Santa Clara County Civic Center Master Plan
May 10th and 24th, 2016
BOARD OF SUPERVISORS
1
![Page 2: Santa Clara County...• May 2015 Board Workshop • May 10, 2016 Public Hearing on Proposed Ordinance and Master Development Agreement 7 BOARD WORKSHOP (May 15, 2015) Board Guidance:](https://reader034.vdocument.in/reader034/viewer/2022052018/6031187e63df2867ec59a195/html5/thumbnails/2.jpg)
INTRODUCTIONS:
2
Administration:• Bruce Knopf, Director, Asset and Economic Development, Office of
the County Executive• David Barry, Senior Facilities Architect, Facilities and Fleet Dept.• Shirley Edwards, Deputy County Counsel • Emily Harrison, Director, Finance Agency
Consultants:• Tim Kelly, President, Keyser Marston Associates, Inc.• Bob Thompson, Partner, Sheppard, Mullin, Richter & Hampton LLP• David Shiver, Principal, BAE Urban Economics (Peer Review)
![Page 3: Santa Clara County...• May 2015 Board Workshop • May 10, 2016 Public Hearing on Proposed Ordinance and Master Development Agreement 7 BOARD WORKSHOP (May 15, 2015) Board Guidance:](https://reader034.vdocument.in/reader034/viewer/2022052018/6031187e63df2867ec59a195/html5/thumbnails/3.jpg)
OVERVIEW
3
Proposed Master Development Agreement:• Long-Term Planning for Civic Center Capital Facilities• Savings from Operations & Maintenance Expenditures and Lease
Payments• Limitation on cost exposure in each phase• Flexibility and Board control
![Page 4: Santa Clara County...• May 2015 Board Workshop • May 10, 2016 Public Hearing on Proposed Ordinance and Master Development Agreement 7 BOARD WORKSHOP (May 15, 2015) Board Guidance:](https://reader034.vdocument.in/reader034/viewer/2022052018/6031187e63df2867ec59a195/html5/thumbnails/4.jpg)
SITE CONTEXT: Santa Clara County Civic Center
4
![Page 5: Santa Clara County...• May 2015 Board Workshop • May 10, 2016 Public Hearing on Proposed Ordinance and Master Development Agreement 7 BOARD WORKSHOP (May 15, 2015) Board Guidance:](https://reader034.vdocument.in/reader034/viewer/2022052018/6031187e63df2867ec59a195/html5/thumbnails/5.jpg)
5
BACKGROUND / CONTEXT
Issues and Opportunities:• Potential Revenue Generation from Private Uses/Development• Outdated Facilities (40+ Years or Older)• Costly Operations & Maintenance• Deferred Maintenance Backlog• Expensive Leased Facilities and Fully Occupied Civic Center• Building Safety and Security• Inadequate Sustainability, Flexibility, Resiliency• Community Benefits• Employee Satisfaction• Poor Public Access
![Page 6: Santa Clara County...• May 2015 Board Workshop • May 10, 2016 Public Hearing on Proposed Ordinance and Master Development Agreement 7 BOARD WORKSHOP (May 15, 2015) Board Guidance:](https://reader034.vdocument.in/reader034/viewer/2022052018/6031187e63df2867ec59a195/html5/thumbnails/6.jpg)
6
MAJOR MILESTONES
July 2011 to May 2016:• Former San Jose City Hall and U.S. Army Reserve Acquisitions• Request for Proposals Process• Facilities Needs Assessment• East and West Wing Building Condition Assessments• Public Outreach • Negotiations with Lowe Enterprises• May 2015 Board Workshop• May 10, 2016 Public Hearing on Proposed Ordinance and Master
Development Agreement
![Page 7: Santa Clara County...• May 2015 Board Workshop • May 10, 2016 Public Hearing on Proposed Ordinance and Master Development Agreement 7 BOARD WORKSHOP (May 15, 2015) Board Guidance:](https://reader034.vdocument.in/reader034/viewer/2022052018/6031187e63df2867ec59a195/html5/thumbnails/7.jpg)
7
BOARD WORKSHOP (May 15, 2015)
Board Guidance:• Retain Civic Center Function at Civic Center Campus• Plan for 1,150,000 SF of Public Space at the Civic Center Campus• Replace the West Wing and the Connector• Explore Redevelopment/Modernization/Replacement of the East
Wing• Initiate Phase 1 Development on the Richey Site• Explore Options to Relocate the Emergency Vehicles Operation
Center (EVOC)
![Page 8: Santa Clara County...• May 2015 Board Workshop • May 10, 2016 Public Hearing on Proposed Ordinance and Master Development Agreement 7 BOARD WORKSHOP (May 15, 2015) Board Guidance:](https://reader034.vdocument.in/reader034/viewer/2022052018/6031187e63df2867ec59a195/html5/thumbnails/8.jpg)
County Services (including Law + Justice)
Land Area (acres) 23.7
GSF 1,150,000±
Parking 2,500 – 3,500
Site Surplus
Land Area (acres) 16.3
PREFERRED SITE OPTION: Centralized Campus and Maximum Development Opportunities
8
![Page 9: Santa Clara County...• May 2015 Board Workshop • May 10, 2016 Public Hearing on Proposed Ordinance and Master Development Agreement 7 BOARD WORKSHOP (May 15, 2015) Board Guidance:](https://reader034.vdocument.in/reader034/viewer/2022052018/6031187e63df2867ec59a195/html5/thumbnails/9.jpg)
9
CURRENT ACTIVITIES
May 10th and May 24th, 2016:• On-going: Law and Justice Planning (Anderson Brule Architects)• May 24th: Approve Contract for CEQA Consultant (David J.
Powers and Associates)• May 24th: Adopt Ordinance (NS-300.894)• May 24th: Adopt Resolution Approving Master Development
Agreement (Lowe Enterprises)
![Page 10: Santa Clara County...• May 2015 Board Workshop • May 10, 2016 Public Hearing on Proposed Ordinance and Master Development Agreement 7 BOARD WORKSHOP (May 15, 2015) Board Guidance:](https://reader034.vdocument.in/reader034/viewer/2022052018/6031187e63df2867ec59a195/html5/thumbnails/10.jpg)
EXECUTIVE SUMMARY
10
MDA Decision Considerations:• Implements stewardship of the County governmental function
and represents long-term re-investment in a community asset• Working with experienced public/private developer• County has approval rights on new County facilities and budget• County cost exposure is capped, with certain exceptions• At key points, County has right of “Termination for Convenience”• Working with a vetted entity and establishing continuity of
implementation of a complex phased project• Other developers may participate in the development of private
revenue generating parcels and other new County Facilities
![Page 11: Santa Clara County...• May 2015 Board Workshop • May 10, 2016 Public Hearing on Proposed Ordinance and Master Development Agreement 7 BOARD WORKSHOP (May 15, 2015) Board Guidance:](https://reader034.vdocument.in/reader034/viewer/2022052018/6031187e63df2867ec59a195/html5/thumbnails/11.jpg)
COUNTY NEGOTIATING TEAM
11
Administration:• Asset and Economic Development, County Executive• Facilities and Fleet Department• County Counsel • Finance Agency• Risk Management
Consultants:• Keyser Marston Associates, Inc.• Sheppard, Mullin, Richter & Hampton LLP• Bay Area Urban Economics (Peer Review)
![Page 12: Santa Clara County...• May 2015 Board Workshop • May 10, 2016 Public Hearing on Proposed Ordinance and Master Development Agreement 7 BOARD WORKSHOP (May 15, 2015) Board Guidance:](https://reader034.vdocument.in/reader034/viewer/2022052018/6031187e63df2867ec59a195/html5/thumbnails/12.jpg)
NEXT STEPS
12
Five MDA Phases Requiring Board Approval:• Master Planning and Due Diligence (Phase A)• CEQA / EIR and Other Approvals (Phase B)• Preliminary Design and Engineering of Initial New County Facility
Phase, Tentatively the Richey Site (Phase C)• Financing and Pre-Construction and Approval of Guaranteed
Maximum Price for Initial New County Facility Phase, the Richey Site (Phase D)
• Construction of Initial New County Facility Phase (Phase E)
![Page 13: Santa Clara County...• May 2015 Board Workshop • May 10, 2016 Public Hearing on Proposed Ordinance and Master Development Agreement 7 BOARD WORKSHOP (May 15, 2015) Board Guidance:](https://reader034.vdocument.in/reader034/viewer/2022052018/6031187e63df2867ec59a195/html5/thumbnails/13.jpg)
Timeline
13
M1 M2 M3 M4 M5 M6 M7 M8 M9 M10 M11 M12 M13 M14 M15 M16 M17 M18 M19 M20 M21 M22
PHASE A – MASTER PLAN AND DUE DILIGENCE
PHASE B – CEQA / EIR & OTHER APPROVALS
PHASE C – PRELIM DESIGN & ENGINEERING
Phases D and E (Schedule TBD):
• Phase D – Financing and Preconstruction
Within 12 months of completion of Phase C
• Phase E – Construction of Initial Phase
No longer than 4 years after Board approval Master
Plan/CEQA (Phase B)
![Page 14: Santa Clara County...• May 2015 Board Workshop • May 10, 2016 Public Hearing on Proposed Ordinance and Master Development Agreement 7 BOARD WORKSHOP (May 15, 2015) Board Guidance:](https://reader034.vdocument.in/reader034/viewer/2022052018/6031187e63df2867ec59a195/html5/thumbnails/14.jpg)
14
Q & A
14
Questions?
![Page 15: Santa Clara County...• May 2015 Board Workshop • May 10, 2016 Public Hearing on Proposed Ordinance and Master Development Agreement 7 BOARD WORKSHOP (May 15, 2015) Board Guidance:](https://reader034.vdocument.in/reader034/viewer/2022052018/6031187e63df2867ec59a195/html5/thumbnails/15.jpg)
15
Project Website: www.sccgovorg/civiccenter
Contacts: [email protected] or (408) 299-5155 [email protected] or (408) 993-4645
15
Contact Information