Page 1: SALTON SEA MANAGEMENT PROGRAM PHASE I: 10-YEAR PLAN ...resources.ca.gov/CNRALegacyFiles/wp-content/... · 2 OVERVIEW State Obligations under the SSMP What is the Phase I ten-year

1

Public WorkshopJune – July, 2017

SALTON SEA MANAGEMENT PROGRAMPHASE I: 10-YEAR PLAN IMPLEMENTATION

http://resources.ca.gov/salton-sea/

Page 2: SALTON SEA MANAGEMENT PROGRAM PHASE I: 10-YEAR PLAN ...resources.ca.gov/CNRALegacyFiles/wp-content/... · 2 OVERVIEW State Obligations under the SSMP What is the Phase I ten-year

2

OVERVIEW State Obligations under the SSMP

What is the Phase I ten-year plan?

Our Partners

Our Projects

Implementation Plan

Air Quality

Future plans: area of focus, schedule, and funding

Page 3: SALTON SEA MANAGEMENT PROGRAM PHASE I: 10-YEAR PLAN ...resources.ca.gov/CNRALegacyFiles/wp-content/... · 2 OVERVIEW State Obligations under the SSMP What is the Phase I ten-year

3

Legislative

Contractual

Section 2940 Fish and Game Code

Salton Sea Task Force

CNRA and DOI Memorandum of Understanding (MOU)

STATE OBLIGATIONS UNDER SSMP

Page 4: SALTON SEA MANAGEMENT PROGRAM PHASE I: 10-YEAR PLAN ...resources.ca.gov/CNRALegacyFiles/wp-content/... · 2 OVERVIEW State Obligations under the SSMP What is the Phase I ten-year

4

Phase I of SSMP

Meet Task Force goals by 2028

Concentrate design and construction for habitat and dust mitigation

Implement longer term solution at the Sea Enhance coordination among stakeholders

SSMP PHASE I TEN YEAR PLAN

Page 5: SALTON SEA MANAGEMENT PROGRAM PHASE I: 10-YEAR PLAN ...resources.ca.gov/CNRALegacyFiles/wp-content/... · 2 OVERVIEW State Obligations under the SSMP What is the Phase I ten-year

5

Page 6: SALTON SEA MANAGEMENT PROGRAM PHASE I: 10-YEAR PLAN ...resources.ca.gov/CNRALegacyFiles/wp-content/... · 2 OVERVIEW State Obligations under the SSMP What is the Phase I ten-year

6

Current projects New River East – (SCH) Red Hill Bay Torres Martinez/SSA Wetland

Proposed 2018 and 2019 New River West Whitewater River

NEAR-TERM DESIGN & CONSTRUCTION

Page 7: SALTON SEA MANAGEMENT PROGRAM PHASE I: 10-YEAR PLAN ...resources.ca.gov/CNRALegacyFiles/wp-content/... · 2 OVERVIEW State Obligations under the SSMP What is the Phase I ten-year

7

New River East

New River West

Page 8: SALTON SEA MANAGEMENT PROGRAM PHASE I: 10-YEAR PLAN ...resources.ca.gov/CNRALegacyFiles/wp-content/... · 2 OVERVIEW State Obligations under the SSMP What is the Phase I ten-year

8

SPECIES CONSERVATION HABITAT (SCH) PHASE 1

Page 9: SALTON SEA MANAGEMENT PROGRAM PHASE I: 10-YEAR PLAN ...resources.ca.gov/CNRALegacyFiles/wp-content/... · 2 OVERVIEW State Obligations under the SSMP What is the Phase I ten-year

9

Geothemal accessBuried water pipelineBerms (of various size)

Water surface elevationWater movementIsland

0 0.25 0.50 0.75 1.0 km

N

Salt water intakeforced main

Fresh waterintake andsettling basins

Red Hill Bay Habitat Improvement ProjectConceptual Design Salton Sea

Alamo River

Vail 3A drainFresh water inlet

Vail 3 drainFresh water inlet

-228

-230.5

2250 ft

-230.5

Submersible pump with forced main line delivering Salton Sea water to the mixing basin

Fresh/Salt watermixing basin

Hazard drainFresh water inlet

-243(sea floor)

-233 (WSE 2016)

-230playa

775 ft

Page 10: SALTON SEA MANAGEMENT PROGRAM PHASE I: 10-YEAR PLAN ...resources.ca.gov/CNRALegacyFiles/wp-content/... · 2 OVERVIEW State Obligations under the SSMP What is the Phase I ten-year

10

TORRES MARTINEZ WETLAND PROJECT

Page 11: SALTON SEA MANAGEMENT PROGRAM PHASE I: 10-YEAR PLAN ...resources.ca.gov/CNRALegacyFiles/wp-content/... · 2 OVERVIEW State Obligations under the SSMP What is the Phase I ten-year

11

Introduction and background

Criteria for water backbone delivery infrastructure Criteria for habitat and later phases

Adaptive design, monitoring and contingencies

Public input and transparency

Projected cost and funding

Implementation

PHASE I: 10-YEAR PLAN OVERVIEW(WORK PLAN)

Page 12: SALTON SEA MANAGEMENT PROGRAM PHASE I: 10-YEAR PLAN ...resources.ca.gov/CNRALegacyFiles/wp-content/... · 2 OVERVIEW State Obligations under the SSMP What is the Phase I ten-year

12

ACREAGE GOALS

Waterless dust control(as needed)

Wet Habitat

0

10,000

20,000

30,000

40,000

50,000

2018 2020 2022 2024 2026 2028

Area

(acr

es)

Cumulative Exposed Area Cumulative Proposed Construction

Page 13: SALTON SEA MANAGEMENT PROGRAM PHASE I: 10-YEAR PLAN ...resources.ca.gov/CNRALegacyFiles/wp-content/... · 2 OVERVIEW State Obligations under the SSMP What is the Phase I ten-year

13

AIR QUALITY

Obligations: Task Force

Contractual obligation under the QSA

Dust mitigation projects in coordination with partners Waterless and water dependent measures

Planning and Implementation

East and West shores of the Salton Sea in 2018

Page 14: SALTON SEA MANAGEMENT PROGRAM PHASE I: 10-YEAR PLAN ...resources.ca.gov/CNRALegacyFiles/wp-content/... · 2 OVERVIEW State Obligations under the SSMP What is the Phase I ten-year

14

AIR QUALITY – CURRENT EFFORTS Methods

Surface roughening

Vegetation Enhancement

Surface Stabilizer

Page 15: SALTON SEA MANAGEMENT PROGRAM PHASE I: 10-YEAR PLAN ...resources.ca.gov/CNRALegacyFiles/wp-content/... · 2 OVERVIEW State Obligations under the SSMP What is the Phase I ten-year

15

AIR QUALITY

Resources http://www.iid.com/water/library/qsa-water-

transfer/mitigation-implementation/air-quality-mitigation

http://www.water.ca.gov/saltonsea/

http://www.co.imperial.ca.us/AirPollution/

https://www.arb.ca.gov/desig/adm/basincnty.htm

Page 16: SALTON SEA MANAGEMENT PROGRAM PHASE I: 10-YEAR PLAN ...resources.ca.gov/CNRALegacyFiles/wp-content/... · 2 OVERVIEW State Obligations under the SSMP What is the Phase I ten-year

16

10-Year plan focuses on key components and locations New River East & West Whitewater River Alamo River North & South

Priorities because of proximity to water sources & completed environmental clearance

Water delivery infrastructure

FOCUS AREAS

Page 17: SALTON SEA MANAGEMENT PROGRAM PHASE I: 10-YEAR PLAN ...resources.ca.gov/CNRALegacyFiles/wp-content/... · 2 OVERVIEW State Obligations under the SSMP What is the Phase I ten-year

17

PRIORITIES2018 – 20232023 – 2028

Page 18: SALTON SEA MANAGEMENT PROGRAM PHASE I: 10-YEAR PLAN ...resources.ca.gov/CNRALegacyFiles/wp-content/... · 2 OVERVIEW State Obligations under the SSMP What is the Phase I ten-year

18

PRIORITIES

Page 19: SALTON SEA MANAGEMENT PROGRAM PHASE I: 10-YEAR PLAN ...resources.ca.gov/CNRALegacyFiles/wp-content/... · 2 OVERVIEW State Obligations under the SSMP What is the Phase I ten-year

19

CONSTRUCTION SCHEDULE

Page 20: SALTON SEA MANAGEMENT PROGRAM PHASE I: 10-YEAR PLAN ...resources.ca.gov/CNRALegacyFiles/wp-content/... · 2 OVERVIEW State Obligations under the SSMP What is the Phase I ten-year

20

1. Continue developing water management design criteria

2. Evaluate habitat locations & types

3. Refine conceptual design options for playa land uses

4. Refine assessment tools for SSMP playa treatments

5. Evaluate SSMP environmental compliance needs

6. Compare & evaluate habitat designs to existing draft Habitat Conservation Plans (HCPs)

7. Plan & implement air quality projects

8. Plan & implement harbor & ancillary facilities

10-YEAR PLAN IMPLEMENTATION STRATEGY

Page 21: SALTON SEA MANAGEMENT PROGRAM PHASE I: 10-YEAR PLAN ...resources.ca.gov/CNRALegacyFiles/wp-content/... · 2 OVERVIEW State Obligations under the SSMP What is the Phase I ten-year

21

Draft Plan Late Summer Next Workshop Early Fall Comment Period Fall Final Implementation Plan End of 2017

IMPLEMENTATION PLAN TIMELINE

Page 22: SALTON SEA MANAGEMENT PROGRAM PHASE I: 10-YEAR PLAN ...resources.ca.gov/CNRALegacyFiles/wp-content/... · 2 OVERVIEW State Obligations under the SSMP What is the Phase I ten-year

22

Water Bond (Proposition 1)

Wildlife Conservation Board (Proposition 50)

U.S. Department of Agriculture

AVAILABLE FUNDING

Page 23: SALTON SEA MANAGEMENT PROGRAM PHASE I: 10-YEAR PLAN ...resources.ca.gov/CNRALegacyFiles/wp-content/... · 2 OVERVIEW State Obligations under the SSMP What is the Phase I ten-year

23

Water Transfer Joint Powers Authority

DOI/CNRA MOU EPA

Philanthropic Organizations

Water Resource Development Act Funding

USDA Partnerships & Funding

Additional State & Local Funding

POTENTIAL FUNDING SOURCES

Page 24: SALTON SEA MANAGEMENT PROGRAM PHASE I: 10-YEAR PLAN ...resources.ca.gov/CNRALegacyFiles/wp-content/... · 2 OVERVIEW State Obligations under the SSMP What is the Phase I ten-year

24

http://resources.ca.gov/salton-seaBruce Wilcox