russell biomass final report

Upload: asaraiszabo

Post on 03-Apr-2018

217 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/29/2019 Russell Biomass Final Report

    1/42

    RUSSELL BIOMASS POWER PLANT

    Pre-Construction Development ActivitiesFinal Report for Loan No. GP-05-13, as Amended

    Prepared by:Russell Biomass LLC

    May 2006

    Funded by the Predevelopment Financing Initiative ofThe Renewable Energy Trust Clean Energy Program

  • 7/29/2019 Russell Biomass Final Report

    2/42

    ________________________________________________________________________________________________Russell Biomass Power PlantPre-Construction Development ActivitiesFinal ReportPage 2

    NOTICE AND ACKNOWLEDGEMENTS

    This report was prepared by Russell Biomass LLC in the course of performing work

    sponsored by the Renewable Energy Trust (RET), as administered by the Massachusetts

    Technology Collaborative (MTC), pursuant to Loan Number GP-05-13, as amended.

    The opinions expressed in this report do not necessarily reflect those of MTC or the

    Commonwealth of Massachusetts, and reference to any specific product, service, process,

    or method does not constitute an implied or expressed recommendation or endorsement

    of it.

    Further, MTC, the Commonwealth of Massachusetts, and the contractor make no

    warranties or representations, expressed or implied, as to the fitness for particular purpose

    or merchantability of any product, apparatus, or service, or the usefulness, completeness,

    or accuracy of any processes, methods or other information contained, described,

    disclosed, or referred to in this report. MTC, the Commonwealth of Massachusetts, and

    the contractor make no representation that the use of any product, apparatus, process,

    method, or other information will not infringe privately owned rights and will assume no

    liability for any loss, injury, or damage directly or indirectly resulting from, or occurring

    in connection with, the use of information contained, described, disclosed, or referred toin this report.,

  • 7/29/2019 Russell Biomass Final Report

    3/42

    ________________________________________________________________________________________________Russell Biomass Power PlantPre-Construction Development ActivitiesFinal ReportPage 3

    ABSTRACT

    This report describes pre-construction project development activities for a 50 MW

    biomass-fired electric generation plant in Russell, Massachusetts. These activities were

    funded in part by a loan to the developer, Russell Biomass LLC, from the Massachusetts

    Technology Collaborative through the Predevelopment Financing Initiative of the

    Renewable Energy Trust Clean Energy Program. The activities described in this report

    include public outreach, preliminary plant and site engineering, initiation of the

    permitting and transmission line interconnection process, obtaining expressions of

    interest from biomass fuel suppliers and prospective power purchasers, and preparation of

    a development funding solicitation memorandum. Additional activities funded by an

    amendment to the original loan focused on securing power purchase commitments and

    key permits and approvals. All activities were completed successfully, and the project is

    continuing the power purchase and permitting work.

    Key words: biomass, biomass power plant, biomass boiler, biomass fuel supply, public

    outreach, permitting, transmission line interconnection, power purchase agreement,

    development financing.

  • 7/29/2019 Russell Biomass Final Report

    4/42

    ________________________________________________________________________________________________Russell Biomass Power PlantPre-Construction Development ActivitiesFinal ReportPage 4

    TABLE OF CONTENTS

    SUMMARY 5

    1.

    PROJECT DESCRIPTION AND DEVELOPMENT PLAN 10

    2. CARRY OUT PUBLIC OUTREACH PROGRAM 153. PRELIMINARY PLANT ENGINEERING 204. SITE ENGINEERING 235. INITIATE PERMIT APPLICATIONS 256. TRANSMISSION LINE DESIGN 307. FUEL SUPPLY COMMITMENTS 338. POWER SALE OPTIONS 359. PROJECT FINANCIAL VIABILITY AND

    DEVELOPMENT FINANCING36

    10. INTERCONNECTION STUDY 37

    11. DRAFT ENVIRONMENTAL IMPACT REPORT 39

    12. AIR DISPERSION MODELING 41

    13. NEGOTIATE POWER PURCHASE AGREEMENTS 42

  • 7/29/2019 Russell Biomass Final Report

    5/42

    ________________________________________________________________________________________________Russell Biomass Power PlantPre-Construction Development ActivitiesFinal ReportPage 5

    SUMMARY

    This report describes pre-construction project development activities of Russell Biomass

    LLC in the development of a 50 MW biomass-fired electric generation plant on 20 acres

    of a 70-acre site that is owned by the developers and is located in the town of Russell in

    Western Massachusetts. The first stage of development, a feasibility study that helped

    assure that no technical or permitting fatal flaws existed, was started in May 2004 and

    completed successfully in January 2005.

    In the fall of 2004 Russell Biomass applied for a loan to provide partial financing for the

    second stage of development, February-June 2005, to finalize plant design and cost

    parameters, secure a Special Permit from the Town of Russell, obtain expressions of

    interest for biomass fuel supply and power purchase, and obtain financing for project

    development. MTC provided a loan of $150,000 to support these activities, and the

    developers were required to provide a cash match of at least 25%.

    In August 2005 the project applied for additional funding to support third-stage

    development work (securing power purchase commitments and remaining permits and

    approvals) during the November 2005 January 2006 period. In December MTCapproved an additional loan of $100,000.

    The project was successful in meeting the objectives and appears to be technically and

    economically viable. The MTC loan played a key role in moving the project forward.

    Work is well underway on the third stage of development. The project is on track to

    complete pre-construction development activities in mid-2007, and following a 2-year

    construction period, to start commercial operation by mid-2009.

  • 7/29/2019 Russell Biomass Final Report

    6/42

    ________________________________________________________________________________________________Russell Biomass Power PlantPre-Construction Development ActivitiesFinal ReportPage 6

    The following tasks were funded by the initial loan:

    Task 1: Carry out public outreach program

    Task 2: Preliminary plant engineering

    Task 3: Site engineering

    Task 4: Initiate permit applications

    Task 5: Transmission line design

    Task 6: Fuel supply commitments

    Task 7: Power sale options

    Task 8: Project financial viability and development financing

    Task 9: Project reporting

    The additional loan was used to fund the following work:

    Task 10: Interconnection study

    Task 11: Draft Environmental Impact Report

    Task 12: Air dispersion modeling

    Task 13: Negotiate power purchase agreements

    This report discusses all of the above tasks. Russell Biomass prepared a similar report on

    the tasks funded by the initial loan in September 2005. The discussion of Tasks 1-9 in

    the current report is essentially unchanged from the earlier report. A brief summary of

    the tasks follows.

    Task 1 Russell Biomass initiated a public outreach program in order to ensure broad

    public support and maximize the likelihood that the Town of Russell would grant a

    Special Permit for the project. The program involved conducting a survey of all Russell

    voters to determine what residents thought of the project and developing communications

    to respond to resident concerns about the project and highlight project benefits.

  • 7/29/2019 Russell Biomass Final Report

    7/42

    ________________________________________________________________________________________________Russell Biomass Power PlantPre-Construction Development ActivitiesFinal ReportPage 7

    Task 2 The purpose of the preliminary plant engineering task was to expand on the

    earlier conceptual design of the power plant, principally the boiler island component,

    and finalize the major plant design parameters, e.g., energy/material/water balances and

    air emissions and water effluent, and capital and operating costs. This information would

    enable Russell Biomass to launch the permitting process and refine the financial

    projections. The developers commissioned two boiler manufacturers to develop design

    and cost information for a bubbling fluidized bed boiler and an advanced stoker-fired

    boiler.

    Task 3 The site engineering task involved the completion of a site survey and

    preparation of a site plan and other plans required for the Special Permit application. The

    developers also undertook an evaluation of alternative wood fuel delivery truck access

    routes to the site.

    Task 4 The permitting task was focused on obtaining a Special Permit for the project

    from the Town of Russell and on documenting the permitting issues associated with the

    use of Clean Recycled Wood (CRW) from C&D sources. Russell Biomass prepared and

    submitted the Special Permit application and participated in three public hearings held by

    the Zoning Board of Appeals and the Planning Board. The boards approved the SpecialPermit at the final hearing, although the developers dropped plans to use CRW because

    of strong objections to this fuel from project opponents.

    Task 5 The transmission line task involved documenting the regulatory approvals

    required for the new 5.2-mile transmission line that will connect the project to the

    Northeast Utilities transmission network. The developers prepared to initiate the ISO

    New England interconnection process and documented two other approvals that might be

    required: the Massachusetts Energy Facilities Siting Board and the Department of

    Telecommunications and Energy.

  • 7/29/2019 Russell Biomass Final Report

    8/42

    ________________________________________________________________________________________________Russell Biomass Power PlantPre-Construction Development ActivitiesFinal ReportPage 8

    Task 6 -- The fuel supply task involved obtaining letters of interest from potential wood

    fuel suppliers in the region. 35 suppliers responded with a total tonnage approximating 2

    x the plants requirements.

    Task 7 -- The objective of the power sale options task was to obtain expressions of

    interest from prospective power purchasers. The response was positive the capacity of

    the project was over-subscribed.

    Task 8 Key activities in the financial task were completion of a financial model for the

    project and preparation of a development funding solicitation memorandum, to help raise

    the funds needed to complete development prior to construction.

    Task 9 The objective was to fulfill the MTC project reporting requirements.

    Task 10 The purpose of the Interconnection Study task was to undertake the first step of

    the ISO New England transmission interconnection process, the Feasibility Study. The

    study consisted of a preliminary evaluation of electrical impacts (thermal overload,

    voltage limit violations, and short circuit) of the project on the existing transmission

    system and a preliminary assessment of the cost of the new transmission line andsubstation.

    Task 11 This task involved important early work related to the preparation of the Draft

    Environmental Impact Report. The effort focused on selected issues noted in the

    Secretary of Environmental Affairs Certificate on the Expanded Environmental

    Notification Form.

    Task 12 The objective of this task was to prepare a refined air dispersion modeling

    report for inclusion in the Major Comprehensive Plan Approval application for the

    project.

  • 7/29/2019 Russell Biomass Final Report

    9/42

    ________________________________________________________________________________________________Russell Biomass Power PlantPre-Construction Development ActivitiesFinal ReportPage 9

    Task 13 This task involved developing terms and conditions for the power purchase

    agreement and continuing to secure commitments from potential power purchasers.

  • 7/29/2019 Russell Biomass Final Report

    10/42

    ________________________________________________________________________________________________Russell Biomass Power PlantPre-Construction Development ActivitiesFinal ReportPage 10

    Section 1

    PROJ ECT DESCRIPTION AND DEVELOPMENT PLAN

    PROJ ECT DESCRIPTION

    Russell Biomass LLC is developing a base load, 50 MW net biomass-fired (wood fueled)

    electric generation plant on 20 acres of a 70-acre site. The site is owned by the developers

    and is located in the town of Russell in Western Massachusetts.

    About 500,000 tons of biomass fuel, which is comprised of whole tree chips from land

    clearing and tree trimming and ground stumps and pallets, will be consumed annually.

    According to independent reports there is nine times (9x) the fuel required within a 100-

    mile radius of the project, the wood supply area. Prior to commencement of construction

    wood supply contracts for all of the wood supply will be in place.

    The Russell site, the former site of the Westfield River Paper Company, is a superior one.

    The water supply will come from the Westfield River next to the site, and a utility

    easement links the site to a 115 kV transmission line approximately five miles away.

    Significant site preparation, land clearing, sand and gravel removal and leveling work hasalready been done; 20 acres of level ground will be available for the power plant and

    related facilities. The Town of Russell is supportive of the project, which will increase

    the towns tax revenues by 20% and provide an average of 50 construction jobs during

    the 2-year construction period and 22 permanent plant operating jobs.

    The project location maximizes the biomass fuel supply and price benefits. Located in

    western Massachusetts, Russell is close to the Springfield metropolitan area and to

    Hartford and other metropolitan areas in Connecticut, the New York City metro area and

    the Albany-Schenectady area, where significant volumes of land-clearing wood and

    pallets are generated and subject to high disposal costs.

  • 7/29/2019 Russell Biomass Final Report

    11/42

    ________________________________________________________________________________________________Russell Biomass Power PlantPre-Construction Development ActivitiesFinal ReportPage 11

    The developers have strong experience and skills suited to a biomass power plant

    development. The team includes a developer, Peter Bos, who previously developed a 45

    MW, 450,000 tpy wood fueled biomass plant in Maine; William Hull, a forester who

    owns the Russell site, runs a sawmill in Connecticut, and has previous biomass power

    plant development experience; Robert Berti and James Dammann, foresters who have

    been procuring wood fuel for biomass plants for 20 years; and James Ramsey, a

    registered professional engineer and businessman. ARS Group LLC (ARS), owned by

    Peter Bos, was the lead developer on the successful 45 MW, 450,000 tons/year Stratton,

    Maine, wood fired electric generation plant built in 1989. This successful plant has had

    availability consistently in the 95% range.

    The developers have assembled a highly qualified team of engineering and consulting

    firms, all of which are currently working on the project:

    Tighe & Bond, Inc. Permitting, site engineering

    Tech Environmental, Inc. Air, noise permitting

    Waldron Engineering, Inc. Power plant engineering

    Cianbro Corporation/Commonwealth Associates Transmission line engineering

    Energy Management Group Power marketing

    Financial Management Group LLC Financing, power marketing

    Darby OBrien and John Bos & Associates Public outreach

  • 7/29/2019 Russell Biomass Final Report

    12/42

    DEVELOPMENT PLAN

    Key activities in the Russell Biomass development work plan are shown in the following

    table:

    Russell Biomass Power Plant Work Plan

    Action 2004 2005 2006 2007 2008 2009

    1. Feasibility Review Complete

    2. Public Outreach

    3. Plant Engineering

    4. Site Engineering

    5. Permits/Approvals

    6. Transmission Line Design/Approval

    7. Fuel Supply

    8. Power Sales

    9. Financial Viability and Financing

    10. EPC Firm Selection

    11. Construction Loan Close and Funding

    12. Construction

    13. Operations Planning

    14. Plant Startup and Operation

    X X

    X

    X

    As shown in the above table, the 3-year pre-construction development period willconclude in mid-2007. Following a two-year construction period, the plant will start

    commercial operation in mid-2009.

    The first stage of development assuring that no technical or permitting fatal flaws exist

    was started in May 2004 and completed successfully in January 2005. The initial

    MTC-funded project (February June 2005) was the second stage of development. The

    objectives of the project were to:

    Finalize the major plant design parameters Secure a Special Permit from the Town of Russell and resolve permitting

    issues associated with clean recycled wood

    ________________________________________________________________________________________________Russell Biomass Power PlantPre-Construction Development ActivitiesFinal ReportPage 12

  • 7/29/2019 Russell Biomass Final Report

    13/42

    ________________________________________________________________________________________________Russell Biomass Power PlantPre-Construction Development ActivitiesFinal ReportPage 13

    Confirm the availability and cost of wood fuel supplies and obtain expressionsof interest from suppliers

    Confirm the likely price and contract term for power sales and obtainexpressions of interest from power purchasers

    Obtain a funding commitment for the remainder of project development up tothe start of construction

    The objective of the subsequent MTC loan was to make progress on the critical stage-

    three activities of securing power purchase commitments and critical-path permits and

    approvals. The project was successful in meeting all objectives, including securing

    additional development funding. Work has been initiated on the third stage of

    development, securing the remaining permits and approvals.

    The following tasks were included in the initial MTC pre-development loan agreement:

    Task 1: Carry out public outreach program

    Task 2: Preliminary plant engineering

    Task 3: Site engineering

    Task 4: Initiate permit applicationsTask 5: Transmission line design

    Task 6: Fuel supply commitments

    Task 7: Power sale options

    Task 8: Project financial viability and development financing

    Task 9: Project reporting

  • 7/29/2019 Russell Biomass Final Report

    14/42

    ________________________________________________________________________________________________Russell Biomass Power PlantPre-Construction Development ActivitiesFinal ReportPage 14

    Tasks funded under the subsequent MTC loan are as follows:

    Task 10: Interconnection study

    Task 11: Draft Environmental Impact Report

    Task 12: Air dispersion modeling

    Task 13: Negotiate power purchase agreements

    Objectives and results for each task are discussed in the remaining sections of the report.

  • 7/29/2019 Russell Biomass Final Report

    15/42

    Section 2

    CARRY OUT PUBLIC OUTREACH PROGRAM

    The community relations between the developers and the town of Russell are excellent.

    Hull Forest Products/Westfield Paper Lands has been an exemplary member of the

    Russell community since purchasing the land in 2000. The company originally intended

    to build a wood manufacturing facility, similar to the Hull Forest Products sawmill in

    Connecticut, on the site, and in October 2000 the town granted a Special Permit to

    construct the facility.

    Changes in the wood products market caused the company to decide not to build a wood

    manufacturing facility in Russell. However, Hull Forest Products uses a portion of the

    site as a log and pulpwood concentration yard and in 2004 built a 4,000 square foot, two-

    story office building and installed a truck weigh scale.

    In mid-2004 William Hull formed a development team to investigate the feasibility of

    developing a biomass power plant on the Russell site. The developers met with Russell

    selectmen in June and December 2004 to describe the project concept and hear about key

    issues from the town, and met once with the assessors to discuss property taxes. TheTown of Russell has been supportive of the biomass power plant project from the outset.

    The small town (population 1500) lost approximately 125 jobs and substantial tax

    revenues when Westfield River Paper Company abandoned the site in 1995. The

    proposed power plant, providing 50 construction jobs for 2 years, 22 new permanent

    operating jobs, and a 20% increase in the towns property tax revenues, would be a

    significant economic development boost for the community.

    In addition to supportive Town officials, the developers knew that broad public support

    for the project was necessary in order to secure a Special Permit from the Town, a key

    approval for the project. The permit application was planned for March 2005, and in

    January Russell Biomass engaged consultants John Bos & Associates and Chestnut

    ________________________________________________________________________________________________Russell Biomass Power PlantPre-Construction Development ActivitiesFinal ReportPage 15

  • 7/29/2019 Russell Biomass Final Report

    16/42

    Productions to develop a public outreach program to gain public support for the project.

    The public outreach effort involved two tasks:

    Conduct a survey of all Russell voters to learn what Russell residents thoughtabout the proposed power plant

    Develop effective public communications and education to respond to residentconcerns about the project and highlight project benefits

    VOTER SURVEY RESULTS

    In January 2005, following a presentation of its proposal to develop a biomass-fired

    power plant to the Russell selectmen on December 21, 2004, Russell Biomass

    commissioned a survey of all Russell voters to find out, as William Hull wrote in his

    survey cover letter, What Russell residents think about our idea. 148 voters out of 987

    voters receiving the mail survey responded, a 15% return. This is a high percentage level

    of respondents for such a survey. Six questions were asked and answered.

    The final question Do the benefits (of the Russell Biomass Project) outweigh your

    concerns captures the overall positive response to the survey. In the survey 98 of 125 or78% of the responses to this question said yes. See chart below.

    ________________________________________________________________________________________________Russell Biomass Power PlantPre-Construction Development ActivitiesFinal ReportPage 16

  • 7/29/2019 Russell Biomass Final Report

    17/42

    The two charts below reflect the residents views as to the Project benefits and concerns.

    ________________________________________________________________________________________________Russell Biomass Power PlantPre-Construction Development ActivitiesFinal ReportPage 17

  • 7/29/2019 Russell Biomass Final Report

    18/42

    ________________________________________________________________________________________________Russell Biomass Power PlantPre-Construction Development ActivitiesFinal ReportPage 18

    PUBLIC COMMUNICATIONS AND EDUCATION

    Following the survey and immediately prior to the first Special Permit hearing in April

    2005, Russell Biomass published a 4-page newspaper supplement in the Country Journal,

    the local weekly newspaper serving Russell and other communities, entitled Why a

    Biomass Power Plant for Russell? The supplement, developed by the outreach

    consultants, included a description and frequently asked questions about the project, voter

    survey results, a brief explanation of biomass energy, and a timeline of industrial activity

    at the Russell project site (which reminded residents that the site had a 100+-year history

    of industrial operations prior to the closing of the Westfield River Paper Company in

    1995).

    The three Special Permit hearings (April, May and June) afforded the developers an

    excellent opportunity to respond to citizen concerns and communicate the benefits of the

    project. At least 3 of the five developers and two Tighe & Bond managers attended each

    meeting. Considerable effort was spent between meetings preparing responses to

    questions, mainly related to project impacts (e.g., truck traffic, visual) from the Zoning

    Board of Appeals and the Planning Board.

    The hearings were challenging. Just prior to the second and third hearings, the

    developers were warned that well-organized opposition groups would attempt to delay or

    stop the project with damaging assertions about project impacts. Preparing for these

    interventions at the last minute was demanding. The public outreach consultants were

    helpful in crafting responses to the anticipated challenge.

    As part of its effort to inform Russell citizens about the planned development, 10 days

    prior to the third hearing Russell Biomass arranged for approximately 30 residents to visit

    the 17 MW Pinetree biomass power plant in Westminster, MA. The Russell group was

    given a guided tour of the Pinetree facility and attended a technical presentation by the

  • 7/29/2019 Russell Biomass Final Report

    19/42

    ________________________________________________________________________________________________Russell Biomass Power PlantPre-Construction Development ActivitiesFinal ReportPage 19

    plant manager. Based on participant feedback following the trip, this tour gave the

    residents a better sense of what it would be like to have such a facility in Russell.

    Throughout the hearings the developers were open and responsive to the concerns of the

    citizens, and in the end the Town approved the permit, affirming the positive response

    from the voter survey. The public outreach effort was essential to this successful

    outcome.

  • 7/29/2019 Russell Biomass Final Report

    20/42

    Section 3

    PRELIMINARY PLANT ENGINEERING

    The Russell Biomass Power Plant will consist of a complete fuel receiving and handling

    system, a single bubbling fluidized bed boiler, a single condensing turbine, a cooling

    system utilizing water from the nearby Westfield River, air and water quality control

    systems, backup fuel oil capability, and essential auxiliaries typical of a stand-alone

    power generating station. Design net station output will be 50 MW; the annual energy

    production net of parasitic load will be 381 million kWh See the site plan below:

    ________________________________________________________________________________________________Russell Biomass Power PlantPre-Construction Development ActivitiesFinal ReportPage 20

  • 7/29/2019 Russell Biomass Final Report

    21/42

    ________________________________________________________________________________________________Russell Biomass Power PlantPre-Construction Development ActivitiesFinal ReportPage 21

    As part of the Feasibility Study undertaken during the second half of 2004, the

    developers commissioned Waldron Engineering, power plant engineers, to perform

    conceptual design development engineering work for the power plant, based on 20, 40

    and 50 MW configurations. Only the bubbling fluidized bed boiler technology was

    evaluated because the Massachusetts Renewable Portfolio Standard (RPS) regulations

    exclude stoker-fired boilers from RPS qualification. By the start of the MTC-funded

    project (Feb 2005), the developers had decided on a 50 MW facility. The potential

    biomass supply in the region appeared sufficient to support a plant of this size, and the

    lower unit capital and operating costs were essential to the projects financial viability.

    The objective of the Preliminary Plant Engineering task was to expand on the earlier

    conceptual design of the power plant, principally the boiler island component, and

    finalize the major plant design parameters, i.e., energy/material/water balances, process

    flow diagrams, air emissions and water effluent, and capital and operating costs. With

    this information Russell Biomass would be able to launch the permitting process and

    refine the financial projections.

    Early in this engineering effort Waldron Engineering found that the boiler manufacturers

    were unable/unwilling to undertake at their own expense the significant additionalengineering effort necessary to refine the design and costing of the boiler and emissions

    control systems. So the developers commissioned Babcock & Wilcox to undertake a paid

    feasibility study and budgetary cost analysis of the best bubbling fluidized bed

    boiler/emission control technology suitable for the project, based on boiler functional

    requirements, e.g. 450,000 lb/hr of steam, and emissions targets, e.g., 0.075 lb/MMBtu

    NOx.

    At about the same time DOER issued favorable Advisory Rulings for two retrofit projects

    involving advanced stoker-fired boilers and indicated that it might propose modifying

    the RPS regulations to remove the stoker exclusion. Although outside the scope of the

    study as initially planned, the developers and Waldron asked Babcock Power, Inc., a

  • 7/29/2019 Russell Biomass Final Report

    22/42

    ________________________________________________________________________________________________Russell Biomass Power PlantPre-Construction Development ActivitiesFinal ReportPage 22

    stoker boiler manufacturer, to develop design and cost information for a stoker-fired

    boiler, in parallel with the B&W fluidized bed design effort.

    In May B&W and Babcock Power submitted their preliminary boiler/emissions system

    designs and cost estimates. Both biomass boiler technologies can meet all emissions

    control targets. Both recommended selective catalytic NOx reduction (SCR) emissions

    control systems to meet the NOx emissions target.

    The installed cost of the bubbling fluidized bed boiler is approximately 15% higher than

    that of the stoker. Bubbling bed operating costs are also estimated to be higher than

    stoker.

    The main advantage of fluidized bed vs. stoker is its ability to handle a wider range of

    biomass fuels (e.g., containing dirt, tramp metals) without fouling or damage. Because of

    this operational advantage, and in light of the uncertainty of stoker eligibility for

    Massachusetts RPS qualification, Russell Biomass will proceed with the bubbling

    fluidized bed design. The preliminary design effort of Waldron/B&W generated

    sufficiently detailed design information to allow the project to begin preparing permit

    applications. The refined capital and operating cost data has been incorporated in thefinancial projections used in the development funding and power purchase solicitations.

    In its Advisory Ruling for Russell Biomass, DOER found that the project meets the

    eligibility criteria for biomass-fueled new renewable generation units and thus would

    qualify under the RPS program.

  • 7/29/2019 Russell Biomass Final Report

    23/42

    ________________________________________________________________________________________________Russell Biomass Power PlantPre-Construction Development ActivitiesFinal ReportPage 23

    Section 4

    SITE ENGINEERING

    The 70-acre industrial zoned site in Russell is a superior one. It is located on the east side

    of town, across the Westfield River and is reasonably isolated from the main residential

    area. Site preparation work since purchase in 2000 has included contamination surveys,

    metals scrapping, building and gravel removal and extensive soil remediation activities

    conducted under the oversight of Tighe & Bond. Approximately 20 acres of level ground

    will be used for the power plant and related facilities.

    The site has deeded water rights to the Westfield River, which will be the source for

    cooling water for the biomass plant. And the existing utility easement will allow the

    completion of a new 5.2 mile transmission line interconnecting the project to the

    Northeast Utilities electric transmission grid.

    The original objectives of the Site Engineering task were for Tighe & Bond to complete a

    survey of the site and to prepare a preliminary site plan showing the arrangement of the

    power plant and fuel storage and handling system. The site plan is shown on page 17.

    Significant additional site engineering work was required for the Town of Russell Special

    Permit application, which was submitted in March 2005. The application, prepared by

    Tighe & Bond, included a site demolition plan, a grading and utility plan, drainage

    analysis and a stormwater management plan, and an erosion control plan.

    During the preparation of the Special Permit application, the developers realized the need

    to evaluate alternative means of delivering biomass fuel to the site. Main Street in

    Russell is the only current truck access to the site, and the biomass truck traffic will add

    significantly to traffic on Main Street; but this added traffic will still be similar in volume

    to the traffic on Main Street when the Westfield River Paper Company was operating

    prior to 1995. Tighe & Bond evaluated alternative access routes to the site from two

  • 7/29/2019 Russell Biomass Final Report

    24/42

    ________________________________________________________________________________________________Russell Biomass Power PlantPre-Construction Development ActivitiesFinal ReportPage 24

    locations along Route 20, both involving new road construction and one requiring a new

    bridge across the Westfield River. The river crossing alternative was found to be

    prohibitively costly. Further, communication with the Massachusetts Department of

    Environmental Protection wetlands section indicated that this alternative would be almost

    impossible to permit under the Wetlands Protection Act, primarily because the project

    already has a viable access to the site via Main Street. The second alternative access

    route was found to be infeasible due to landowner unwillingness at the time to sell the

    land required for the route.

  • 7/29/2019 Russell Biomass Final Report

    25/42

    ________________________________________________________________________________________________Russell Biomass Power PlantPre-Construction Development ActivitiesFinal ReportPage 25

    Section 5

    INITIATE PERMIT APPLICATIONS

    A biomass power plant is subject to federal, state and local permitting requirements. In

    2004 the developers engaged Tighe & Bond and Tech Environmental to identify the

    required permits and regulatory approvals and associated costs and timelines for the

    power plant. They performed preliminary air pollution modeling and conducted a fatal

    flaw analysis for early identification of critical permitting issues. The air pollution

    modeling indicated that the Russell plant will be in compliance with all applicable air

    quality standards. There are no technical or permitting fatal flaws for a plant size up to

    50 MW. The permits and approvals for the project are listed on the following page:

  • 7/29/2019 Russell Biomass Final Report

    26/42

    ________________________________________________________________________________________________Russell Biomass Power PlantPre-Construction Development ActivitiesFinal ReportPage 26

    Town of Russell Zoning Board of Appeals and Planning

    Board

    Special Permit

    Massachusetts Environmental Policy Act (MEPA),

    Massachusetts Executive Office of Environmental Affairs

    Environmental Notification Form

    and Environmental Impact Report

    Major Comprehensive Plan, MA Department of

    Environmental Protection (DEP)

    Air and noise permits

    Beneficial Use Determination (DEP) Approval to burn clean recycled

    wood and dispose of ash

    Water Management Act (DEP) Permit to withdraw water from

    Westfield River

    Surface Water Discharge (DEP) Permit to discharge to river

    NPDES Industrial Discharge (EPA) Permit to discharge to river

    NPDES Storm water Discharge (EPA) Permit for storm water runoff from

    site

    Wetlands/Riverfront Protection Act (DEP) Permit to modify existing water

    intake structure

    Spill Prevention (EPA) Fuel oil tank permit

    Massachusetts Historical Commission Historical/archaeological sitereview

    Industrial Holding Tank (DEP) Permit for blowdown tank

    Stack Registration (FAA) Stack approval

    Sewer Connection (Town of Russell) Plant sanitary sewer approval

    The developers decided that the primary objective of the Initiate Permit Applications task

    would be securing the Special Permit from the Town of Russell. It was consideredimportant to confirm and lock in the towns commitment to the project as soon as

    possible, before committing the significant funds and time required for the major

    environmental permits.

  • 7/29/2019 Russell Biomass Final Report

    27/42

    ________________________________________________________________________________________________Russell Biomass Power PlantPre-Construction Development ActivitiesFinal ReportPage 27

    While no other permit applications were planned for the first half of 2005, the developers

    intended to hold informal scoping meetings with DEP and MEPA, to provide information

    on the project and gain an understanding of the key permitting processes.

    RUSSELL SPECIAL PERMIT

    The Special Permit application was prepared by Tighe & Bond and submitted to the

    Russell Zoning Board of Appeals on March 1, 2005. A joint public hearing on the

    project before the Zoning Board and the Planning Board (for Site Plan Approval) was set

    for April 4. Town By-Laws required the boards to make a final determination on the

    project within 90 days of the first hearing, i.e., by July 1. Two additional hearings, on

    May 17 and June 28, were required to address the concerns of board members and the

    public.

    The major areas of concern were: fuel truck traffic on Main Street and at the plant site,

    air emissions, noise, visual impact of the stack, and hours of operation. At the conclusion

    of each of the first two hearings, the boards requested that Russell Biomass develop

    additional information, mostly related to these impacts, for submission to the boards prior

    to the following meeting.

    The greatest challenge to the project came during the final hearing from a well organized

    opposition group that objected to the planned use of clean recycled wood (CRW) from

    C&D sources. The objection centered on the adverse health effects associated with air

    emissions containing lead and other metals that may be present in small amounts in

    CRW. The opponents were supported by two New Hampshire residents, from Hinsdale

    and Hopkinton, where CRW use in power facilities is a current and hotly-contested issue,

    especially with the recently enacted New Hampshire one-year moratorium on the burning

    of wood from C&D sources. The opponents argued for a delay in the Special Permit

    process to allow further study of the C&D issue and other project impacts. (The

  • 7/29/2019 Russell Biomass Final Report

    28/42

    ________________________________________________________________________________________________Russell Biomass Power PlantPre-Construction Development ActivitiesFinal ReportPage 28

    developers would have to agree to a delay, as the statutory 90-day review period was at

    an end.)

    During the hearing the developers, having previously determined that the plant would be

    viable without CRW from the C&D waste stream, agreed not to use CRW until and

    unless the town specifically approved its use. The developers did not agree to a delay in

    the Special Permit process. Both boards then voted to approve the Special Permit at the

    conclusion of the hearing.

    CLEAN RECY CLED WOOD (CRW) FROM C&D SOURCES

    While Russell Biomass ultimately agreed to give up CRW as a fuel source, during the

    course of the project the developers were able to develop a better understanding of the

    permitting issues associated with the use of this material as a power plant fuel. The

    developers and engineering consultants met twice with DEP to discuss CRW issues, and

    Tech Environmental conducted a literature search and file reviews of air permits at the

    New Hampshire Department of Environmental Services and Maine Department of

    Environmental Protection, to document metals content in CRW and in the air emissions

    and ash resulting from CRW combustion.

    Nearly all of the lead and other metals in CRW wind up in the combustion ash; the small

    quantities of metals that go up the stack are expected to result in ambient concentrations

    that are within current environmental standards. Chlorine contained in CRW could

    necessitate the inclusion of a limestone injection system in the boiler to neutralize the

    HCl.

    Although to date no Massachusetts power plant has applied to DEP for approval to burn

    CRW, the principal regulatory control of CRW would be the Beneficial Use

    Determination (BUD) process of DEP. DEP would use the BUD process to approve

    individual CRW suppliers to the power plant and to regulate the disposal of ash from

  • 7/29/2019 Russell Biomass Final Report

    29/42

    ________________________________________________________________________________________________Russell Biomass Power PlantPre-Construction Development ActivitiesFinal ReportPage 29

    biomass combustion. Each CRW supplier, whether located in or out of state, must obtain

    a BUD in order to change the classification of its materials from solid waste to fuel.

    Likewise, Russell Biomass would need a BUD for ash disposal. DEP has established

    lead concentration limits for ash, the lowest of which allows land application.

    Increasingly costly disposal options for higher lead concentrations include: sanitary

    landfill cover, disposal in sanitary landfill and disposal as hazardous waste. It would be

    to the projects financial advantage for DEP to determine that the ash could be land

    applied, rather than requiring disposal as a hazardous waste.

    Russell Biomass would need to evaluate the metals content of CRW sources, and

    determine the CRW percentage in the fuel mix that would result in the optimum balance

    between CRW quality and cost and ash disposal cost. The developers have obtained

    information on metals content from some prospective CRW suppliers, but at this point no

    further analysis is planned in light of the developers agreement with the Town not to

    burn CRW.

    (See Section 11 for an update on the MEPA approval process.)

  • 7/29/2019 Russell Biomass Final Report

    30/42

    Section 6

    TRANSMISSION LINE DESIGN

    Northeast Utilities owns an easement that extends southeast from the power plant site to

    their 115 KV transmission line approximately five miles away. The figure below shows

    the easement and likely connection point to the transmission line. Following preliminary

    discussions with Northeast Utilities and ISO New England, the developers believe that

    they will be able to obtain an agreement to erect a transmission line connecting the power

    plant site with their transmission system. Northeast Utilities would eventually own the

    new transmission line, but Russell Biomass would be responsible for permitting, design

    and construction of the line.

    ________________________________________________________________________________________________Russell Biomass Power PlantPre-Construction Development ActivitiesFinal ReportPage 30

  • 7/29/2019 Russell Biomass Final Report

    31/42

    ________________________________________________________________________________________________Russell Biomass Power PlantPre-Construction Development ActivitiesFinal ReportPage 31

    The original objective of the Transmission Line Design task was to start the ISO New

    England Interconnection Process for Large Generators (greater than 5 MW). This

    process, which is designed to ensure compatibility between the new generating facility

    and the existing electric transmission system, would result in an Interconnection

    Agreement among Russell Biomass, ISO and Northeast Utilities.

    The 15-month ISO process, which is initiated by submitting an Interconnection Request

    for A Large Generating Facility, consists of 3 major steps: Feasibility Study, System

    Impact Study and Facility Study. The developers had planned to submit the

    Interconnection Request and start the Feasibility Study. However, it was not until late in

    the project that sufficient data was available to complete the Request, and a draft

    Interconnection Request was submitted for ISO review in early July.

    During the project the developers learned that two additional approvalsmightbe required

    for the transmission line: Massachusetts Energy Facilities Siting Board (EFSB) and

    Department of Telecommunications and Energy (DTE). Each approval involves a costly

    and lengthy adjudicatory process. Each would take approximately 12 months and could

    not be started before the completion of the ISO Feasibility Study and some additional

    transmission line design work. The ISO process was already on the project critical path;if EFSB and/or DTE approval were required as well, 3-6 months would be added to the

    project timeline. In light of the possibility that EFSB and DTE mightnothave

    jurisdiction over the Russell Biomass transmission line, the developers devoted

    considerable time and effort to making this case and attempting to gain concurrence from

    the agencies.

    EFSB has jurisdiction over transmission facilities as follows:

    A new transmission line of 69 KV or more and a length of more than 1 mileon a new transmission corridor

  • 7/29/2019 Russell Biomass Final Report

    32/42

    ________________________________________________________________________________________________Russell Biomass Power PlantPre-Construction Development ActivitiesFinal ReportPage 32

    A new transmission line of 115 KV or more which is 10 miles or more inlength on an existing transmission corridor

    Northeast Utilities had a transmission line in the proposed Russell Biomass corridor until

    the early 1980s, when the line was decommissioned and ultimately removed. So the

    developers made the case to EFSB that the corridor is existing and EFSB would not

    have jurisdiction since the line is less than 10 miles in length. Unfortunately, because the

    corridor has been inactive for more than 20 years, few indications of the previous use

    remain, and after observing the route EFSB determined the corridor to be new, not

    existing. While it would be desirable for the new line to be 115 KV, the project is

    considering a voltage less than 69 KV in order to avoid EFSB jurisdiction.

    If EFSB has jurisdiction, a likely simultaneous DTE review is not expected to have a

    significant additional impact on the project. The DTE approval process is similar to

    EFSBs and could be accomplished at little additional time and cost (beyond the time and

    cost for EFSB approval).

    (See Section 10 for an update on transmission line activities.)

  • 7/29/2019 Russell Biomass Final Report

    33/42

    ________________________________________________________________________________________________Russell Biomass Power PlantPre-Construction Development ActivitiesFinal ReportPage 33

    Section 7

    FUEL SUPPLY COMMITMENTS

    Within a 100-mile radius of Russell there is a supply of approximately 9 times the

    roughly 500,000 tons of biomass fuel that will be consumed annually. Fuel will include

    whole tree chips from land clearing, road side tree trimming and power line maintenance,

    and ground stumps and pallets. The western Massachusetts site location is close to the

    Springfield metropolitan area, Hartford and other metropolitan areas in Connecticut, the

    New York City metropolitan area, and the Albany/Schenectady area, where significant

    volumes of biomass waste are generated and subject to high disposal costs.

    North Country Procurement (NCP) of New Hampshire has committed to supplying the

    entire fuel volume to the Russell plant. NCP, incorporated in 1986, procures wood fuel

    for six wood fired generating stations in New Hampshire, Vermont, and Massachusetts

    with a combined annual consumption of approximately 1,200,000 tons.

    As a first step in executing its commitment, NCP obtained letters of interest from 35

    potential New England and New York fuel suppliers for more than 900,000 TPY starting

    in 2009. This represents 1.8 x the plants fuel requirement. (See the table on the followingpage.) The project has not assumed any Clean Recycled Wood or paper cubes in its fuel

    mix.

  • 7/29/2019 Russell Biomass Final Report

    34/42

    MA CT NY NH Total

    1 Whole tree chips 165,790 242,166 59,250 - 467,206

    2 Municipal Wood 33,500 65,360 12,500 - 111,360

    3 Stump Grindings 88,500 123,200 16,000 - 227,700

    4 Pallet wood 23,500 43,800 8,000 20,000 95,300

    5 Other 2,000 12,000 1,000 - 15,000

    Total LOI's to date 313,290 486,526 96,750 20,000 916,566

    Requirement 500,000

    Coverage 1.8 x

    Tonnage of Fuel Represented by Letters of Interest

    by Type of Fuel and by State

    ________________________________________________________________________________________________Russell Biomass Power PlantPre-Construction Development ActivitiesFinal ReportPage 34

  • 7/29/2019 Russell Biomass Final Report

    35/42

    ________________________________________________________________________________________________Russell Biomass Power PlantPre-Construction Development ActivitiesFinal ReportPage 35

    Section 8

    POWER SALE OPTIONS

    The Project expects to sign a power purchase agreement for the balance of the power

    plant output with a power marketer, or directly with large purchasers. The timing and

    conditions for moving ahead with soliciting power purchase agreements are positive

    because of load growth, the maturing of existing contracts that have gone to term, lost

    contracts due to bankruptcies of merchant development companies, the prospect for

    continuing high oil and natural gas prices, and the elimination of excess capacity in

    NEPOOL.

    Following discussions with a number of potential customers, Russell Biomass and its

    consultants Energy Management Group and Financial Management Group developed a

    power purchase solicitation package that included a detailed description of the project

    and proposed power pricing and other terms and conditions. The package was submitted

    to prospective power purchasers on July 15. Purchasers were asked to send a non-

    binding indication of interest (for capacity and term of contract) by July 29 and a non-

    binding commitment to the proposed terms and conditions by September 15. The initial

    indications of interest are promising potential demand from responding customersexceeds the 50 MW capacity of the Russell plant.

    (See Section 13 for an update on the status of power purchase agreements.)

  • 7/29/2019 Russell Biomass Final Report

    36/42

    ________________________________________________________________________________________________Russell Biomass Power PlantPre-Construction Development ActivitiesFinal ReportPage 36

    Section 9

    PROJ ECT FINANCIAL VIABIL ITY AND

    DEVELOPMENT FINANCING

    The objectives of this task were to update the project financial model, incorporate the

    resultant financial projections in a development financing solicitation memorandum, and

    approach investors to secure a commitment to fund the remainder of project development

    up to the start of construction.

    Financial Management Group created a sophisticated financial model for the project and

    incorporated the latest cost and revenue assumptions coming out of the other project

    tasks. The developers established a financial structure for the project following

    discussions with prospective debt and equity investors. The projected return on equity

    appeared likely to attract equity investors to the project.

    The financing requirement for the developers was to raise the several million dollars

    necessary to complete development prior to construction. Most equity investors are not

    interested in the higher risk (and higher return) development funding, so the challenge

    was identifying prospective development funders. Financial Management Groupprepared a development financing solicitation memorandum, which was distributed to a

    number of investors. Russell Biomass met with six potential development funders in

    June, and discussions are continuing with three of those. The developers are optimistic

    about obtaining the funding necessary to complete development.

    (The developers were eventually successful in obtaining additional development

    funding.)

  • 7/29/2019 Russell Biomass Final Report

    37/42

    ________________________________________________________________________________________________Russell Biomass Power PlantPre-Construction Development ActivitiesFinal ReportPage 37

    Section 10

    INTERCONNECTION STUDY

    The project submitted the Interconnection Request for a Large Generating Facility to ISO

    New England in August 2005. The request contained a description of the proposed

    transmission line route, the point of interconnection with the Northeast Utilities system in

    Westfield and technical information on the generating facility. In September ISO New

    England held a Scoping Meeting on the project to review the ISO interconnection

    process, resolve issues related to the Interconnection Request and discuss the scope of the

    Feasibility Study, the first step in the process. Participants included representatives of the

    project, ISO and Northeast Utilities. One important item of discussion was the voltage of

    the new transmission line. Northeast Utilities expressed a strong preference for 115 KV.

    While the project was considering a lower voltage (see Section 6), the developers

    eventually agreed to the 115 KV configuration.

    In October the project submitted the scoping parameters for the Feasibility Study, and the

    Feasibility Study Agreement was executed by ISO New England, the project and

    Northeast Utilities in November. According to the agreement the study would provide

    the following:

    Preliminary identification of any circuit breaker or other facility short circuitcapability limits exceeded as a result of the interconnection

    Preliminary identification of any thermal overload or voltage limit violationsresulting from the interconnection

    Preliminary review of grounding requirements and electric system protection Preliminary description and estimated cost of facilities required to

    interconnect the proposed facility to the transmission system

  • 7/29/2019 Russell Biomass Final Report

    38/42

    ________________________________________________________________________________________________Russell Biomass Power PlantPre-Construction Development ActivitiesFinal ReportPage 38

    ISO engaged a consultant to conduct a load flow analysis and identify thermal overload

    and voltage issues. Northeast Utilities was responsible for the short circuit and facility

    cost analyses.

    The consultant had completed much of the load flow analysis by the end of the MTC-

    funded project. In a progress review on January 16, the consultant reported the

    preliminary finding of the study: under certain outage conditions the project appears to

    worsen the overload on two existing transmission lines. However, the overload appeared

    to be relatively insignificant, with minimal upgrade cost implications for the project.

  • 7/29/2019 Russell Biomass Final Report

    39/42

    ________________________________________________________________________________________________Russell Biomass Power PlantPre-Construction Development ActivitiesFinal ReportPage 39

    Section 11

    DRAFT ENVIRONMENTAL IMPACT REPORT

    In September 2005 the project submitted an Expanded Environmental Notification Form

    (EENF) to the Massachusetts Secretary of Environmental Affairs. The EENF is the first

    step in the Massachusetts Environmental Policy Act (MEPA) approval process, one of

    the key approvals required for the project.

    On October 31, 2005 the Secretary of Environmental Affairs issued a Certificate on the

    EENF, which prescribed the content of the Draft Environmental Impact Report (DEIR)

    for the project see the following list of sections for the DEIR:

    Project Description and Permitting Alternatives Land Alteration & Stormwater Rare Species Wetlands Waterways Westfield River Impacts Energy/Air Solid and Hazardous Waste Historic Resources Construction Period Impacts Mitigation Response to Comments

    Russell Biomass and its consultant Tighe & Bond commenced work on the DEIR in

    December 2005 and expect to complete the document in August 2006. Following is a

    summary of work on the DEIR during December and January.

  • 7/29/2019 Russell Biomass Final Report

    40/42

    ________________________________________________________________________________________________Russell Biomass Power PlantPre-Construction Development ActivitiesFinal ReportPage 40

    This early DEIR activity focused on two important issues raised in the Certificate:

    potential impacts on state-listed rare species and water withdrawal and discharge impacts

    on the Westfield River. Following is a summary of progress through January.

    Rare Species Impacts

    The Certificate stated that the Massachusetts Natural Heritage and Endangered Species

    Program (NHESP) had indicated that the project has the potential to result in a take of

    state-listed rare species in the vicinity of Mount Tekoa, as a result of the proposed

    clearing for the transmission line in this area. In December project representatives met

    with NHESP to discuss rare species concerns. Russell Biomass and Northeast Utilities

    met in January to begin a discussion of transmission line routing alternatives that would

    address the NHESP concerns.

    Water Withdrawal and Discharge Impacts on the Westfield River

    Tighe & Bond evaluated the water withdrawal and discharge impacts of the power plant

    on the Westfield River. Peak withdrawal will be 885,000 gallons per day, which

    represents 0.2% of the average annual river flow, 1.3% of the average August flow, andapproximately 4% of the 7Q10 flow (the average flow over the lowest 7-day period in the

    previous 10 years). Water discharge is estimated to cause a river temperature increase of

    less than 1 degree F.

    Russell Biomass and Tighe & Bond met with representatives of the Massachusetts

    Department of Environmental Protection (DEP) and Department of Fisheries and

    Wildlife in December to present reports on project impacts on the river and aquatic life.

    The agency representatives acknowledged that the anticipated withdrawal and discharge

    impacts appear to be relatively minor.

  • 7/29/2019 Russell Biomass Final Report

    41/42

    ________________________________________________________________________________________________Russell Biomass Power PlantPre-Construction Development ActivitiesFinal ReportPage 41

    Section 12

    AIR DISPERSION MODELING

    The project submitted the Major Comprehensive Plan Approval Application, dealing with

    air emissions and noise impacts, to DEP in September 2005. The application included a

    report on air quality dispersion modeling by Tech Environmental, a consultant to the

    project. This report, based on conservative screening dispersion modeling, demonstrated

    that the project will not have an adverse effect on air quality.

    The MTC-funded work involved subsequently performingrefineddispersion modeling to

    more precisely quantify the air quality effects of the project. The following is taken from

    the Executive Summary of Tech Environmentals report: The refined air quality

    dispersion modeling further demonstrates that the maximum air concentrations from the

    Project will safely comply with the NAAQS [National Ambient Air Quality Standards]

    for criteria pollutants and with the Massachusetts TELs [Threshold Effects Exposure

    Limits] and AALs [Allowable Ambient Limits] for non-criteria pollutants.

  • 7/29/2019 Russell Biomass Final Report

    42/42