sarasota memorial hospital campus improvement plan

23
Sarasota Memorial Hospital Campus Improvement Plan Neighborhood Advisory Council March 13, 2012

Upload: kaseem-hawkins

Post on 01-Jan-2016

47 views

Category:

Documents


6 download

DESCRIPTION

Sarasota Memorial Hospital Campus Improvement Plan. Neighborhood Advisory Council March 13, 2012. Sarasota Memorial Hospital Campus Improvement Plan Site Improvements Utility Construction / Landscape / Walkways / Driveways. 2. 3. Sarasota Memorial Hospital Campus Improvement Plan. - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: Sarasota Memorial Hospital Campus Improvement Plan

Sarasota Memorial HospitalCampus Improvement Plan

Neighborhood Advisory CouncilMarch 13, 2012

Page 2: Sarasota Memorial Hospital Campus Improvement Plan

Sarasota Memorial HospitalCampus Improvement Plan

Site ImprovementsUtility Construction / Landscape /

Walkways / Driveways

2

Page 3: Sarasota Memorial Hospital Campus Improvement Plan

3

Page 4: Sarasota Memorial Hospital Campus Improvement Plan

Sarasota Memorial HospitalCampus Improvement Plan

Patient Tower / Bridges / Stair / Elevator Structure Development

4

Page 5: Sarasota Memorial Hospital Campus Improvement Plan

Project Phasing 7

Surgery/CS Vertical Expansion & Connector Complete

New Patient Tower Structure

Legend: Green box means that portion will be completed in that phase. Beige box is ongoing.

13

Page 6: Sarasota Memorial Hospital Campus Improvement Plan

6

Page 7: Sarasota Memorial Hospital Campus Improvement Plan

7

Northeast TowerSecond Floor Waiting Room

Page 8: Sarasota Memorial Hospital Campus Improvement Plan

Sarasota Memorial HospitalCampus Improvement Plan

Patient Tower And Epic ParkCourtyards

8

Page 9: Sarasota Memorial Hospital Campus Improvement Plan

9

9

Page 10: Sarasota Memorial Hospital Campus Improvement Plan

10

10

Page 11: Sarasota Memorial Hospital Campus Improvement Plan

Sarasota Memorial HospitalCampus Improvement Plan

New Patient TowerInterior DevelopmentNinth thru First Floor

11

Page 12: Sarasota Memorial Hospital Campus Improvement Plan

12

9th Floor

Page 13: Sarasota Memorial Hospital Campus Improvement Plan

13

8th Floor

Page 14: Sarasota Memorial Hospital Campus Improvement Plan

7th Floor

14

Page 15: Sarasota Memorial Hospital Campus Improvement Plan

15

6th Floor

Page 16: Sarasota Memorial Hospital Campus Improvement Plan

16

5th Floor

Page 17: Sarasota Memorial Hospital Campus Improvement Plan

17

4th Floor

17

Page 18: Sarasota Memorial Hospital Campus Improvement Plan

18

3rd Floor

18

Page 19: Sarasota Memorial Hospital Campus Improvement Plan

19

1st Floor

19

Page 20: Sarasota Memorial Hospital Campus Improvement Plan

Sarasota Memorial HospitalCampus Improvement Plan

Project Safety Report

20

Page 21: Sarasota Memorial Hospital Campus Improvement Plan

Campus Improvement Plan

21

MONTHLY PROJECT SAFETY REPORT 1/31/12

SKANSKA PROJECT SAFETY STATISTICS

Current Month

Year to Date

Project to Date

Current Month

Year to Date

Project to Date

Work Hours 3,970 3,970 196,326 0 0 0

Fatalities 0 0 0 0 0 0

Lost Workday Cases

0 0 0 Recordable Cases 0 0 1

Days Away From Work

0 0 0

SUBCONTRACTOR SAFETY STATISTICS

Current Month

Year to Date

Project to Date

Current Month

Year to Date

Project to Date

Work Hours 42,696 42,696 990,782

Fatalities 0 0 0

Lost Workday Cases

0 0 0

Days Away From Work

0 0 0 Recordable Cases 1 1 19

Total 46,666 46,666 1,187,108 Total Recordable Cases 1 1 20

Page 22: Sarasota Memorial Hospital Campus Improvement Plan

Sarasota Memorial HospitalCampus Improvement Plan

Project Participation By

Local Subcontractors and Vendors

22

Page 23: Sarasota Memorial Hospital Campus Improvement Plan

Project Name Central Energy Plant

Patient Tower

Number of Employees on Site 259 564

Employees Living in Primary Market Area 131 418

Employees Living in Secondary Market & Other Areas

98 146

Through Dec 2010. Will increase as Bed Tower Construction Progresses

Local Participation

23