OVERVIEW OF OPERATIONAL AREA IN KENYA
Representation of a 1,000 HH community
200 HH village
100 kW generation
Radius = 7km
Location*:•The projects are located in Central Province, at the Southern face of Mount Kenya (see map)•Accessible via Kianyaga town, a 3.0 hour car ride from Nairobi.
Project Sites
Population and Demographics:
•Total beneficiaries estimated at 50,000 people with an average of 5.0 persons per household; average population density at 550 per square-km.•17 CBO’s with 1000 household membership identified with (see box in left-bottom corner)•Life expectation is relatively long at 65 years; no accurate data available on HIV status within the operational area.
Economics:•Small farmers with an average of 1 acres per household•Most households are within the tea- and coffee zone and produce tea, coffee, maze, beans, banana’s and hold cattle cows and chicken•Average income per household is 800-900 USD per year
•80-90% completed primary education •50-70%completed secondary education
Education:
•Less than 4% of the households electrified•Telecommunication networks cover the area.•50% has access to water for domestic usage
Connectivity:
* Project locations include Kirinyaga District, Embu District
Transformer
3
PROJECT MISSIONS AND GOALSE
lem
ents
fo
r S
ust
ain
ed D
evel
op
men
t Self - Governance
Hard Assets
Technical Capability
CommunityInvestments
Create local governance mechanisms based on collaborative social- and economic values.
Generate monetary assets (power plants, distribution systems and factories) which provide access to formal credit markets and centralize development initiatives to a local level.
Manifest business- and management expertise to operate and maintain commercial enterprises. Social- and economic capacity building via scale-up initiatives.
Create decentralized social investment opportunities (i.e. education facilities and infrastructure) through the control and isolation of fund channels which are presently inefficient (kerosene, candles, battery charging)
4
A THREE-PHASE APPROACH
•Agreement, community contribution and post-valued labor create sustainability and filter governance structures. •Independent Power producer- and distributor.
Self - Governance
Hard Assets
Technical Capability
Community Investments
Goals / Milestones:
PHASE I: PILOT PHASE II: ROLL OUT PHASE III: ENHANCE
•10 prime structures of 100kW generation facilities•One fully operational 100kW-1000 connection project.
•In-house know-how and expertise to design and construct prime structures.•Business management basics
•Awareness of economic structures and access to credit markets.
•Filtered governance structure translates and expands itself through co-operative relations with succeeding CBO’s.•Cooperative of Independent power producer- and distributors
•Ten 100kW-1000 connection facilities.•2 MW plant prime structures•Design of commercial platforms
•In-house capacity to design, produce and install energy pilots, controls and distribution networks
•Establishment of social investment committees which govern development initiatives
•Cooperative supports expansion and replication. •Social investment committees support education, infrastructure, social welfare and health programs•Electricity cooperative
•2 MW generation plant•10 100KW commercial platforms•Private grid extension.
•In-house capacity to design, produce and install MW energy pilots.•Training and maintenance programs. Operation and management programs.
•Locally governed development initiatives
5
ORGANIZATION STRUCTURE
HH 2HH 1 HH 3 1,000 HHs
Social Investments Committee
3 Representatives Appointed by the Local Board
Operations Committee
4 Full-Time (Paid) Staff Supervised by the Board
10 Elected Community Representatives
Local Board - 1
Management
Collections
Engineering
Finance
HH 2HH 1 HH 3 1,000 HHs
Social Investments Committee
3 Representatives Appointed by the Local Board
Operations Committee
4 Full-Time (Paid) Staff Supervised by the Board
10 Elected Community Representatives
Local Board - 2
Management
Collections
Engineering
Finance
Green Power LTD Executive Board
1 Representative from each Community - Total of 70%Robert Mutsaers and Nyaga Ndiga– Total of 30%
10 – 17 Local Boards
Local Partners:•GreenPower – NGO
•Sintronics (Control Systems)•Numerical Engineering (Turbine Manufacture)
6
TIMELINE
2004 20102005 2006 2008 20092007
Green Power LTD: Robert and
Nyaga
First 100kW generators
successfullytested
First primary structure
completed
TARDA grants
35k Euro
Primary structures completed in 3
sites; 7 others are underway
Liberty grants 30k Euro for
finalization of pilot generation project
French embassy granted 50k Euros for finalization of pilot distribution
project
Robert selected as
Echoing Green social entrepreneur
fellow
Completion of first mini
grid and pilot
TODAY
2011 2012
PHASE I: PILOT PHASE II: ROLL OUT PHASE III: ENHANCE
Start prime structures for
2 MW generation, commercial
platforms, and micro-hydro
manufacturing shop
3 more projects are finalized, 6 are pending mini-grids
All 10 projects
are finalized
Construction of MW plant and commercial
platforms
Interconnect grids and connect to MW
generation plant
Finalization of MW
generation plant and
commercial platforms
7
•Agreement, community contribution and post-valued labor create sustainability and filter governance structures. •Independent Power producer- and distributor.
Self - Governance
Hard Assets
Technical Capability
Community Investments
Goals / Milestones:
•10 prime structures of 100kW generation facilitiesOne fully operational 100kW-1000 connection project.
•In-house know-how and expertise to design and construct prime structures.Business management basics
•Awareness of economic structures and access to credit markets.
PHASE I: Ten prime structures and one 100KW-1000 connection Model
Financing :
•Prime structures •100KW generation •Control units •Mini Grid •Transformers and switch gear
100KW-1000 Connection project
•Weekly lectures with local communities•Technical training of local skilled laborers•Theoretical training at polytechnic Kenya•Evaluation Study
Capacity building
•Post valued labor agreements towards finalization of Prime structures and core distribution network•Post valued labor agreements installation generation pilot and controls.•Post valued labor design, construction, assembly and installation of generation and distribution systems.•Land allocation and license agreements•Investment return agreements
Implementation
COMPLETION EXPECTED AS OF NOVEMBER 2007
Total financing need for Phase I forecasted: 300 Thousand USD
8
Self - Governance
Hard Assets
Technical Capability
Community Investments
Goals / Milestones:
•Ten 100kW-1000 connection facilities.•2 MW plant prime structures•Design of commercial platforms
•In-house capacity to design, produce and install energy pilots, controls and distribution networks
•Establishment of social investment committees which govern development initiatives
Financing :
•Prime structures, 100KW generation •Control units, Mini Grid-1000 Connections •Transformers and switch gear
Nine 100KW-1000 Connection project
•Prime structures•Commercial platforms
MW-Prime structures and commercial platforms
•Post valued labor agreements of Generation plants, distribution networks, MW-prime structures and commercial platforms•Post valued labor installation generation pilot and controls.•Post valued labor GP, design, construction, assembly and installation of energy systems and commercial platforms.•Land allocation and license agreements•Investment return agreements
Implementation
PHASE II: nine 100KW-1000 Connection projects and MW-Prime Structures
Total financing need for Phase II forecasted: 3 Million USD
•Weekly lectures with local communities•Technical training of local skilled laborers•Theoretical training at polytechnic Kenya•Evaluation study
Capacity building
•Filtered governance structure translates and expands itself through co-operative relations with succeeding CBO’s.•Cooperative of Independent power producer- and distributors
9
PHASE III: 2MW Generation Plant, Substation and Ten Commercial Platforms
•Cooperative supports expansion and replication. •Social investment committees support education, infrastructure, social welfare and health programs•Electricity cooperative
Self - Governance
Hard Assets
Technical Capability
Community Investments
Goals / Milestones:
•2 MW generation plant•10 100KW commercial platforms•Private grid extension.
•In-house capacity to design, produce and install MW energy pilots.•Training and maintenance programs. Operation and management programs.
•Locally governed development initiatives
Financing :
•Structures •Equipment
Ten 100KW-Commercial platforms
•Generation pilots and controls•Substation and high voltage feeding line•Interconnection of isolated grids
MW-Generation Installation
•Post valued labor agreements of Generation plants, distribution networks, MW-prime structures and commercial platforms•Post valued labor installation generation pilot and controls.•Post valued labor GP, design, construction, assembly and installation of energy systems and commercial platforms.•Land allocation and license agreements•Investment return agreements
Implementation
•Weekly lectures with local communities•Technical training of local skilled laborers•Theoretical training at polytechnic Kenya•Evaluation study
Capacity building
Total financing need for Phase III forecasted: 9 Million USD
10
FINANCIAL- AND OTHER PARTNERS PHASE I – 2005 - Jun 2008
Financing 100KW project
Training / Consulting
•Local communities (GP)
Organization Type Amount Purpose
•Equity Investment
$100k •Feasibility, Prime structures and skeleton network
•Liberty •Grant $20k Euro •100KW Generation Facility
•TARDA* •Grant $35k Euro •100KW Generation Facility
•Liberty •0% Loan $100k Euro •1000 connection Mini-Grid
•French Embassy •Grant $50k Euro •1000 connection Mini-Grid
•Green Power (NGO) •Organizational structuring
Organization Duration Purpose
•Over 2 years
•Green Power (NGO) •Technical- and maintenance•Over 1 year
* TARDA = Tana and Athi River Development Authority, Kenya
•University UQAM/ CAN •Evaluation and impact assessment•Over 2 years
•Netherlands Embassy •Grant $25k Euro •Workshop
•Linklaters •Legal Assistance•Over 2 years
11
FINANCIAL- AND OTHER PARTNERS PHASE I – 2005 - Jun 2008
Financing nine 100KW projects
Total Need: Euro 3 m
Training / Consulting
•Local communities (GP)
Organization Type Amount Purpose
•Equity Investment
$100k•Feasibility, Prime structures and skeleton network
•GTZ
•NRECA
•Liberty
•Mlinda Foundation
•Support nine-1000 connection Distribution networks (Under negotiation for interest free loans)
•Green Power (NGO)
Organization Duration Purpose
•Continuous
•NRECA•Technical capacity building
•3 Years
•Support nine 100KW generation installations and substations (Under negotiation for grant support0
•Capacity building (Under negotiation Pro-Bono assistance)
•Support for Workshop and construction of Prime Structures. (Under negotiation)
•Good Energy •Support nine 100KW/1000 connection projects (Under negotiations for low interest loans)
•ACUMEN Fund •Support nine 100KW/1000 connection projects (Under negotiations for low interest loans)
•Linklaters •One year •Legal assistance•Capacity building
•University UQAM/ CAN •Evaluation and impact assessment•Over 2 years
12
COLLABORATION IN PHASE II – TO BE FINALIZED BY END OF 2009
Financing
Total Need: Euro 10 m
Training / Consulting
Organization Type Amount Purpose
•Local communities (GP)
•Equity Security
•GTZ
•NRECA
•Liberty
•Mlinda Foundation
•Support High voltage feeding line. (Suggested)
•Support MW power plant. (Suggested)
•Capacity building (Under negotiation Pro-Bono assistance)
•Support Commercial Platforms. (suggested)
•USAID •Support MW Generation Plant and commercial platforms. Suggested)
•Green Power (NGO)
Organization Duration Purpose
•Continuous
•NRECA •3 Years
•Linklaters •One year
•University UQAM/ CAN •Over 2 years
•Technical capacity building
•Legal assistance•Capacity building
•Evaluation and impact assessment