  • Previous Issue: 28 January 2012 Next Planned Update: 28 January 2017

    Revised paragraphs are indicated in the right margin Page 1 of 17

    Primary contact: Kakpovbia, Anthony Eyankwiere on +966-3-8801772

    CopyrightSaudi Aramco 2013. All rights reserved.

    Engineering Procedure SAEP-381 17 March 2013

    Project Quality Issues Escalation Process

    Document Responsibility: Inspection Engineering Standards Committee

    Saudi Aramco DeskTop Standards Table of Contents 1 Scope... 2

    2 Purpose 2

    3 Conflicts and Deviations 2

    4 Applicable Documents.. 3

    5 Definitions 3

    6 Violations Definitions. 4

    7 Instructions.. 5

    8 Responsibilities.. 8

    9 Cancelled Quality Notifications.. 10

    Appendix A - Quality Issues Reporting Process 11

    Appendix B - Contractors Internal NCR. 12

    Appendix C - Quality Issues Escalation Matrix.. 13

    Appendix D - Examples of Violations and Escalation Steps... 14

    Appendix E - Responsibilities for Quality Issue Notification... 16

    Appendix F - Index.... 17

  • Document Responsibility: Inspection Engineering Standards Committee SAEP-381

    Issue Date: 17 March 2013

    Next Planned Update: 28 January 2017 Project Quality Issues Escalation Process

    Page 2 of 17

    1 Scope

    1.1 This Procedure establishes instructions for escalation of unresolved quality issues

    in Saudi Aramco projects including delinquent quality concern notifications.

    1.2 This SAEP does not apply to:

    Escalation of non-conformities identified by Operation Inspection Division

    (OID) during assessments of Operation Inspection Units (OIUs) in operating

    facilities.

    Deficiencies noted during internal assessments by the Inspection Department.

    Deficiencies noted during Health Checks conducted by APMID for Asset

    Performance Management (APM).

    2 Purpose

    2.1 The purpose of this SAEP is to:

    2.1.1 Implement a consistent method for escalating quality issues including

    Logbook Entries (LBEs), Non-Conformance Reports (NCRs),

    Worksheets (WSs) and Delinquent Worksheets (DWSs), as defined in

    Appendix A, Quality Issues Reporting Process.

    2.1.2 Clearly define the corporate process for project quality issue escalation

    including its documentation, requirements and definition of violation

    categories, systems and procedures.

    2.1.3 Ensure roles and responsibilities for project quality issue escalation are

    well defined and auditable.

    2.2 The intent of quality issue notification is to report and record quality or technical

    deficiencies, determine the root cause of the problem, record the actions taken to

    correct non-conformities, avoid recurrence and enhance overall project quality.

    3 Conflicts and Deviations

    3.1 Any conflict between this procedure and other applicable Mandatory Saudi

    Aramco Engineering Requirement (MSAER) shall be resolved in writing

    through the Chairman, Inspection Engineering Standards Committee (IESC).

    3.2 Direct all requests to deviate from this procedure in writing to the Manager,

    Inspection Department of Saudi Aramco, Dhahran.

  • Document Responsibility: Inspection Engineering Standards Committee SAEP-381

    Issue Date: 17 March 2013

    Next Planned Update: 28 January 2017 Project Quality Issues Escalation Process

    Page 3 of 17

    4 Applicable Documents

    The applicable requirements in the latest edition of the following Saudi Aramco

    Engineering Procedures, Schedule Q and General Instructions (GIs) shall be considered an integral part of this procedure.

    Saudi Aramco Engineering Procedures

    SAEP-301 Instruction for Establishing and Maintaining Saudi

    Aramco Engineering Requirements

    SAEP-302 Instructions for Obtaining a Waiver of a Mandatory Saudi

    Aramco Engineering Requirement

    SAEP-379 Quality Issues Notification

    SAEP-380 Equipment Deficiency Report

    SAEP-1150 Inspection Coverage on Projects

    SAEP-1151 Inspection Requirements for Contractor Procured

    Materials and Equipment

    Contract Schedule Q Quality Requirements

    Saudi Aramco General Instruction

    GI-0400.001 Quality Management Roles and Responsibilities

    GI-0002.710 Mechanical Completion and Performance Acceptance of

    Facilities

    5 Definitions

    ACD: Agreed Completion Date

    APM: Asset Performance Management

    APMID: Asset Performance Management Integration Division

    DWS: DELINQUENT WORKSHEET - Mechanism to escalate unresolved Worksheets

    CQP: Contractor Quality Personnel

    CQR: Contractor Quality Representative

    INCR: Internal Non Conformance Report (Issued by Contractor)

    LBE: Logbook Entries (First level of reporting quality deficiency using Manual

    Logbook or the Quality Management Information System, QMIS)

  • Document Responsibility: Inspection Engineering Standards Committee SAEP-381

    Issue Date: 17 March 2013

    Next Planned Update: 28 January 2017 Project Quality Issues Escalation Process

    Page 4 of 17

    MCC: Mechanical Completion Certificate

    MPCS: Mechanical Performance and Close-out System

    MSAER: Mandatory Saudi Aramco Engineering Requirements

    Non-Conformities Escalation: A structured mechanism to progressively escalate

    pending quality and technical deficiencies to the concerned management.

    NCR: Non Conformance Report (Issued by Saudi Aramco through SAP QM).

    Project Quality Manager (PQM): The Senior Inspection Representative responsible

    for coordinating all inspection requirements on behalf of Inspection Department with

    SAPMT throughout all project phases, from Project Proposal up to Mechanical

    completion.

    QMIS: Quality Management Information System (also known as electronic Inspection

    Logbook).

    Repeat Violation: A non-compliance of the same MSAER, project specifications or

    standard drawings in the same activity area, that occurred more than once within

    six (6) months.

    SAPMT: Saudi Aramco Project Management Team

    SAP QM: Systems, Applications and Products in Data Processing-Quality Module

    Technical Deficiencies: Non-compliance to any MSAER or project specifications

    Worksheet: Mechanism for reporting major violations or escalating pending valid

    NCRs as stipulated in this Procedure.

    6 Violations Definitions

    MAJOR (If any one of the following applies)

    1) Violations of company standards including GIs that put the quality and integrity of

    the facility including its workers and equipment at risk.

    2) Actions that violate the Corporate values by submitting forged items & counterfeit

    materials.

    MODERATE (If any one of the following applies)

    1) Any violation to MSAER, project specifications and approved IFC drawings that if

    the next phase of work (critical path) is continued without correcting the violation,

  • Document Responsibility: Inspection Engineering Standards Committee SAEP-381

    Issue Date: 17 March 2013

    Next Planned Update: 28 January 2017 Project Quality Issues Escalation Process

    Page 5 of 17

    the structural integrity of the next phase will be jeopardized. Such violation if not

    corrected in a timely manner will lead to more severe damage or complexity.

    2) Any violation to Schedule Q.

    Commentary Note:

    Minor violations related to Schedule Q listed in Appendix D are excluded from this definition.

    3) If the violation will be categorized YES item as defined in GI-0002.710 during the partial MCC stage.

    MINOR (If any one of the following applies)

    1) Any violation to SAES, SAMSS, project specifications and approved IFC drawings

    but the next phase of work is not dependent on the correction of the violation.

    2) If the violation will be categorized as NO item as defined in GI-0002.710 during the partial MCC stage.

    7 Instructions

    7.1 Quality Issues Notification

    7.1.1 Quality or technical deficiencies shall be reported in a timely manner

    through QMIS for LBE, or SAP QM (NCR or WS) depending on the

    identified violation as defined in Section 6.

    7.1.2 Potential non-conforming materials, products or work shall be pro-

    actively highlighted through the QMIS to avoid re-work.

    7.1.3 A letter of concern signed by the PID Superintendent shall be addressed

    to the Department Head of the MCC/PMCC Chairman whenever

    MCC/PMCCs are approved in the MPCS without ID signature due to

    converted and unresolved YES items for other Organizations. This letter shall be copied to ID and PMT Department Managers.

    7.1.4 A letter of concern signed by the ID Manager shall also be addressed to

    the Manager of the MCC/PMCC Chairman whenever MCC/PMCCs are

    approved in the MPCS system and IDs YES items are converted to NO without obtaining IDs agreement. This letter shall be copied to Proponent VP, ES VP and PM VP.

    7.1.5 A letter of concern signed by the ES Chief Engineer shall be addressed

    to the Admin Area head of the MCC/PMCC Chairman whenever a

    Facility is commissioned without Inspection Departments

  • Document Responsibility: Inspection Engineering Standards Committee SAEP-381

    Issue Date: 17 March 2013

    Next Planned Update: 28 January 2017 Project Quality Issues Escalation Process

    Page 6 of 17

    review/signature on the MCC/PMCC. This letter shall be copied to

    Internal Auditing, ES VP and PM VP.

    7.1.6 Starting a project which excludes ANY Mandatory Saudi Aramco

    Engineering Requirement (MSAER), without securing the required

    waiver approved by applicable management level authority shall be

    issued a Worksheet.

    7.1.7 Initiators, approvers and other interested parties of quality issue

    notifications shall be in accordance with Appendix E, Table of Responsibilities for Quality Issue Notification.

    7.1.8 Third Delinquent Worksheet (DWS3) shall be copied to Internal

    Auditing for their follow-up action.

    7.2 Agreed Completion Date (ACD) for LBEs, NCRs and Worksheets

    7.2.1 PID PQM, SAPMT Senior Project Engineer or Lead Project Engineer and

    the Contractor Quality Representative are responsible for determining the

    initial Agreed Completion Date (ACD) for LBEs, NCRs and Worksheets.

    7.2.2 When no agreement on the ACD of any type/category of Quality

    Notification could be reached, the ACD shall be decided mutually by the

    next level of authority from ID and PMT, depending on the Quality

    Notification category.

    7.2.3 If an extension of ACD is justified and mutually agreed by ID & PMT

    representatives, one-time basis approval of ACD extension is allowed.

    If no agreement of the new ACD is reached by the ID and PMT initiators

    and approvers, the ACD shall be established by the next higher signature

    level(s) per the below matrix.

    Quality Notification Type ID Rep PMT Rep

    Contractors Internal NCR ID Field Supvr PMT Project Engineer

    Logbook Entry (LBE) ID Field Supvr PMT Project Engineer

    NCR ID Unit Supervisor PMT Sr. Project

    Engineer

    Worksheet ID PQM PMT Project Manager

    In case a conflict on establishing the ACD continues, the PMT Department

    Manager shall make the final decision.

  • Document Responsibility: Inspection Engineering Standards Committee SAEP-381

    Issue Date: 17 March 2013

    Next Planned Update: 28 January 2017 Project Quality Issues Escalation Process

    Page 7 of 17

    7.3 Handling of Contractors Internal NCR

    7.3.1 Saudi Aramco strongly encourages all Contractors to take advantage of

    all opportunities to enhance their quality management system

    implementation and to fully utilize their internal QA/QC system towards

    a high project quality delivery.

    7.3.2 ID shall initiate escalation if a Contractor does not act to correct

    quality/technical non compliances within the mutually agreed ACD.

    7.3.3 To encourage Contractors QC Team to implement their internal quality management system effectively, the Contractors recommended completion date shall be accepted, unless found unreasonable by PMT

    project engineer and the ID Field Supervisor.

    7.3.4 When the Contractors QC personnel report and document a quality non-compliance, ID shall follow the work process per Appendix B,

    Contractors Internal NCR.

    7.3.5 When an Internal NCR has been issued by the Contractors QC, Saudi Aramco quality notification shall be recorded by PID in the General Comments category of the QMIS, for the purpose of Lessons Learned collection. The QMIS entry shall be closed when the internal NCR is

    completed or when escalated to SA NCR due to non-compliance within

    the ACD.

    7.4 Clarifications to Appendix D Examples of Violations and Escalation Steps

    7.4.1 Clearance of Unavailability of approved Contractor QA Manager or Contractor QC Manager" in Appendix D shall be based on actual

    mobilization at the project site of the approved Contractor QA Manager

    or QC Manager and not just submission or approval of resumes. Absence of an already approved and mobilized Contractor QA/QC

    Manager, due to verified emergency leave could be exempted by the

    PQM provided that the leave of absence shall not be more than seven (7)

    calendar days without an approved replacement.

    7.4.2 Clearance of Insufficient QC Manpower (Deficiency > 10% of Plan) in Appendix D shall also be based on actual mobilization of the approved

    Contractor QC personnel at the project site, and not just submission or

    approval of resumes.

    7.5 Non-Conformities Escalation Process

    7.5.1 Escalation processes shall be in accordance with Appendix C, Quality Issues Escalation Matrix.

  • Document Responsibility: Inspection Engineering Standards Committee SAEP-381

    Issue Date: 17 March 2013

    Next Planned Update: 28 January 2017 Project Quality Issues Escalation Process

    Page 8 of 17

    7.5.2 Logbook Entries (LBEs) shall be made for deficiencies defined as

    Minor.

    LBEs shall be made through the QMIS or Manual logbook. (Manual

    logbook entry shall be done only in exceptional cases and shall have

    prior approval by the relevant Division Head.

    7.5.3 Repeat of Moderate or Major violation within six (6) months will result

    to a Quality Notification starting at the next higher level of Violation

    Category and Notification. Repeat of a Minor violation due to

    negligence shall be considered as Moderate violation.

    7.5.4 Repeated Internal Non-Conformance Report (INCR) within six (6)

    months shall be, as in Appendix B, Contractors Internal NCR:

    7.5.4.1 Escalated to SA NCR if the Contractor failed to Report the

    Repeated INCR

    7.5.4.2 Escalated to Violation-after-the-fact Entry in the QMIS if the

    contractor has detected and reported the Repeated INCR

    7.5.5 Valid NCR shall be escalated to a Worksheet (WS) when any of the

    following applies:

    7.5.5.1 Valid NCR is not corrected or completed on the ACD

    (including the extension period, if extension is approved)

    7.5.5.2 Valid NCR issued by Inspection Department is not approved

    by SAPMT within five (5) working days

    7.5.6 A Worksheet that was not resolved on or before the ACD, including the

    approved extension period (if extension is approved), shall be escalated

    to Delinquent Worksheet, after discussing and notifying the relevant

    PMT representative.

    7.5.7 Once the project reaches its MCC stage, all open LBEs, NCRs,

    Worksheets and DWS shall be transferred to MPCS. Items required for

    start-up or impacting safety are to be marked as YES Items. All other items shall be designated as No Items.

    8 Responsibilities

    8.1 Project Inspection Division Head

    8.1.1 Reviews and approves or rejects PMT request to extend ACD for

    Worksheets

  • Document Responsibility: Inspection Engineering Standards Committee SAEP-381

    Issue Date: 17 March 2013

    Next Planned Update: 28 January 2017 Project Quality Issues Escalation Process

    Page 9 of 17

    8.1.2 Approves Worksheets issued by the PQM/Sr. Supervisor

    8.1.3 Initiates issuance of Delinquent Worksheet (DWS1)

    8.1.4 Reviews and approves or rejects the deletion of SAP notifications

    8.2 Project Quality Manager (PQM) or Senior Supervisor

    8.2.1 PQM may initiate issuance of Non-Conformance Reports (NCRs) in lieu

    of Field Supervisor

    8.2.2 Initiates issuance of Worksheet (WS)

    8.2.3 Reviews and may grant one-time approval of ACD extension prior to

    escalation of valid NCR

    8.2.4 Decides cases of violations not clearly defined in Section 6 and not listed

    in Appendix D Examples of Violations and Escalation Steps

    8.2.5 Performs quality roles and responsibilities defined in this SAEP,

    GI-0400.001 Quality Management Roles and Responsibilities and GI-0002.710 Mechanical Completion and Performance Acceptance of Facilities

    8.3 Project Inspector or Field Supervisor

    8.3.1 Highlights to SAPMT any potential non-conforming material, product or

    work through the QMIS to avoid re-work.

    8.3.2 Reports in a timely manner any quality or technical deficiency through

    the QMIS or SAP QM (LBE or NCR) depending on the committed

    violations as defined in Section 6 and categorized in Appendix C,

    Quality Issues Escalation Matrix

    8.3.3 Field Supervisor may initiate issuance of Non-Conformance Reports

    (NCRs) in lieu of Project Quality Manager (PQM)

    8.4 SAPMT

    8.4.1 Ensures project full compliance with SAEP-302, Instructions for Obtaining a Waiver of a Mandatory Saudi Aramco Engineering

    Requirement

    8.4.2 Approves valid NCRs initiated by Inspection Department within five (5)

    working days

  • Document Responsibility: Inspection Engineering Standards Committee SAEP-381

    Issue Date: 17 March 2013

    Next Planned Update: 28 January 2017 Project Quality Issues Escalation Process

    Page 10 of 17

    8.4.3 Performs quality roles and responsibilities defined in this SAEP,

    GI-0400.001 Quality Management Roles and Responsibilities and GI-0002.710 Mechanical Completion and Performance Acceptance of Facilities

    9 Cancelled Quality Notifications

    Submitted quality notifications in SAP QM shall not be marked for deletion without

    proper justification approved by PID Division Head. The approved justification shall

    be attached in the quality notification being marked for deletion.

    Revision Summary

    28 January 2012 New Saudi Aramco Engineering Procedure. 17 March 2013 Minor revision to provide clarification on selected sections.

  • Document Responsibility: Inspection Engineering Standards Committee SAEP-381

    Issue Date: 17 March 2013

    Next Planned Update: 28 January 2017 Project Quality Issues Escalation Process

    Page 11 of 17

    Appendix A - Quality Issues Reporting Process

  • Document Responsibility: Inspection Engineering Standards Committee SAEP-381

    Issue Date: 17 March 2013

    Next Planned Update: 28 January 2017 Project Quality Issues Escalation Process

    Page 12 of 17

    Appendix B Contractors Internal NCR

    Contractors INCR

    PID to Initially record

    INCR in the General

    Comments of QMIS,

    marked as For Info

    Moderate

    Or

    Major

    Violation?

    Repeat INCR?

    w/in 6 Months

    Yes

    Repeat Minor

    INCR?

    w/in 6 months

    No

    Yes

    No

    Escalate INCR into

    SA-NCR, then

    Close INCR & QMIS

    Yes

    Follow the

    Quality Issue

    Reporting

    Process

    Close INCR & QMIS

    Change QMIS entry

    to Violation-after-the fact

    Completed on

    ACD?

    No

    Yes

    Completed

    on Extension

    Date?

    Yes

    One-time

    extension

    granted?

    No

    No

    No

    One-time

    extension

    granted?

    No

    Completed on

    Extension date?

    Completed on

    ACD?

    No

    Yes

    Yes

    Yes

    Yes

    No

    Reported by

    Contractor?

    Yes

    No

  • Document Responsibility: Inspection Engineering Standards Committee SAEP-381

    Issue Date: 17 March 2013

    Next Planned Update: 28 January 2017 Project Quality Issues Escalation Process

    Page 13 of 17

    Appendix C - Quality Issues Escalation Matrix

    Violation

    Type

    1st

    Notification

    ESCALATION STAGES

    1 2 3 4 5

    Minor LBE NCR WS DWS1 DWS2 DWS3

    Moderate NCR WS DWS1 DWS2 DWS3 -

    Major WS DWS1 DWS2 DWS3 - -

  • Document Responsibility: Inspection Engineering Standards Committee SAEP-381

    Issue Date: 17 March 2013

    Next Planned Update: 28 January 2017 Project Quality Issues Escalation Process

    Page 14 of 17

    Appendix D - Examples of Violations and Escalation Steps

    ESCALATION MATRIX

    Recommended Phase for Proactive Notification

    Violation Category S/N Sample Violation

    1. Forged Quality Documents Job X/Kick-off/Weekly QC Meetings

    Major

    2.

    Procurement and/or Installation of counterfeit materials classified as inspectable per SAEP-1151

    Note: For non-inspectable materials, PQM decides on the initial Violation Category

    Job X/Kick-off/Weekly QC Meetings

    Major

    3.

    Starting a project which excludes ANY Mandatory Saudi Aramco Engineering Requirement (MSAER), without securing the required waiver approved by applicable management level authority.

    Job X/Kick-off Meetings Major

    4. Unavailability of approved Contractor QA Manager or Contractor QC Manager

    Job X/Kick-off Meetings/ Weekly QC Meetings

    Moderate

    5. Commencing of Special Process activity as specified in Schedule Q without approved procedures/personnel

    Job X/Kick-off/Weekly QC Meetings

    Moderate

    6. Concrete or Asphalt placement without pre-approval of the batching plant or mix design

    Kick off Meetings/Weekly QC meetings Moderate

    7. Use of non-approved third party service providers Kick off Meetings/Weekly QC meetings Moderate

    8.

    Starting work without IFC Drawings or not submitting required Quality Documents as per Schedule Q

    Note: Categorization is PQM discretion

    Kick off Meetings/Weekly QC meetings

    Moderate

    Minor

    9. Placing RVL/Inspectable materials and equipment with unapproved source

    Kick off Meetings/Weekly QC meetings

    Moderate

    10. Carrying out modification work on accepted systems (PROCESS-RELATED) without SA approval

    Kick off Meetings/Weekly QC meetings

    Moderate

    11.

    Preservation and Storage of equipment and materials classified as Inspectable per SAEP-1151 that are not in accordance with the approved quality plan and schedule Q

    Note: Categorization is PQM Discretion

    Kick off Meetings/Weekly QC meetings

    Moderate

    Minor

    12. Contractors Internal NCR not resolved at the approved completion date

    Kick off Meetings / Weekly QC meetings

    Moderate

    13.

    Failure of the Contractor to control and implement the quality requirements of its batch plants, subcontractors and other service providers as required per Schedule Q. (e.g., Not assigning his own QC inspectors at the manufacturer and service provider locations per Schedule Q, and relying only on the In-House QC)

    Kick off Meetings / Weekly QC meetings

    Moderate

    14. Contractor failure to conduct complete quality system audits per Schedule Q requirements

    Kick off Meetings / Weekly QC meetings

    Moderate

  • Document Responsibility: Inspection Engineering Standards Committee SAEP-381

    Issue Date: 17 March 2013

    Next Planned Update: 28 January 2017 Project Quality Issues Escalation Process

    Page 15 of 17

    ESCALATION MATRIX

    Recommended Phase for Proactive Notification

    Violation Category S/N Sample Violation

    15.

    Contractor failure to conduct the 6-months Management Review Meetings and submit the results/recommendations to Saudi Aramco at the prescribed time

    Kick off Meetings / Weekly QC meetings

    Moderate

    16. Insufficient QC Manpower (Deficiency > 10% of Plan)

    Job X / Kick-off Meetings/ Weekly QC Meetings

    Moderate

    17.

    Contractor failure to perform/implement inspection per approved ITP without adequate notification or justification (HOLD POINT activities)

    Kick off Meetings / Weekly QC meetings

    Moderate

    18.

    Contractor failure to perform/implement inspection per approved ITP without adequate notification or justification (Witness Point activities)

    Kick off Meetings / Weekly QC meetings

    Minor

    19.

    QC Personnel on part time basis, either routinely performing non-QC functions or covering QC jobs in a different geographical location without prior approval of the ID Area Field Supervisor

    Job X / Kick-off / Weekly QC Meetings

    Minor

    20. Insufficient QC Manpower (Deficiency < 10% of Plan) Job X / Kick-off Meetings Minor

    21.

    Failure to submit, incomplete, poor quality or late submittal of the required weekly or monthly deliverables as required by Schedule Q

    Kick off Meetings / Weekly QC meetings

    Minor

    22.

    Poor or incomplete quality submittals or documentations

    Note: PQM has the option to increase this category as

    MAJOR if the submittals are for critical activities such as hydro test package of oil & gas facilities

    Kick off Meetings / Weekly QC meetings

    Minor

    23.

    Poor, late or incomplete submission of the required weekly or monthly deliverables/documentations as required by Schedule Q

    Note: PQM has the option to increase this category as MAJOR if the submittals are for critical activities such as hydro test package of oil & gas facilities

    Kick off Meetings / Weekly QC meetings

    Minor

    24.

    Failure to submit the required weekly or monthly deliverables/documentations as required by Schedule Q

    Note: PQM has the option to increase this category as MAJOR if the submittals are for critical activities such as hydro test package of oil & gas facilities

    Kick off Meetings / Weekly QC meetings

    Minor

    Legend:

    L = e-Log Book entry

    N = Non-Conformance Report (Q8 Notification)

    W = Worksheet (Q9 Notification)

  • Document Responsibility: Inspection Engineering Standards Committee SAEP-381

    Issue Date: 17 March 2013

    Next Planned Update: 28 January 2017 Project Quality Issues Escalation Process

    Page 16 of 17

    Appendix E - Table of Responsibilities for Quality Issue Notification

    Responsible Initiator / Issuer Approver Recipient /

    Addressed To Interested/Copied Parties

    NCR Field Supervisor/ PQM

    Project Engineer / Sr. Project Engineer

    PM Representative

    Division Head, PID

    Division Head, PM

    Project Manager

    Proponent Site Rep.

    Worksheet PQM/ID Sr. Supervisor

    Division Head, PID Department Manager, PM

    General Manager, PM

    Sr. Project Engineer

    Department Manager, ID

    Division Head, PM

    Proponent Site Rep.

    DWS1 PID Division Head

    Department Manager, ID

    General Manager, PM

    Vice President, PM

    Vice President, ES

    Chief Engineer

    Project Manager

    Dept. Managers, PMT & Proponent

    DWS2 ID Manager Chief Engineer Vice President, PM

    Vice President, ES

    General Manager, PM

    General Auditor

    Dept. Managers, PMT & Proponent

    PID Division Head

    DWS3 Chief Engineer Vice President, ES Sr. Vice President, E&PM

    Vice President, PM

    General Manager, PMT

    General Auditor

    Project Manager

    ID Manager

    Dept. Managers, PMT & Proponent

  • Document Responsibility: Inspection Engineering Standards Committee SAEP-381

    Issue Date: 17 March 2013

    Next Planned Update: 28 January 2017 Project Quality Issues Escalation Process

    Page 17 of 17

    Appendix F - Index

    1 Scope.. 2

    2 Purpose.. 2

    3 Conflicts and Deviations.. 2

    4 Applicable Documents.. 3

    5 Definitions... 3

    6 Violations Definitions 4

    7 Instructions. 5

    8 Responsibilities. 8

    9 Cancelled Quality Notifications. 10

    Appendix A Quality Issues Reporting Process... 11

    Appendix B Contractors Internal NCR 12

    Appendix C Quality Issues Escalation Matrix. 13

    Appendix D Examples of Violations and Escalation Steps... 14

    Appendix E Responsibilities For Quality Issue Notification... 16

    Appendix F Index 17