sao paulo, brazil and - world...
TRANSCRIPT
SAO PAULO, BRAZIL AND SOUTH AMERICA
Area (km²)¹ Population(thousand inhab)²
% Population
Brazil 8.514.877 183.987 -
Sao Paulo 248.210 39.827 21,65%
RMSP 7.944 19.221 10,44%
Sao PauloState
¹ IBGE – Res 05 , October 2002² Estimated Population – IBGE, 2007
Brazil
METROPOLITAN REGIONS
Campinas Metropolitan RegionSão Paulo Metropolitan Region
Baixada Santista Metropolitan Region
Sao PauloState
39 cities19,2 million inhabitants*
9 cities1,6 million inhabitants *
19 cities2,6 million
inhabitants *
*IBGE, Estimated population 2007.
AREA OF OPERATION
São Paulo State Metropolitan Regions: São Paulo 39 cities, 19.5 million inhabitants Campinas 19 cities, 2.6 million inhabitants Baixada Santista 9 cities, 1.6 million inhabitants
São Paulo State Metropolitan Transportation AuthorityMetropolitan mass transit system, including rail rapid transit.
Companies linked to the São Paulo State Metropolitan Transportation Authority (STM): São Paulo Subway – Metrô
(Companhia do Metropolitano de São Paulo - Metrô)
São Paulo Metropolitan Train Company – CPTM (Companhia Paulista de Trens Metropolitanos – CPTM)
Metropolitan Urban Transport Company – EMTU(Empresa Metropolitana de Transportes Urbanos de São Paulo)
7,3 million passengers per day
METROPOLITANTRANSPORTATION NETWORK
CPTM METRÔ EMTU
22 cities São Paulo city67 cities
(3 Metropolitan Regions)
2 million passengers/day
3.4 million passengers/day
2 millionpassengers/day
262 km network 61 km network33 km BRT Corridor
5,380 Bus fleet
6 lines 4 lines 844 lines
89 stations 55 stations 10 terminals
11Tatuapé
Paraíso
Estudantes
São Mateus
Jabaquara
Jurubatuba
Ferrazópolis
DiademaSão Bernardo
Capão Redondo
Santo André
V.Madalena
Rio Grandeda Serra
Francisco Morato
Itapevi
8
Alto doIpiranga
EL
Today´s Network
Tucuruvi
Luz
PalmeirasBarra Funda
Lgo. Treze
SéCorinthians-
ItaqueraGuaianazes
7
9 10
12
Grajaú
EXPANSION PLAN: STM´s KEY DRIVERS
Improving the commuter rail system to 240 km with Metrô quality standard
Increasing the fleet: 107 new trainsets (47 Metrô / 60 CPTM)
Refurbishing the existing train fleet
Rationalizing the Metropolitan Bus System
Developing new bus corridors – BRT
Adopting modern transport system: Tramway
INVESTMENT PROGRAM
R$ 20 billionlargest infrastructure investment program
underway in Brazil
Suzano
Grajaú
Rio Grandeda Serra
EL
Francisco Morato
MauáEa
Guaianazes11
7
9
10
12Luz
Brás
EA
13
8
6
Paraíso
São Mateus
Jabaquara
Ferrazópolis
São Bernardo
Capão Redondo
Santo André
Alto doIpiranga
Autódromo
Tucuruvi
Paulista
PalmeirasBarra Funda
Freguesia
Taboão Aeroporto
Zezinho Magalhães (Cecap)
Corinthians-Itaquera
EL
São Caetano
Tamanduateí
OratórioVila
Prudente
Diadema
Vila Sônia
Pinheiros
Jurubatuba
Butantã
V.MadalenaItapevi
Brooklin –Campo Belo
Morumbi
Brasilândia
Ticoatira
C.C. RuthCardoso
Ferraz
AdolfoPinheiro
NETWORKEXPANSION PLAN
Oratório / Pq. São Lucas
+ 100 thousand Passengers per day
in 2010(extension)
Extension –design phase2,3 km
Sacomã
Sectionin Operation
UnderConstruction
3,9 km
Vila Prudente
Tamanduateí
Sacomã:Transfer with Tiradentes
Express and EMTU
Daily RidershipToday: 380 thousand2010: 800 thousand
LINE 2 – GREEN
Luz
República
Higienópolis-Mackenzie
Oscar FreireFradiqueCoutinho
Faria Lima
Pinheiros
Butantã
Vila Sônia
São Paulo – Morumbi
Paulista
1st Phase2nd Phase
Transfer with Emerald Line
705 thousand Passengers per day in 2010 (1st phase)
Transfer withBlue, Red and Green
Lines
LINE 4 – YELLOW1st Phase: 2010
Line underConstruction
12,8 km
Transfer withCPTM Lines
Capão Redondo
Campo Limpo
Vila dasBelezas
Santo Amaro Largo Treze
Adolfo Pinheiro
Borba Gato
Brooklin – Campo Belo
Ibirapuera
Água Espraiada
GiovaniGronchi
Moema
Servidor
Vila Clementino
Chácara Klabin
Line inOperation
Design Phase5,7 kmAlto da Boa Vista
Daily RidershipToday: 106 thousand
2010: 286 thousand
Integration with Blue and Green Lines
Santa Cruz
1st Phase2nd Phase
LINE 5 – LILAC
Design Phase19 km
Integration withBlue, Yellow, Ruby and
Diamond Lines
651 thousand passengers transported
per day in 2014
LINE 6 – ORANGE (Project)
Freguesia do Ó
Água Branca
Turiaçu
PUC
Santa Marina
Pacaembu Angélica
Higienópolis-Mackenzie
Bela Vista
13 de Maio São Joaquim
João Paulo I
Jardim Primavera
C.C. Ruth Cardoso
HospitalVila Penteado
Morro Grande
Brasilândia
Saúde
Conceição
CONGONHAS AIRPORT TRAMWAY
São Judas
Jabaquara
Congonhas
18 thousand Passengers transported
(Phase 1)Phase 13,7 km
Phase 26,1 km
Morumbi (CPTM)
Phase 34,3 km
Água Espraiada
58 thousand Passengers transported (Phase 1 e 2)
85 thousand Passengers transported (3 Phases)
Metrô standard:
Reliability
Safety (Signaling)
Speed (up to 5 min. headway reduction, more than doubling
service offer)
Station quality
Train quality
SURFACE RAIL RAPID SYSTEM UPGRADE 160KM
Mauá
Luz
Guapituba
Ribeirão PIres
Rio Gde da Serra
Brás
Moóca
Ipiranga
São Caetano
Utinga
Santo AndréCapuava
Line in Operation
Disign Phase25,2 km
Daily RidershipToday: 270 thousand
2010: 670 thousand
Tamanduateí
Pref. Saladino
LINE 10 - TURQUOISEAND ABC EXPRESS
Passengers transported Luz – Guaianazes (today): 250 thousand/ day
Luz – Ferraz: 395 thousand/day
LINE 11 – CORAL - EAST EXPRESSAND LIGHT METRÔ - FERRAZ / MOGI
East Expressin operation Extension to
Ferraz de Vasconcelos
TramwayFerraz – Mogi
IN STUDY
BRÁSTATUAPÉ
LUZ
CECAP
TPS 1 e 2TPS 3
PENHA
ENGº GOULART
USP LESTE COM. ERMELINO
Design Phase28,1 km
CECAP:Transfer with
Guarulhos – São Paulo BRT corridor
Airport Express:20 thousand passengers
transported per day
Design Phase20,2 km
Jade Line:106 thousand passengers
transported per day
Sapphire Line (existing)
GUARULHOS AIRPORT EXPRESS
INTEGRATED METROPOLITAN TRANSPORT SYSTEM – BAIXADA SANTISTA
Linha A – Tramway
Linha B – BRT Corridor
Bus regular lines EMTU (integrated)
TERMINALBARREIROS
TERMINALPORTO
TERMINALVALONGO
E.T. PONTADA PRAIA
TERMINALFERRY BOAT
E.T. PÇA DAREPÚBLICA
B
A
165 thousand passengers per day
(1st phase - SIM)
Transfer with Jade Line (CPTM trains)
Est. TucuruviMETRÔ
Term. Vila Galvão
Term. Emílio Ribas
Term. Antonio de Souza
Term. CECAP
Term. Taboão
Município deSão Paulo
Município deGuarulhos
Term Intermodal
140 thousand passengers transported per day
Transfer with Blue Line (subway)
Design Phase22,5 km
GUARULHOS – SÃO PAULO BRT CORRIDOR
NORTHWEST CORRIDOR – CAMPINAS
Under Construction
32,7 km
Design Phase
Northwest Corridor (under construction)
Northwest Corridor (design phase)
Additional Conection
TerminalCampinasEst. Tranf.
Anhanguera
Terminal Hortolândia
Est. EmbarqueMonte Mor
TerminalCampo Grande
(municipal)
Terminal Sumaré
Terminal Nova Odessa
Terminal Americana 110 thousand passengers
per day
60 NEW TRAINSETS BY 2010CPTM
12 new trainsetsin operationEmerald Line
47 NEW TRAINSETS BY 2010Metrô
1st NEW TRAINIn operation
MAR/09
PPP LINE 8 – DIAMOND: REFURBISHING AND NEW TRAINS
3 TRAINSREFURBISHED
BY 2010
• Refurbishing of 12 trains:• Air conditioning• Increasing Motorization
• 24 New Trains
• Public-PrivatePartnership:• 20 years of contract• Preventive and Corrective
Maintenance
REFURBISHING OFCPTM TRAINSETS
BEFORE AFTER
REFURBISHING OFCPTM TRAINSETS
27 TRAINSETSREFURBISHEDIN OPERATION
REFURBISHING OF METRÔ TRAINS
REFURBISHING OF TRAINSLINES 1 and 3
98 TOTAL
HEADWAY REDUCTION
LINE CURRENT HEADWAY 2010 HEADWAYLine 1 – Blue 109 sec 95 sec
Line 2 – Green 150 sec 128 sec
Line 3 – Red 101 sec 80 sec
Line 4 – Yellow - 131 sec
Line 5 – Lilac 307 sec 208 sec
Line 7 – Ruby 10 min 4 min
Line 8 – Diamond 9 min 5 min
Line 9 – Emerald 7 min 4 min
Line 10 – Turquoise 10 min 6 min
ABC Express (Line 10 – Turquoise) - 8 min
Line 11 – Coral 11 min 8 min
East Express (Line 11 – Coral) 7 min 5 min
Line 12 – Sapphire 11 min 4 min
Line 13 – Jade - 10 min
Airport Express (Line 14 – Onyx) - 15 min
TRAVEL TIME GAIN
Routes Current Time Time Gain(minutes/day) (minutes/day)
Butantã Luz 120 90Capão Redondo Sé 198 54Grajaú Campo Belo 200 114Grajaú Clínicas 244 142Grajaú Sé 244 128Itaquera Pinheiros 118 40Lapa Pinheiros 76 34Tucuruví Pinheiros 100 44USP Leste Pinheiros 128 62Vila Prudente Jabaquara 100 44Vila Prudente Pinheiros 166 114Vila Prudente Sé 80 40Diadema Vila Prudente 200 118Francisco Morato Paulista 192 62Guarulhos Tucuruvi 167 89Itapevi Paulista 166 46Itaquaquecetuba Sé 160 30Perus Pinheiros 106 32Poá Luz 122 30Santo André Barra Funda 92 30Taboão da Serra Luz 164 44