  • ID Task Name Duration

    1 PROJECT MILESTONE 296 days2 Project Start 0 days3 Project Finish 0 days4 GENERAL PRELIMINARIES 144 days5 Design and detailed fabrication drawing preparation for all 28 types existing baskets and

    submission for TPI/ADMA approval96 days

    6 Review and approval by TPI/ADMA 18 days7 Preliminary document submission (ITP, welding procedure, NDT Procedure etc.) 6 days8 Partial material procurement for all the 28 Types (100 nos) existing CCU baskets 24 days9 Material identification with TPI (1st Stage TPI inspection) 6 days10 MAINTENANCE AND REPAIR WORKS 152 days11 Mobilization of 15 nos Existing CCU Baskets (25 Nos/each) 20 days12 Sandblasting and Preliminary Inspection 60 days13 Damaged Door Repair 50 days14 Damaged Side Structure Repair 110 days15 MPI before & after Load Test 40 days16 Door Hinges Replacement 30 days17 Door Hinges Repair 38 days18 Door Rod Replacement 30 days19 Main Structure Bend Repair 130 days20 Side Mesh Welding & Repair 90 days21 Side Mesh Replacement 140 days22 Broken Support Welding 60 days23 Provide New Rubber Bushings 40 days24 Pad Eyes Replacement 90 days25 Top Plate Repair 44 days26 Corroded Channels Repair 75 days27 Bottom & Side Wooden Panel Replace 45 days28 Roof hole covered by Welding & Painting 68 days29 Side hole covered by Welding & Painting 40 days30 Door Lock Repair 38 days31 Exhaust Cover Fabrication 30 days32 Bottom Grill Replace 100 days33 Brottom Grill Repair 60 days34 Any other Type of Repair / replacement (to be listed) 20 days35 Load Test 50 days36 Sandblasting and Painting 140 days

    7/156/8

    Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May JunQtr 3, 2015 Qtr 4, 2015 Qtr 1, 2016 Qtr 2, 2016

    Task

    Split

    Milestone

    Summary

    Project Summary

    Inactive Task

    Inactive Milestone

    Inactive Summary

    Manual Task

    Duration-only

    Manual Summary Rollup

    Manual Summary

    Start-only

    Finish-only

    External Tasks

    External Milestone

    Deadline

    Progress

    Manual Progress

    SIGMA ENGINEERING WORKS LLCMussafah, Abu Dhabi UAE

    Project: Repair of 28 Types Exisitng CCU Baskets for ADMA-OPCO (Approximate assumed quantity is 150 nos)

    CLIENT: ADMA-OPCO

    SEW WO No. 158839 Page 1

    Project:Repair of 28 Types Exisitng CCU Baskets for ADMA-OPCO(Approximate assumed quantity is 150 nos)

    kritti_nimboonchajTypewriter

    kritti_nimboonchajTypewriter

    kritti_nimboonchajTypewriter

    kritti_nimboonchajTypewriter

    kritti_nimboonchajTypewriter

    kritti_nimboonchajTypewriter

    kritti_nimboonchajTypewriter

    kritti_nimboonchajTypewriter

    kritti_nimboonchajTypewriter

    kritti_nimboonchajTypewriter

    kritti_nimboonchajTypewriterNote: Total project duration were based on 6 working days per week, 10 hrs per day.