sample iee batanes resort and hotel
TRANSCRIPT
-
8/18/2019 Sample IEE Batanes Resort and Hotel
1/26
CONTENT OUTLINE
EXECUTIVE SUMMARY .................................................................................................................................
Brief Project Description
Project Rationale
Project Components
Project Phases
Pre-Construction
Construction
Operational
Project Details
Production Capacity
Waste Generation
Manpower
Cost
Duration and Schedule
Summary of Project’s IEER
Name of Preparer Team
Study Period
Study Area
-
8/18/2019 Sample IEE Batanes Resort and Hotel
2/26
MAIN IEER .......................................................................................................................................................
IEE ProcessTerms of Reference of the IIE Study
IEE Team
IEE Study Schedule
IEE Study Area
IEE Methodology
Project Description
Project Rationale
Project Area and Location
Project Components and Development Plan
Project Phases
Pre-ConstructionConstruction
Operational
Abandonment
Manpower Requirements
Project Cost
Project Schedule and Duration
Baseline Environmental Conditions, Impact Assessment and Mitigation
Physical Environment
-
8/18/2019 Sample IEE Batanes Resort and Hotel
3/26
ANNEXES .........................................................................................................................................................
IEE Process
_____________________________________________________________________________________
A. Terms of Reference of the IEE Study
Background: This Study is conducted in accordance to the Implementing Rules and Regulations of
Presidential Decree No. 1586 under DENR Administrative Order No. 30 Series of 2003 (DAO 2003-30),which requires proponents of all development projects to conduct an Environmental Impact Assessment
(EIA) and prepare an Environmental Assessment Report (EIR), that will be subjected for review and
approval of the Environmental Management Bureau (EMB) under the Department of Environment and
Natural Resources (DENR), prior to issuance of an Environmental Compliance Certificate (ECC) and
implementation of the Project. Aside from the ECC, there are other environmental permits and
approvals that are necessary for the start of construction works to proceed. The said permits shall be
issued by authorized government and non-government agencies, stakeholder associations, private
groups, etc.
Table 1. Other Permits Applicable to the Proposed Lodging House
Permit/Clearance Issuing Agency Purpose
Permit to Cut/Ball Out Trees DENR-FMB If the proposed project will
cut/ball out trees
Municipal Clearance Municipal Government ofBasco, Batanes
The Proposed Project and itsphases must follow the existing
Land Use policies and Zoning
Ordinance of the Municipality of
-
8/18/2019 Sample IEE Batanes Resort and Hotel
4/26
b) Describe the baseline environment, ecosystem (including existing marine and terrestrial flora
and fauna) and socio-economic status of the Project Site and adjacent areas, including
environmentally sensitive areas, if any;
c) Identify any potential environmental impacts of the proposed development;
d) Determine feasible mitigation and maintenance strategies to either eliminate or minimize any
negative impacts;
e) Generate necessary maps for the Final Report;
f) Perform necessary investigations and prepare a write-up for the following: Project Description,
Baseline Study, Impact Assessment and Management/Mitigation, Abandonment Strategies and
Monitoring Plans;
g) Prepare an Initial Environmental Examination Report and Checklist;
h) Evaluate the overall environmental risk of the Proposed Project at post-implementation of the
mitigation measures; and
i) Provide recommendations for further study and strategies for future monitoring of the Project
and similar studies in the area.
Scope of Work and Expected Output: The Consultant is expected to undertake the following tasks and
deliver the following outputs:
Table 2. The Consultant Team’s Scope of Work and Expected Output
ACTIVITY DESCRIPTION EXPECTED OUTPUT
C ll i h C l i ll b i i h I
-
8/18/2019 Sample IEE Batanes Resort and Hotel
5/26
A. INITIAL ENVIRONMENTAL EXAMINATION REPORT (IEER) – four (4) months after issuance of the Notice
to Proceed (NTP)
B. INITIAL ENVIRONMENTAL EXAMINATION CHECKLIST – four (4) months after issuance of the Notice toProceed (NTP)
C. ENVIRONMENTAL IMPACT ASSESSMENT REPORT (OPTIONAL) – to be submitted by the end of MONTH
4
Consulting Staff: The Consultant Team shall include of the following:
A. Team Leader
The Team Leader must have at least seven (7) years of experience in EIA Study. He/She should have at
least four (4) projects of similar nature.B. Socio-Economist
The Socio-economist should have at least five (5) years of experience in the fields of Economics and
Sociology, and should have at least four (2) projects of similar nature.
C. EIA Consultant
The EIA Consultant should have at least three (3) years of experience in EIA and IEE Study. He/She
should have acquired at least two (2) jobs of similar nature.
D. GIS SpecialistHe/She should have at least two (2) years of previous experience in GIS Mapping and Analysis and have
been involved in two (2) projects of similar nature.
E. Engineering Consultant
The Engineering Consultant must have a Civil and Sanitary Engineering background. He/She must have
at least two (2) years of previous experience in civil structures design and construction, and must have
been involved in at least two (2) projects of similar nature as well.
F. Technical Assistant
The Technical Assistant must have a background in Ecology, Biology or Environmental Science, and musthave at least two (2) years of previous experience in a similar project.
-
8/18/2019 Sample IEE Batanes Resort and Hotel
6/26
of the Socio-Economic Section of the Final
Report
EIA Consultant Ecologist/Environmental Scientist Gather all pertinent data about the ProjectArea’s ecosystem, environmental conditions
and stakeholders
Responsible for the final write-up of the
Project Site’s Baseline Studies
GIS Specialist Environmental Geologist/GIS Gather all pertinent data necessary for map
generation and analysis
Responsible for generation of needed maps
Engineering Consultant Civil/Sanitary Engineering Gather all pertinent data important to
construction issues
Technical Assistant Ecologist/Biologist/Environmental
Scientist
Assist all experts whenever and wherever
necessary
C. IEE Study Schedule
The IEE Study must compose of the following activities:
Table 4. Schedule of Tasks for IEE Study
Activity M1 M2 M3 M4
Data Collection xxxx xxxx xxxx
GIS Mapping xxxx xxxx xxxx xxxx
Public Consultation xxxx xxxx
Submission of Output
-
8/18/2019 Sample IEE Batanes Resort and Hotel
7/26
E. IEE Methodology
All pertinent data shall be collected from primary and secondary sources and be organized to constructthe report. The following are the generic IEE Study approach and the Data Sources
Air quality – Secondary data on TSP, SO2, and NO2 from DENR-EMB
Surface water – FS, water sampling results, secondary data from DENR-EMB
Land use – Reconnaissance survey, Comprehensive Land Use Plan of Basco, Batanes
Soil and geology – Secondary data from MGB
Tectonic setting – PHIVOLCS, previous researches/studies
Terrestrial flora and fauna – Field survey, secondary data from DENRClimate – PAGASA
Demographics – Secondary data from Socio-economic Profile of Basco, Batanes and NSO Census on
Population (2010)
Social impact assessment – Public consultation meetings, Key informant interviews/focused group
discussions
Identification of the primary and secondary (to tertiary, if needed) impact area receptors was done to
determine and classify adverse, potential and recurring impacts that shall be generated in the pre-construction, construction, operation, abandonment and monitoring phases of the project.
Sensitive receptors existing within the primary impact area, which was determined based on the
Project’s potential impacts during the pre-construction and construction phases. Such impacts include
dust generation, noise and vibration, soil runoff, and waste generation and disposal.
The secondary impact area was the area within 300-m radius of the Proposed Project Site, wherein more
residents are situated. The said people may be directly or indirectly exposed to the probable impacts ofsecondary impact area, which might include issues in sanitation, community health condition, and water
quality of receiving coastal waters.
-
8/18/2019 Sample IEE Batanes Resort and Hotel
8/26
Project Description
_____________________________________________________________________________________
A. Project Rationale
The Project aims to:
Construct a privately-owned Lodging House at Brgy. Chanarian in Basco, Batanes;
Ensure that the existing ecosystem and stakeholders thriving within and nearby the
Project Area shall not be adversely impacted during the Project’s pre-construction,
construction proper, operational and abandonment phases; Perform all Project operations pursuant to all applicable national and local laws, policies
and regulations of authorized government and non-government agencies, groups and
associations; and
Promote tourism and consequently, increase the livelihood and economic improvement
opportunities, to residents not only of the barangay but the municipality and the whole
province.
B. Project Area and Location
The Proposed Project Site is situated along the National Highway of Brgy. Chanarian in Basco, Batanes. It
is a five-minute drive from the Basco Airport and Town Proper. Access to the site is possible through the
National Road connecting Ihubok I and II to Chanarian, and a 15-m Barangay Road that enters the
Project Site directly. Figure 1 presents a bird’s eye view of the Proposed Project Site location, while
Figure 2 shows a clearer view of the said location, as well as the access roads to the site. The Project Site
has an area of 664 square meters. It is situated in a land classified as a residential area.
Figure 1. Bird’s Eye View of Proposed Project Site
-
8/18/2019 Sample IEE Batanes Resort and Hotel
9/26
Figure 2. Project Location and Access Roads
C. Project Components and Development Plan
-
8/18/2019 Sample IEE Batanes Resort and Hotel
10/26
D. Project Phases
Pre-construction Phase: This phase consists of the project planning and activities related to securing thenecessary permits and clearances prior to construction proper. The acquisition of the project site, if it is
just previously purchased or leased, is also included in this phase. Preparation of the Proposed Project
Site is also carried out in this phase. Such preparations might include cutting/balling out trees,
barricading the area in preparation for the construction phase, leveling and excavation, and conducting
public consultation or key interviews with residents and other stakeholders.
Construction Phase: All civil works pursuant to the Engineering Plan and Detailed Design shall be
executed in this phase, including temporary structures that are essential for the whole constructionprocess (e.g. workers’ temporary settlement, including amenities such as public lavatories, material
storage area, etc.) This phase shall be finished within six (6) months.
Operational Phase: The start of this phase is the day the lodging house is opened for the public. The
lodging house shall offer food and accommodation, tour packages and transport services to tourists. All
schemes for proper waste disposal shall be maintained all throughout the years that the lodging house
will operate. Wastes shall include solid materials (recyclable, biodegradable and non-biodegradable),
which will be strictly subjected to proper and regular segregation, and liquid materials (detergents,house cleaning agents, human wastes), which will be directed into a receiving septic tank and subjected
to regular monitoring and transfer to a proper sewage treatment facility. Other activities which shall be
performed during the operational phase of the Project are maintenance of open spaces within the
Project Area, and regular check-up/monitoring (and replacement if necessary) of Project structures and
components, such as water pipes and drainage systems, ceilings, walls, etc.
Abandonment Phase: No abandonment plan is foreseen for the Proposed Project, but if indeed the
lodging house will be closed and abandoned in the future, all environment monitoring and mitigationmeasures shall be performed.
-
8/18/2019 Sample IEE Batanes Resort and Hotel
11/26
report about
environmental impacts
of the Project and the
necessary measures to
either mitigate or
regulate such impacts.
Public Consultation 0.1
Secondary Data
Acquisition
0.05
Civil Works Area Clearing/Tree-
cutting
0.1
Leveling and Excavation 1
Construction of
Temporary Settlement
for Laborers (inclusive of
basic amenities)
0.1
Salary of workers
(experts and laborers)
1
Construction Civil Works Construction proper of
all buildings
30
-
8/18/2019 Sample IEE Batanes Resort and Hotel
12/26
Acquisition of other
equipment
.5
Abandonment Phase Applicable tasks for
abandonment
1
Total 49.85
G. Project Schedule and Duration
The whole Project shall be accomplished within a specific schedule as shown below.
Table 6. Project Schedule and Duration
Phase Operation Duration
M1 M2 M3 M4 M5 M6 M7 M8 M9 M10 M11
Pre-construction EIA Study
Civil Works
Construction Civil Works
Operation Operation
-
8/18/2019 Sample IEE Batanes Resort and Hotel
13/26
Baseline Environmental Conditions
_____________________________________________________________________________________
A. Physical Environment
The physical conditions existent in the Project Site is basically the same as the occurring environment in
the whole municipality of Basco. Basco is situated in Batan island, which is one of the large islands of
Batanes. It is surrounded by coastal seas, therefore giving its primary geographical characteristic of
beach and sand occurrences.
The Project Site, just like the whole Basco, is characterized by rolling hills and steep to very steep slopes.The site is actually elevated at 100meters above sea level. It is along the National Road traversing from
Basco Proper to Chanarian, the barangay where the site is specifically located.
The geomorphological characteristic of the site is Pliocene quaternary, the same as the whole
municipality of Basco. Soil is characterized by sandy-loam attributes. The climate here is the same as the
whole Batanes. The whole province is often lambasted by typhoons.
Figure 3. Geomorphological Map
-
8/18/2019 Sample IEE Batanes Resort and Hotel
14/26
Figure 4. Slope Map
B. Biological Environment
-
8/18/2019 Sample IEE Batanes Resort and Hotel
15/26
Impact Assessment
_____________________________________________________________________________________
Pre-construction activities which posed a significant effect to environment are vegetation clearing for
the civil works, and possible acquisition of land which would involve change in land allocation. During
construction, employment generation had been identified as the only immediate positive impact. All
other positive values are attributed to future gains once the project is completed. Physical and socio-
economic resources were preliminarily identified to be affected during this phase. The civil works and
land preparation are the potential activities that will disturb the soil. Pollution generation with regard to
noise and dust is also taken into consideration in the subsequent Environmental Management Plan.
As the lodging house goes into full operation, anticipated impacts include probable increase of
impermeable surface and problems with waste disposal, but only if proper maintenance and monitoring
measures are not taken.
-
8/18/2019 Sample IEE Batanes Resort and Hotel
16/26
b. Water quantity and quality
There is no nearby surface water in the Project Site, hence the concern about water
pollution and surface runoff can be eliminated. Moreover, the site is located 100 metersfrom sea level, hence the existence of low-depth water table is close to nil.
c. Air and noise quality
Increase in dust is caused by excavation, embankment and hauling activities. This can be
mitigated by regularly spraying of exposed areas with water and covering the dump trucks
with sheets. To somehow minimize the spread of dust particles and noise, putting up a
barricade during all construction works may be necessary. Moreover, laborers must bestrictly monitored in order to ensure that cleanliness and orderliness are practiced at all
times. Provision of temporary lavatories that will be regularly cleaned and removed of
wastes must be carried out to ensure sanitation and proper hygiene, and avoid the spread
of disease and undesirable odours.
d. Terrestrial environment
Construction of the lodging house will require cutting of trees and clearing of vegetativecover which will cause loss of habitat for some species, although there are only house birds
like maya and other common avian species thriving in the Project Site. Securing or permits
and clearance prior to cutting and clearing must be incurred.
e. Social environment
There are no consideration regarding planning of resettlement required for the Project
Site. There are other residential structures proximate to the Site but not within it. However,consultation with neighboring resident and families must be performed prior to any
construction due to the possibility of noise and dust spread that might be of inconvenience.
There is also the concern for safety and security since some of the laborers might not be one
-
8/18/2019 Sample IEE Batanes Resort and Hotel
17/26
Recyclables are to be directed in junk shops and all biodegradables to the trash collecting
truck. Domestic wastes like urines, chemical fluids and sewage must be directed in a
privately-owned septic tank. This septic tank must be regularly monitored and removed ofwastes as necessary, particularly during rainy seasons. Septage is to be collected and
brought to a sewage treatment facility. Hazardous wastes such as batteries must be
disposed wisely as well. Contacting a professional HazMat collection and storage facility to
help with this issue might be necessary.
b. Water Pollution
As mentioned, there are no surface water bodies proximate to the site. However, it is
indeed situated in a beach. Testing the waters on the beach and the area proximate to the
site for fecal contamination might be necessary.
-
8/18/2019 Sample IEE Batanes Resort and Hotel
18/26
Emergency Plan
_____________________________________________________________________________________
The Project Site is considerably proximate to Basco Proper, where fire protection department and police
offices are situated. Hotlines for security officials such as fire personnel, hospital workers and policemen
must be provided in the rooms of all lodging houses, as well as in the front desk. Basic fire and safety
equipment must be provided in the lodging house. These will include fire extinguishers, and water
hoses. For tours and ocean activities, provision of life vests and other safety apparel must be practiced.
Lifeguards and lodging house personnel must guide tourists all throughout their tours.
-
8/18/2019 Sample IEE Batanes Resort and Hotel
19/26
Table 7:
Summary Environmental Management Plan
Environmental
Component Project Activity Potential Impact
Environmental Management Plan
Mitigating/ EnhancementMeasures
Estimated Cost of
Mitigation/
Enhancement
ResponsibleInstitution
Guarantee
Pre-Construction/ Construction Phase
P h y s i c a l E n v i r o n m e n t
S o i l / L a n d U s e
Leveling and Excavation
Vegetational Clearing
Disruption of
soil/land
Restoration of vegetation after
the construction
Ensure that due consideration is
given to the proper trade-offs
between land values
Include in contract of
ContractorContractor
Contract
Comprehensive
land use plan
of LGU
Ecological
Disturbance
Prohibition of further
unnecessary disruption in
ecosystem after construction
Include in contract of
Contractor
Contractor Contract
W a t e r Q u a n t i t y a n d Q u a l i t y
Temporary construction
camps
Water
contamination;
turbidity
Placement of temporary comfort
facilities for workers; septic
tanks, etc.
Include in contract of
ContractorContractor Contract
Competition in
water use
Observe water conservation
measures; implement rain water
harvesting
Include in contract of
ContractorContractor Contract
Excavation, embankment
and hauling
Turbidity;
Siltation;
Sedimentation
Containment and construction of
silt traps and silt curtains;
minimum vegetative removal
Include in contract of
ContractorContractor Contract
A i r a n d N o i s e Q u a l i t y Excavation, embankment
and haulingincrease in dust
Minimize and control dust
generation/ Regular spraying of
exposed areas; covering dump
trucks with sheets
Include in contract of
ContractorContractor Contract
Construction proper of the
lodging houseincrease in dust
Minimize and control dust
generation/ Regular spraying of
exposed areas; covering dump
trucks with sheets
Include in contract of
ContractorContractor Contract
-
8/18/2019 Sample IEE Batanes Resort and Hotel
20/26
Environmental
ComponentProject Activity Potential Impact
Environmental Management Plan
Mitigating/ Enhancement
Measures
Estimated Cost of
Mitigation/
Enhancement
Responsible
InstitutionGuarantee
Acute elevated
levels of noise
Operation of heavy equipment
and other appurtenant facilitieswill be limited during daytime. In
case operation beyond these
hours is required, proper
notification and information of
the concerned barangay officials
will undertake.
Include in contract of
ContractorContractor Contract
T
e r r e s t r i a l
E n
v i r o n m e n t
Slight disruption of soil,
vegetation and thriving
species
Loss of habitat
Cutting of trees and clearing of
vegetative cover to be
undertaken only when
necessary/ relevant permits and
clearances will be secured priorto cutting and clearing activities.
Include in contract of
ContractorContractor Contract
S o c i a
l E n v i r o n m e n t
Hauling and excavation
Construction proper of
lodging house
Possible Built up
of traffic
Provide a traffic enforcer among
laborers (green and red flags)
Include in contract of
ContractorContractor Contract
Security/Safety
concerns among
residents
Provision of security guard that
will monitor attendance of all
laborers
Consultation with proximateresidents
Include in contract of
Contractor
LGU
Contractor
Contract
Job
opportunities
and local
employment
Preference given to qualified
local residents
Include in contract of
ContractorContractor
Social
Development
Program
-
8/18/2019 Sample IEE Batanes Resort and Hotel
21/26
Environmental
ComponentProject Activity Potential Impact
Environmental Management Plan
Mitigating/ Enhancement
Measures
Estimated Cost of
Mitigation/
Enhancement
Responsible
InstitutionGuarantee
Operational Phase
P h y s i c a l E n v i r o n m e n t Operation of Lodging
House
Waste Generation
Regularly monitor proper
domestic waste disposal
O & M cost for the
ProjectLGU
Environmental
Monitoring
plan
Manage proper solid waste
disposal including collection,
hauling and final disposal
O & M cost for the
ProjectLGU
Environmental
Monitoring
plan
water pollution Monitor illegal dumping of
sewage in nearby beach
O & M cost for the
ProjectLGU
Environmental
Monitoring
plan
S o c i a l
E n v i r o n m e
n t
Promotion of tourism and
livelihood
Job opportunitiesand local
employment
Preference given to qualified
local residents
Include in contract of
Proponent
Proponent
LGU
Proponent
Social
Development
Program
-
8/18/2019 Sample IEE Batanes Resort and Hotel
22/26
Environmental Monitoring Plan
______________________________________________________________________________________________________________________
Table 8:
Environmental Monitoring Plan
PARAMETER LOCATION FREQUENCY ESTIMATED COST
(PER ANNUM)
Pre-Construction Phase
Protection & safeguard of adjacent
properties and the general public
Project Site Daily
Inventory of Trees Project Site Once, prior to construction Php 20,000.00
Geotechnical Investigation Project Site & Slope
Protection
Once, prior to construction Php 100,000.00
Construction Phase
Noise & Vibration Construction site During major noise emission, in cases of
consistent complaints
Part of construction cost
Access to the rivers by residents & boat
operators
Construction site Daily Part of the construction cost
Volume of overburden soil and wastes Construction site During hauling of excavated soil and wastes
and dredging of conveyance system
Part of the construction cost
Dust Construction site During major dust emission, in cases of
consistent complaints
Part of the construction cost
Safety Signage, barricades, fencing, PPEs Construction site Daily Part of construction cost
Visual Monitoring of storm water run-off Manholes sites During rain events Part of construction cost
-
8/18/2019 Sample IEE Batanes Resort and Hotel
23/26
PARAMETER LOCATION FREQUENCY ESTIMATED COST
(PER ANNUM)
Traffic alternative route &t traffic aides
and signage
Affected major roads and
highways
Daily Part of construction cost
Sediment deposit Ocean/Beach Daily
Twice a day
(rain event)
Part of the construction cost
Litter (Cleanliness) Construction Site Daily Part of the construction cost
(health & safety)
Operation Phase
Water Quality Coastal Water Monthly Php 100,000.00
Waste disposal Project Site Monthly
-
8/18/2019 Sample IEE Batanes Resort and Hotel
24/26
Bibliography
_____________________________________________________________________________________
o Wikipedia
o DENR-DAO 2003-30
o EIA of Pasay City Sewage Treatment Plant
o Water Management Study of the Sta. Rosa River Basin
-
8/18/2019 Sample IEE Batanes Resort and Hotel
25/26
Project Briefer
PROVIDE PROJECT ASIIGNEMNT DESCRIPTION
-
8/18/2019 Sample IEE Batanes Resort and Hotel
26/26