safety_evaluation_of_a_25m_high_cfrd.pdf

2
1 Safety Evaluation of a CFRD in Japan Yoshikazu YAMAGUCHISpeakerDr. of Eng, Principal Researcher (Team Leader) Dam Structures Research Team, Public Works Research Institute, Japan 1. INTRODUCTION The first full-scale introduction of a modern CFRD undertaken in Japan as a permanent structure is the saddle dam at the Tomata Dam operated by the Chugoku Regional Development Bureau of the Ministry of Land, Infrastructure and Transport, Government of Japan. The construction of the dam was accompanied by detailed studies on the design and execution of modern CFRDs. A typical cross section and a profile of the Tomata Saddle Dam are described in Fig. 1. To examine safety of the Tomata Saddle Dam, seepage/leakage and deformation have been measured with gauges and sensors. This report presents the safety evaluation of the Tomata Saddle Dam based on the measured results of seepage/ leakage through the body and its rock foundation, settlement of the dam body and deflection of a toe slab, that were carried out during the first filling of the Tomata Dam reservoir. 2. INSTRUMENTATION 2.1 OUTLINE OF MEASUREMENTS Fig. 2 shows the purpose of the measurements at the Tomata Saddle Dam: 1) construction management during embanking, 2) safety management after completion, and 3) data acquisition for future design and research. In this paper, we will introduce measurements for safety management of the Tomata Saddle Dam concerning seepage and deformation. 2.2 MEASUREMENT OF LEAKAGE/SEEPAGE Measurements of leakage/seepage through the dam body and its foundation were conducted by dividing the dam body into five zones, and collecting the water in a measuring pit downstream from the drainage pipe as shown in Fig. 3. Newly developed leakage detective sensors were installed in the slabs [1]. The leakage detective sensor applies electrical pulses to a twin-lead cable and observes the reflected waves to detect the location of leakage. Fig.4 shows the appearance of the leakage detective sensor. Fig.5 shows the leakage observation locations. The sensors were installed in the F11 slab, which is the longest slab in the Tomata Saddle Dam. 2.3 MEASUREMENT OF DEFORMATION Measuring points were installed on surface of the dam to measure the exterior deformation, that is, horizontal and vertical deformations. The deformation of CFRDs under water load is often measured by the face deflection. At the Tomata Saddle Dam, the face deflection was measured by the newly developed slide-type inclinometer on the longest slab, F11. Drain layer Rock zone 2 Special transition zone Rock zone 1 Upstream side Downstream side Fig. 1 Typical cross section and profile of Tomata Saddle Dam Construction management in embankment Deformation of dam body Earth pressure Examination of safety for seepage Seepage / leakage Pore water pressure in foundation Measurement Safety management After completion Examination of safety for deformation Deformation of main and toe slabs Exterior deformation of dam body Interior deformation of dam body Data acquisition for design and research Deformation of main and toe slabs Interior deformation of dam body Earth pressure Dynamic measurement Fig. 2 Purpose of measurements at Tomata Saddle Dam L1 L2 L3 L4 L5 Downstream side Upstream side Flume Fig. 3 Plane layout of seepage/leakage drainage pipes Pervious textile Impervious part Twin-lead cable (conductor) (Appearance of sensor) (Sensor section) Fig. 4 Leakage detective sensor 13mm Type CFRD Height 25.00 m Crest length 259.00 m Crest width 10.00 m Slope Upstream 1:2.00 Downstream 1:2.00

Upload: tansel-yilmaz

Post on 10-Nov-2015

212 views

Category:

Documents


0 download

TRANSCRIPT

  • 1

    SSaaffeettyy EEvvaalluuaattiioonn ooff aa CCFFRRDD iinn JJaappaann

    Yoshikazu YAMAGUCHISpeaker Dr. of Eng, Principal Researcher (Team Leader)

    Dam Structures Research Team, Public Works Research Institute, Japan 1. INTRODUCTION

    The first full-scale introduction of a modern CFRD undertaken in Japan as a permanent structure is the saddle dam at the Tomata Dam operated by the Chugoku Regional Development Bureau of the Ministry of Land, Infrastructure and Transport, Government of Japan. The construction of the dam was accompanied by detailed studies on the design and execution of modern CFRDs.

    A typical cross section and a profile of the Tomata Saddle Dam are described in Fig. 1. To examine safety of the Tomata Saddle Dam, seepage/leakage and deformation have been measured with

    gauges and sensors. This report presents the safety

    evaluation of the Tomata Saddle Dam based on the measured results of seepage/ leakage through the body and its rock foundation, settlement of the dam body and deflection of a toe slab, that were carried out during the first filling of the Tomata Dam reservoir. 2. INSTRUMENTATION 2.1 OUTLINE OF MEASUREMENTS

    Fig. 2 shows the purpose of the measurements at the Tomata Saddle Dam: 1) construction management during embanking, 2) safety management after completion, and 3) data acquisition for future design and research.

    In this paper, we will introduce measurements for safety management of the Tomata Saddle Dam concerning seepage and deformation. 2.2 MEASUREMENT OF LEAKAGE/SEEPAGE

    Measurements of leakage/seepage through the dam body and its foundation were conducted by dividing the dam body into five zones, and collecting the water in a measuring pit downstream from the drainage pipe as shown in Fig. 3.

    Newly developed leakage detective sensors were installed in the slabs [1]. The leakage detective sensor applies electrical pulses to a twin-lead cable and observes the reflected waves to detect the location of leakage.

    Fig.4 shows the appearance of the leakage detective sensor.

    Fig.5 shows the leakage observation locations. The sensors were installed in the F11 slab, which is the longest slab in the Tomata Saddle Dam. 2.3 MEASUREMENT OF DEFORMATION

    Measuring points were installed on surface of the dam to measure the exterior deformation, that is, horizontal and vertical deformations.

    The deformation of CFRDs under water load is often measured by the face deflection. At the Tomata Saddle Dam, the face deflection was measured by the newly developed slide-type inclinometer on the longest slab, F11.

    DDrraaiinn llaayyeerr

    RRoocckk zzoonnee 22 Special transition zone

    RRoocckk zzoonnee 11

    UUppssttrreeaamm ssiiddee

    DDoowwnnssttrreeaamm ssiiddee

    FFiigg.. 11 TTyyppiiccaall ccrroossss sseeccttiioonn aanndd pprrooffiillee ooff TToommaattaa SSaaddddllee DDaamm

    Construction management in embankment Deformation of dam body Earth pressure

    Examination of safety for seepage Seepage / leakage Pore water pressure in foundation

    Measurement Safety management After completion

    Examination of safety for deformation Deformation of main and toe slabs Exterior deformation of dam body Interior deformation of dam body

    Data acquisition for design and research

    Deformation of main and toe slabs Interior deformation of dam body Earth pressure Dynamic measurement

    FFiigg.. 22 PPuurrppoossee ooff mmeeaassuurreemmeennttss aatt TToommaattaa SSaaddddllee DDaamm

    LL11

    LL22

    LL33 LL44

    LL55

    Downstream side

    Upstream side

    Flume

    FFiigg.. 33 PPllaannee llaayyoouutt ooff sseeeeppaaggee//lleeaakkaaggee ddrraaiinnaaggee ppiippeess

    Pervious textile Impervious part

    Twin-lead cable (conductor)

    ((AAppppeeaarraannccee ooff sseennssoorr))

    ((SSeennssoorr sseeccttiioonn))

    FFiigg.. 44 LLeeaakkaaggee ddeetteeccttiivvee sseennssoorr

    13m

    m

    Type CFRD

    Height 25.00 m

    Crest length 259.00 m Crest width 10.00 m

    Slope Upstream 1:2.00 Downstream 1:2.00

  • 2

    3. RESULTS OF MEASUREMENT AND SAFETY EVALUATION 3.1 SEEPAGE/LEAKAGE

    Fig. 6 shows the results of observations of seepage/leakage, reservoir water level, and rainfall. Seepage/leakage at the saddle dam ranged from 3.7 to 27.6 /min. The highest seepage/leakage observed was from 2.4 to 20.2 /min. at L-4. Inversely, at 0.1 /min., there was almost no leakage at L-1. The average of the observed seepage/leakage at the other drainage pipes was only 2 /min.

    Temporarily high leakage occurred under the effects of rainfall, but at other times, its behavior was linked to fluctuation of the reservoir water level.

    Considering the seepage/leakage by omitting the impact of the base flow (approx. 4 /min.) and of rainfall, the quantity produced by the reservoir is no higher than 20 /min., an extremely low value.

    020406080

    100

    Prec

    ipita

    tion

    (mm

    /day

    )

    0

    10

    20

    30

    10/16 10/27 11/7 11/18 11/29 12/10 12/21 1/1 1/12

    Seep

    age

    quan

    tity

    (l/m

    in.)

    170

    180

    190

    200

    210

    220

    230

    240R

    eser

    voir

    wat

    er le

    vel (

    El. m

    )L - Total L-1 L-2 L-3 L-4 L-5 Reservoir water level

    FFiigg.. 66 MMeeaassuurreedd rreessuullttss ooff sseeeeppaaggee//lleeaakkaaggee,, rreesseerrvvooiirr lleevveell,, aanndd rraaiinnffaallll

    The measured results by the leakage defective sensors installed in the face slab F11 revealed the absence

    of leakage caused by cracks in the slab. 3.2 DEFORMATION

    The measured settlement at the top of the typical cross section of the dam was only 1.0cm during the first filling of reservoir. And the maximum deflection of the slab measured at EL.229.7m, which is the surcharge water level, was only 0.4cm. These valves of deformation are very small. 4. CONCLUSIONS

    The results of overall evaluations including the results of measurements of seepage/leakage, deformation/deflection and of visual inspections confirm the safety of the Tomata Saddle Dam, which is the first full-scale modern CFRD in Japan. REFERENCE [1] Yamaguchi, Y. and Kobori, T. (2004): Development of Leakage Detective Sensor for Face Slab of CFRDs. ICOLD 72nd Annual

    Meeting Workshop, W1-26-A011 (CD-Rom).

    FFiigg.. 55 LLeeaakkaaggee ddeetteeccttiivvee sseennssoorrss iinnssttaalllleedd iinn FF1111 ssllaabb

    SSeennssoorr ccaabbllee

    FF1111 ssllaabb

    :Leakage detective system

    F11 slab

    Main sensor cable

    Top of dam

    Sub sensor cable

    Toe of dam