work.

Types of work for which permits will be required include:

Excavation and the digging of trenches.

Working at height, including on roofs.

Working in confined spaces, for example entering a manhole.

Hot work, which is welding, soldering or cutting steel with angle grinders or by gas torch.

Slide 2 of 2

Page 154: Runway Construction Project Execution Plan

Environmentally Friendly Site Air, Noise, Water & Soil Pollution

Page 155: Runway Construction Project Execution Plan

Hazardous Substances Symbols H

ealth,

Safe

ty &

Envir

onm

ent

COSHH stands for the Control of Substances Hazardous to Health

Shown are the new hazard symbols

Page 156: Runway Construction Project Execution Plan

Water Pollution PreventionG

en

era

l It

em

s

Page 157: Runway Construction Project Execution Plan

Segregation of Waste H

ealth,

Safe

ty &

Envir

onm

ent

Segregation of waste for proper disposal and recycling. Less waste goes to landfill and hazardous waste is treated to make it safe.

Colour Code for Skips & Bins

Page 158: Runway Construction Project Execution Plan

Putting Waste Concrete to use

ⓒ David H Moloney

Health,

Safe

ty &

Envir

onm

ent

Precast bases for signs and hoarding, Precast blocks for walls.

Page 159: Runway Construction Project Execution Plan

Administration

Page 160: Runway Construction Project Execution Plan

Organogram

Brief Description

Shown are the line and

lateral relationships

between the various team

members and their relative

position in the site

organisation.

Page 161: Runway Construction Project Execution Plan

Staff Responsibility Matrix

Page 162: Runway Construction Project Execution Plan

Staff Directory

Brief Description

List of staff and their

contact details

Page 163: Runway Construction Project Execution Plan

Daily Work Record

Brief Description

Daily Work Records showing the

allocation of resources, materials and

work activities carried out daily.

Page 164: Runway Construction Project Execution Plan

Quotations Comparison Sheet

Page 165: Runway Construction Project Execution Plan

Filing System

Page 166: Runway Construction Project Execution Plan

Quality Assurance

Page 167: Runway Construction Project Execution Plan

Quality Assurance Dashboard Dashboard is a single page, graphical representation of

current statistics and historical trends

Page 168: Runway Construction Project Execution Plan

Runway Asphalt Pavement - TestsR

oads &

Pavin

gs

Page 169: Runway Construction Project Execution Plan

Quality Assurance Tests

Page 170: Runway Construction Project Execution Plan

Runway Concrete Pavement - TestsR

oads &

Pavin

gs

Page 171: Runway Construction Project Execution Plan

Runway LaboratoryR

oads &

Pavin

gs

Page 172: Runway Construction Project Execution Plan

Laboratory

ⓒ David H Moloney

Asp

ha

lt P

avin

g

Page 173: Runway Construction Project Execution Plan

Programme & Progress Monitoring

Page 174: Runway Construction Project Execution Plan

Progress Monthly, Monitoring & Reporting - DashboardDashboard is a single page, graphical representation of current

progress and historical trends

Page 175: Runway Construction Project Execution Plan

Histogram Charts for Resources & Outputs

Manpower per Discipline

Concrete per Location

Man-hours for each month of the Project

Quantity for each month of the Project

ⓒ David H Moloney

Brief Description

Histograms shows resources etc. for each month of a project.

Page 176: Runway Construction Project Execution Plan

Plant & Equipment List & Worker’s Job Titles

ⓒ David H Moloney

Page 177: Runway Construction Project Execution Plan

Programme for Construction

Gantt Charts to plan and schedule projects

Page 178: Runway Construction Project Execution Plan

Primary Substation-

Chiller Plant

Pump House

IRRIGATION WATER TANKS

Irrigation Pump House-

POTABLE/FIRE WATER TANK

Programme using Timeline & 3D Images

Airport Central Utility Yard

Page 179: Runway Construction Project Execution Plan

Pump House

Piling

Page 180: Runway Construction Project Execution Plan

Primary Substation

Chiller PlantPump House

Irrigation Pump House

Page 181: Runway Construction Project Execution Plan

Primary Substation-711

Chiller Plant-714Pump House-715

Irrigation Pump House-716

Page 182: Runway Construction Project Execution Plan

Primary Substation-711

Chiller Plant-714Pump House-715

IRRIGATION WATER TANK

Irrigation Pump House-716

Page 183: Runway Construction Project Execution Plan

Primary Substation-711

Chiller Plant-714Pump House-715

IRRIGATION WATER TANK

Irrigation Pump House-716

Page 184: Runway Construction Project Execution Plan

Primary Substation-711

Chiller Plant-714Pump House-715

IRRIGATION WATER TANK

Irrigation Pump House-716

Page 185: Runway Construction Project Execution Plan

Primary Substation-711

Chiller Plant-714Pump House-715

IRRIGATION WATER TANK

Irrigation Pump House-716

Page 186: Runway Construction Project Execution Plan

Primary Substation-711

Chiller Plant-714Pump House-715

IRRIGATION WATER TANK

Irrigation Pump House-716

POTABLE/FIRE WATER TANK

Page 187: Runway Construction Project Execution Plan

Miscellaneous

Page 188: Runway Construction Project Execution Plan

Structural Steel

Page 189: Runway Construction Project Execution Plan

Airport Roof Truss

ⓒ David H Moloney

Str

uctu

ral S

tee

l

Brief Description

Roof Truss 190 tonne in weight. Sections welded together on

trestles and the truss is lifted into position.

Page 190: Runway Construction Project Execution Plan

Airport Roof TrussS

tru

ctu

ral S

tee

l

Roof Truss Sections Roof Truss Sections assembled on trestles

Trusses weigh 190 tonnes Crane Demag CC 8800

Page 191: Runway Construction Project Execution Plan

Airport – Roof Section Mock-up S

tru

ctu

ral S

tee

l

Page 192: Runway Construction Project Execution Plan

Airport Piers Roof Frames S

tru

ctu

ral S

tee

l

Sections assembled on trestles

Page 193: Runway Construction Project Execution Plan

Pedestrian Boarding Bridges & Bridge House S

tru

ctu

ral S

tee

l

Page 194: Runway Construction Project Execution Plan

Pedestrian Boarding Bridges & Bridge HouseS

tru

ctu

ral S

tee

l

Page 195: Runway Construction Project Execution Plan

Pedestrian Boarding Bridges & Bridge HousesS

tru

ctu

ral S

tee

l

Mock-up

Page 196: Runway Construction Project Execution Plan

Airport Roof TrussS

tru

ctu

ral S

tee

l

Page 197: Runway Construction Project Execution Plan

Airport Roof TrussS

tru

ctu

ral S

tee

l

Page 198: Runway Construction Project Execution Plan

Piers ConstructionS

tru

ctu

ral S

tee

l

Page 199: Runway Construction Project Execution Plan

Piers ConstructionS

tru

ctu

ral S

tee

l

Page 200: Runway Construction Project Execution Plan

Roof Covering

ⓒ David H Moloney

Str

uctu

ral S

tee

l

Brief Description

Sequence is

Fix bottom sheet

Fix Vapour barrier

Fix Top Hat section and clips

Fit Insulation

Fix top sheet

Page 201: Runway Construction Project Execution Plan

Roof Covering

ⓒ David H Moloney

Str

uctu

ral S

tee

l

Page 202: Runway Construction Project Execution Plan

Roof Covering

ⓒ David H Moloney

Str

uctu

ral S

tee

l

Page 203: Runway Construction Project Execution Plan

Roof Covering

ⓒ David H Moloney

Str

uctu

ral S

tee

l

Page 204: Runway Construction Project Execution Plan

View from ATC TowerM

isce

llan

eo

us

Page 205: Runway Construction Project Execution Plan

View from ATC TowerM

isce

llan

eo

us

Page 206: Runway Construction Project Execution Plan

View from ATC TowerM

isce

llan

eo

us

Page 207: Runway Construction Project Execution Plan

Tower ConstructionC

on

cre

te

Brief Description

Air Traffic Control Tower constructed

using a jump-up shutter system.

Page 208: Runway Construction Project Execution Plan

ATC Tower CladdingC

on

cre

te

Page 209: Runway Construction Project Execution Plan

Production by David H Moloney

My YouTube Channel link: https://www.youtube.com/channel/UCeJR9J7svhBd-C0ZoAH2fhQ

Page 210: Runway Construction Project Execution Plan

Heathrow Airport, 3rd Runway Construction

© David H Moloney

Page 211: Runway Construction Project Execution Plan

Runway Construction Sequence & Methods

© David H Moloney

Page 212: Runway Construction Project Execution Plan

Runway Construction Methods

© David H Moloney

Earthworks Basecourse Ducts for ground lights

Asphalt Paving Line Marking Flight Check

Page 213: Runway Construction Project Execution Plan

M25 Tunnel under Runway Construction Sequence & Methods

© David H Moloney

Page 214: Runway Construction Project Execution Plan

Culvert under Runway Construction Methods

© David H Moloney

Earthworks Prepare Formation Floor

Walls Roof Backfill

Page 215: Runway Construction Project Execution Plan

Heathrow Airport, 3rd Runway Construction

Introduction

This Presentation shows in a straightforward way how a runway

is constructed and how the progress, safety and quality is

monitored and controlled. Also the measures to ensure that

the site is environmentally friendly.

The Presentation can be used to engage Stakeholders and to

get the Site Teams commitment to the programme. Also can be

used as a way to capture and share knowledge.

Presentation can be used for safety and induction Training for

apprentices from the nearby communities that will be

employed on the new infrastructure. The Presentation shows

what to expect prior to stepping onto site and is currently used

for Training in Safety Compliance in airside operations to avoid

safety incidents and accidents

© David H Moloney