SAE PEV Communication & Interoperability

Task Force Status

EPRI Bus and Truck Charge Interface Groupand

Infrastructure Working Council (IWC) MeetingNovember 15th/16th, 2016

PG&E, San Francisco, CA

11/16/2016Rich Scholer - SAE Communication and

Interoperability Task Force1

Page 2: SAE PEV Communication Task Force Status SAE 15118 Controls Update... · –SEP2 PLC on Control Pilot (between PEV and EVSE), then SEP2 PLC or Wi-Fi or ZigBee to ESI –Requires bridge

Index• SAE & ISO Communication Background• Current Status• Communication and Energy Transfer Combinations

– AC– DC – Wireless Power Transfer (WPT)

• SAE to ISO Comparisons– DC charging connection compatibility– WPT compatibility

• Initial • Final

• Summary/Backup

11/16/2016Rich Scholer - SAE Communication and

Interoperability Task Force2

Page 3: SAE PEV Communication Task Force Status SAE 15118 Controls Update... · –SEP2 PLC on Control Pilot (between PEV and EVSE), then SEP2 PLC or Wi-Fi or ZigBee to ESI –Requires bridge

SAE and ISO 15118 Background

11/16/2016Rich Scholer - SAE Communication and

Interoperability Task Force3

Page 4: SAE PEV Communication Task Force Status SAE 15118 Controls Update... · –SEP2 PLC on Control Pilot (between PEV and EVSE), then SEP2 PLC or Wi-Fi or ZigBee to ESI –Requires bridge

SAE Communication BackgroundMajor Documents and Functions

Rich Scholer - SAE Communication and Interoperability Task Force

4

1. J2836™ - Instructions and Use Cases (establishes

requirements)

Technical Information Report (TIR)

2. J2847 – Messages, diagrams, etc. (derived from the use

case requirements)

-2 is a Standard, others are Recommended Practice (RP)

3. J2931 – Communication Requirements & Protocol

TIR

4. J2953 – Interoperability

RP

5. J3072 – Interconnection Requirements for Onboard, Utility-

Interactive, Inverter Systems

Standard

11/16/2016

Page 5: SAE PEV Communication Task Force Status SAE 15118 Controls Update... · –SEP2 PLC on Control Pilot (between PEV and EVSE), then SEP2 PLC or Wi-Fi or ZigBee to ESI –Requires bridge

Rich Scholer - SAE Communication and Interoperability Task Force

5

SAE Document Interaction

11/16/2016

J2931/7 Security

Smart Charging

(U1 – U5)

DC Charging

PEV as

Distributed Energy

Resource (DER)

(U6 & U7)

Diagnostics

Customer to PEV

and HAN/NAN

(U8 & U9)

Wireless Power

Transfer

Use Cases Messages / Signals Protocol

PLC

(BB OFDM)

Internet

IEEE 802.11n, p

Requirements

J2836/1™ J2847/1 J2931/1

J2836/2™ J2847/2

J2836/3™ J2847/3

J2836/4™ J2847/4

J2931/4

J2836/5™ J2847/5J2931/5

J2836/6™ J2847/6 J2931/6

J2953/1 Interoperability requirements, J2953/2 Test Plan & Procedures,

J2953/3 Test Cases

J3072

On-board

Inverter

DER

Mode

J2836 - Instructions for PEV Communications, Interoperability and Security

Documents

Page 6: SAE PEV Communication Task Force Status SAE 15118 Controls Update... · –SEP2 PLC on Control Pilot (between PEV and EVSE), then SEP2 PLC or Wi-Fi or ZigBee to ESI –Requires bridge

ISO 15118 ED 1

11/16/2016Rich Scholer - SAE Communication and

Interoperability Task Force6

• ISO 15118-1: Road vehicles - Vehicle to grid communication interface– Part 1: General information and use-case definition (J2836)

• ISO 15118-2: Road vehicles – Vehicle to Grid communication Interface– Part 2: Technical protocol description and Open Systems Interconnections (OSI) layer

requirements (J2847)

• ISO 15118-3: Road Vehicles - Vehicle to grid communication interface– Part 3: Physical layer and Data Link layer requirements (J2931)

• ISO 15118-4 Ed.1: Road vehicles — Vehicle to grid communication interface– Part 4: Network and application protocol conformance test (J2953 is Interoperability)

• ISO 15118-5 Ed.1: Road vehicles - Vehicle to grid communication interface– Part 5: Physical and data link layer conformance test (J2953 is Interoperability)

• ISO 15118-6 Ed. 1.0: Road vehicles - Vehicle to grid communication interface– Part 6: General information and use-case definition for wireless communication (J2836/6)

• ISO 15118-7 Ed. 1.0: Road vehicles - Vehicle to grid communication interface – Part 7: Network and application protocol requirements for wireless communication (J2847/6)

• ISO 15118-8 Ed. 1.0: Road vehicles - Vehicle to grid communication interface – Part 8: Physical layer and data link layer requirements for wireless communication (J2931/6)

Page 7: SAE PEV Communication Task Force Status SAE 15118 Controls Update... · –SEP2 PLC on Control Pilot (between PEV and EVSE), then SEP2 PLC or Wi-Fi or ZigBee to ESI –Requires bridge

ISO 15118 ED 2

11/16/2016Rich Scholer - SAE Communication and

Interoperability Task Force7

• ISO 15118-1: ED 2 - Road vehicles - Vehicle to grid communication interface– Part 1: General information and use-case definition (J2836)

• ISO 15118-2: ED 2 - Road vehicles – Vehicle to Grid communication Interface– Part 2: Technical protocol description and Open Systems Interconnections (OSI) layer

requirements (J2847)

• ISO 15118-3: ED 2 - Road Vehicles - Vehicle to grid communication interface– Part 3: Physical layer and Data Link layer requirements (J2931)

• ISO 15118-4 Ed.1: Road vehicles — Vehicle to grid communication interface– Part 4: Network and application protocol conformance test (J2953 is Interoperability)

• ISO 15118-5 Ed.1: Road vehicles - Vehicle to grid communication interface– Part 5: Physical and data link layer conformance test (J2953 is Interoperability)

• ISO 15118-6 Ed. 1.0: Road vehicles - Vehicle to grid communication interface– Part 6: General information and use-case definition for wireless communication (J2836/6)

• ISO 15118-7 Ed. 1.0: Road vehicles - Vehicle to grid communication interface – Part 7: Network and application protocol requirements for wireless communication (J2847/6)

• ISO 15118-8 Ed. 1.0: Road vehicles - Vehicle to grid communication interface – Part 8: Physical layer and data link layer requirements for wireless communication (J2931/6)

Page 8: SAE PEV Communication Task Force Status SAE 15118 Controls Update... · –SEP2 PLC on Control Pilot (between PEV and EVSE), then SEP2 PLC or Wi-Fi or ZigBee to ESI –Requires bridge

Current Status

11/16/2016Rich Scholer - SAE Communication and

Interoperability Task Force8

Page 9: SAE PEV Communication Task Force Status SAE 15118 Controls Update... · –SEP2 PLC on Control Pilot (between PEV and EVSE), then SEP2 PLC or Wi-Fi or ZigBee to ESI –Requires bridge

Active SAE Documents

1. J2836™ – V1 - Instructions for PEV Communications, Interoperability and Security Documents

2. J2836/3™ - V2 - Use Cases for the PEV Communicating as a Distributed Energy Resource (DER)

3. J2836/4™ - V1 – Diagnostics

4. J2836/5™ - V2 – Customer to PEV Use Cases

5. J2847/2 – V4 - DC Charging messages/signals

6. J2931/1 – V4 – Communication Requirements

7. J2931/7 – V1 - Security

8. J2953/1 – V2 - Interoperability requirements

9. J2953/2 – V2 – Interoperability Plan and Report

10. J2953/3 – V1 – Interoperability Test Cases

11/16/2016Rich Scholer - SAE Communication and

Interoperability Task Force9

Page 10: SAE PEV Communication Task Force Status SAE 15118 Controls Update... · –SEP2 PLC on Control Pilot (between PEV and EVSE), then SEP2 PLC or Wi-Fi or ZigBee to ESI –Requires bridge

11/16/2016Rich Scholer - SAE Communication and

Interoperability Task Force10

Summary of active documents in 7 categories:1. New document “J2836 - Instructions for PEV Communications, Interoperability and

Security Documents”1st cut of the document is posted with meetings soon. The intent is to summarize Bubble & Venn diagrams, then instructions, history and future plans for the documents based on functional objective (e.g. (1) if I want to do V2G with an off-board inverter, what documents and items within them do I need, (2) What do we intend for V3 of J2953, etc…)

2. Diagnostics - J2836/4 Use CasesCompleted clean-up and posted, determining if other items can be included (diagnostics), then start the ballot cycle.This includes the analogue diagnostics for the Control Pilot & Prox for opens, shorts low and high at various points.Plan to re-open later for additional charging requirements (AC, DC, WPT …)

3. Customer to PEV J2836/5 Use Cases, U10 for payment is posted & 1st meeting to be scheduled soon.Next steps are messages/protocol documents

4. DC Charging (J2847/2 - V4)Continuing to outlining variations to messages/signals/enumerations between SAE and ISO 15118 ED 2. Working with ANL & JRC to determine when the Golden Test Device will be available and how it will be used to validate Test Cases.

Page 11: SAE PEV Communication Task Force Status SAE 15118 Controls Update... · –SEP2 PLC on Control Pilot (between PEV and EVSE), then SEP2 PLC or Wi-Fi or ZigBee to ESI –Requires bridge

11/16/2016Rich Scholer - SAE Communication and

Interoperability Task Force11

Categories (cont)5. PEV as a Distributed Energy Resource (DER) - Hank McGlynn is lead

J2836/3™ - V2 - Use Cases for the PEV Communicating as a Distributed Energy Resource (DER)

Topic to task force is complete and in Hybrid committee ballot.J2847/2 updates are next (for off-board inverters).J3072 published and still working authority and testing items.UL 9741 V1 is published and plans to include PEV on-board inverter effects.

6. Security – Gorden Lum is leadJ2931/7 – V1 – Security details - Continuing monthly meetings and reviewing other security documents for reference.

7. Interop – Ted Bohn is leadJ2953/1 – V2 - Interoperability requirementsJ2953/2 – V2 – Interoperability Plan and ReportJ2953/3 – V1 – Test Cases (DC charging is 1st, potentially AC Test Cases)Meetings to review Test Cases, both AC and DC and any potential changes to J1772, V7.Golden Test Device (GTD) expected to be released end of 2016 for validation of test cases, then inclusion in J2953/3.Test Event #5 in Korea in November 10th & 11th along with ISO 15118 meetings Nov 9th.

Page 12: SAE PEV Communication Task Force Status SAE 15118 Controls Update... · –SEP2 PLC on Control Pilot (between PEV and EVSE), then SEP2 PLC or Wi-Fi or ZigBee to ESI –Requires bridge

Communication and Energy Transfer Combinations

11/16/2016Rich Scholer - SAE Communication and

Interoperability Task Force12

Disclaimers:1. No claim is made on “issues, problems, preferences, etc.” with any

combinations. 2. Only “comments” are included.3. The intent is to summarize all expected systems (in the home) that is also

intended for public locations with Energy Management System to grid. 4. No claim is made that this is complete.

Page 13: SAE PEV Communication Task Force Status SAE 15118 Controls Update... · –SEP2 PLC on Control Pilot (between PEV and EVSE), then SEP2 PLC or Wi-Fi or ZigBee to ESI –Requires bridge

AC Charging

10/11/2016Rich Scholer - SAE Communication and

Interoperability Task Force13

Page 14: SAE PEV Communication Task Force Status SAE 15118 Controls Update... · –SEP2 PLC on Control Pilot (between PEV and EVSE), then SEP2 PLC or Wi-Fi or ZigBee to ESI –Requires bridge

AC Charging – DR control of EVSE(SEP1.x or SEP2 DR signal)

Comments:• No indicator of when the PEV connects?• No info on what power level does the PEV need?• No info on how long is the power needed?• No acknowledgement (feedback) of DR accepted

or rejected (customer opt out) by the vehicle.• Not clear on the DR signal frequency/latency.

EMS Signal needs to adjust power flow every minute to maybe three minutes (not a 15 minute interval)

10/11/2016Rich Scholer - SAE Communication and

Interoperability Task Force14

Page 15: SAE PEV Communication Task Force Status SAE 15118 Controls Update... · –SEP2 PLC on Control Pilot (between PEV and EVSE), then SEP2 PLC or Wi-Fi or ZigBee to ESI –Requires bridge

10/11/2016Rich Scholer - SAE Communication and

Interoperability Task Force15

AC Charging (SEP1.x vs SEP2)

Page 16: SAE PEV Communication Task Force Status SAE 15118 Controls Update... · –SEP2 PLC on Control Pilot (between PEV and EVSE), then SEP2 PLC or Wi-Fi or ZigBee to ESI –Requires bridge

10/11/2016Rich Scholer - SAE Communication and

Interoperability Task Force16

AC Charging w/ ISO 15118 (PEV to EVSE)

Page 17: SAE PEV Communication Task Force Status SAE 15118 Controls Update... · –SEP2 PLC on Control Pilot (between PEV and EVSE), then SEP2 PLC or Wi-Fi or ZigBee to ESI –Requires bridge

AC Charging – ISO 15118 High Level Communication (HLC) NAFTA vs. EMEA vs. SEP2

Comments:• SEP1.x is communication between the Smart Meter and ESI

– Time of Use Price (TOU – months ahead), Critical Peak Price (CPP - day ahead) or Real Time Price (RTP – minutes ahead) plus Demand Response (DR)

• SEP2 is communication between PEV and Utility. – SEP2 PLC on Control Pilot (between PEV and EVSE), then SEP2 PLC or Wi-Fi

or ZigBee to ESI– Requires bridge at EVSE to ESI or Utility– Same as SEP1.x price and DR, adds FlowReservation (request power level,

energy amount required and “both initial & actual” Time Charge is Needed (TCIN) for charge session, dynamically adjusts to actual values, with acknowledgement to utility)

• 15118 is communication between PEV and EVSE. – PowerLine Carrier (PLC) on Control Pilot– Requires gateway (not bridge) at EVSE for Utility or home interface to other

protocols.

10/11/2016Rich Scholer - SAE Communication and

Interoperability Task Force17

Page 18: SAE PEV Communication Task Force Status SAE 15118 Controls Update... · –SEP2 PLC on Control Pilot (between PEV and EVSE), then SEP2 PLC or Wi-Fi or ZigBee to ESI –Requires bridge

FlowReservation (FR) - Initial TCIN

10/11/2016Rich Scholer - SAE Communication and

Interoperability Task Force18

Page 19: SAE PEV Communication Task Force Status SAE 15118 Controls Update... · –SEP2 PLC on Control Pilot (between PEV and EVSE), then SEP2 PLC or Wi-Fi or ZigBee to ESI –Requires bridge

FR - Actual optimized charging(still has high peak load in home)

10/11/2016Rich Scholer - SAE Communication and

Interoperability Task Force19

Page 20: SAE PEV Communication Task Force Status SAE 15118 Controls Update... · –SEP2 PLC on Control Pilot (between PEV and EVSE), then SEP2 PLC or Wi-Fi or ZigBee to ESI –Requires bridge

SEP2 Offers FR dynamic load control

10/11/2016Rich Scholer - SAE Communication and

Interoperability Task Force20

Page 21: SAE PEV Communication Task Force Status SAE 15118 Controls Update... · –SEP2 PLC on Control Pilot (between PEV and EVSE), then SEP2 PLC or Wi-Fi or ZigBee to ESI –Requires bridge

FR Optimized Charging process

10/11/2016Rich Scholer - SAE Communication and

Interoperability Task Force21

OBCMCustomer interface

Initial Time Charge is Needed

(TCIN) & end SoC desired

(if not 100%)

Utility info

Price & DRLC

Vehicle info

Current SoC, charger efficiency, 12V (hotel) loads, etc.

OBCMCustomer interface

(Show Fastest, Cheapest and Optimized choices)

select value or use presets

OBCMCustomer interface

(Select Fastest, Cheapest or Optimized)

each session or implement presetsVehicle

(Implements)

Step 1

Step 2

Step 3 Utility info

FlowReservation

Energy, power,

actual TCIN

plus acknowledgment

Page 22: SAE PEV Communication Task Force Status SAE 15118 Controls Update... · –SEP2 PLC on Control Pilot (between PEV and EVSE), then SEP2 PLC or Wi-Fi or ZigBee to ESI –Requires bridge

Other options (optimized charging)

• RTP program where both positive and negative priced are available

– Negative prices (utility pays for a source to use excess energy) can be used for vehicle charging

• Clean energy can be identified so PEV can charge when this is available

11/16/2016Rich Scholer - SAE Communication and

Interoperability Task Force22

Page 23: SAE PEV Communication Task Force Status SAE 15118 Controls Update... · –SEP2 PLC on Control Pilot (between PEV and EVSE), then SEP2 PLC or Wi-Fi or ZigBee to ESI –Requires bridge

What else? DC Charging (in the home)

10/11/2016Rich Scholer - SAE Communication and

Interoperability Task Force23

Page 24: SAE PEV Communication Task Force Status SAE 15118 Controls Update... · –SEP2 PLC on Control Pilot (between PEV and EVSE), then SEP2 PLC or Wi-Fi or ZigBee to ESI –Requires bridge

Xtreme Fast Charge (XFC) effects in the home

• BEVs may be charged similar to IC vehicle refueling (once a week instead of “every opportunity”).

• 7 kW/vehicle may be once a week instead of daily

– Steady 7 kW for 10-12 hrs duration (50 kWh for 150 miles) once a week

– instead of 2 hrs daily (10 kWh for 30 miles)

– Two BEVs = 14 kW for 12 hours!

11/16/2016Rich Scholer - SAE Communication and

Interoperability Task Force24

Page 25: SAE PEV Communication Task Force Status SAE 15118 Controls Update... · –SEP2 PLC on Control Pilot (between PEV and EVSE), then SEP2 PLC or Wi-Fi or ZigBee to ESI –Requires bridge

10/11/2016Rich Scholer - SAE Communication and

Interoperability Task Force25

AC DER (on-board inverter)

Page 26: SAE PEV Communication Task Force Status SAE 15118 Controls Update... · –SEP2 PLC on Control Pilot (between PEV and EVSE), then SEP2 PLC or Wi-Fi or ZigBee to ESI –Requires bridge

10/11/2016Rich Scholer - SAE Communication and

Interoperability Task Force26

DC DER (DC Discharging)

Page 27: SAE PEV Communication Task Force Status SAE 15118 Controls Update... · –SEP2 PLC on Control Pilot (between PEV and EVSE), then SEP2 PLC or Wi-Fi or ZigBee to ESI –Requires bridge

Telematics – Indirect communications(macro Charging control – save XX MW)

10/11/2016Rich Scholer - SAE Communication and

Interoperability Task Force27

OpenADR2 for DR signal to OEM Central Server using

Hot Spot Prediction

Page 28: SAE PEV Communication Task Force Status SAE 15118 Controls Update... · –SEP2 PLC on Control Pilot (between PEV and EVSE), then SEP2 PLC or Wi-Fi or ZigBee to ESI –Requires bridge

Wireless Power Transfer (WPT)(additional items)

1. Wireless communication (instead of PLC)

a) IEEE 802.11n (static WPT, 802.11p for dynamic)

2. Additions:

a) Alignment

• Service Discovery occurs during this step

b) Foreign Object Detection (FOD)

c) Living Object Protection (LOP)

3. Customer HMI (items 2a, b & c)

10/11/2016Rich Scholer - SAE Communication and

Interoperability Task Force28

Page 29: SAE PEV Communication Task Force Status SAE 15118 Controls Update... · –SEP2 PLC on Control Pilot (between PEV and EVSE), then SEP2 PLC or Wi-Fi or ZigBee to ESI –Requires bridge

SAE to ISO 15118 Comparisons (Updates focused on 15118 ED 2, not ED 1)

1. DC Charging (DIN 70121: 2014/J2931/1 & J2847/2 both V3) – (Grandfathered)

2. 15118-2 Ed 2 (AC) – Add to SAE3. 15118-2 Ed 2 (DC) – Add to SAE (347 variations!)4. 15118-2 Ed 2 (AC DER) – Add to SAE5. 15118-2 Ed 2 (DC DER) – Add to SAE6. 15118-2 Ed 2 (ACD) – Add to SAE7. 15118-2 Ed 2 (WPT) – Add to SAE8. WPT (J2847/6) – (Grandfathered)9. WPT (ISO 15118-7) – no plan to add to SAE

11/16/2016Rich Scholer - SAE Communication and

Interoperability Task Force29

Page 30: SAE PEV Communication Task Force Status SAE 15118 Controls Update... · –SEP2 PLC on Control Pilot (between PEV and EVSE), then SEP2 PLC or Wi-Fi or ZigBee to ESI –Requires bridge

11/16/2016Rich Scholer - SAE Communication and

Interoperability Task Force30

Association Association Association

M SLAC M SLAC

M Service Discovery Protocol M Service Discovery Protocol

Initialization Initialization Initialization Initialization

M SupportedAppProtocol M SupportedAppProtocol M SupportedAppProtocol M SupportedAppProtocol

M SessionSetup M SessionSetup M SessionSetup M SessionSetup

Identification, Authentication and Authorization

M ServiceDiscovery M ServiceDiscovery M ServiceDiscovery M Service Discovery

O ServiceDetail M ServiceDetail

N/U ServicePaymentSelection M PaymentServiceSelection M PaymentServiceSelection M ServicePaymentSelection

N/U Contract Authentication M Authorization M Authorization M Contract Authentication

O CertificateUpdate

O CertificateInstallation

M PaymentDetails (PnC)

M FinePositioning

M Start Alignment

M EndAlignment

M Pairing M Pairing

M Start AlignmentCheck

M EndAlignmentCheck

Target Setting and Charge Scheduling

M ChargeParameterDiscovery M ChargeParameterDiscovery M ChargeParameterDiscovery M ChargeParameterDiscovery

Isolation Monitoring & PreCharge Isolation Monitoring & PreCharge Isolation Monitoring & PreCharge PreCharge

CableCheck CableCheck

Pre-Charge PreCharge O PreCharge WPPreCharge

M PowerDelivery M PowerDelivery M PowerDelivery M PowerDelivery

Energy Transfer Energy Transfer Energy Transfer Charging

CurrentDemand CurrentDemand PowerDemand PowerDemand

M MeteringReceipt (PnC)

Welding Check & Termination Welding Check & Termination Finalize Finalize

PowerDelivery PowerDelivery

WeldingDetection M WeldingDetection

M SessionStop M SessionStop M SessionStop M SessionStop

WirelessWired

DC Charging (DIN/J2847/2) WPT (J2847/6)15118-2 Ed 2 (DC) 15118-2 Ed 2 (WPT)

Page 31: SAE PEV Communication Task Force Status SAE 15118 Controls Update... · –SEP2 PLC on Control Pilot (between PEV and EVSE), then SEP2 PLC or Wi-Fi or ZigBee to ESI –Requires bridge

DC Charging Connection Compatibility (DIN/SAE) – some common parts to WPT

11/16/2016Rich Scholer - SAE Communication and

Interoperability Task Force31

SECC Response (0b) – SupportedAppProtocolRes (DC L1 or DC L2)

Energy Transfer Type

2 DC Core

3 DC Extended

EVCC Request (3a) - ChargeParameterDiscoveryReq

Disconnect Association Initialization

t0 t0' t0" t1EVCC Request SLAC SDP 0a 1a 2a Xa Ya 3a

SECC Response 0b 1b 2b Xb Yb 3b

• EVSE message for what connection is made:

• PEV message for what connection is expected:

EV Requested Energy Transfer Type

0 AC Single Phase Core1 AC three phase core2 DC core

3 DC extended

4 DC combo core

5 DC unique

Page 32: SAE PEV Communication Task Force Status SAE 15118 Controls Update... · –SEP2 PLC on Control Pilot (between PEV and EVSE), then SEP2 PLC or Wi-Fi or ZigBee to ESI –Requires bridge

DC Charging - SECC response code

11/16/2016Rich Scholer - SAE Communication and

Interoperability Task Force32

Response Code

0 OK

1 OK_NewSessionEstablished

2 OK_OldSessionJoined4 FAILED

5 FAILED_SequenceError

7 FAILED_UnknownSession8 FAILED_ServiceSelectionInvalid9 FAILED_PaymentSelectionInvalid

11 (B) FAILED_SignatureError

16 (10) FAILED_WrongChargeParameter17 (11) FAILED_PowerDeliveryNotApplied18 (12) FAILED_TariffSelectionInvalid

19 (13) FAILED_ChargingProfileInvalid22 (16) FAILED_WrongEnergyTransferType

SECC Response (3b) – ChargeParameterDiscoveryRes (0 or 22)

• EVSE message for what passed or failed:

Page 33: SAE PEV Communication Task Force Status SAE 15118 Controls Update... · –SEP2 PLC on Control Pilot (between PEV and EVSE), then SEP2 PLC or Wi-Fi or ZigBee to ESI –Requires bridge

WPT Charging Initial Compatibility

11/16/2016Rich Scholer - SAE Communication and

Interoperability Task Force33

Procedure to communicate Initial compatibility information between EVCC and

SECC

Can have several vehicles approaching several WPT choices:

SECC

SD SD SD

Circular DD Solenoid

①SECC send several supported method to EV.

②EV select one of the supported method to use and send it to SECC.

Using Service detail response message

Using Payment service selection request message

Otherwise, EV rejects the SECC request. By this procedure, the method of fine positioning, pairing, initial alignment check to use should be chosen.

Page 34: SAE PEV Communication Task Force Status SAE 15118 Controls Update... · –SEP2 PLC on Control Pilot (between PEV and EVSE), then SEP2 PLC or Wi-Fi or ZigBee to ESI –Requires bridge

11/16/2016Rich Scholer - SAE Communication and

Interoperability Task Force34

Communication SetupSupportedAppProtocolReq_ResSessionSetupReq_Res

Identification Authentication Authorization

ServiceDiscoveryReq_ResServiceDetailReq_ResPaymentServiceSelectionReq_ResPaymentDetailReq_ResFinePositioningReq_ResAlignmentCheckReq_ResPairingReq_ResAuthorizationReq_Res

Target setting and Charge SchedullingChargeParameterDiscoveryReq_ResPowerDeliveryReq_Res

Charge Control and Re-Schedulling PowerDemandReq_Res

End of charging processPowerDeliveryReq_ResSessionStopReq_Res

ISO/IEC15118-2 Ed2.0 CD

(ISO/IEC15118-2 Ed2.0 CD)

Service Detail Response

Service Payment List

Parameter Set

ParameterSetID

WPTSupplyDeviceID

WPTType

WPTPowerClass

MinPower

MaxPower

PairingMethod

ZGapClass

SECC→EVCC

(ISO/IEC15118-2 Ed2.0 CD)

Payment Service Selection Request

SelectServiceList

selectedservice

ParameterSetID

WPTSupplyDeviceID

WPTType

WPTPowerClass

MinPower

MaxPower

PairingMethod

ZGapClass

EVCC→SECC

Page 35: SAE PEV Communication Task Force Status SAE 15118 Controls Update... · –SEP2 PLC on Control Pilot (between PEV and EVSE), then SEP2 PLC or Wi-Fi or ZigBee to ESI –Requires bridge

WPT Charging Final Compatibility

11/16/2016Rich Scholer - SAE Communication and

Interoperability Task Force35

Procedure to communicate Final compatibility information between EVCC and

SECC

SECC

SD SD SD

Circular DD Solenoid

①EV send SECC one of supported method to use again.

②SECC checked EV to supported method to use again. And send response to EV.

Using ChargeParameterDiscoveryRequestmessage

Using ChargeParameterDiscoveryResponsemessage

Otherwise, SECC rejects the EV request. By this procedure, the method of initial alignment check to use should be checked.

Page 36: SAE PEV Communication Task Force Status SAE 15118 Controls Update... · –SEP2 PLC on Control Pilot (between PEV and EVSE), then SEP2 PLC or Wi-Fi or ZigBee to ESI –Requires bridge

11/16/2016Rich Scholer - SAE Communication and

Interoperability Task Force36

ISO/IEC15118-2 Ed2.0 CD

SECC→EVCC EVCC→SECC

Communication SetupSupportedAppProtocolReq_ResSessionSetupReq_Res

Identification Authentication Authorization

ServiceDiscoveryReq_ResServiceDetailReq_ResPaymentServiceSelectionReq_ResPaymentDetailReq_ResFinePositioningReq_ResAlignmentCheckReq_ResPairingReq_ResAuthorizationReq_Res

Target setting and Charge SchedullingChargeParameterDiscoveryReq_ResPowerDeliveryReq_Res

Charge Control and Re-Schedulling PowerDemandReq_Res

End of charging processPowerDeliveryReq_ResSessionStopReq_Res

(ISO/IEC15118-2 Ed2.0 CD)Charge Parameter Discovery Request

EVChargeParameterWP_EVChargeParameter

ParameterSetIDWPTSupplyDeviceID

WPTType

WPTPowerClass

MinPower

MaxPower

PairingMethodZGapClass

(ISO/IEC15118-2 Ed2.0 CD)Charge Parameter Discovery Response

EVSEChargeParameterWP_EVSEChargeParameter

ParameterSetIDWPTSupplyDeviceID

WPTType

WPTPowerClass

MinPower

MaxPower

PairingMethodZGapClass

(SAE J2847/6)

Charge Parameter Discovery

RequestEVChargeParameter

WP_EVChargeParameterWP_EVStatusEVMaimumPowerLimitEVEnergyCapacityEVEnergyRequestFullSOCBulkSOCAlignmentMethodPairingMethod

(SAE J2847/6)

Charge Parameter Discovery

ResponseEVSEChargeParameter

WP_EVSEChargeParameterWP_PrimaryList

PDIDCoilPowerCapabilityAlignmentMethodPairingMethodACPlugAvailableDCPlugAvailable

Page 37: SAE PEV Communication Task Force Status SAE 15118 Controls Update... · –SEP2 PLC on Control Pilot (between PEV and EVSE), then SEP2 PLC or Wi-Fi or ZigBee to ESI –Requires bridge

11/16/2016Rich Scholer - SAE Communication and

Interoperability Task Force37

ISO/IEC15118-2 Ed2.0 CD

SECC→EVCC EVCC→SECC

EVPC power classMaximum receivable powerMaximum secondary device ground clearanceMinimum secondary device ground clearanceMinimum operating frequencyMaximum operating frequencyType of geometry of the secondary deviceCircuit topologyFine Positioning methodsPairing methodsInitial alignment check methodsManufacturer IDManufacturer specific data containerSpecific Service Provider (optional)

Under discussion: (in CD commenting phase)

MF-WPT input power classMaximum output powerMaximum supported secondary device ground clearanceMinimum supported secondary device ground clearanceMinimum primary device operating frequencyMaximum primary device operating frequencyType of geometry of the primary devicePrimary device Circuit topologySupported Fine Positioning methodsSupported Pairing methodsSupported Initial alignment check methodsManufacturer IDManufacturer specific data containerSpecific Service Provider (optional)

Page 38: SAE PEV Communication Task Force Status SAE 15118 Controls Update... · –SEP2 PLC on Control Pilot (between PEV and EVSE), then SEP2 PLC or Wi-Fi or ZigBee to ESI –Requires bridge

Summary/Backup

11/16/2016Rich Scholer - SAE Communication and

Interoperability Task Force38

Page 39: SAE PEV Communication Task Force Status SAE 15118 Controls Update... · –SEP2 PLC on Control Pilot (between PEV and EVSE), then SEP2 PLC or Wi-Fi or ZigBee to ESI –Requires bridge

Use Case Document Status - TIRJ2836™ - Instructions for PEV Communications, Interoperability and Security Documents

- V1 Started

J2836/1™ - Utility Use Cases– V1 Published 4-8-10

J2836/2™ - DC Charging Use Cases– V1 Published 9-15-11

J2836/3™ - PEV as a Distributed Energy Resource (DER) Use Cases– V1 Published 1-3-13– V2 in Hybrid committee affirmation ballot, next is SAE formatting, then publication

J2836/4™ - Diagnostics Use Cases– V1 Started for failures on control pilot and prox, adding diagnostics– V2 will be later after J2953/1 & /2 (Interoperability) for DC charging is complete

J2836/5™ - Customer to PEV Use Cases– V1 published 5-7-15– V2 reopened for U10 (Payment)

J2836/6™ - Wireless Charging Use Cases– V1 Published 5-3-13.– V2 Planned for updates from 15118-1 ED 2– V3 Potentially for dynamic

Rich Scholer - SAE Communication and Interoperability Task Force

3911/16/2016

Page 40: SAE PEV Communication Task Force Status SAE 15118 Controls Update... · –SEP2 PLC on Control Pilot (between PEV and EVSE), then SEP2 PLC or Wi-Fi or ZigBee to ESI –Requires bridge

Signal/Message Document Status – RP/StandardJ2847/1 - Utility signals/messages

– V1 Published 6-16-10, V2 5-9-11, V3 11-9-11, V4 11-5-13

J2847/2 - DC Charging (Standard)– V1 Published 10-21-11, – V2 – 8-20-12 to align with J1772 V5 (DC charging).– V3 Published 4-9-15 to align with DIN SPEC 70121 V6a– V4 restarted (June, 2015) to cover

• EVSE inverter with DC RPF (J2836/3 V2) • Include ISO/IEC 15118-2 & -3 ED 2 updates (variations to DIN SPEC 70121)• Include Wireless Charging updates

J2847/3 - PEV as a Distributed Energy Resource (DER)– V1 Published 12-10-13

J2847/4 - Diagnostics– Started but waiting for J2836/4™ V1 & J2953/1 & /2 V2 (Interoperability)

J2847/5 - Customer to PEV– Meetings to start after J2836/5™ Use Case 10 is complete.

J2847/6 - Wireless Charging– V1 published 8-5-15– V2 planned for unresolved issues from V1 and updates from ISO 15118-2 (ED 2).– V3 potentially for dynamic

Rich Scholer - SAE Communication and Interoperability Task Force

4011/16/2016

Page 41: SAE PEV Communication Task Force Status SAE 15118 Controls Update... · –SEP2 PLC on Control Pilot (between PEV and EVSE), then SEP2 PLC or Wi-Fi or ZigBee to ESI –Requires bridge

Requirements and Protocol Documents - TIR

J2931/1 – Requirements– V1 Published 1-24-12, V2 Published 9-7-12– V3 Published 1-5-15 for DC Charging – V4 Reopened for Security additions

J2931/4 – PowerLine Carrier (PLC) – wired communication protocol– V1 Published 7-26-12, V2 Published 11-14-13– V3 Published 10-22-15 for DC Charging

J2931/5 – Telematics – wireless communication protocol– Waiting for J2847/5

J2931/6 – Wireless Charging Communication (IEEE 802.11n – Static, 802.11p for dynamic) wireless charging protocol– V1 Published 8-27-15– V2 Will reopen for updates to 15118-3 ED 2– V3 Will reopen for dynamic

J2931/7 - Security– V1 Restarted to align with J2931/1

Rich Scholer - SAE Communication and Interoperability Task Force

4111/16/2016

Page 42: SAE PEV Communication Task Force Status SAE 15118 Controls Update... · –SEP2 PLC on Control Pilot (between PEV and EVSE), then SEP2 PLC or Wi-Fi or ZigBee to ESI –Requires bridge

Interoperability Documents - RPJ2953/1 – Requirements

– V1 Published 10-7-13.• V1 started testing for the analogue communications (J1772™

control pilot and prox).

– V2 is addressing digital communication for DC charging– V3 planned to include WPT

J2953/2 – Test plan– V1 Published 1-22-14– V2 Adding V1 updates and DC Charging– V3 planned to include WPT

J2953/3 – Test Cases– V1 started to capture AC and DC test cases

Rich Scholer - SAE Communication and Interoperability Task Force

4211/16/2016

Page 43: SAE PEV Communication Task Force Status SAE 15118 Controls Update... · –SEP2 PLC on Control Pilot (between PEV and EVSE), then SEP2 PLC or Wi-Fi or ZigBee to ESI –Requires bridge

On-board Inverter - Standard

J3072 – Interconnection Requirements for Onboard, Utility-Interactive, Inverter Systems

• V1 published 4-9-15.

Rich Scholer - SAE Communication and Interoperability Task Force

4311/16/2016

Page 44: SAE PEV Communication Task Force Status SAE 15118 Controls Update... · –SEP2 PLC on Control Pilot (between PEV and EVSE), then SEP2 PLC or Wi-Fi or ZigBee to ESI –Requires bridge

The End

Questions?

Rich Scholer - SAE Communication and Interoperability Task Force