rvm1 hydro electric power (pty) ltd appellant chief ... 1 hydro electric power... · 3.5. solar pv...
TRANSCRIPT
Page 1 of 80
“ANNEXURE A”
RVM1 HYDRO ELECTRIC POWER (PTY) LTD Appellant
CHIEF DIRECTOR: INTEGRATED ENVIRONMENTAL
AUTHORISATIONS, DEPARTMENT OF
ENVIRONMENTAL AFFAIRS Respondent
APPEAL PURSUANT TO SECTION 43(1) OF THE NATIONAL ENVIRONMENTAL MANAGEMENT ACT 107 OF 1998 AGAINST THE REFUSAL TO GRANT ENVIRONMENTAL AUTHORISATION TO RVM1 HYDRO ELECTRIC POWER (PTY) LTD ON 19 OCTOBER 2016
1. INTRODUCTION
1.1. This is an appeal to the Minister of Environmental Affairs, directed at
the Director: Appeals and Legal Review of the Department of
Environmental Affairs, against the decision of the Chief Director:
Integrated Environmental Authorisations of the Department of
Environmental Affairs (“DEA”) to refuse to grant an environmental
authorisation to RVM1 Hydro Electric Power (Pty) Ltd for the
establishment of a 40 megawatt (MW) Hydro power station and
associated infrastructure on the Farm Riemvasmaak, the Remainder
of Farm No. 497 and Portion 1 of Farm No. 498, on the Orange River
in the vicinity of the Augrabies Falls National Park, Kai !Garib Local
Municipality, in the Northern Cape Province, under register number
14/12/16/3/3/2/600 (“the Refusal Decision”).
Page 2 of 80
1.2. This appeal is lodged in terms of section 43(1) of the National
Environmental Management Act, 1998 (NEMA),
2. PARTIES
2.1. The appeal is submitted by RVM1 Hydro Electric Power (Pty) Ltd (“the
Appellant”).
2.2. The respondent is the Chief Director: Integrated Environmental
Authorisations (“the Respondent”), cited herein in his official capacity
as the person who signed the Refusal Decision on 19 October 2016.
3. BACKGROUND
The Project
3.1. Significant expansion of the South African economy during the past
few decades resulted in consequent and (substantial) increased growth
in electricity demand without the necessary growth in the supply side.
Currently, the majority of electricity in South Africa is generated from
burning fossil fuel (there is one nuclear power plant in the Eskom
fleet), the South African Government has determined to source energy
from the broadest spectrum of proven renewable technologies. The
driver of the need for diversification in the energy mix is the
Department of Energy (DoE) being the policy department within
Government for energy. The South African Integrated Resource Plan
(IRP), promulgated in May 2010 by the DoE, calls for an 18GW
renewable energy programme over the next 20 years.
3.2. The Renewable Energy Independent Power Producer Procurement
(REIPPP) Programme, established to achieve the above mandate, has
been an effective vehicle for South Africa to not only expand the
Page 3 of 80
country’s generation capacity and socio-economic growth, but also to
do it in such a way that environmental harm is minimized and to
provide tangible benefits to communities in the vicinity of the projects
through the requirement to return a percentage of the net profit before
tax to Corporate Social Responsibility Projects. The main focus of
technologies in the REIPPP Programme is Wind Power, Solar
Photovoltaic (PV), Concentrated Solar Power (CSP) and Hydro Electric
Power.
3.3. If one examines Figure 1 (below), it can be seen that Hydro Power has
yet to be utilized effectively.
Figure 1: REIPPPP Capacity Installations (Bid Windows 1-4)(
http://www.ipp-projects.co.za/PressCentre)
3.4. Wind Power would not be a viable renewable energy resource at this
location as there is simply not enough wind for sufficient generation.
Utility scale wind turbines require wind speeds of around 25-30km/h
to achieve their full rated capacity. As one can see in Figure 2, there is
not enough wind of this magnitude to produce any significant energy.
Page 4 of 80
Figure 1: Kakamas Average Wind Speed.
(https://www.meteoblue.com/en/weather/forecast/modelclimate/kakam
as_south-africa_993014)
3.5. Solar PV would also not be a viable option as it is simply too hot in
this region. At temperatures significantly above 25ºC the photovoltaic
cells experience a decrease in (already low) efficiency.
3.6. At 45°C, the efficiencies of the panels will decrease by approximately
20%. The inverters, transformers, battery banks (if any) and the cells
themselves suffer greatly in temperatures of this magnitude. This
region has been known to reach 50°C, which would more than likely,
cause irreversible damage to the solar cells and/or other equipment.
Optimal PV conditions would be found at approximately 25°C.
3.7. See the Figure below for average temperatures of the nearby town,
Kakamas:
Page 5 of 80
Figure 3: Kakamas Average Temperatures and Precipitation.(
https://www.meteoblue.com/en/weather/forecast/modelclimate/kakam
as_south-africa_993014)
3.8. Concentrated solar power is the only other viable renewable energy
source available, but has its disadvantages as it is mainly an
intermittent power source, expensive, involves a complex operation,
needs intensive maintenance, requires a very large utilization of space
and has a large visual impact.
3.9. All Energy sources have some impact on our environment. Given South
Africa’s current environmental condition, it is very important to try and
limit these impacts and select the energy sources that have the least
environmental impacts. The only way this objective will be achieved is
to support renewable energy sources, which provide energy at the
lowest cost to the environment.
3.10. Hydro Electricity is one of the cleanest energy resources on the planet
and is almost twice as efficient as any other renewable energy
technology (+90%).
3.11. Hydroelectric power is by far the most viable option for a renewable
Page 6 of 80
energy source in this location. The Orange River in this location
provides sufficient water and the best elevation differential, in South
Africa, for significant hydroelectric power generation.
3.12. Hydroelectric power plants provide baseload energy, whereas no other
renewable source in the REIPPP Programme can. South Africa currently
relies on its baseload energy to be supplied almost exclusively from
coal-fired power plants, which are massively carbon intensive. One of
the only disadvantages of hydropower involving impoundment is that
river flow is interrupted/altered. This can shift the equilibrium of the
downstream ecosystem. In Run-of-River (ROR) hydroelectric power this
disadvantage is erased as ROR Plants do not consume or store any
water. The difference between a dam and ROR is extensively dealt with
in section 11 of the EIAr. Furthermore the design of the RVM
hydropower project has ensured that a minimum of 30 cubic metres of
water per second are to flow along the natural course of the Orange
River and over the Augrabies Falls, before any diversion for power
generation is commenced. The reason why the 30 cubic metres has
been selected is because that is the figure agreed to by DWS. Attached
marked “RVM1” is a copy of the minutes held between Appellant and
DWS in this regard. It consists of a covering mail in which the DWS
gives permission for the distribution of the minutes of the meeting of
the 8th of August 2013, in which the 30m/sec issue is confirmed. This
then leads into permission by the DWS to submit the Water Use License
Application (which is found at
https://www.dropbox.com/sh/f6zx8il1rpr7p4g/AADQXcEa7o-
POqQKTXv9HOoJa?dl=0. The submission of the WULA is the precursor
to the receipt of the unbinding DWS letter which is also attached
marked “RVM2”.
Page 7 of 80
3.13. Flowing from the above, an application for environmental
authorisation was made, and authorisation subsequently refused for
the construction of a 40MW Hydro power station and associated
infrastructure, the (“the project”).
3.14. The site of the project (“the project site”) is situated partially in the
Augrabies Falls National Park and in the main on land outside the
Park on land owned by the Riemvasmaak community.
3.15. The project does not involve the extractive use of natural resources,
does not consume water and does not involve the construction of a
dam.
4. THE ENVIRONMENTAL IMPACT ASSESSMENT PROCESS
4.1. The Competent Authority confirmed by letter dated 21 September
2016 that the Final Environmental Impact Report (“Amended FEIR”),
as amended, was acceptable in terms of Regulation 34(2)(a).
4.2. The FEIR was amended following the rejection of the EIA Report lodged
on 29 September 2015.
4.3. The Competent Authority issued the Refusal Decision on 19 October
2016.
5. ADMINISTRATIVE ACTION
5.1. The activities that form part of the project will have impacts which are
regulated by specific legislation in addition to NEMA.
5.2. In addition to the environmental authorisation addressed herein, the
Appellant will be required to obtain a water use licence (WUL) in terms
of the National Water Act, 1998 (NWA) in order to undertake some of
Page 8 of 80
the activities envisaged as part of the project.
5.3. There are therefore two main regulators, the departments of
Environmental Affairs and Water and Sanitation, which will have
oversight over the project.
6. THE NATURE AND SCOPE OF THE APPEAL
6.1. The administrative remedy provided for in section 43, read with the
relevant regulations in the NEMA, constitute an administrative appeal.
The nature of the appeal in terms of section 43 is a “wide-appeal” as
opposed to an “ordinary appeal”.(Baxter L:Administrative Law -1984
Juta & Co, p256/Tikly v Johannes NO 1963 (2) SA 588 (t) at 590F-
591(A))
6.2. A wide appeal allows the Minister a “…complete re-hearing of, and
fresh determination on the merits of the matter with or without
additional evidence or information”. An ordinary appeal on the other
hand is a “re-hearing on the merits but limited to the evidence or
information on which the decision under appeal was given, and in
which the only determination is whether that decision is right or
wrong”.
6.3. Section 43(6) authorises the Minister to “confirm, set aside or vary the
decision” and also to “make any other appropriate decision”. This
endorses the view that this is a wide appeal affording the Minister a
wide discretion.
6.4. Regulation 61(2)(b) of the EIA Regulations determines that an appeal
must be accompanied by, inter alia, supporting documentation which
is referred to in the appeal and which is not in possession of the
Page 9 of 80
Minister. This confirms that the Minister is not limited to the
documentation on which the Refusal Decision was based, and can
consider additional information not previously considered.
6.5. The Appellant submits this appeal relying on its statutory right to have
the Minister reconsider the Refusal Decision and to make a fresh
determination on the merits having regard to all relevant information
presented as part of this Appeal and the documentation attached
hereto.
7. INTENTION TO APPEAL
7.1. Regulation 60(1) of the EIA Regulations, 2010 states that a notice of
intention to appeal must be submitted to the Minister within 20 days
after the date of the decision.
7.2. Regulation 60(2) of the EIA Regulations, 2010 provides that the
appellant must give notice of its intention to appeal by providing a
copy of its notice of intention to appeal to each person and organ of
state which was registered as an interested and affected party (I&AP)
within 10 days of dispatching this notice to the Minister as
contemplated in regulation 60(1), and indicating where and for what
period the appeal submission will be available for inspection.
7.3. On 4 November 2016, a notice of intention to appeal (“the notice”),
addressed to the Department of Environmental Affairs (“DEA”) was
submitted, by email to Mr Z Hassam, Director: Appeals and Legal
Review of DEA.
7.4. On 4 November 2016, Ms Marcia Davids of the DEA confirmed receipt
of the notice and advised that the appeal submissions were due on 7
December 2015, subsequently clarified to mean 7 December 2016.
Page 10 of 80
8. CONDONATION
8.1. On 1 December the EIA Process Facilitator caused a notice to be sent
to each person and organ of state which was registered as an I&AP as
required by the regulations. That notice is attached hereto marked
“RVM3”.
8.2. Unfortunately and owing to a genuine honest oversight in the office of
the EAP this notice was not despatched to the I&APs strictly according
to the timeframe set out in the Regulations and was in fact issued 17
days late. As soon as the delay was discovered the EAP wrote to Ms
MN Davids of the Directorate: Appeals and Legal Review, copied to the
Control Environmental Officer, Integrated Environmental
Authorisations (Ref: Mr. D Smit) and the Case Officer (Mr. V Chauke)
to admit to the error. That communication is attached marked
“RVM4”.
8.3. It is Appellant’s humble submission that this delay can cause the
I&APs no prejudice because the said notice was received by them
before the substance of the appeal, namely this document, and
because of the dies non over the December period. In this instance
Regulation 1(3) of the 2010 EIA Regulations excludes the reckoning of
days from the period of 15 December to 2 January so the I&APs
actually have extra time to deal with the substance of the appeal.
8.4. Appellant respectfully seeks and request that this administrative
oversight be condoned for the reasons set out above and because it
has caused no prejudice, was not deliberate, was not done on
Appellant’s instruction, was a genuine honest administrative oversight
and can have no effect on the time available for the I&APs to consider
and answer the appeal properly.
Page 11 of 80
The structure of this appeal is as follows: the Reasons for the Refusal
Decision are considered, the Findings are then responded to and finally the
Grounds of Appeal are addressed. There are various recurring themes in the
Findings which are repeated under different headings which range from
canal construction to water resources. For purposes of responding to the
Findings the themes are grouped together where practical or dealt with
separately.
9. THE REFUSAL DECISION
9.1. Annexure 1: Reasons for Decision.
Page 11 Item 1. Information Considered in making the Decision
9.2. The Competent Authority’s letter dated 9th November (actually
December) 2015 rejecting the EIA Report requested additional
information, in paragraphs a) to h), in order to enable the Competent
Authority to make a decision on the application. The request also
included a reminder to ensure that all information requested in the
earlier acceptance of the Scoping Report was forthcoming.
9.3. All of this information was provided in the Addendum Report. In the
few places where it was necessary the EIAR and EMPr were also
amended.
9.4. It is not clear from the Reasons for Decision whether the Competent
Authority included the Addendum under the heading of the Amended
EIAR, but given the detail provided of the other documents considered
this seems unlikely. There is thus no indication that the information
contained in the Addendum was considered by the Competent
Authority and consequently for that reason alone the Refusal Decision
should be set aside.
Page 12 of 80
9.5. The Competent Authority in reaching its decision did not list the
comments of any I&APs as being “Information considered in making
the decision” (Annexure 1: Reasons for Decision, page 11 Item 1 b))
but then says that a “Key factor” was the “concerns raised by” I&APs
(Annexure 1: Reasons For Decision, page 12 Item 2 c)). This points to
bias as the Competent Authority chose deliberately not to consider any
I&APs who may have supported the project preferring to only consider
those who expressed “concerns”. To ignore the interests of the
Riemvasmaak Community alone is a fundamental flaw in the
Competent Authority’s process to evaluate the application in light of
its statutory obligation to give equal weighting to the “social, economic
and environmental impacts of activities” as required in Section 2(4)(i)
of NEMA. The Competent Authority thus failed a mandatory procedure
prescribed by the empowering statute.
9.6. The Competent Authority discloses that it also considered the
objectives and requirements of relevant legislation and guidelines. The
Appellant will show that this disclosure is either incorrect or the
Competent Authority ignored certain pertinent information.
9.7. Annexure 1: Reasons for Decision
Page 12 Item 2. Key Factors in making the Decision
9.8. The Refusal Decision acknowledges that the “findings of all the
specialist studies conducted and their recommended mitigation
measures” were considered a most significant key factor considered.
(Annexure 1: Reasons For Decision, page 12 Item 2 a)). Inconceivably
not one specialist finding or mitigation measure has been explicitly
referred to in the Refusal Decision. Clearly the Competent Authority
decided that the specialists have failed to identify the relevant impacts,
Page 13 of 80
have underestimated their significance, or misstated the Appellants
ability to mitigate them. That said, no evidence of any significance is
presented to dispute or refute the specialists’ findings and so the
Refusal Decision is not rationally connected to the information
presented in the FEIR.
9.9. Despite considering information from the Department of Water and
Sanitation, which found that there was sufficient water in the Orange
River system for the project, the Competent Authority did not consider
the views of the department mandated to manage water resources as
being a key factor. It elected to make findings based on considerations
beyond its statutory mandate since the Competent Authority is not
empowered to deal with water use.
9.10. It is the Appellants submission that the Competent Authority erred in
only looking at the “physical, biological, social, economic and cultural
aspects of the environment” since that is not the measure required in
terms of Chapter 5 of NEMA. Furthermore Section 2(2) NEMA
stipulates that “environmental management must place people and
their needs at the forefront of its concern, and serve their physical,
psychological, developmental, cultural and social interest equitably”.
Rather the Competent Authority chose to concern itself predominantly
with the environment and did not give equal weighting to the “social,
economic and environmental impacts of activities” as required in
Section 2(4)(i) of NEMA. It was therefore not possible for the
Competent Authority to make an “appropriate” decision because a
material requirement for the proper evaluation of the application was
not complied with by the Competent Authority.
9.11. The fundamental flaw in the Competent Authorities decision as to
Page 14 of 80
what issues were of the most significance is the key factor of “the
cumulative impacts the proposed development will have within the
Orange River as an international river”. The cumulative impacts
should have been evaluated with reference to the entire Orange River
system, the region and the country as a whole and not just the river.
Section Regulation 31(20(I)(i) of the EIA regulations, 2010 requires an
evaluation of the cumulative impacts of the area, not just the river.
This constitutes a ground for appeal in its own right and is dealt with
in detail later under the appeal heading, Respondent Failed to take
into Account the Cumulative Impacts of the Project.
9.12. The Competent Authority did not rely on current legislation and
guidelines considered in the preparation of the Amended EIAr dated
June 2016 or the Addendum so the Competent Authority could not
properly have evaluated the information tabled in the Amended EIAr
dated June 2016. Instead it relied on legislation and guidelines
considered in the preparation of the EIAr dated September 2015
(Annexure 1: Reasons for Decision, page 12 Item 2 e)) and
consequently could not have applied its mind adequately, or at all,
relying on dated information in the circumstances.
9.13. The mention of alternatives in Item 2 f) (Annexure 1: Reasons for
Decision, page 12 Item 2 f)) in all likelihood refers to a previous multi-
station project, which was the subject of a Basic Assessment Report
and subsequently withdrawn by the Appellant. This is an illustration
of the issue raised in paragraph 8.12 above, namely reliance on dated
information. The original Basic Assessment addressed three possible
alternatives for 10MW stations, as 10MW was the maximum size DoE
would allow. Two sites were to be selected from the three. The
specialists were tasked with ranking the alternatives. When DoE
Page 15 of 80
raised the generation threshold to 40MW the project was rationalised
into a single enlarged station, based on the best alternative. There are
no fundamental alternatives (type of project, or locations and routes)
discussed in the EIAR documents.
9.14. In Annexure 1: Reasons for Decision, page 13 Item 2 Key Factor 2 I
the Competent Authority acknowledges that the specialists got the
methodology for determining the impacts right, but then got the
results so hopelessly wrong that it was necessary to refuse the
authorisation. It is entirely unreasonable to agree that the
methodology used in assessing potential impacts is correct but that all
the results are unacceptable as there is no other indication as to
which results were found wanting and no reasonable person could
have come to that conclusion.
10. Annexure 1: Reasons for Decision
Page 13 Item 3. The Findings
First we deal with procedural issues in the Findings and then move
onto the main themes. Thereafter we address certain specific findings.
10.1. Finding 3a) reads: “A sufficient public participation process was
undertaken and the applicant has satisfied the minimum
requirements as prescribed in the EIA Regulations, 2010 for public
involvement.”
10.2. This finding is incorrect. Appellant has never seen the comments of
the Department: Environment & Nature Conservation which is
registered as an I&AP and Regulation 56(1) (b) requires that those
comments ought to have been served on the EAP. Applicant has
therefore been denied the opportunity to answer these comments and
Page 16 of 80
accordingly the Refusal Decision is procedurally unfair. So, despite the
principle of audi altrem partem Appellant has never had sight of the
reasons advanced by Department: Environment & Nature
Conservation (Finding 3d)) or the SANParks letter as part of the EIA
process. It was private correspondence between Appellant and
SANParks in the context of Appellant seeking a meeting with
SANParks to further explain the project.
10.3. To the extent the SANParks letter (referred to in Finding 3 c) and 3 f))
was sent directly to DEA, it was only copied to two officials, and was
not served on the EAP as required in terms of Regulation 56(1) (b). The
letter was not written in response to the RVM Addendum Notification
letter to I&APs as that was only issued on 7 July 2016, after the
SANParks letter. This means SANParks prejudged the Addendum and
the Amended EIAr or didn’t read it as no comments were received.
The Competent Authority cannot therefore rely on unanswered
objections as that amounts to unfair administrative action and is
procedurally unfair. The SANParks letter contains a number of factual
inaccuracies (canal) generalised and un-attributed deductions
(concerning visitors experience and sense of place) and shows bias
against sustainable development by a rigid adherence to the AFNP
Management Plan and reliance on an incorrect interpretation of
section 42 of NEM:PAA. Its approach appears to be made on the basis
preserving the status quo at all costs, contrary to the vision and
mission of SANParks, or in terms of its statutory obligation in terms of
section 53 NEM:PAA specifically and its Constitutional duty to protect
the environment generally. This response is indicative of a “fortress”
conservation approach and indicates a bias towards retaining the
AFNP as an island. The approach is contradicted by the AFNP mission
Page 17 of 80
recorded in the AFNP Management Plan to be: “Augrabies Falls
National Park will manage [sic] and conserve the biodiversity, geology
and cultural heritage as part of the functional and sustainable
patchwork of different land uses within the Benede-Orange region,
through collaboration and education, to promote better livelihoods as
well as benefits and enjoyment to all”.
10.4. Appellant has also never seen the comments of the Department:
PAPLCM dated 22 August (Annexure 1: Reasons for Decision, page 14
Finding 3 f)) and was never given an opportunity to address any
objections. Department: PAPLCM is also registered as an I&AP so the
Competent Authority should have acted in terms of Regulation 56(1)
(b). Its failure to do so denied Appellant the right to answer the
comments and is administratively and procedurally unfair.
10.5. The same unfairness is true for the DEA:BC and its comments referred
to in Finding 3 g).
10.6. It is not clear in what capacity these Department: PAPLCM and DA:BC
offered comments but as registered I&APs the Competent Authority
was obliged by the empowering statute to comply with Regulation
56(1) (b).
10.7. It is not clear when any of Department: PAPLCM, DEA:BC or the
Department: Environment & Nature Conservation received
instructions from the Competent Authority to comment on the
Amended Final EIA Report as the dates are confusing. One of a
number of scenarios is possible. Either the three departments received
Regulation 56(7) requests at different times hence the response dates
of 22 August compared to 22 April or they all got similar requests. If so
the comments from Department: PAPLCM are out of time and it must
Page 18 of 80
be regarded in terms of Regulation 56(9)(b) as having no comments.
Another scenario is that both DEA:BC or the Department:
Environment & Nature Conservation issued their comments before the
RVM Addendum Notification letter to I&APs as that was only issued on
7 July 2016.
10.8. The timing is uncertain but should the Competent Authority have
accepted comments outside of the time limit it cannot rely on them
without giving the Appellant an opportunity to be heard, first about
any condonation, and secondly about the comments themselves.
10.9. The process by which the Competent Authority receives comments and
does not share those comments with the Appellant is unfair
administrative action and denies Appellant an opportunity to be
heard. As can be seen from this appeal many of the inaccuracies and
the reliance on incorrect facts could have been corrected and another
decision arrived at.
11. Finding 3b) determines: “The procedures followed for impact
assessment is deemed adequate for the decision-making process.”
11.1. This finding contradicts any reliance on the development being
inconsistent with section 50(5) of NEM:PAA and Finding 3f). The EIAr
was initially rejected, inter alia, because it did not have SANParks
section 50(5) approval so on that version the Competent Authority
ought not to have accepted the report later in terms of Regulation
34(2)(a) but still without such section 50(5) approval. In the interim
the Competent Authority had issued a clarification to the effect that no
such prior approval was required only to retract that interpretation
later. The exchange of emails is attached marked “RVM5”. The
Regulation 34(2)(a) acceptance without section 50(5) approval is, it is
Page 19 of 80
submitted, the correct approach. It is manifestly unfair to refuse an
EIA for lack of section 50(5) compliance, then to grant the Appellant
an audience to discuss the issue, then invite the Appellant to submit
legal argument concerning the issue which the Appellant does in the
form of an attorney’s opinion fortified by an opinion from a Senior
Counsel, to then accept the EIAr as amended, without section 50(5)
approval, but then use the fact that there is no section 50(5) prior
approval from SANParks as a reason to support the Refusal Decision.
This is precisely what the Competent Authority has done which is
procedurally unfair and has resulted in a decision materially
influenced by an error in law.
11.2. The plain meaning of section 50(5) in any event says no development
can take place in a national park “prior” to written approval from the
management authority. It does not say approval is required prior to
the granting of an environmental authorisation. This is logical since
not all developments inside national parks require environmental
authorisation.
11.3. The section 50(3) issue has no place in the EIA process and even less
in a proper and fair evaluation of an application for an environmental
authorisation.
12. The proposed construction of a weir, canal and a portion of the power
line
12.1. A canal is mentioned in Finding 3 c), 3 f)i), 3 f)iii), 3 g)ii), and 3 i).
12.2. The Applicant applied for environmental authorisation in respect of
Activity R.544 Activity. Page 3 of the Refusal Decision expressly
records that “the proposed project requires water conveyance
Page 20 of 80
infrastructure which will comprise an underground conduit to convey
water from the diversion weir to the headpond…”.
12.3. SANParks (Finding 3 c)) DEA:PAPLCM (Finding 3 f)), and DEA:BC
(Finding 3 g)) object to the construction of a canal, not an
underground conduit. The objections lack credibility and indicate a
complete misunderstanding of the proposed development and the
nature of the activity actually applied for. There is no canal. There is
no subdivision of the Park into semi-isolated remnants. "Canal" means
an open structure that is lined or reinforced, for the conveying of a
liquid or that serves as an artificial watercourse. An underground
conduit is not a canal. This position of SANParks in respect of its
objection to the construction of a canal is even more confusing given,
for example, the public article it contributed to in August 2015 which
specifically mentions an “underground culvert” attached marked
“RVM6”.
12.4. The Competent Authority relies on this factual error and makes the
finding at Finding 3 i) based on the objections to the development of a
canal. The finding of the Competent Authority is therefore based on an
error of fact and cannot hold true.
12.5. SANParks compounds its misunderstanding of the proposed
development by objecting to a “portion of the power line” being inside
the Park. There is no power line inside the Park. A subterranean
evacuation powerline is contemplated as opposed to the overland
power lines crossing the Kruger National Park from Cahora Bassa as
depicted in the photograph attached “RVM7”. It is unreasonable for
the Competent Authority to rely on an error of fact to support the
Refusal Decision.
Page 21 of 80
13. The area of the park through which the canal is planned is currently
zoned remote and falls in a special management category
13.1. SANParks (Finding 3 c)i)) and the Competent Authority (Finding 3 h))
relies on zonation as a reason against the proposed development. They
impermissibly elevate zonation to some form of unalterable restriction
in title. It is not, it is a guide to management, set out in a
management plan that is entirely alterable.
13.2. The proposed development is not an activity one would typically find in
a management plan as it is not a park specific or park centric activity.
The AFNP Management Plan has the following to say about zonation:
“The zoning of AFNP was based on an analysis and mapping of the
sensitivity and value of a park’s [sic] biophysical, heritage and scenic
resources; an assessment of the regional context; and an assessment
of the park’s current and planned infrastructure and tourist routes
/products; all interpreted in the context of park objectives”. It deals
exclusively with the park’s current and planned infrastructure.
13.3. In any event management plans do not specify services infrastructure
in the park or any future services infrastructure required by, for
example, Eskom. Under the heading Access and Facilities: Section 7
AFNP Management Plan says the following at page 18:
“7.8 Servitudes
There are servitudes registered against title deed [sic] for secondery
[sic] roads and Escom [sic] transition [sic] lines traversing the park.
The park has initiated a process to deregister the servitudes
applicable to the secondery [sic] roads.”
Page 22 of 80
13.4. This is no different to the Management Plan for the West Coast
National Park (WCNP) which is traversed in part by a subterranean oil
pipeline, In respect of the WCNP the subterranean oil pipeline
traverses areas zoned “Remote”. That has not caused the management
plan to become invalid or require changes. That plan says at page 25
item
“7.10 Servitudes
The only servitudes registered on title deeds are on eight properties
included in the park for a buried crude oil pipeline running from
Saldanha Bay to the refinery in Cape Town.”
13.5. Clearly the buried crude oil pipeline in the WCNP has nothing to do
with the park or its management. SANParks has nothing to do with its
management until there is an oil spill in the park.
13.6. That zonation can be amended is clear from section 40 (2) of NEM:PAA
which allows a management authority to amend such a plan by
agreement with the Minister. This principle was aptly demonstrated
when it suited SANParks to amend the KNP Management plan to
accommodate the proposed Malelane Hotel development. The draft
scoping report records at page 93 which is attached marked “RVM8”:
“The preferred site is located in the Peripheral Development Zone of
the Park. This zonation was provided to V&L in December 2011 to
be utilized as the latest zonation plan for the Kruger National Park.
According to the Zoning included in the current Management Plan
for the Kruger National Park, the site was initially zoned primitive in
the beginning stages of the EIA process for the proposed safari
resort. SANParks have however informed V&L that the PDZ zone
Page 23 of 80
should now be utilised as this is the latest proposed zoning for the
park which still needs to be approved by the Minister of
Environmental Affairs. V&L confirmed with the DEA that this
zonation may be used on condition that it will be approved by the
minister [sic] before the development of the safari resort may
proceed.”
13.7. For this proposed development, which is not park dependent or
specific, no reasons have been advanced why the zonation needs to be
changed. It is submitted that there is precedent for subterranean
services infrastructure in protected areas and in areas zoned remote.
Consistency in decision making is one of the cornerstones of
administrative action and is an imperative requirement for fairness.
13.8. The enabling legislation permits precisely the kind of situation
SANParks and the Competent Authority say is impermissible, namely
the conduct of an activity not contained in a management plan.
Regulations 21 and 23 of the Regulations promulgated under
NEM:PAA specifically legislate for temporary deviations from a
zonation under an internal rule or a protected area notice.
13.9. Finding 3 h) is wrong as the Competent Authority has taken irrelevant
considerations into account based on a misunderstanding about the
legal status and purpose of a park management plan. The AFNP
Management Plan has no application outside the AFNP and so in
respect of that aspect of the proposed development it is not relevant.
14. The proposal to divert sizable portion of the river’s flow from the
Augrabies waterfall would have a negative impact on the river
experience to the falls
Page 24 of 80
14.1. The effect of the diversion on the Orange River has been addressed in
detail in section 3.3 of the Amended Final EIAR and in much greater
detail, in response to DEA’s enquiries, in Chapter 2 of the Addendum
Report. It is Appellant’s submission that SANParks and the Competent
Authority have reached a conclusion about the diversion and its
impact on tourism without the relevant facts at their disposal and
have made up their minds to the effect that that the diversion of flow
would:
14.1.1. be a sizable portion of the river’s flow; and
14.1.2. have a negative effect on the visitor experience of the falls; and;
14.1.3. especially during the low flow periods.
14.2. With regard to paragraph 13.1.1, the statement is untrue. The actual
situation is described in section 3.3 of the Final EIA Report
(Considerations for the Diversion Weir), and repeated in section 2.2 of
the Addendum Report (Flow Rate of 30 cubic metres per second), as
follows:
Diversion of water into the headrace will commence when the flow
rate in the river exceeds 30m³/sec, and the rate of diversion will
increase progressively until the flow rate approaching the weir
reaches 90m³/sec, at which time the diverted flow rate will be at its
maximum of 38m³/sec, with 52m³/sec flowing over the weir to the
Augrabies Falls. This means that, at a total flow rate of 90m3/sec in
the river, 42% of the flow in the river will be diverted into the project
headrace to generate electricity, and 58% will continue over the weir
to the Augrabies Falls. This is the largest proportion of the total
river flow that will be diverted into the headrace. When the flow
rate in the river exceeds 90m³/sec the radial gates at the upstream
ends of the headrace culverts in the offtake structure will be used
to regulate discharge into the headrace so that it never exceeds the
design discharge of 38m³/sec. The proportion of total river flow
diverted into the headrace decreases progressively as the flow rate
Page 25 of 80
in the river increases: when the river is flowing at 200m³/sec the
proportion of total flow diverted into the headrace will be 19%, for
instance, which will decrease to 9.5% when the river is flowing at
400m³/sec, and so on. In case of power failure at the offtake
structure or machine shut-down in the power house the radial gates
will be lowered completely to prevent flow entering the headrace.
The flow duration curves1 in Figure 3.17 compare the flow rate over
the falls before and after implementation of the proposed RVM HPP
for an average hydrological year. The curves show that:
For ±20% of the time no flow will be diverted into the tailrace:
For ±15% of the time (55 days) the river flows at or less
than 30m³/sec, so no flow will be diverted into the headrace
and the HPP will not operate.
For ±5% of the time (18 days) the river flows at more than
800m³/secsee Note. At this flow rate it is anticipated that the
sediment loads in the river will begin to increase to such an
extent that sediment could be drawn into the headrace, and
could result in damage to the turbines. No flow will be
diverted into the headrace; power generation will be shut
down to prevent damage to the turbines.
For ±45% of the time (165 days, or 5.4 months) river flows are
between 30m³/sec and 90m³/sec, diverted flow will
progressively increase from zero to 38m³/sec, and the power
station will operate at less than its installed generating
capacity.
For ±35% of the time (128 days, or 4.2 months river flows
exceed 90m³/sec but are less than 800m³/sec, diverted flow
will be at a maximum of 38m³/sec, and the power station will
operate at its full design capacity”
Note: Further studies on the sediment regime of the river may indicate
that it is possible, with minor changes to the design of the offtake
structure, to increase the proposed threshold at which the power
station is shut down, currently conservatively set at a river flow rate of
800m3/sec, to 1 500m3/sec or even 2 000m3/sec. This would have
the advantage of prolonging the generating range of the station by an
additional 10 to 14 days in an average year, with minimal
environmental or tourism impacts. At these elevated flow rates the
1 A flow duration curve (Figure 3.17 in the Amended Final EIAR) is a graphical plot that shows the
percentage of time that the volumetric flow rate in a river or stream is likely to equal or exceed some specified value.
Page 26 of 80
impact on the flow over the falls of diverting 38m3/sec to the power
station would be negligible (a reduction of 2.5% at 1 500m3/sec and
1.9% at 2 000m3/sec), and the visual impact would be undetectable.
14.3. Section 2.2.2 of the Addendum Report also describes the structure of
the diversion weir, which makes it physically impossible to commence
diversion into the power station until the flow rate in the river reaches
30m3/sec or more.
14.4. With regard to paragraph 13.1.2, the statement is subjective and
unsubstantiated.
14.5. Section 2.7 of the Addendum Report presents photographic
information to show that the difference between the range of flows that
will be affected by the diversion is difficult to discern.
14.6. With regard to paragraph 13.1.3, Chapter 3 of the Addendum Report
presents information from the Socio-Economic Impact Assessment
that was conducted by ACER Africa in 2014, which analysed the flow
rate in the river and compared it with the record of the number of
visitors to the Park between March 2009 and August 2013. The study
concluded that:
(i) During periods of very high flow (flood events) there was a noticeable
spike in the number of visitors to the Park. The flow during times of
floods will not be affected by the proposed hydro scheme, because
once the flow in the river exceeds 90m³/sec (a monthly total of 233
million cubic metres if that flow rate is maintained), the hydropower
scheme will reach its maximum possible diversion rate of 38m3/sec.
For comparison:
o The monthly flow volume recorded at DWS’s gauging station at
Neusberg in February 2010 (a flood event that saw a significant
spike in tourist numbers) was 2 820 million cubic metres.
o The monthly flow volume during the period January to June
2011, the most-recent major flood in the river, ranged from
1 853 to 5 995 million cubic metres. The highest daily flow rate
Page 27 of 80
in January, when the flood was at its peak, was a little less
than 4 000m3/sec (average flow rate during the month was
2 240m3/sec. An average total of 3 300 million cubic metres
flowed in the river for a period of six months.
(ii) Over the period analysed, there are consistent spikes in visitor
numbers during the August/September period, December/January
period and to a lesser degree March/April period, regardless of the
flow over the falls. This is most noticeable between September 2011
and August 2013 where the flow has remained consistently low but
there are clear spikes in visitor numbers during these periods (refer
to Figure 4.1). A spike in visitors during the August/September
period can be attributed to an increased number of tourists passing
through the area en route to view the flowers in Namaqualand, while
the spike in visitors during December/January and March/April can
be attributed to the Christmas and Easter holiday periods
respectively.
14.7. There is therefore no historical data to support the contention that
visitor numbers will be adversely affected by low flow rates over the
falls. There is no foundation for the conclusion drawn by the
Competent Authority in Finding 3 i).
15. The proposed hydro power station at the specific location will impact
the flow of water over the falls which will negatively impact visitors
experience
15.1. This is essentially the same as the previous reason for refusal, except
that it adds the essentially indefinable concept of sense of place.
Appellant deals with this in more detail later in paragraph 20.
15.2. It must be acknowledged that the flow regime of the Orange River is by
no means natural, and has not been natural since the waters of the
river were first abstracted to irrigate, among others, vineyards
alongside the river. Section 2.1 of the Addendum Report concludes
with this statement (which is followed by a schematic diagram that
Page 28 of 80
shows how the Lower Orange system is modelled and managed):
The purpose of this brief description of the Orange River Basin and its
management in South Africa is to emphasise that any discussion of the
river’s flow regime and its impacts must be founded on a clear
understanding that the flow in the river is managed almost entirely by
releases from the country’s two largest impounding dams, Gariep and
Vanderkloof, and that no part of the riverine system can be regarded as
natural or unmodified.
15.3. This information is within the knowledge of the Competent Authority
but has seemingly not been considered or incorrectly considered
irrelevant. Page 17 of the Draft ORM Estuarine Management Plan on
the DEA webpage at
https://www.environment.gov.za/.../orm_sitestrategic_eustuarineman
agemntplan.pdf reads:
“The Orange River has become highly regulated by virtue of more
than 20 major dams and numerous weirs within its catchment. As a
consequence, river inflows to the Orange River Estuary have been
markedly reduced from reference, with only an estimated 44% of
natural flows still reaching the system (DWAF, 2003). Abstraction
and regulation has also resulted in a marked reduction in the
variability in river inflows from a pronounced seasonal flow to a
nearly even flow distribution throughout the year. Surplus water
releases for the generation of hydropower has resulted in the
elimination of water deficits in the lower reaches of the river and the
mouth now remains open almost permanently. The lack of mouth
closure and associated back-flooding is regarded as particularly
problematic as it is during such occurrences that flows into the
saltmarsh area typically occur (CSIR, 2011a)”.
15.4. This competing environmental management requirement, if achieved,
Page 29 of 80
is what will cause the flow to diminish almost entirely and totally
remove any visitor experience to the falls, not the project. Hydropower
along the Orange River has actually enhanced the visitor experience at
the falls making sure the experience is not only during floods but
throughout the year.
16. The proposed development will have impact on biodiversity around
and on the national park (e.g. birds, fish, mammals, reptiles and
vegetation) and its scenic value of the waterfall
16.1. Findings 3 d) i); 3 e) i); 3 f) iii); 3 g) i) and 3 i) all allege some form of
biological impact.
16.2. The Findings in this regard as very broad statements, and no
supporting data or information has been provided by the Competent
Authority in support of the contention.
16.3. In particular, there is no indication that the Competent Authority has
considered the Amended Final EIAR and the supporting
documentation, including the specialist reports, in which the potential
impacts of the project are identified, discussed and assessed.
16.4. Appellant is well aware of the diversity of species in the general area of
the park and in the park itself, which is why one of the objectives set
for the faunal specialist, Dr Bill Branch, was to describe the faunal
diversity of the area. In his report Dr Branch pays particular attention
to this issue, and makes, as far as possible, quantitative estimates of
the numbers of species of terrestrial vertebrate fauna (amphibians,
reptiles, mammals and birds) that can be expected to be found in the
area.
16.5. Dr Branch assessed the potential impacts of the project on the on the
Page 30 of 80
diversity of these species, before and after implementing mitigation
measures. The impacts are summarised on pages vii to xi of the
Executive Summary of the specialist report, and in detail in Chapter 8
of the body of the text, as well as in the Amended Final EIAR. Most of
the potential impacts on the fauna can, Dr Branch believes, be
mitigated to Low significance, while three remain at Moderate
significance after mitigation.
16.6. Nothing in Dr Branch’s study indicated that any of the impacts on the
fauna of the area will be so severe as to constitute a fatal flaw for the
project that will prevent it from being implemented; consequently the
Competent Authority simply relies on unsubstantiated concerns to
reach the Refusal Decision which is unfair.
16.7. Finding 3 e) i) is entirely vague. It is not certain that the proposed
development “can cause” the loss of habitat for and displacement of
bird species. To simple say it “can cause” without reference to the
specialist reports and the proposed mitigation measures renders the
concern an unsubstantiated generalisation unconnected to the facts
presented.
16.8. The arbitrary nature of the concerns expressed is further
demonstrated by DEA: BC, charged with biodiversity management,
expressing the view that there are implications for the direct and
indirect negative biodiversity impacts “through to the probable
negative impact on tourism that will impact on the funding available to
protect critical species, from listed plant, invertebrate and reptile
species through to the White Rhinoceros resident in the Augrabies
Falls National Park”.(Finding 3 g)iii)).
16.9. There are three issues in this Finding that destroy any credibility of
Page 31 of 80
the concerns expressed. First. it is premised on an unsubstantiated
probability, secondly it deals with issues outside of DEA:BC’s
mandate, namely tourism and then suggests that the loss of tourism
will impact on the funding available to protect the White Rhinoceros
resident in the AFNP. SANParks has confirmed that there are no white
Rhinoceros in the AFNP. (SANParks email attached marked “RVM9”.)
Furthermore DEA: BC contradicts its reasoning by demonstrating that
the natural range of the white rhinoceros is not remotely near the
AFNP. (Government Gazette dated No. 40398:Notice 727 of 2016
attached marked “RVM10”.)
16.10. It is no coincidence that the Competent Authority does not make any
finding about biodiversity risk from a SANParks perspective, the
protected area manager for the AFNP, rather it relies on concerns
expressed by other commentators not charged with the day to day
biodiversity management of the park. SANParks position is
understandable as the AFNP Management Plan at page 11 says, “Over
the next 20 years it is predicted that the relative biodiversity value of
AFNP will be stable, and the biodiversity risks are low compared to
other parks”. Further at page 19 of the AFNP Management Plan
SANParks concedes that the AFNP does not fall within one of the nine
nationally recognised priority conservation areas.
16.11. The Competent Authority ignores the protected area manager’s
assessment of biodiversity risks as set out in the AFNP Management
Plan but instead relies on “probable” concerns about tourism and
irrelevant considerations concerning the protection of a species not
found in the park. Reliance on such concerns is so unreasonable that
no reasonable person could have made the Refusal Decision relying on
them.
Page 32 of 80
17. The area also holds substantial importance as a buffer for
conservation of biodiversity against future impacts brought about by
climate change
17.1. It is not clear to Appellant how the park and the surrounding areas
will provide a buffer against the impacts of climate change, and the
comment provides no indication why the Competent Authority relies
on an unfounded concern.
17.2. It is also not clear how the project could influence the alleged buffer
against climate change, and the Competent Authority has not provided
any information to support the assertion.
17.3. The statement is unsubstantiated, and cannot be taken as a legitimate
reason for the Refusal Decision.
18. The proposed development has the potential to have grave impacts on
the well protected and managed Augrabies Falls National Park
18.1. This is a very broad statement, and no supporting data or information
has been provided by the Competent Authority in support of the
contention.
18.2. In particular, there is no indication that the Competent Authority has
considered the Amended Final EIAR and the supporting
documentation, including the specialist reports, in which the potential
impacts of the project are identified, discussed and assessed.
18.3. The statement is unsubstantiated, and cannot be taken as a legitimate
reason for the Refusal Decision.
19. The Augrabies Falls holds significant intrinsic value within the ZF
Mcgawu and broader Northern Cape Province. Any alteration to the
Page 33 of 80
falls will definitely contribute to the depreciation in its intrinsic value
19.1. The value of the Augrabies Falls at all geographic levels is not disputed
in any of the documentation submitted to the Competent Authority.
19.2. It appears however that word intrinsic is used as a reinforcing adjective
to emphasis the unquantifiable, as intrinsic is a value in and of itself.
Most of the objections to the alterations to the flow regime over the
falls are not about the falls at all, but relate to the appearance of the
falls to tourists (the visitor experience and sense of place), and
ultimately to the numbers of tourists and importantly the perceived
loss of revenue.
19.3. The repeated and uninformed concerns raised in the Refusal Decision
that the project will significantly degrade the visual amenity and value
of the falls is disputed and remains unfounded. Appellant has
demonstrated this in detail in the documents submitted to the
Competent Authority.
19.4. The intrinsic value of the falls is dependent on the Orange River being
one of the most highly regulated rivers in South Africa with the real
threat to the flow regime over the falls being the way in which the DWS
manages releases to the river and abstractions from the river in the
reaches upstream of the falls.
20. The proposed development will impact the flow of water over the falls
which will have a negative impact on visitors experience and sense of
place of the AFNP
20.1. This theme is repeated in Findings 3 c) iii); 3 3 f) iii) and 3 g) ii).
20.2. The point is that, if anything, it is the sense of place of the falls, not
Page 34 of 80
the AFNP. In a paper commissioned by SANParks entitled “Viewshed
and sense of place as conservation features: A case study and research
agenda for South Africa's national parks” it is concluded that “Both
SoP and viewsheds have the potential to inform conservation action,
and these concepts should form an integral part of objective
hierarchies and management plans for national parks. However, while
legislation and park management plans make provision for the use of
these concepts, associated research in South Africa is virtually non-
existent.” The case study can be located at
http://dx.doi.org/10.4102/koedoe.v58i1.1357.
20.3. The AFNP Management Plan is silent on the sense of place.
20.4. With DWS managing the flow of water over the falls there will be no
discernable change in a visitor’s sense of place, if at all, except during
excess water and flood flow times.
20.5. The legislation relied on in the research paper is the NEM:PAA
(Strategy on Buffer Zones for National Parks, Notice 106 in
Government Gazette No. 35020, 08 February 2012) in the context of
managing activities in buffer zones surrounding national parks. One of
the legal opinions submitted with the Addendum finds that there is no
formal or legally recognised buffer zone for the AFNP. As pointed out
later there is no enabling legislation for the publication of the Strategy
on Buffer Zones for National Parks.
20.6. The two essential requirements of an appreciation of sense of place are
that it be a person that experiences this sensation and that it must be
a place that is being experienced. Sense of place therefore requires an
interaction between the visitor and the place where it happens. A
critical measure of a sense of place is accordingly the value that the
Page 35 of 80
visitor gives to it. There is nothing in the Refusal Decision to support
such a valuation and the Competent Authority cannot experience a
sense of place so cannot rely on it as a yardstick.
20.7. The measure is an abstract, intangible and subjective one which does
not permit an objective evaluation which is what the Competent
Authority is required to do. It is indeterminable and therefore unfair as
a measurement as Appellant has no reasonable means of dealing with
the concern.
21. The Birdlife South Africa in their comments 04 October 2013 and
comments on 22 March 2016 does not support the proposed
development due to the following reasons
21.1. Finding 3 e) confirms that Birdlife Africa ignored the Amended EIAr
Dated June 2016 and the Addendum so their value as concerns is
premature and thus fall to be ignored.
21.2. BirdLife SA’s March 2016 comments are addressed in in Chapter 1 of
the Addendum report, and the detailed responses to the October 2013
comments are included in Appendix F of the Addendum report. The
central thrust of the March 2016 comments was to support SANParks
in its objections to the project, and to encourage DEA to do the same.
These comments are not a valid response to a detailed EIA and its
comprehensive supporting documents, which BirdLife SA gave no
indication that it had read. Its objections rely instead on its own
assessment of the:” … landscape being so worthy of protection as to be
accorded South Africa’s highest conservation status, that of a national
park, is a principle that must be upheld.” That Groenkloof National Park
is a national park and iSimangaliso Wetland Park is not completely
diminishes the value of this statement.
Page 36 of 80
21.3. The October 2013 comments were much more detailed, and are
addressed, also in detail, in Appendix F of the Addendum Report.
However, as noted in the Addendum report, these earlier comments
were sent to the previous EAP after the Final Scoping Report had been
submitted to DEA. As a result they did not have the benefit of the more
recent information about the development of the project (such as, for
instance, that the evacuation powerline crossing the park will be
buried), or of site-specific environmental information in the subsequent
reports, especially those prepared by the faunal and botanical
specialist. Neither of these specialists agreed with BirdLife SA’s
pessimistic assessment of the impacts of the project on the avifauna of
the area. Absolute reliance on the AFNP being a national park and
therefore no development can be supported is not endorsed globally or
by SANParks. It is common knowledge that there is a large hydro
scheme located in a UNESCO world heritage site at Victoria Falls. An
article discussing this is attached marked “RVM11”. Also SANParks is
aware of essential services infrastructure and other bulk infrastructure
in its own parks and elsewhere. The minutes attached marked “RVM12”
of a meeting early in 2013 confirms that SANParks is aware that similar
developments exist in protected areas globally. At page 4 of the minutes
it is recorded that “FR (SANParks) questioned what other projects
similar to that proposed were operating elsewhere in the world and
whether these projects were successful. NW(Entura) noted that Hydro
Tasmania in Tasmania, Australia, operated 26 hydropower stations
similar to those proposed and that three of these were within or
adjacent to world heritage sites. NP (SANParks) noted that the proposed
projects were, however, the first in South Africa to be within a national
park.”
Page 37 of 80
21.4. It is unfair to rely on an organisation’s general objections to any
development in or around a national park, instead of considering the
project on its own merits.
22. The proposed development can cause the loss of habitat for and
displacement of bird species, particularly threatened, endemic and
range-restricted species
22.1. The botanical specialist rated the loss of habitat as Moderate negative
after mitigation, while the faunal specialist rated the loss of bird
diversity as Low negative. The main mitigation measure in both cases
was to minimise habitat destruction during construction, and to
rehabilitate disturbed habitat, under specialist supervision, on
completion of construction, both of which are the Appellants intention.
22.2. The botanical specialist noted that the construction of the offtake
structure will necessitate the clearance of Lower Gariep Alluvial
Vegetation, which is classed as Endangered A1. He noted that the loss
of this type of vegetation along the Orange River has mainly been as a
result of (apparently unregulated) clearance for “the intense agriculture
(mainly table grapes and citrus) on the alluvial soils”, and that the
impacts of the off take structure would be “within a localized area”.
23. Global IBA (SA029). Developments that cause habitat loss should not
be allowed within such protected areas which are important for the
conservation of biodiversity
23.1. Finding 3 e) ii). All national protected areas, apart from Groenkloof
National Park, form part of an IBA. They overlap and don’t give the area
an enhanced conservation status.
23.2. The potential impacts of the project on the IBA are addressed in section
Page 38 of 80
6.2 of the faunal specialist study. There is no attempt to deny the
importance of the IBA to avifauna. Since the boundaries of IBA ZA022
are identical to the boundaries of the AFNP – the AFNP is the IBA - the
arguments against the project are essentially the same: no development
should be allowed in protected areas which is not a position supported
by either the enabling legislation or AFNP Management Plan.
23.3. The threshold here is an absolute prohibition since any development,
from a management road to an accommodation camp, results in habitat
loss. The philosophy seems to go further than the peripheral
development theory which finds some support by SANParks. Besides
NEM:PAA sections 49, 50, 52 and 53 specifically provide for the specific
evil BLA argues against. The only absolute prohibition supported by
legislation is in respect of mining and prospecting.
23.4. The Appellant submits that any development, by definition, will cause
habitat loss. The Competent Authority cannot rely on an arbitrary
absolute standard prohibiting developments that cause habitat loss to
support the Refusal Decision as that results in arbitrary decision
making directed at the Applicant only as it is not a standard applied
consistently across protected areas. If it were there would be no need
for zonation in parks as they would all be wilderness inaccessible to
tourists and communities.
23.5. Besides if “no-development” was a policy it ought to be in the AFNP
Management Plan and it should have been brought to the attention
and disclosed to the Applicant before the Refusal Decision was made,
especially as the Refusal Decision purports to rely on this policy.
Notwithstanding, on a less restrictive policy of peripheral development,
and mentioned in the AFNP Management Plan, a research study
Page 39 of 80
commissioned by SANParks (Koedoe, vol 42, No2 (1999) says the
“principle does not merit the status of a rule”. The abstract is attached
marked “RVM13”.
23.6. It is difficult in these circumstances to understand on what basis the
Competent Authority would chose to rely on a developmental theory
that has not been adopted either by SANParks or DEA.
23.7. For the Competent Authority to rely on a “not in my back yard” anti-
development position not supported by the enabling legislation, policies
and plans reviewed by it, is unfair, illogical and so unreasonable that no
reasonable person could have made the Refusal Decision relying on
such a policy.
24. The proposed development will negatively impact the falls, which is a
tourism attraction to both national and international tourist
24.1. This issue has been extensively addressed previously and is completely
unsubstantiated. There is no evidence submitted by SANParks or
anyone to support the contention that tourism will be affected by the
alteration of the flow regime over the falls or that the Department of
Tourism was even consulted and accordingly it is not a fair reason to
support a Refusal Decision.
24.2. The Specialist Report noted that the area includes the major tourist
attraction, namely, the Augrabies Falls but the part of the AFNP
adjacent to the project site where the main facility is located is not open
to visitors.
24.3. The CBA further determines at 5.4.2.3 of the report that “The AFNP is a
significant tourist attraction in the region, mainly because of the 56m
waterfall. A key concern expressed by SANParks over the construction
Page 40 of 80
of the RVM hydropower project is that the reduced amount of water
reaching the falls when the river is flowing above 30m³/s will have a
negative impact on the number of tourists to the park. It was found,
however, that the slight reduction in the volume of water channelled to
the falls will not be likely to have an impact on tourist levels as the
number of visitors to the Park is not solely determined by the volume of
water over the falls and will thus not result in a decrease of tourism-
related revenues for AFNP (Environmental Impact Report, RVM 1 Hydro
Electric Power (Pty) Ltd - 40 MW Hydroelectric Scheme on Orange River,
October 2015, CESNET, accessed on 15.10.2015
http://www.cesnet.co.za/rvm.html).
25. The location alternative for the proposed construction of a weir is not
feasible as it is not in line with the zonation plan of the AFNP
25.1. The reliance on zonation to block the construction of the weir is not
supported by the enabling legislation and is dealt with in detail in
paragraph AA above.
25.2. Regulation 39 (2) NEM:PA Regulations specifically contemplates that
weirs can be constructed inside national parks consequently to rely on
zonation for the Refusal Decision is based on an error in law.
25.3. There is no alternative site.
26. The proposed development will affect part of the AFNP and its buffer
zone
26.1. This theme is found in Findings 3 e) ii); 3 f) ii); 3 g) i); 3 g) ii); and 3 l).
26.2. The area outside the park where the project will be situated is not part
of the AFNP, it is on land owned by the Riemvasmaak Community.
Page 41 of 80
26.3. As submitted in the Addendum:EIAr the legal opinions demonstrate
that there is no buffer zone for the Park as contemplated in section 28
of NEM:PAA and accordingly no regulations in terms of section 51
regulating any development that may be inappropriate in that
environment, The reliance on a buffer zone is not enforceable against
third parties outside the Park including on the Riemvasmaak land.
Other than in respect of EIA regulations which require environmental
authorisation for certain activities within 10 kilometres of a protected
area, but do not prohibit such activities, the entire buffer zone issue is
a guide for SANParks alone.
26.4. NEM:PAA does not authorise the issuing of strategy, only regulations,
consequently reliance on the buffer zone strategy is misplaced.
Especially when SANParks was asked to provide these policies none
were forthcoming (see legal opinion Hannes Gouws & Partners Inc,
para 2.5.5.). A decision maker cannot rely on an undisclosed policy in
support of a Refusal Decision.
27. The proposed development is not consistent with NEM:PAA, 2003
Section 50(5)
27.1. The Competent Authority relies in Finding 3 f) on a letter from
SANParks dated 2 June 2016. First that letter was part of private
correspondence between the Appellant and SANParks and only found
its way into the EIA process when it was submitted as part of the
Addendum. The Appellant is advised that the reliance on section 50(5)
is wrong in law for the reasons set out in the legal opinions.
Furthermore the Competent Authority, after doing an about turn, by
acceptance of the FEIR confirms section 50(5) compliance is not an
EIA requirement in any event.
Page 42 of 80
27.2. Critically the reliance of SANParks and the Competent Authority on
section 50(5) is against the law. Section 53 (1) provides that:
“Section 45, 46, 49, 50., or 52 may not be applied in a manner that
would obstruct the resolution of issues relating to land rights dealt
with in terms of-
(a) ….
(b) The provision of essential services and the acquisition of
servitudes for that purpose”.
27.3. Government Gazette No. 18276, GN No. 1216, dated 12 September
1997 designated the generation, transmission and distribution of
power as an essential service. It is attached marked “RVM14”.
27.4. SANParks and the Competent Authority make an issue about
SANParks consent being required before the lodgement of the EIAr is
procedurally unfair. First DEA said it was required, then it clarified via
email that prior consent was not needed from SANParks but that it
was before implementation, then DEA retracted that view only to
accept the amended EIAr without SANParks approval being a part
thereof. Finally the Competent Authority then relies on the lack of
SANParks prior approval as a Refusal Decision.
27.5. This created procedural uncertainty and simply wrong in law. The
words implemented and commenced provide the answers.
27.6. The reliance of section 50(5) is misplaced and is based on an incorrect
reading of the legislation and is wrong in law.
28. The proposed development is not consistent with the National
Protected Areas Expansion Strategy 2008 (NPAES)
Page 43 of 80
28.1. Finding 3 f) i). The AFNP Management Plan approved by the Minister
relies on different reasoning to that now relied on by DEA concerning
expansion. The AFNP Management Plan records at page 19: “The
expansion and consolidation of the park is in line with the national
strategic objective (DEA 2005) of expanding South Africa’s protected
area system. The expansion and consolidation programme are [sic]
also informed by SANParks policy regarding land inclusion (SANParks
2006; Knight et al. 2009), and the National Protected Areas Expansion
Strategy (DEA 2008) and the three year rolling land acquisition plan”.
28.2. For DEA to reason therefore that the development “is not consistent
with the National Protected Areas Expansion Strategy 2008 (NPAES)”
(which is the same Strategy as the one referenced DEA 2008)
introduces a different standard to the publicly quoted one.
28.3. Besides it is clear from the SANParks map attached hereto marked
“RVM15” (being Appendix 4, Map 3 to the AFNP Management Plan)
that the development has absolutely no impact whatsoever on any
SANParks expansion programme as all the expansion is west of and
outside the AFNP and the Riemvasmaak property where the
development is planned.
28.4. The reliance on one national strategic objective, DEA 2005, in
approving SANParks expansion programme and then on another
strategy, 2008 (NPAES), which merely “informed” the approved
expansion plan, to determine that the proposed development “is not
consistent” amounts to unfair administrative action. The criteria ought
to be the same for both SANParks and the Applicant.
29. Given the potential adverse threats posed by the project on water
resources
Page 44 of 80
29.1. Findings 3 i) and 3 g) iii).
29.2. Water is not for SANParks or DEA to regulate but the Minister with the
concurrence of the Minister DWS – section 53 (2) NEM:PAA – the
reliance on their comments about water is ultra vires their authority.
29.3. It is not clear what the reference to water levels in the park means. It
could relate to the flow regime over the falls, in which case it has been
addressed extensively previously. If it refers to elevated water levels in
the river upstream of the weir (which they will be), the faunal
specialist rated this as a positive impact, because at low flows it will
result in more water being retained in the braided channel upstream
of the weir, thereby providing more aquatic (and probably riparian)
habitat. Also, the tailrace outfall into the currently mainly-dry paleo-
channel will create more aquatic and riparian habitat.
30. The proposed development will impact on the specific attributes for
which the area was originally declared as a national park
30.1. Finding 3 g) i) and 3 i). Both DEA: BC and the Competent Authority
rely on the following in support of the Refusal Decision: “impact on the
specific attributes for which the area was originally declared as a
national park”.
30.2. The AFNP Management Plan at page 1 says: “It (the Park) was initially
proclaimed in order to conserve a small area of geological interest
around the Augrabies Falls which is the largest waterfall on the
Orange River”. Then the AFNP Management Plan at page 11 says:
“NEM:PAA requires that the park be managed in accordance with
purpose [sic] for which it was declared. The original purpose of the
park is not officially specified, neither in the first gazetted declaration
Page 45 of 80
nor any subsequent addition (Appendix 1)”. Neither DEA:BC nor the
Competent Authority advance any objective criteria used in their
evaluation as to how they concluded that the proposed development
will impact on “a small area of geological interest around the
Augrabies Falls”. The said falls and the geology around it are
unaffected and untouched by the project. At best this shows that the
decision maker was ill-informed and relied on similarly ill-informed
submissions which resulted in decision making that was factually
incorrect, unreasonable and unfair.
30.3. This point, the park expansion and the NIMBY approach of BLA
demonstrate that the Competent Authority could not have considered
the AFNP Management Plan, but if it did, it dismissed it. This, despite
the Competent Authority, stating at page 12 1 e), that it took into
consideration all policies and guidelines. On the Competent
Authorities version it follows that the AFNP Management Plan must be
considered a guideline. Guidelines do not have the force of law
30.4. Given that the original purpose of the park is not officially specified,
not in the first gazetted declaration nor any subsequent addition it is
illogical to rely on a non-existent declaration to support the Refusal
Decision.
31. The proposed development has the potential to have grave impacts on
the well protected and managed AFNP
31.1. Finding 3 d) iii); 3 e) ii); 3 f) ii) 3 g) ii) and 3 i).There is a theme that
runs through the comments relied on by the Competent Authority
which is that because part of the area where the proposed
development will be located is a proclaimed National Park, the project,
which entails the provision of essential services, just simply cannot
Page 46 of 80
proceed. This reliance on a 'fortress’ conservation' model is seemingly
no longer supported by SANParks and certainly not by the enabling
legislation.
31.2. There is no single official policy about development in protected areas
as development is park specific and management authority dependent
and to argue that because the area is a national park no development
should be allowed is not supported by the enabling legislation.
31.3. In June 2015 the former CEO of SANParks said, “The Constitution's
section 24 defines a social contract that is completely different from
that followed by the National Parks Board before 1994. Whereas
communities were evicted to make way for conservation areas..."we are
mainstreaming conservation areas into communities in a formula that
creates a healthy balance between people's aspirations and
conservation objectives in line with international best practice that
dictates the Convention on Biological Diversity (CBD) which protects
biodiversity and encourages access and benefit sharing of such
resources."” (the extract is attached marked “RVM16”)
31.4. He said the Programme of Action of the CBD underpins the
management of national parks and is completely different in the
approach followed by both the Colonial and Apartheid era
conservation strategies which informed a purist view that national
parks must be exclusively managed for animals. The Competent
Authority is relying on an out dated policy consideration which has
not been canvassed with the Appellant and is furthermore not
supported by the enabling legislation or the management plans of
various protected areas.
32. The proposed development also does not take into consideration the
Page 47 of 80
need for an offset to mitigate for the loss of pristine wilderness in a
declared National Park
32.1. Finding 3 g) ii and repeated in 3 g) iii) by DEA: BC.
32.2. There is no enabling legislation mandating biodiversity offsetting.
Offsets have been the subject of frequent policy discussion, with a
draft national policy produced in 2012 and a further discussion
document on ‘environmental offsets’ produced by DEA in 2015.
Applicant could not therefore have considered “offset” as an integral
part of the EIA process. Furthermore no one from the Competent
Authority at any stage of the EIA process or anywhere else has raised
the requirement of an off-set which would obviously have been
considered by the Applicant. The Refusal Decision is also the first
time this concept has been raised.
32.3. If biodiversity off-sets are policy then that policy had to have been
brought to the attention of the Applicant before the Refusal Decision
was made.
32.4. The concern also goes to an offset for the loss of pristine wilderness. It
is not clear to the Appellant how not sure the area can be described as
pristine, given its history as the home to a community, a military
training area, and 4x4 trail including a rustic camp. Even if pristine
means restored to its original state, SANParks does not appear to have
attempted do so by, for instance, removing the 4x4 camp.
32.5. An environmental standard not supported by the facts is relied on to
support the Refusal Decision. It is instructive that the regulations
speak about land that has been undisturbed for 10 years. Most of this
land is former military land and cannot be considered pristine. The
Page 48 of 80
measure for EIA purposes is "indigenous vegetation" which refers to
“vegetation consisting of indigenous plant species occurring naturally
in an area, regardless the level of alien infestation and where the
topsoil has not been lawfully disturbed during the preceding ten
years;” not an undefined immeasurable reference to a pristine
wilderness when the area is by and large one under restoration.
32.6. Besides the route of the underground conduit as depicted in figures
3.2, 3.3, 3.4 and 3.5 at pages 61/62/64 of paragraph 3 “ General
Project Description of the EIAR shows the route of the underground
conduit following as far as practically possible the path of an existing
road, an already disturbed environment
32.7. The most obvious and inherent offset of the project but ignored by the
Competent Authority and seemingly DEA:BC is the contribution to
greening the economy by the reduction in reduction in carbon
emissions
33. The Competent Authority is of the opinion that the listed activities will
be in conflict with the general objectives of integrated environmental
management stipulated in Chapter 5 of NEMA
33.1. This concluding Finding is dealt with in detail in the Grounds for
Appeal below as Appellant submits that the Competent Authority has
not given effect to the general objectives and has applied a
precautionary approach incorrectly by applying only environmental
protection without reference to human health and the sustainable
utilisation of natural resources which should include the
consideration of all possible means to prevent harm occurring, directly
and indirectly.
Page 49 of 80
34. GROUNDS OF APPEAL
It is the appellant’s submission that the decision to refuse to grant
environmental authorisation to Appellant for the project must be set aside by
the Minister for the reasons set out in paragraphs 9 to 33 above which must be
read into the Grounds of Appeal below as if specifically incorporated therein.
35. First Grounds of Appeal: The Respondent Failed to Comply with
Section 24 of the Constitution and the provisions of NEMA.
35.1. The first respondent failed to comply with section 24 of the
Constitution (The Constitution of the Republic of South Africa, 108 of
1996) and the provisions of NEMA – which failure is, in itself, a
contravention of section 240(1)(a) of NEMA – by:
35.2. Failing to apply the principles of national environmental management
set out in section 2 of NEMA; and
35.3. Failing to give effect to the general objectives of integrated
environmental management laid down in Chapter 5 of NEMA; and
35.4. Failing to take into account all relevant factors as required by section
240(1)(b) of NEMA, and
35.5. Any feasible and reasonable modifications or changes to the activity
that may minimise harm to the environment – s240(1)(b)(iv); and
35.6. Comments received from organs of state that have jurisdiction over
any aspect of the activity which is the subject of the application –
s240(1)(b)(vii) and s240(1)(c); and
35.7. Guidelines, departmental policies and decision making instruments
that have been developed or any other information in the possession of
Page 50 of 80
the competent authority that is relevant to the application –
s240(1)(b)(viii).
35.7.1. Section 2 of NEMA sets out the environmental management
principles that must “serve as guidelines by reference to which any
organ of state must exercise any function when taking any decision
in terms of [NEMA] or any statutory provision concerning the
protection of the environment” and must “guide the interpretation,
administration and implementation of [NEMA], and any other law
concerned with the protection or management of the environment.”
35.7.2. The respondent was therefore under an obligation to have regard to
the provisions of section 2 addressed herein in making the decision
in respect of the authorisation.
35.7.3. Section 2(2) NEMA stipulates that “environmental management must
place people and their needs at the forefront of its concern, and serve
their physical, psychological, developmental, cultural and social
interest equitably”.
In this regard, respondent ought to have had reference to the wealth
of evidence regarding the significant negative health impacts of coal
fired power stations.(For example: Business Enterprises University of
Pretoria. 29 September 2001, “The external cost of coal-fired power
generation: The case of Kusile”, at:
http://www.greenpeace.org/africa/Global/africa/publicatins/coal/F
ULL%20SCIENTIFIC%PAPER%20139%20pages.pdf), A recent report
on the health impacts and social costs of coal-fired power stations
concluded that atmospheric emissions from coal-fired power stations
“are currently causing an estimated 2,200 premature deaths per year,
due to exposure to fine particulate matter (PM2.5). This includes
Page 51 of 80
approximately 200 deaths of young children. The economic cost to the
society is estimated at 30 billion rand per year, including premature
deaths from PM2.5 exposure and costs from the neurotoxic effects of
mercury on children.”(79 Bellanger, M et al. 2013, “Economic benefits
of methylmercury exposure control in Europe: Monetary value of
neurotoxicity prevention” Environ Health. 2013; 12:3. available
at:http://www.ncbi.nlm.nih.gov/pmc/articles/PMC3599906.)The
aforementioned study evidences that, in addition to the detrimental
health impacts which the project would help in alleviating additional
expenses are incurred by people living in close proximity to coal fired
power stations. These are generally low-income settlements, and this
will give rise to further impacts upon their physical, psychological,
developmental, cultural and social interests. This is contrary to the
following NEM Principle: “Environmental justice must be pursued so
that adverse environmental impacts shall not be distributed in such
a manner as to unfairly discriminate against any person, particularly
vulnerable and disadvantaged persons”.(section(4)(c)).
35.7.4. Section 2(3) of NEMA requires that development be socially,
environmentally and economically sustainable and section 2(4) of
NEMA provides that:
“sustainable development requires the consideration of all relevant
factors including, but not limited to, the following:
(a) That the disturbance of ecosystems and loss of biological
diversity are avoided, or, where they cannot be altogether
avoided, are minimised and remedied.”
(b) That a risk averse and cautious approach is applied, which
takes into account the limits of current knowledge about the
Page 52 of 80
consequences of decisions and actions; and
(c) That negative impacts on the environment and on people’s
environmental rights be anticipate and prevented, and where
they cannot altogether be prevent, are minimised and
remedied.”
35.7.5. The ‘positive effects’ of the project listed in the FEIR are “an increase
in national electricity, economic development, job creation, increase
in household income and government revenue” are simply overlooked
in favour of preserving the physical environment at the project site
and ignores its contribution to sustainable development. The
assessment of the economic sustainability of an activity must look
not only at the needs of Appellant but also at the needs of the general
public and communities in the immediate vicinity of the project. In
this regard the Riemvasmaak community will directly benefit
financially from a rental income and a shareholding interest in the
Appellant. The estimated annual rental income for the Riemvasmaak
Community Trust will be R 13 million, compared to the
approximately R 45 000-00 per annum now paid by SANParks. The
shareholding interest of the Riemvasmaak Community in the project
could earn dividends as much as an estimated R 26 million per
annum.
35.7.6. Benefits in this context do not refer only to material benefits but also
to environmental goods and services provided or environmental costs
and hazards avoided. In this project the net environmental impact on
the general public consists of reduced health hazards from pollution
and reduced carbon emissions and the unnecessary waste of scarce
water in the generation of coal fired electricity.
Page 53 of 80
35.7.7. South Africa’s immediate and future energy needs can be much
better addressed through securing renewable energy that can come
online much more quickly than a coal-fired power station.
35.7.8. It is submitted that the proposed activity is socially, environmentally
and economically sustainable and brings many benefits to the area
and beyond as is evidenced in the summary Cost Benefit Analysis
attached marked “RVM17”. What RVM 17 shows is a massive
contribution to community upliftment in the form of Community
Development Expenditure benefits of R 1.46 billion being the total
direct economic impact over the lifetime of the project.
35.7.9. In addition the project will:
35.7.9.1. Positively impact on the health of communities living in the area
and beyond, which would be directly attributable to the
anticipated atmospheric emissions savings of pollutants such as
particulate matter (PM), including dust, SO2 and mercury by
directly resulting in 40 MW not having to be produced using fossil
fuels;
35.7.9.2. Result in reduced medical and other expenses being incurred by
affected communities and the state;
35.7.9.3. Have absolutely no impact upon the limited and scarce water
resources in the country as it is not an extractive use of natural
resources;
35.7.9.4. Have no impact upon heritage resources
35.7.9.5. Have little biodiversity impact on the AFNP site since the weir is
not an impoundment so there will always be a flow of water over
Page 54 of 80
the falls, the water conveyance is via an underground conduit and
the evacuation powerline is also underground;
35.7.9.6. Create much needed employment opportunities in a very poor and
economically depressed part of the country during both the
construction phase and operational phase of the project; and
35.7.9.7. Positively impact upon the economy in the medium to long-term,
given the global trend towards divestment in coal and other fossil-
fuels (http://blueandgreentomorrow.com/2015/03/17/un-
backing-fossil-fuel-divestment-campaign) and towards investment
in renewable energy sources.
35.8. It is submitted that the Refusal Decision also violates section 2(4)(b) of
NEMA, which requires: “environmental management must be
integrated, acknowledging that all elements of the environment are
linked and interrelated, and it must take into account the effects of
decisions on all aspects of the environment and all people in the
environment by pursuing the selection of the best practicable
environmental option”. The best practicable environmental option
(BPEO) is that “option that provides the most benefit or causes the
least damage to the environment as a whole, at a cost acceptable to
society, in the long term as well as in the short term”.(Section 1(1)).
35.9. Section 2(4)(p) of NEMA provides that “the cost of remedying pollution,
environmental degradation and consequent adverse health effects and
of preventing, controlling or minimising further pollution,
environmental damage or adverse health effects must be paid by those
responsible for harming the environment.” The project contributes
positively by the reduction of pollution.
Page 55 of 80
35.10. It is submitted that the respondent has failed the proper evaluation
required of NEMA, in that it issued the Refusal Authorisation without
regard, inter alia, to the impacts on health or the climate impact. The
respondent should, at the very least, have considered:
35.10.1. The health impact on communities with regard to air quality and
water resources;
35.10.2. The impacts of climate change for, in particular, water resources
estimated to be made available as a result of this project, as well
as the impacts of the project on greenhouse gas emissions and
adaptation to a changed climate.
35.10.3. It is submitted that any envisaged loss of revenue from a reduction
in visitors, which is denied, the environmental, social and
economic benefits deriving from the project outweigh speculated
harm to tourist numbers.
35.10.4. Failing to give effect to the general objectives of integrated
environmental management laid down in Chapter 5 of NEMA
through failing to comply with section 240(1)(b)(vii) and section
240(1)(c) of NEMA.
35.10.5. Section 240(1)(b)(vii) of NEMA provides that when a decision-maker
is considering an environmental authorisation application, he or
she must take into account “any comments received from organs of
state that have jurisdiction over any aspect of the activity which is
the subject of the application.” Section 240(1)(c) of NEMA also
obliges a decision-maker to take into account the comments of any
organ of state charged with the administration of any law which
relates to the activity in question.
Page 56 of 80
35.10.6. It appears that the Competent Authority ignored the comments
received from DWS in relation to the project.
35.10.7. It is not known to what extent the DoE or other relevant state
departments were involved in the decision-making process of the
respondent with regard to the Refusal Decision. It is however
noted that, given the anticipated impacts of the project on the
surrounding community, the respondent should have consulted
with DEA: Directorate People & Parks, DEA: Directorate Air
Quality and the Department of Energy should have participated in
this decision-making process. Failure to do so amounts to a
neglect of their constitutional and legislative obligations. This
especially when the DEA says when the DEA Minister officially
opened the seventh People and Parks Conference entitled
“Unlocking Protected Areas Economic Potential,” a month before
the Refusal Decision, that the initiative was to provide a platform
for stocktaking on progress being made in addressing land claims
issues affecting protected areas and measures instituted to
facilitate the contribution of protected areas in the enhancement of
rural livelihoods. Speaking at the conference, The Minister urged
the delegates to actively engage in deliberations that will result in
the formulation of “South African People and Parks Midrand
Declaration.” The Midrand Declaration will be taken to CITES COP
17, to ensure South African voice is heard in the space of
endangered species management. (DEA Media release at
http://www.environment.gov.za/mediarelease/molewa_opens7th_
people and parks_co). Then delivering the closing remarks, the
Deputy Minister said “the conference is another pivot in our efforts
as government to create platform for engagement with
communities on protected areas management and how such areas
can be repositioned to respond to the economic development of our
rural areas, the deliberations attained here gives me satisfaction
that our envisaged goal will be achieved.” (DEA Media release at
http://www.environment.gov.za/mediarelease/thomson_closes7th
_people and parks_co) It is not immediately evident that the
Page 57 of 80
Riemvasmaak Community share the same sentiments but it is
submitted that the Refusal Decision was taken without having
regard to all the relevant considerations.
35.10.8. Failure to consider applicable policies relevant to the application,
as required by section 240(1(b)(viii) NEMA.
35.10.9. Section 240(1)(b)(viii) NEMA provides that a decision maker must
consider “any guidelines, departmental policies, and environmental
management instruments that have been adopted in the
prescribed manner by the Minister or MEC, with the concurrence
of the Minister, and any other information in the possession of the
competent authority that are relevant to the application”.
35.10.10. It is submitted that the respondent, in refusing the authorisation,
evidently failed to take into account the National Climate Change
Response White Paper (the “White Paper”)( Available at
http://www.sanbi.org/sites/default/files/documents/national-
climate-change-response-white-paper.pdf) which “presents the
South African government’s vision for an effective climate change
response and the long-term, just transition to a climate-resilient and
lower carbon economy and society.”(Page 5, Executive Summary,
National Climate Change Response White Paper.)
35.10.11. It acknowledges, inter alia, that: “although there will be costs
associated with South Africa’s adaptation and GHG [greenhouse
gas] emission reduction efforts, there will also be significant short
and long-term social and economic benefits…Furthermore various
economic studies have shown that the costs of early action will be
far less than the costs of delay and inaction”. In its objectives, it
records that it will “effectively manage inevitable climate change
Page 58 of 80
impacts through interventions that build and sustain South
Africa’s social, economic and environmental resilience and
emergency response capacity [and] make a fair contribution to the
global effort to stabilise GHG concentrations in the
atmosphere.”(Page 11, National Climate Change Response
Objective, National Climate Change Response White Paper.)
35.10.12. This White Paper confirms, among other things, that “South Africa
is a water scarce country with a highly variable climate and has
one of the lowest run-offs in the world – a situation that is likely to
be significantly exacerbated by the effects of climate change.”(Page
17, Section 5.2: Water, National Climate Change Response White
Paper.)
35.10.13. The White Paper indicates clearly the intention of the government
to take positive steps to address issues of air quality and climate
change in South Africa. In refusing the authorisation, and given
the significant greenhouse gas emissions of coal-fired power
stations, the respondent, has directly contradicted these intentions
and consequently contravened section 240(1)(b)(viii) NEMA.
36. Second Grounds of Appeal: The Respondent Failed to give Appellant
an opportunity to be heard
36.1. Respondent received comments from Northern Cape Department:
Environment & Nature Conversation and did not share these with the
EAP or the Appellant but nevertheless relied on those comments in
making the Refusal Decision. That is in breach of Appellant’s right to
be heard, renders the process unfair and, as has been demonstrated
contributed to the Competent Authority relying on factually incorrect
objections such as the construction of a canal and the white
Page 59 of 80
rhinoceros issue.
36.2. The comments relied on by the Competent Authority received from
DEA: PAPLCM and the DEA: BC were never shared with the Appellant.
Consequently the Appellant never had the opportunity to respond to
the comments.
37. Third Ground of Appeal: the First Respondent Failed to take into
Account the Cumulative Impacts of the Project
37.1. The NEMA EIA Regulations, 2010 define cumulative impacts as “in
relation to an activity…the impact of an activity that in itself may not
be significant, but may become significant when added to the existing
and potential impacts eventuating from similar or diverse activities or
undertakings in the area.”(Regulation 1(1) NEMA EIA Regulations,
2010.)
37.2. Regulation 31(20(I)(i) of the EIA regulations, 2010 requires an EIA to
contain an assessment of each identified potentially significant impact
including, inter alia, cumulative impacts.
37.3. The “Integrated Environmental Management Information series:
Cumulative Effects Assessment 7 issued by DEA” to be found at
http://www.deat.gov.za confirms that indirect effects need to be
assessed. This is international practice as demonstrated by the
Nathan Dam case (refer paragraph 39.5 below).
37.4. The Competent Authority failed to take cumulative impacts into
account adequately or at all as it confined its evaluation to the
“cumulative impacts the proposed development will have within the
Orange River as an international river”.(Key factor 2 g))
Page 60 of 80
37.5. Appellant submits that the project will have no impacts in the river
beyond a point about 10km downstream of the falls, where discharge
from the tailrace re-joins the mainstream channel via the paleo-
channel. There will be some minor evaporative losses from the open
surface of the power station headpond, but it’s improbable that these
losses will exceed the evaporative losses from the river as it passes
through the gorge, which is compounded by the spray from the very
turbulent water surface. The issue is addressed in section 3.3.4 of the
Amended Final EIAR and, at the request of DEA, in section 6.9 of the
Addendum Report.
37.6. With regard to the potential cumulative socio-economic impacts the
Refusal Decision did not take climate change and South Africa’s
commitment to the international community. The Competent Authority
confined itself to “within the Orange River” and not the area as
required by NEMA.
37.7. South Africa is a party to the United Nations Framework Convention
on Climate Change 1992 (UNFCCC) and the Kyoto Protocol 1997. The
‘Conference of the Parties 17’ (COP17) was hosted in Durban, KZN.
37.8. COP is the supreme decision-making body of the International
Convention (Public International Law). Our country committed to take
on a more active role in ensuring that global CO2 emissions decrease
37.9. South Africa is one of the largest carbon emitters in the world (12th)
and contributes over 480 million tons of CO2 per year.( United Nations
Framework Convention on Climate Change (UNFCCC)
Page 61 of 80
Figure 4: CO2 Emissions [Metric tons per capita]
37.10. Over 90% of South Africa’s electricity is generated via coal-fired power
stations. These power stations are responsible for over 80% of South
Africa’s yearly CO2 emissions. (Department of Energy, Republic of
South Africa, Basic Electricity Overview).
37.11. Coal fired power stations are also responsible for the release of
approximately 20 toxic-release chemicals (sulphur dioxide, mercury,
nitrogen oxide, carbon monoxide, lead, hydrocarbons, arsenic,
cadmium, uranium and others).
37.12. South Africa has an economy that is highly energy and carbon
intensive, with the energy sector being highly responsible for a
significant proportion of greenhouse gas (GHG) production. These
GHGs are responsible for the global warming phenomenon. Average
global temperatures have been on the increase for the past 50 years at
an alarming rate. It is estimated that by the year 2035 the average
temperature increase would be 2-5°
Page 62 of 80
37.13. South Africa is particularly vulnerable to the effect of climate change
given our economic dependence on the primary sector (agriculture,
fisheries, mining, etc.). Approximately 64% of South Africans are
employed in this sector. (Discussion Paper for Public Comment,
Reducing Greenhouse Gas Emissions: The Carbon Tax Option,
National Treasury Republic of South Africa, Dec 2001)
37.14. It is estimated that a temperature change of 3-4°C, could cause a 15%
deterioration in crop yields, with significant drawbacks in sub-
Saharan Arica, where only 4% of arable land is irrigated. An increase
in average temperature of this magnitude will lead to massive food
shortages, rise in mosquito populations (malaria) and a reduced
growth rate.(Discussion Paper for Public Comment, Reducing
Greenhouse Gas Emissions: The Carbon Tax Option, National
Treasury Republic of South Africa, Dec 2010)
37.15. It is of the utmost importance to understand the carbon footprint
associated with various technologies of Energy Resources, see Figure 5
(below). For technologies that do not actively emit CO2 during
operation, a value has been given for the emission during construction
and development. (IPCC Special Report on Renewable Energy Sources
and Climate Change Mitigation, 2012)
Page 63 of 80
Figure 5: Various Carbon Intensities of Energy Technologies
37.16. Although a nuclear power plant does not emit CO2 (Figure 5), it
utilizes non-renewable resources and nuclear waste remains
radioactive and hazardous to health for thousands of years
(Plutonium-239 has a half-life of 24,000 years) (IPCC Special Report
on Renewable Energy Sources and Climate Change Mitigation, 2012).
37.17. A 40 MW Run-of-River (ROR) hydroelectric power plant would spare
the atmosphere 13.5 million tons of CO2 from a coal fired power
station of the same installed capacity over 60 years. One must also
consider that sulphur dioxide (acidic counterpart) and nitric oxide
(ozone depleter) are also by-products (in the magnitude of thousands
of tons) of coal being burnt.
37.18. If one examines the renewable technologies, it can be seen that there
are still carbon emissions associated with construction and
development:
Page 64 of 80
Figure 6: Renewable Energy Technology Carbon Intensities
37.19. As one can see (Figure 6), hydroelectric power is three times more
carbon friendly than its nearest competitor (wind power) in the REIPPP
Programme.
37.20. According to the Kyoto Protocol South Africa is classified as a non-
annex 1 developing country and is not explicitly required to undertake
specific emission reduction commitments; however, South Africa has
announced a willingness to undertake nationally appropriate
mitigation actions to deviate from its high GHG production activities.
South Africa announced, that upon availability of adequate,
predictable levels of funding, a goal to reduce its GHG emissions by
34% by 2020 and 42% by 2025.
(https://www.environment.gov.za/speech/molewa_cop17delegation_re
adiness
“Minister Edna Molewa engages media on the state of readiness
of South African delegation to COP17“ 22/11/2011
37.21. The consultancy Airshed Planning Professionals prepared a report (Air
Pollution Health Risk Analysis of Operations of Current and Proposed
Eskom Power Stations located in the Limpopo Province 2006) for
Eskom Holdings in which it states that “Current Eskom power stations
Page 65 of 80
are cumulatively calculated to be responsible for 17 non-accidental
mortalities per year and 661 respiratory hospital admissions”.( “Air
Pollution Health Risk Analysis of Operations of Current and Proposed
Eskom Power Stations Located in the Limpopo Province”, Report No.:
APP/06/ESKOM-07 Rev 0, November 2006, Airshed Planning
Professionals (Pty) Ltd)
37.22. It is submitted that the respondent failed to attach any weight to the
cumulative impacts beyond “within” the Orange River, and should
have. To consider cumulative impacts only “within” the river is an
extremely narrow horizon. Whenever an economic activity has benefits
or costs that are shared by persons other than the demanders or
suppliers of a good or a service, an externality is involved. Pollution is
a negative externality. Externalities need to be dealt with in a way that
enhances the social good. (See Hydropower Externalities: A meta-
Analysis, M.Mattman 2016:
http://www.sciencedirect.com/science/article/pii/SO1409883163009
50)
38. Fourth Ground of Appeal: The First Respondent Failed to take into
Page 66 of 80
Account International and National Obligations
38.1. It is an established fact that climate change impacts upon, and will
continue to impact upon, inter alia:
38.2. water resources due to changes in rainfall and evaporation rates,
which will consequently impact upon agriculture, forestry and
industry due to an increased irrigation and water supply demand;(
Pages 6 – 9, Long Term Adaptation Scenarios: Summary for Policy
Makers available at
http://www.sanbi.org/sites/default/files/documents/Itassummary-
policy-makers2013high-res.pdf)
38.3. air quality, through the impacts upon weather patterns which will
negatively influence criteria pollutants such as PM, SO2, NO2, ozone,
carbon, monoxide, benzene, lead; (Page 11, Long Term Adaptation
Scenarios: Summary for Policy Makers).
38.4. human health, through bringing about an increase in, for instance,
vector-borne diseases, heat stress, increased natural disasters; (Page
11, Long Term Adaptation Scenarios: Summary for Policy Makers.)
38.5. biodiversity due to, for instances, loss of habitat resulting from
increased temperatures and desertification; (Page 15, Long Term
Adaptation Scenarios: Summary for Policy Makers.) and
38.6. marine fisheries, due to changes in water flows and ocean
temperatures.( Page 13, Long Term Adaptation Scenarios: Summary
for Policy Makers).
38.7. South Africa is a signatory to the United Nations Framework
Convention on Climate Change and the Kyoto Protocol, international
Page 67 of 80
agreements which seek to address climate change and set
internationally binding emission reduction target.
38.8. According to a media release of the DEA on 18 November and speaking
from Marrakech the DEA Minister said the Paris Agreement
represented a major step towards an inclusive low carbon and climate
resilient future, guiding the task of managing climate change and its
associated impacts by all stakeholders-including communities, civil
society, labour and the private sector: with government taking a
leadership and facilitative role. “each and very South African must be
a part of the climate action solution. At the end of the day, we are all
in this together”, the Minister said.
(http://www.environment.gove.za/mediarelease/marrakechclimatecha
ngeconference_o). At the Paris meeting South Africa undertook to
make commitment for nation contributions towards greenhouse gas
(GHG) emission reductions for period 2020-2030, and signed a
universal agreement on climate change into at COP21 in Paris in
December 2015. South Africa acknowledges that “the science is clear
that action to address the causes and impacts of climate change by a
single country or small ground of countries will not be successful. This
is a global problem requiring a global solution through the concerted and
cooperative efforts of all countries.”(Pages 8 and 9, Introduction,
National Climate Change Response: White Paper.) It is incumbent on
the state to ensure that its actions, laws and decision-making coincide
with its evident intentions to address climate change and take into
account internationally binding climate change obligations.
38.9. The South African Government has acknowledged the risks of climate
Page 68 of 80
change by adopting the White Paper which is addressed in paragraph
XX above. It confirms that “the policy outlined in this White Paper
embodies South Africa’s commitment to a fair contribution to stabilising
global GHG concentrations in the atmosphere and to protecting the
country and its people from the impacts of inevitable climate
change.”(White Paper p 10) The White Paper includes a National
Climate Change Respondent Strategy (“the climate change response
strategy”), which has listed, as one of its strategic priorities, the need
to “prioritise the mainstreaming of climate change considerations and
responses into all relevant sector, national, provincial and local planning
regimes such as, but not limited to, the Industrial Policy Action Plan,
Integrated Resource Plan for Electricity Generation, Provincial Growth
and Development Plans, and Integrated Development Plans.”(p 15) This
White Paper, as a national policy document, speaks to and should
direct decision-making in respect of authorisations for any
developments.
38.10. It can be concluded that, as part of the integrated environmental
authorisation process envisaged by chapter 5 of NEMA and
requirements in section 240(1)(b)(viii) of NEMA to consider relevant
policy and other relevant information in deciding whether or not to
grant an authorisation, the GHG emissions and climate change
impacts of the project should have been taken into account in deciding
whether or not to grant the authorisation. They were not considered –
either adequately or at all.
38.11. Nevertheless, it is submitted that the EIA evaluation did not include
climate change considerations in full as part of the evaluation process,
and no ‘climate change screening’ was done. This screening includes
both mitigation , potential contribution to further GHG emissions, as
Page 69 of 80
well as adaptation measures. In other words, every development
decision must be based on its contribution to both mitigation and
adaptation. In this regard, it is submitted that the evaluation of all
developments should provide for, inter alia:
38.11.1. maximising reduction in direct and indirect GHG emissions;
38.11.2. maximising potential for further mitigation, including
‘sequestration offsets’, ideally seeking a negative GHG balance;
38.11.3. optimising adaptation to impacts over the full life of the
development, using best available knowledge and modelling
projections of future impacts, which will become more extreme
over time;
38.11.4. ensuring that such adaptations are not misdirected
‘maladaptations’ which will fail and/or exacerbate
impacts/increase vulnerability over time; and
38.11.5. contributing to restoration of ecological infrastructures to better
enable ecosystem-based adaptation, namely building improved
resilience in people, infrastructure and ecosystems.
38.11.6. The above all serve to indicate a clear intention on the part of
government to address climate change, and record a national
stance to take steps to reduce GHG emissions, therefore all
decisions, including the current authorisation, should give effect to
and be aligned with the above.
38.12. The Long Term Adaptation Scenarios (LTAS)( See
https://www.environment.gov.za/sites/default/files/docs/ltaspha
se2report7_longterm_adaptationscenarios.pdf and
Page 70 of 80
https://www.environment.gov.za/sites/default/files/docs/implica
tions_waterbookV4.pdf) aims to respond to the White Paper by
developing national and sub-national adaptation scenarios for
South Africa under plausible future climate conditions and
development pathways. The LTAS reports acknowledge that
impacts on South Africa are likely to be felt primarily via effects on
water resources.( Page 6, Long Term Adaptation Strategies:
Summary for Policy-Makers. Available at
http://www.sanbi.org/sites/default/files/documents/documents/
ltasummary-policy-makers2013high-res.pdf) The LTAS report on
implications for the water sector states that “at present, specific
provisions for climate change adaptation have been made in very few
of the water resources planning tools. There are some early attempts
that have simulated simple scenarios of changed surface water
supply in reconciliation studies.” Page 15, Long Term Adaptation
Strategies: Summary for Policy-Makers. Available at
http://www.sanbi.org/sites/default/files/documents/documents/
ltasummary-policy-makers2013high-res.pdf )
38.13. As already stated above, the project has a positive effect on water
resources as less is required to be used and wasted in mining coal,
washing coal and lost in the production of electricity.
38.14. The LTAS records that “development aspirations in South Africa will
likely be influenced by opportunities and constraints that arise from
climate change impacts on the water sector. Key decisions would
benefit from considering the implications of a range of possible
climate-water futures facing South Africa.”(Page 6, Long Term
Adaptation Strategies: Summary for Policy-Makers. Available at
http://www.sanbi.org/sites/default/files/documents/documents/ltas
Page 71 of 80
ummary-policy-makers2013high-res.pdf )
38.15. The lack of policy coherence with the national climate change response
policy and a disregard for the provision of NEM:AQA and NEMA which
require consideration of international obligations and GHG emissions
as set out above prevented the Competent Authority from evaluating
the application fairly.
38.16. The water flow and probable impact on tourism concerns of the
Competent Authority are without foundation and ultra vires its
jurisdiction. The Orange Rive mouth, as a Ramsar site, is under the
jurisdiction of the Competent Authority so from that perspective it will
be managed appropriately. Applicant has shown that the mouth of the
Orange River will not be affected by the project. Interestingly, if it was
managed correctly there would be a direct impact on water flow and
tourist experience since DEA would want the river to run dry at times.
Nevertheless, that is not going to happen as South Africa is a party to
an international agreement concerning the Orange–Senqu River
Commission. Clause 7.12 of that agreement enjoins the parties to
“take all measures that are necessary to protect and preserve the River
System from its sources to its common terminus.” The water flow
down the Orange River as managed by DWS is accordingly assured.
39. Fifth Ground of Appeal: The Reasons for the Refusal Authorisation are
Vague
39.1. The Competent Authority and others refer to uncertain future issues,
see paragraphs 3 d) iii);3 e) i) 3 g) iii); 3 i) and the conclusion
predicated on the “potentially detrimental environmental impacts”
may not be mitigated to acceptable levels. Acceptable levels remains
an unknown, unspecified, quantified abstract determination
Page 72 of 80
unsupported by any facts, yet relied on by the Competent Authority as
the foundation for the Refusal decision.
39.2. The Competent Authority concludes that due to the existence of a
number of such potential problems the application must be refused. It
is not evident what a potential issue entails or when a threshold of
potentiality will be reached. The Appellant submits that the
Competent Authority’s assessment criteria were subjective to the point
where it endows a department official with an arbitrary discretion in
deciding when a potential issue becomes a fatal flaw. The exercise of
unfettered administrative discretion is unconstitutional and infringes
upon the right of the Appellant to reasonable and fair administrative
decision making.
39.3. The Appellant submits that, while from EIA perspective, a potential
fatal flaw should be identified and investigated by an EAP as a trigger
event that necessitates further assessment, the discretionary and
subjective element of “potentiality” as adopted by the Competent
Authority, as a reason to reject the application should, within the
context of administrative decision making, not be adopted as the
guiding principle or the discretionary assessment criteria utilised in
reaching a decision. The Appellant submits that an administrative
decision must be taken once certainty has been achieved through the
EIA process as to whether a potential fatal flaw or a fatal flaw indeed
exists. In this regard Section 23 of NEMA lists that a general objective
of integrated environmental management, inter alia, is to identify,
predict and evaluate the actual and potential impact on the
environment, socio-economic conditions and cultural heritage, the
risks and consequences and alternatives and options for mitigation of
activities, with a view to minimizing negative impacts, maximizing
Page 73 of 80
benefits and promoting compliance with the principles of
environmental management set out in Section 2. Furthermore Section
24 requires that to give effect to the general objectives of integrated
environmental management the “potential consequences for all
impacts on the environment of listed activities or specified activities
must be considered, investigated, assessed and reported on.”
39.4. The Competent Authority has failed to indicate how and why any of
the mitigation measures proposed by Applicant are not deemed
sufficient or relevant to the environmental impacts identified. It is not
clear how the Competent Authority could, as late as the decision
making phase of the EIA, reject Applicant’s specialist reports in broad
terms and adopt the assessment threshold of “potentiality” in order to
support the contention that the application must be refused.
39.5. The Competent Authority has attributed a new meaning to the term
“impact” by relying on potentiality as foundation for a refusal
decision. In the leading international case known as the Nathan Dam
case (2004) FCAFC 190; (2004) 139 FCR294 ( attached marked
“RVM18”) the Australian court stressed that “it is a question of fact”
for the Commonwealth Environmental Minister whether a particular
adverse effect is an “impact” of a proposed action or merely one that
lies “in the rounds of speculation”, at paragraph 28 of the judgement
“RVM18”. The test to be applied is an “objective one in the sense that
which impacts are relevant is a matter of law. But it is a matter of fact
what are the impacts in any particular set of circumstances provided
they are as a matter of law relevant.”(Page 10, UNSW Australian
Environmental Management: A ‘Dams’ Story attached marked
“RVM19”) The critical question is whether adverse environmental
impacts can be said to have some reasonable connection to the
Page 74 of 80
project, as opposed to being purely speculative or as a hypothetical
possibility. To suggest, as a reason for the Refusal Decision, that the
“probable negative impact on tourism” or the “potential adverse
threats” or that the proposed development “can cause the loss of
habitat for and displacement of bird species” without reference to any
of the scientific reports underpinning the application places the
decisions in the realm of speculation. It renders them vague.
39.6. It is further submitted that the test in the concluding paragraph of
“any potentially detrimental environmental impacts”, is the wrong test
and is contrary to the general objective set out in Section 23 (b) and is
dismissive of the scientific reports. It fails as a test as it is futuristic as
it speaks of potential impacts which are detrimental to the
environment and which result from the proposed activities and does
not deal with the actual and potential impact on the environment,
socio-economic conditions and cultural heritage or the risks and
consequences and alternatives and options as required by NEMA.
39.7. Appellant submits that there can be no abandonment of any
international commitments to the Orange River or to reduce carbon
emissions but if SANParks treats the Park like an island and isolates
it, if the air the community at large breathes is suffocated, then there
will be no river, no sense of place and finally no community.
40. Sixth Ground of Appeal: The Reasons for the Refusal Decision are not
justifiable grounds for refusal
40.1. The absolute reliance on the zonation in the AFNP Management Plan,
besides being unlawful, precludes the exercise of discretion, results in
the plan being applied inflexibly and applied as if it is irrebuttable, is
unfair. SANParks version that only the Minister can amend a
Page 75 of 80
management plan is not supported by the enabling legislation.
40.2. The policies and standards relied on are not compatible with the
requirements of the community as evidenced by recent legislative
innovation. For example the requirements for coastal management
require that decisions are taken in the “ interests of the whole
community” meaning the collective interests of the community
determined by (a) prioritising the collective interests in coastal public
property of all persons living in the Republic over the interests of a
particular group or sector of society;(b) adopting a long-term
perspective that takes into account the interests of future generations
in inheriting coastal public property and a coastal environment
characterised by healthy and productive ecosystems and economic
activities that are ecologically and socially sustainable; and(c) taking
into account the interests of other living organisms that are dependent
on the coastal environment.” (National Environmental Management:
Integrated Coastal Management Act, 2008 (Act No. 24 of 2008)). In this
instance the only sector of the community which seems to have been
considered are tourists.
40.3. The competent authority failed to weigh the different competing
interests adequately, relying rather on incorrect facts and a narrow
environmental view, and not giving due consideration to
proportionality, the bedrock of the Constitution.
41. Seventh Ground of Appeal: The Respondent’s Refusal to Grant the
Authorisation is in Contravention of PAJA
41.1. Section 22 of the Constitution recognises that everyone has the right
to administrative action that is lawful, reasonable and procedurally
fair. PAJA seeks to give effect to this right.
41.2. Section 6(2) provides that a court or tribunal has the power to
judicially review administrative action if, inter alia:
Page 76 of 80
41.2.1. The action was taken because irrelevant considerations are taken
into account or relevant considerations were not considered.
(Section 6(2)(e)(iii) PAJA)
41.2.2. As already mentioned, it is submitted that the respondent failed to
take into account relevant considerations such as:
41.2.3. the cumulative impacts of the project and other developments in
the region;
41.2.4. the socio-economic benefits to the community;
41.2.5. the air quality impacts of the projects;
41.2.6. the impacts on the water resource;
41.2.7. the health impacts of the project; and
41.2.8. the climate change impacts and obligations.
41.2.9. In addition, besides the fact that the project will be beneficial for
job creation and will benefit the economy; it fails to take into
consideration the health impacts, climate change impacts and
ultimate external costs that would otherwise have been borne by
the state.
41.3. The Refusal Decision itself contravenes a law or is not authorised by
an empowering provision (section 6(2)(f)(i) PAJA).
41.4. It is submitted that, for the reasons outlined above, this decision
constitutes a direct contravention of the constitutional right to an
environment not harmful to one’s health or well-being and to “have the
environment protected, for the benefit of present and future generations,
Page 77 of 80
though reasonable legislative and other measures that-
(i) prevent pollution and ecological degradation;
(ii) promote conservation; and
(iii) secure ecologically sustainable development and use of natural
resources while promoting justifiable economic and social
development.” (Section 24(a) and (b), the Constitution of the
Republic of South Africa, 108 of 1996)
41.5. As submitted above, it is recorded that the Refusal Decision
contravenes section 240(1) of NEMA (as the framework legislation to
give effect to the constitutional environmental right), which requires
that the Minister or MEC responsible must, in considering an
application, comply with the provisions of NEMA. It is submitted that
the respondent has failed to comply with the provisions of NEMA in,
inter alia:
41.5.1. failing to take into account the relevant factors listed in section
24O(1)(b) NEMA in considering the application, as addressed
above; and
41.5.2. failing to take into account the comments of DWS and/or any
other organ of state charged with the administration of any law
which relates to the activity in question, as required by section
240(1)(c).
41.5.3. The Refusal Decision is not rationally connected to the information
before the Competent Authority (Section 6(2)(f)(ii)(bb) PAJA). In
refusing the authorisation, the respondent demonstrates that it
failed to give adequate consideration to the specialist reports in the
Page 78 of 80
FEIR. As a result, this decision is not rationally connected to the
information that was before the respondent.
41.6. The exercise of the power or the performance of the function
authorised by the empowering provision, in pursuance of which
administrative action was purportedly taken, is so unreasonable that
no reasonable person could have so exercised the power or performed
the function.(Section 6(2)(h) PAJA.)
41.7. In the circumstances it is submitted that the decision is unreasonable
in that it:
41.7.1. fails to give recognition to the long-term and cumulative impacts on
the emission reductions and to attach sufficient weight to the
contribution to reduce these impacts (impacts likely to increase in
severity as a result of climate change); and
41.7.2. fails to attach sufficient weight to the significant health impacts likely
to be brought about as a result of the project; and
41.7.3. fails to take into account climate change and South Africa’s
international commitments and national obligations in respect of
climate change mitigation; and
41.7.4. fails to apply the principles and provisions of NEMA and to give
recognition to the duty to uphold the constitutional rights to an
environment not harmful to health or well-being; and
41.7.5. took irrelevant factors into account and did not consider relevant
factors; and
41.7.6. its unlawfulness; and
Page 79 of 80
41.7.7. the fact that the Refusal Decision is not rationally connected to the
information before the respondent in making the decision or to the
reasons given for it by the respondent; and
41.7.8. the fact that the decision is so unreasonable, that no reasonable
person could have refused to grant the environmental authorisation.
42. CONCLUSION
42.1. In the context of the Riemvasmaak Community and the proposed
hydro project, which is sustainably significant on the human,
environmental, social and economic fronts, the Refusal Decision is
unlawful, in that it failed to comply with NEMA and NEM:PA. It also
fails to give effect to the constitutional environmental right.
42.1.1. The Refusal Decision constitutes unfair administrative action for all
the reasons stated above and for all of these reasons, the Appellant
submits that the appeal should succeed and that an environmental
authorisation should be granted to Appellant, with or without
conditions.
____________________________ D'ARCY-HERRMAN RANEY
Appellant’s’s Attorney
45 Avonwold Rd, Cnr Ashwold Rd
SAXONWOLD
JOHANNESBURG
P.O. Box 41546, Craighall, 2024
Tel: (011) 486 3894
Fax: (011) 486 0646
Email: [email protected]
Ref: Mr S. Raney/tm
Page 80 of 80
TO: DIRECTORS: APPEALS AND LEGAL REVIEW DEPARTMENT OF ENVIRONMENTAL AFFAIRS
Mr Z Hassam
Environment House
473 Steve Biko Street
Arcadia
Pretoria
0083
Private Bag X447
Pretoria
0001
Email: [email protected]
Tel: 012 399 9356
Ref: 14/12/16/3/3/2/600
AND
TO: CHIEF DIRECTOR: INTEGRATED ENVIRONMENTAL AUTHORISATIONS
Sabelo Malaza
Email : [email protected]