  • SAP: Project System

    TATA TECHNOLOGIES Page 1 of 41

    Version2: Arpita

    20.01.2005

    SAP

    PROJECT SYSTEM HANDBOOK

    FOR NPI PLANNERS

  • SAP: Project System

    TATA TECHNOLOGIES Page 2 of 41

    Version2: Arpita

    20.01.2005

    General Login Information

    Double Click on SAP LOGON Icon Select development server of SAP 4.6C Select Client 250 Enter User id & Password

    Master Data Requirements Controlling Area Company Code Business Area Plant Cost Center Activity Type Cost Element GL Account Purchasing Organisation Purchasing Group Material Group Profit Center

    Project Management Transactional Steps

    Project Definition creation WBS Creation Network & Activity creation Component Planning Plant Approval Corporate Planning Approval Budget Creation Board Approval Budget Release WBS Release Purchase order release Procurement cycle starts Production cycle starts Labour hour confirmation Settlement of Cost WBS completion AUC converts to Asset

  • SAP: Project System

    TATA TECHNOLOGIES Page 3 of 41

    Version2: Arpita

    20.01.2005

    Project Definition

    The project definition is the binding framework for all organizational elements within a project. You can also define non-binding start and finish dates for the project

    Menu Path: Logistics -> Project System -> Project -> Special Maintenance Functions -> Structure Planning -> Work Breakdown Structure -> Project Definition -> Create Transaction: CJ01 This transaction is carried out for the creation of Project Definition by the Coordinator or the NPI office after he receives the approved proposals from the respective cost centers.

    Person Responsible: Coordinator / NPI Office

    Refer to the Project Coding Mask for TATA Motors as explained below

  • SAP: Project System

    TATA TECHNOLOGIES Page 4 of 41

    Version2: Arpita

    20.01.2005

    T.00.X1X2X3.000.000.00.00

    T Represents projects in Tata Motors

    00 Year of Project Commencement e.g. 03 ,04

    X1X2X3 X1 : C = CVBU ; M = MUV ; K = CAR X2 : A = HCV ; B = MCV ; C = LCV ; D = SUB FOUR TONNE-CUB ; E = BUS-HCV ; F = BUS-MCV ; G = BUS-LCV ; H = ENGINES ; I = TRANSMISSION ; J = AXLE ; K = CAB ; L = SUMO/SPACIO ; M = SAFARI ; N = 207 ; O = INDICA ; P = SEDAN ; Q = ESTATE X3 : N = NEW GENERATION ; D = DERIVATIVE ; E = ENHANCEMENT ; F = FACELIFT ; U = UPGRADE ; V = VERSION

    000 Running Serial number for given project category 001 to 500 = PCBU & CAR 501 to 999 = CVBU

    000 Level 1 WBS element serial number to be standardized as follows: Characters Work breakdown (alternate characters) 001 ERC(Inhouse) ERI 002 ERC(Outsource) ERO 003 PE (Inhouse) PET 004 PE(Outsource) PEO 005 SQIG /ADD SQI and ADD 006 Plant and Machinery PAM 007 PO,PP Trials TRI 008 Marketing(Launch) MKT 009 Others(not known) MSC

    00 Level 2 WBS element serial number to be standardized as follows (for PE toolings only) : Characters Activity (alternate characters) (Toolings reqd for) 01 ENGINE AE 02 GEAR BOX AG 03 BIW AB 04 PRESS/FRAME AF 05 VEH ASSY AV 06 STEERING AS 07 AXLE AA 08 PAINT AP

    0 Level 3 WBS element serial number to be standardized as follows (for PE toolings only) : Characters Activity (alternate characters) (Toolings reqd for) 1 Non Foundry toolings N 8 Foundry toolings F

    All projects for TATA Motors will be defined as per above coding mask. In TATA Motors WBS can be created up to level 4.

  • SAP: Project System

    TATA TECHNOLOGIES Page 5 of 41

    Version2: Arpita

    20.01.2005

    Field Definitions: Field Name Mandatory Remarks

    Project def Yes Enter new project number System help is available to search next available number, using OPEN NUMBER Push Button

    Project Profile

    Yes Profile determines which kind of project it is and based on settings fields are displayed on the screen

    Template Optional Data will be copied from reference template

  • SAP: Project System

    TATA TECHNOLOGIES Page 6 of 41

    Version2: Arpita

    20.01.2005

    Project Definition Details Screen: Basic Data Tab:

    Field Definitions: Field Name Mandatory Remarks

    Description Yes Enter Project Description

    Start Yes Enter Start Date of overall project

    End Yes Enter End Date of overall project

    Controlling Area

    Yes Use '0100' for Tata Motors

    Company Code

    Yes Use '0100' for Tata Motors

    Business Area

    Yes Based on Location select BA from drop down box

    Plant Optional Based on Location select

    Click here to see the Project Status

  • SAP: Project System

    TATA TECHNOLOGIES Page 7 of 41

    Version2: Arpita

    20.01.2005

    Plant from drop down box

    Profit Center Yes Enter the Correct Profit Center from drop down box

    Mask ID Optional Free field helps you to search project

    Factory Calendar

    Optional Select calendar for location where work is going to get exceeded

    Enter in all the relevant data. TATA Motors TAB:

    Field Name Mandatory Remarks

    Market Classification

    Yes Select from Drop Down

    Project Type No Select from Drop Down

    Launch Date No Enter Launch date

  • SAP: Project System

    TATA TECHNOLOGIES Page 8 of 41

    Version2: Arpita

    20.01.2005

    NPV No To be put by User

    IRR No To be put by User

    EVA No To be put by User

    Life Cycle Volume

    No To be put by User

    Pay Back No To be put by User

    Project Status Management: The current status of a project or an object in a project determines which business transactions can be executed. Statuses document the current processing stage of an object

    When the different stages of the project are completed, the relevant gate status is ticked by the project office.

  • SAP: Project System

    TATA TECHNOLOGIES Page 9 of 41

    Version2: Arpita

    20.01.2005

    Work Breakdown Structure It is the functional basis for further planning steps in a project, for example, for process planning, cost planning, scheduling, capacity planning or costing as well as projects control. It gives you a clear picture of the project and facilitates the coordination and implementation of the project from a management standpoint.

    Menu Path: Logistics -> Project Systems -> Project -> Special Maintenance Functions -> Structure Planning -> Change Project Transaction: CJ20 This transaction is carried out by the Project Planner, Coordinator / NPI Office, Department Head for creating WBS for each cost center. Person Responsible: Project Planner, Coordinator / NPI Office, Department Head

    Field Name Mandatory Remarks

    Project def Yes Use drop down menu to select existing project number

  • SAP: Project System

    TATA TECHNOLOGIES Page 10 of 41

    Version2: Arpita

    20.01.2005

    Press Enter.

  • SAP: Project System

    TATA TECHNOLOGIES Page 11 of 41

    Version2: Arpita

    20.01.2005

    Short Cut: Use ' .01 to generate new WBS. Field Name Mandatory Remarks

    WBS element

    Yes Based on Masking system allows to create running WBS number

    Description Yes Enter WBS description

    Short id No You can change default number to identify WBS by different name

    Note: To Create a lower level WBS change the level to 2 instead of 1 and follow the same steps as that of creating the first level wbs element.

  • SAP: Project System

    TATA TECHNOLOGIES Page 12 of 41

    Version2: Arpita

    20.01.2005

    Double Click on WBS Element for Details Screen: Tata Motors Tab:

    Field Name Mandatory Remarks

    Supply Source Yes Select from drop down box

    Basis of Estimate Yes Select from drop down box

    Primary Category Yes Select from drop down box

    Secondary Category No Select from drop down box

    Aggregate No Select from drop down box

    Business Unit Yes Select from drop down box

    Inv. Classification Yes Select from drop down box

    NPI Process Yes Select from drop down box

    WBS Element description

    Yes Appropriate description to be put

    Go to next tab WBS Basic Data

  • SAP: Project System

    TATA TECHNOLOGIES Page 13 of 41

    Version2: Arpita

    20.01.2005

    WBS Basic Data:

    Field Name Mandatory Remarks

    Project type

    No Select from drop down box

    Priority No Select from drop down box

    Responsible Person

    No Select from drop down box

    Resp. Cost Center

    Yes Cost Center where asset will be capitalised

    Req. Cost Center

    No Who is going to consume

    Billing Element

    Optional If WBS is billable to customer then check this option

    User Status

    Detail explanation on another page

    System Status

    System based on different business transaction maintains different statuses

    Go to next tab Dates.

  • SAP: Project System

    TATA TECHNOLOGIES Page 14 of 41

    Version2: Arpita

    20.01.2005

    Dates Tab:

    Field Name Mandatory Remarks

    Basic Start Date

    Yes Plan Start date

    Duration Yes Duration of the activity

    Basic End Date

    No Plan End date

    Forecast Start No

    Forecast End No

    Calendar Yes Select Calendar

  • SAP: Project System

    TATA TECHNOLOGIES Page 15 of 41

    Version2: Arpita

    20.01.2005

    Addition of PS Text to a WBS Element In the CJ20 Screen go to Details -> PS texts as shown below:

    This will give the following screen:

  • SAP: Project System

    TATA TECHNOLOGIES Page 16 of 41

    Version2: Arpita

    20.01.2005

    Select the type of PS text like in the example Z1 has been selected and give a Description and press Enter which will give the following screen where one can enter the text in detail.

  • SAP: Project System

    TATA TECHNOLOGIES Page 17 of 41

    Version2: Arpita

    20.01.2005

    Back and Save.

  • SAP: Project System

    TATA TECHNOLOGIES Page 18 of 41

    Version2: Arpita

    20.01.2005

    NETWORK

    A network can represent the sequence of activities in a project or the sequence of a single activity within a project.

    Menu Path: Logistics -> Project Systems -> Project -> Special Maintenance Functions -> Network -> Create Transaction: CJ20 This Transaction is carried out by the Planner who creates separate Network activities for each WBS. Person Responsible: Project Planner Select the WBS element and click on Activity Data Tab. This will bring us to the detail screen for creating Network Activity.

    Click on Activity data tab

  • SAP: Project System

    TATA TECHNOLOGIES Page 19 of 41

    Version2: Arpita

    20.01.2005

    Type: Internal Activity (Mainly for Internal Labor usage)

    Field Name Mandatory Remarks

    Activity Yes System defaults number

    Description No Activity Description

    Duration Unit No E.g. Hours/ Day

    Plan Duration Yes Plan Duration

    Work Center Yes Resource group within Cost Center

    Plant Yes Facility where activity is going to be perform

    Activity type Yes Skill set from cost center / Work Center

    For selecting the Activity Type, follow the process wherein the dates for the activity are to be put in. Double click on activity and then go to Dates tab where the dates can be put in. Save.

  • SAP: Project System

    TATA TECHNOLOGIES Page 20 of 41

    Version2: Arpita

    20.01.2005

    This will enable us to select the relevant Activity Type.

  • SAP: Project System

    TATA TECHNOLOGIES Page 21 of 41

    Version2: Arpita

    20.01.2005

    Type: External Activity (Mainly for Material)

    External Activity can be Material and Services. For Components: Select Activity and click on the Component Overview Icon to go to the component overview screen.

    Select the Activity and click on the Component Overview icon

  • SAP: Project System

    TATA TECHNOLOGIES Page 22 of 41

    Version2: Arpita

    20.01.2005

    Component Overview Screen:

    If Material was procured before or if it is Stock item then select material code from drop down list else for new Capital Material procurement use Generic material CAPITAL_DOM for domestic procurement and CAPITAL_IMP for imports. Double click on the item number and enter the price for the component.

  • SAP: Project System

    TATA TECHNOLOGIES Page 23 of 41

    Version2: Arpita

    20.01.2005

    Click here for Invoice Plan.

  • SAP: Project System

    TATA TECHNOLOGIES Page 24 of 41

    Version2: Arpita

    20.01.2005

    Invoice Plan: Click on the Button Invoice Plan as shown above to get the following screen:

    Save. Field Name Mandatory Remarks

    Activity Yes System defaults number

    Description No Description of the activity

    Purchasing Org No Who is going to perform procurement activity

    Cost Element Yes Where cost to get booked

    Vendor No Required at the time of WBS release

    Material Group Required at the time of WBS release

    Price Yes Expected price of the material

    Activity Qty Yes Plan Quantity

    Enter the Details as shown

  • SAP: Project System

    TATA TECHNOLOGIES Page 25 of 41

    Version2: Arpita

    20.01.2005

    Type: External Activity (Mainly for Services)

    Select Service tab & enter description of activity. Press Enter to get to the next screen.

    Tick the Services Box for creation of Service

  • SAP: Project System

    TATA TECHNOLOGIES Page 26 of 41

    Version2: Arpita

    20.01.2005

    Enter the Contract number where relevant. If Service is coded then pick up number from drop down else enter short text manually. Enter all the relevant info including Qty and Price and press F3 twice.

  • SAP: Project System

    TATA TECHNOLOGIES Page 27 of 41

    Version2: Arpita

    20.01.2005

    Type: Primary Cost Activity (Mainly General Expenses)

    Field Name Mandatory Remarks

    Activity Yes System defaults number

    Description No Description of the activity

    Amount Yes Total Plan amount

    Currency Yes

    Cost Element Yes While using search, put TATA in the chart of accounts.

    Press Enter to fill up Details.

  • SAP: Project System

    TATA TECHNOLOGIES Page 28 of 41

    Version2: Arpita

    20.01.2005

    Save after having filled up the details in the respective Tabs.

  • SAP: Project System

    TATA TECHNOLOGIES Page 29 of 41

    Version2: Arpita

    20.01.2005

    WBS Status Management The current status of a project or an object in a project determines which business transactions can be executed. Statuses document the current processing stage of an object

    To check the WBS Status Select the WBS Element or the Activity and the click on the Status Button

  • SAP: Project System

    TATA TECHNOLOGIES Page 30 of 41

    Version2: Arpita

    20.01.2005

    Based on Status certain business transactions will be allowed: Draft Capex: By Default WBS will have this status. Deferred Capex: If the WBS is not approved, it is put on hold and this status is set. (Plant Head / Corporate Planning) Project Manager Approved: This Status is set by Project Manager Project Office Approved: This Status is set by Project Office HO Clarification requested: This status is set when the Head Office asks for any clarification. (Corporate Planning) Management Approved: When Management Approves the Budget, this status is set. (Corporate Planning) Budget Closed: In case the work was dropped in the middle and the budget is no longer required then this status is set. (Planner) Budget Not Required: This status is set in case planner wants to return approved budget. Budget Carry Forward: This Status is set in case the excess budget for the year is to be carried forward to the next financial year. (Corporate Planning)

  • SAP: Project System

    TATA TECHNOLOGIES Page 31 of 41

    Version2: Arpita

    20.01.2005

    To use Template for creating new proposals. For including Standard Network as an activity set in the WBS Element. Go to Activity screen then go to menu Network -> Include Std. Network which will give the following screen.

    Select a Standard Network from the List and press Enter

  • SAP: Project System

    TATA TECHNOLOGIES Page 32 of 41

    Version2: Arpita

    20.01.2005

    Standard Network has been included which contains these three activities

  • SAP: Project System

    TATA TECHNOLOGIES Page 33 of 41

    Version2: Arpita

    20.01.2005

    To attach a document to a WBS Element Select the WBS and then click on the Services for object button -> Create -> Create attachment as shown below.

    Click here and follow the path

  • SAP: Project System

    TATA TECHNOLOGIES Page 34 of 41

    Version2: Arpita

    20.01.2005

    Which then gives us the option of selecting which ever document we want to attach from the directory as needed.

  • SAP: Project System

    TATA TECHNOLOGIES Page 35 of 41

    Version2: Arpita

    20.01.2005

    Create Standard Network

    Menu Path: Logistics -> Project Systems -> Basic Data -> Templates -> Standard Network Transaction: CN01 This transaction is carried out by the Project Planner, Coordinator / NPI Office, or Corporate Planning for creating Standard Network. Person Responsible: Project Planner, Coordinator / NPI Office, Corporate Planning

    Fill up the Profile and press Enter.

    To be left blank system generated number

  • SAP: Project System

    TATA TECHNOLOGIES Page 36 of 41

    Version2: Arpita

    20.01.2005

    Field Name Mandatory Remarks

    Network Usage No Select from drop down

    Planner Group No Select from Match Code

    Network Status No Select from drop down

    Std. WBS Element

    No Select from Match Code

    Predefined Plant

    No Select from Match Code

    Click on activities button to go to the next screen.

    Click on Activities Button

  • SAP: Project System

    TATA TECHNOLOGIES Page 37 of 41

    Version2: Arpita

    20.01.2005

    Click on the External Activities Tab and create the Activity as follows:

    Press Enter to go to the details screen.

  • SAP: Project System

    TATA TECHNOLOGIES Page 38 of 41

    Version2: Arpita

    20.01.2005

    Field Name Mandatory Remarks

    Work Center / Plant

    Yes Select from Match code

    Material Group Yes Select from Match Code

    Purchasing Group

    Yes Select from Match Code

    Purchase Organisation

    No Select from Match Code

    Net Price No Enter the Price of the Component

  • SAP: Project System

    TATA TECHNOLOGIES Page 39 of 41

    Version2: Arpita

    20.01.2005

    Click on the Internal Activities Tab and create the Activity as follows:

    Press Enter to go to the Details Screen.

  • SAP: Project System

    TATA TECHNOLOGIES Page 40 of 41

    Version2: Arpita

    20.01.2005

    Field Name Mandatory Remarks

    Work Center / Plant

    Yes Select from Match code

    Work No No. of days to be filled up

    Click on tick which takes you back to the previous screen and save the internal number gets generated as shown below.

  • SAP: Project System

    TATA TECHNOLOGIES Page 41 of 41

    Version2: Arpita

    20.01.2005

    The Standard Network with the system generated number has been created.

    Internal Number Generated by the system