sasol secunda complex: materials management … · 5/16/2019 · 1.2 redundant materials...
TRANSCRIPT
SASOL SECUNDA COMPLEX: MATERIALS MANAGEMENT
ENVIRONMENTAL EXEMPTION COMPLIANCE AUDIT REPORT
17.2.17 EV 40 - REDUNDANT MATERIALS MANAGEMENT (ESTABLISHMENT OF A RECLAMATION YARD)
16 MAY 2019
CONFIDENTIAL
WSP Environmental (Pty) Ltd.
ENVIRONMENTAL EXEMPTION COMPLIANCE AUDIT REPORT
17.2.17 EV 40 - REDUNDANT MATERIALS MANAGEMENT (ESTABLISHMENT OF A RECLAMATION YARD)
SASOL SECUNDA COMPLEX: MATERIALS
MANAGEMENT
TYPE OF DOCUMENT (VERSION)
CONFIDENTIAL
PROJECT NO.: 41101534
DATE: MAY 2019
WSP
BUILDING C
KNIGHTSBRIDGE, 33 SLOANE STREET
BRYANSTON, 2191
SOUTH AFRICA
T: +27 11 361 1392
F: +27 11 361 1381
WSP.COM
Q U A L I T Y M A N A G E M E N T
ISSUE/REVISION FIRST ISSUE REVISION 1 REVISION 2 REVISION 3
Remarks Draft for Review –
Compliance Audit
EA Ref:
17.2.17 EV40
Draft V.2 –
Compliance Audit
EA Ref:
17.2.17 EV40
Final report –
Compliance Audit
EA Ref:
17.2.17 EV40
Date April 2019 May 2019 May 2019
Prepared by Ashlea Strong Ashlea Strong Ashlea Strong
Signature
Checked by Jenny Cope Jenny Cope Jenny Cope
Signature
Authorised by Jenny Cope Jenny Cope Jenny Cope
Signature
Project number 41101534 41101534 41101534
Report number 019 019 019
File reference file:///W:\000 NEW Projects\41101534 - Sasol EA and EMP Audits\42 ES\2-REPORTS\
S I G N A T U R E S
PREPARED BY
Ashlea Strong
Principal Consultant
REVIEWED BY
Jenny Cope
Associate
This Compliance Audit report (Report) has been prepared by WSP Environmental (Pty) Ltd (WSP) on behalf
and at the request of Sasol Synfuels: Secunda Operations (Client), to provide the Client with an understanding
of their compliance with the conditions included in the Environmental Authorisation
Unless otherwise agreed by us in writing, we do not accept responsibility or legal liability to any person other
than the Client for the contents of, or any omissions from, this Report.
To prepare this Report, we have reviewed only the documents and information provided to us by the Client or
any third parties directed to provide information and documents to us by the Client. We have not reviewed any
other documents in relation to this Report, except where otherwise indicated in the Report.
P R O D U C T I O N T E A M
CLIENT
SHE: Environmental Compliance
Specialist
Broni van der Meer
Materials Management Production
Senior Manager, Sasol Supply Chain
Johan Fouche
WSP
Associate Jenny Cope
Lead Auditor Anri Scheepers
Lead Auditor Ashlea Strong
Auditor Mpendulo Dlamini
ENVIRONMENTAL EXEMPTION COMPLIANCE AUDIT REPORT Project No. 41101534 SASOL SECUNDA COMPLEX: MATERIALS MANAGEMENT
WSP May 2019
TABLE OF CONTENTS
1 INTRODUCTION ........................................ 1
1.1 Terms of Reference ................................................. 1
1.2 Redundant Materials Management (Authorisation
Number: 17.2.17 EV40) ............................................ 1
2 AUDIT SCOPE ........................................... 3
3 AUDIT METHODOLOGY ........................... 4
3.1 Audit Checklist ........................................................ 4
3.2 Site Inspection ......................................................... 4
3.3 Documentation Considered ................................... 4
3.4 Audit Compliance Assessment .............................. 5
3.5 Audit Team ............................................................... 5
3.6 Assumptions and Limitations ................................ 6
4 AUDIT FINDINGS ...................................... 7
5 SUMMARY OF THE AUDIT FINDINGS ... 24
5.1 Environmental Exemption .................................... 24
ENVIRONMENTAL EXEMPTION COMPLIANCE AUDIT REPORT Project No. 41101534 SASOL SECUNDA COMPLEX: MATERIALS MANAGEMENT
WSP May 2019
TABLES
TABLE 1: COMPLIANCE LEVEL DEFINITION AND TARGET COMPLETION DATES .................. 5
TABLE 2: AUDIT FINDINGS – ENVIRONMENTAL EXEMPTION . 7
TABLE 3: SUMMARY OF EXEMPTION COMPLIANCE AUDIT FINDINGS .................................... 24
FIGURES
FIGURE 1: REDUNDANT MATERIAL MANAGEMENT LAYOUT (SOURCE: GOOGLE EARTH, 2016) .............................................. 2
FIGURE 2: NUMBER/COUNT CONTRIBUTION OF FINDINGS MADE TO THE EXEMPTION CONDITIONS PER SECTION ..... 25
FIGURE 3: OVERALL COUNT FINDINGS ON COMPLIANCE TO THE EXEMPTION CONDITIONS ........ 25
FIGURE 4: PERCENTAGE CONTRIBUTION OF FINDINGS MADE TO THE EXEMPTION CONDITIONS PER SECTION ..................................... 26
FIGURE 5: OVERALL PERCENTAGE FINDINGS ON COMPLIANCE TO THE EXEMPTION CONDITIONS 26
APPENDICES
A ENVIRONMENTAL EXEMPTION (17.2.17 EV40)
ENVIRONMENTAL EXEMPTION COMPLIANCE AUDIT REPORT Project No. 41101534 SASOL SECUNDA COMPLEX: MATERIALS MANAGEMENT
WSP May 2019
Page 1
1 INTRODUCTION
1.1 TERMS OF REFERENCE
Sasol South Africa (Pty) Limited operating through its Secunda Synfuels Operations (Sasol) appointed WSP
Environmental (Pty) Ltd (WSP) as an independent environmental consultant, to undertake a compliance audit
and compile an audit report according to the requirements of the National Environmental Management Act (No.
107 of 1998) as amended (NEMA). This report presents the findings of the compliance audit completed for the
Environmental Exemption (Reference number: 17.2.17 EV40 issued on 23 March 2005) for the period
December 2014 to February 2019.
1.2 REDUNDANT MATERIALS MANAGEMENT
(AUTHORISATION NUMBER: 17.2.17 EV40)
The Redundant Materials Management (RMM) area (Reclamation Yard) of Sasol Secunda is used for the
handling of obsolete materials that are unrequired by Sasol businesses and are sold/disposed of through a service
provider. An Exemption in terms of Section 28A of the Environmental Conservation Act (No. 73 of 1989)
(ECA) with conditions set out in an attached Record of Decision (RoD) was received from the Mpumalanga
Department of Agriculture and Land Administration (MDALA) on 23 March 2005 (Reference Number: 17.2.17
EV40) (Appendix A).
The site is legally permitted to handle metals, steel, plastic drums and containers, conveyer belting, motor
vehicle tyres, instrumentation equipment, electric cables, plastics, wood, furniture, housing units and vehicles.
Directions in terms of Section 20 were also received from the Department of Water Affairs and Forestry
(DWAF) on 17 March 2005 (Reference Number: 16/2/7/C121/B/028), however these conditions do not form
part of the scope of this audit.
The site is identified by the Department of Water Affairs and Forestry (DWAF) as a temporary waste storage,
reclamation and recycling site. The site is classified by DWAF as Class G:C:B-.
Figure 1 provides an overview of the RMM (Reclamation Yard).
ENVIRONMENTAL EXEMPTION COMPLIANCE AUDIT REPORT Project No. 41101534 SASOL SECUNDA COMPLEX: MATERIALS MANAGEMENT
WSP May 2019
Page 2
Figure 1: Redundant Material Management Layout (Source: Google Earth, 2016)
ENVIRONMENTAL EXEMPTION COMPLIANCE AUDIT REPORT Project No. 41101534 SASOL SECUNDA COMPLEX: MATERIALS MANAGEMENT
WSP May 2019
Page 3
2 AUDIT SCOPE The 7 April 2017 amendment to the Environmental Impact Assessment (EIA) regulations introduced the
requirement for the auditing for all EAs and EMPrs in effect on 8 December 2014 and submission of audit
reports to the Department of Environmental Affairs (DEA) by 7 December 2019 and every five years thereafter.
This audit is designed to meet the requirements of Regulation 34 of the EIA Regulations, 2014.
The Audit period runs from December 2014 to February 2019, therefore any construction related conditions that
would have been relevant pre-December 2014 are considered not applicable (outside Audit period).
The objective of the audit was to:
— Assess the level of compliance with the conditions of the Exemption;
— Identify and assess any new impacts and risks that result from undertaking the activity;
— Make recommendations in order to achieve compliance in terms of the Exemption; and,
— Ensure the commitments contained in Condition 8.01 of the Exemption are completed, more specifically:
— “Records relating to the compliance or non-compliance with the conditions of this Exemption must be
kept in good order. Such records must be made available to this Department within seven (7) working
days from the date of a written request by the Department for such records.”
ENVIRONMENTAL EXEMPTION COMPLIANCE AUDIT REPORT Project No. 41101534 SASOL SECUNDA COMPLEX: MATERIALS MANAGEMENT
WSP May 2019
Page 4
3 AUDIT METHODOLOGY The International Organisation of Standardisation (ISO) 14010, ISO 14011 and ISO 14012 guideline documents
were utilised as a template during the compliance audit process. This methodology ensures that the compliance
audit was conducted in a systematic and independent manner that was documented and objectively evaluated to
determine compliance to the Exemption conditions.
The audit process comprised the following:
— Confirmation of the audit checklist;
— Site inspection (25 March 2019);
— Review of documentation relevant to the conditions of the Exemption (e.g. records,
permits/certificates/maintenance logs/monitoring results/previous reports etc.); and
— Compilation of an audit report.
3.1 AUDIT CHECKLIST
WSP compiled an audit checklist to assist with the Exemption compliance audit (Section 4).
3.2 SITE INSPECTION
Environmental Consultant, Mpendulo Dlamini, conducted the site inspection on 25 March 2019. The findings
and observations of the site visit are recorded and summarised in Section 4 with evidence included in Table 2.
Key personnel interviewed included:
— Manager, Redundant Materials Management: Pieter Carter.
3.3 DOCUMENTATION CONSIDERED
The following documentation was provided and considered:
— 1.03_EX_Direction_16.2.7.C121.B.028_2005-03-17;
— 1.03_EX_DWAF Reasons_16.2.7.C121.B.028_2004-11-12;
— 1.03_2nd Hand Goods Cert;
— 1.06_EX_Minutes ROD Discussion_17.2.17_2005-04-11;
— 1.06_EX_Reclamation yard_Appl for exemption_2004-08-13;
— 3.01_Declaration of scrap example;
— IWWMP SIC 2015 Final_2018-05-15;
— 3.06_EX_Storm water management report_RMM_2016-11-24;
— Sasol Compliance Statement – Water
— 3.05_RESM Weekly Monitoring_2004-2019
— GWMonitor Report Nov 2017 Final_Prj6129rev-01_2018-11-20
— Fugitive Emission Monitoring Plan_2018-10-18 updated;
— Waste Management Procedure_SGR-SHE-000017_Rev10_2017-09;
— 7.01_ERA-SCSS-RMM-BvdM 2015-11-03
— 7.01_Emergency Management Plan
— 5.01_EX_Storm water management report_RMM_2016-11-24;
— Sasol Compliance Statement – Complaints;
— Environmental complaints procedure_SGR-SHE-000022_Rev04_2015-08;
ENVIRONMENTAL EXEMPTION COMPLIANCE AUDIT REPORT Project No. 41101534 SASOL SECUNDA COMPLEX: MATERIALS MANAGEMENT
WSP May 2019
Page 5
— Environmental complaints procedure_SGR-SHE-000022_Rev05_2019-01;
— Environmental Complaints Register_2019-02-18;
— Onsite Checks; and
— Various email correspondence.
3.4 AUDIT COMPLIANCE ASSESSMENT
WSP utilised a pre-prepared audit checklist to assist with the audit execution (Table 2). The checklist included
the conditions and associated requirements as specified in the Exemption.
Each condition was verified, either by reviewing documentation, interviewing employees and/or visually
inspecting the facility. Each condition was rated in accordance with Table 1 below, and recommendations with
associated target completion dates included.
It should be noted that some of the Exemption conditions were apportioned according to the elements requiring
compliance assessment therein. Although some elements of the condition may have been compliant, if one of
the elements was determined to be non-compliant, the entire condition has been reported as such (and counted
as such during percentage compliance calculation). This apportionment further allowed for the development of
focussed recommendations and timeframes.
Table 1: Compliance Level Definition and Target Completion Dates
COMPLIANCE LEVEL DEFINITION
Compliant (C) Sasol could provide evidence for compliance with the commitment and condition and/or
relevant actions were implemented.
Non-compliant (NC) Specified commitments, conditions and documents were not in place or implemented
according to the requirements of the Exemption. Non-complaint conditions are given target
completion dates, as follows:
— Short term: 0 – 6 months.
— Medium term: 6 – 12 months.
— Long term: 12 – 18 months.
Not applicable (N/A) These are commitments are either not required yet or not applicable to Sasol.
— Conditions marked as “Noted” are considered information points only.
— Where conditions are considered “not auditable” within the scope of this assessment this
is stated and explained within the condition commentary.
Refer to Section 4 for the detailed audit findings (including evidence, recommendations and target completion
dates).
3.5 AUDIT TEAM
Environmental Consultant, Mpendulo Dlamini, was hosted by Broni van der Meer, Pieter Carter and Johan
Erasmus to whom we express our gratitude for their time and attention during our visit. A brief summary of the
external auditors’ experience is provided below.
— Auditor: Mpendulo Dlamini
Mpendulo has 5 years’ experience and is a multi-disciplined individual who completed his double major BSc
Environmental Science degree (Life Science and Environmental Science) at the University of KwaZulu-Natal
in 2014. He then further completed his BSc Honours Environmental Science (Spatial Epidemiology Research)
in 2015 at the same institution. Mpendulo has had exposure in the following sectors; oil and gas,
environmental consulting as well as environmental and public health. As a University Student, he has had
extensive training in biodiversity management and monitoring with a focus in plant science (undergraduate),
ENVIRONMENTAL EXEMPTION COMPLIANCE AUDIT REPORT Project No. 41101534 SASOL SECUNDA COMPLEX: MATERIALS MANAGEMENT
WSP May 2019
Page 6
and with Lakes Environment air quality and modelling software as well as environmental GIS and remote
sensing in spatial modelling (Post graduate). He also has experience as an Environmental Control Officer as
well as with working on Water Use License Applications and Integrated Water and Waste Management Plans
(Triplo4 Sustainable Solutions).
— Lead Auditor and Quality Assurance: Ashlea Strong
Ashlea has 16 years’ experience and holds a Masters in Environmental Management; a BTech (Nature
Conservation), and a National Diploma (Nature Conservation); She is also a Certified Environmental
Assessment Practitioner of South Africa (CEAPSA). She currently provides technical and strategic
expertise on a diverse range of projects in the environmental management field, including environmental
scoping and impact assessment studies, environmental management plans, waste and water management, as
well as the provision of environmental management solutions and mitigation measures. She has been
involved in the management of a number of large EIAs within South Africa and has environmental auditing
and training experience and expertise. Ashlea has carried out over 50 compliance audits and is well versed
in the audit process.
— Project Manager and Quality Assurance: Jenny Cope
Jenny is an environmental due diligence specialist, with over 11 years’ experience in the Environmental
Sector. Jenny’s experience includes managing and completing projects and portfolios internationally;
undertaking both detailed and broad Environmental, Health & Safety compliance and audits of across a
range of sectors. Jenny’s recent experience includes completion and management of several pan-European
and global projects requiring reviews of extensive virtual data rooms, on a very rapid turnaround, and
providing clients with ‘red flag’ reports to give clear commercial advice. Jenny has worked both in
environmental consultancies and with a developer, giving context to understanding the practicalities of
implementing recommendations.
3.6 ASSUMPTIONS AND LIMITATIONS
This Report has been prepared by WSP on behalf and at the request of Sasol, to provide the Client an
understanding of the Relevant Documents.
Unless otherwise agreed by us in writing, we do not accept responsibility or legal liability to any person other
than the Client for the contents of, or any omissions from, this Report.
To prepare this Report, we have reviewed only the documents and information provided to us by the Client or
any third parties directed to provide information and documents to us by the Client. We have not reviewed any
other documents in relation to this Report and except where otherwise indicated in the Report.
The findings, recommendations and conclusions given in this report are based on the author’s best scientific and
professional knowledge, as well as available information. This report is based on survey and assessment
techniques which are limited by time and budgetary constraints relevant to the type and level of investigation
undertaken; WSP and its staff reserve the right to modify aspects of the report including the recommendations if
and when new information may become available from on-going research or further work in this field, or
pertaining to this investigation.
Although WSP exercises due care and diligence in rendering services and preparing documents, WSP accepts
no liability, and Sasol, by receiving this document, indemnifies WSP and its directors, managers, agents and
employees against all actions, claims, demands, losses, liabilities, costs, damages and expenses arising from or
in connection with the services rendered, directly or indirectly by the use of the information contained in this
document.
This report must not be altered or added to without the prior written consent of the author. This also refers to
electronic copies of this report which are supplied for the purposes of inclusion as part of other reports.
Similarly, any recommendations, statements or conclusions drawn from or based on this report must make
reference to this report. If this report is used as part of a main report, the report in its entirety must be included
as an appendix or separate section to the main report.
ENVIRONMENTAL EXEMPTION COMPLIANCE AUDIT REPORT Project No. 41101534 SASOL SECUNDA COMPLEX: MATERIALS MANAGEMENT
WSP May 2019
Page 7
4 AUDIT FINDINGS Table 2: Audit Findings – Environmental Exemption
REF: COMMITMENT COMPLIANCE FINDING RECOMMENDATION
1. GENERAL CONDITIONS
1.01 This Exemption refers only to the project as specified above.
Separate applications must be lodged for any other
development and/or activity at or near the proposed
development, which is covered by S21 and 22 of the Act and
Government Notice R1182 of 5 September 1997.
N/A Noted None.
1.02 Exemption is only granted in terms of S 28A of the Act and
does not exempt the holder from compliance with other
relevant legislation.
N/A Noted None.
1.03 Ensure that the necessary permits, approvals, service level
agreements where it is relevant from or between the
following institutions’ are in place:-
1.3.1 Govan Mbeki Municipality
1.3.2 DWAF"
C The Auditor noted that all relevant permits, approvals and
agreements are in place for the RMM. These include:
— Second Hand Goods Permit issued by the South African Police
Service (Valid until 01 November 2022); and
— Directions in terms of the Section 20 permit issued by the
Department of Water Affairs and Forestry
The Auditor noted that the Govan Mbeki Municipality currently
holds jurisdiction for the Air Emission Licence (AEL). It is noted
that the activities undertaken at the RMM do not constitute
activities that would require an AEL and therefore no known
permits are required from the Municipality.
Evidence:
— 1.03_EX_Direction_16.2.7.C121.B.028_2005-03-17
— 1.03_EX_DWAF Reasons_16.2.7.C121.B.028_2004-11-12
— 1.03_2nd Hand Goods Cert
None.
ENVIRONMENTAL EXEMPTION COMPLIANCE AUDIT REPORT Project No. 41101534 SASOL SECUNDA COMPLEX: MATERIALS MANAGEMENT
WSP May 2019
Page 8
REF: COMMITMENT COMPLIANCE FINDING RECOMMENDATION
1.04 This Department may change and/or amend any of the
conditions in this exemption if, in the Department's opinion
is environmentally justified
N/A Noted. The Auditor noted that there has been no correspondence
forthcoming from the Department.
None.
1.05 A copy of this Exemption must be made available on site
during construction and all relevant staff, contractors and sub
contractors must be familiar with the contents of this
Exemption.
N/A This condition is considered outside of the audit period
(construction pre-2014).
It is therefore considered not applicable.
None
1.06 The content of this exemption must be made known to all
registered interested and affected parties within 5 days from
the date of issue.
N/A This condition is considered outside of the audit period
(construction pre-2014).
The exemption process was undertaken internally by Sasol. The
Auditor noted a set of minutes dated 11 March 2004 wherein Sasol
noted that a Mpumalanga Department of Agriculture, conservation
and Environment (MDACE) application would be compiled and
that Sasol would apply for exemption from the EIA process as well
as from appointing an independent consultant and public
participation. In addition, the Auditor was provided with the
covering letter to MDACE (dated 13 August 2004) which
accompanied the original application.
Therefore, due to the fact that no public participation was
undertaken, no registered interested and affected parties could be
notified of the exemption.
Evidence:
— 1.06_EX_Minutes ROD Discussion_17.2.17_2005-04-11
— 1.06_EX_Reclamation yard_Appl for exemption_2004-08-13
None.
2. ESTABLISHMENT OF ENTERPRISE
2.01 This exemption is valid for 2 years from the date of issue
and will lapse if construction activities have not taken place
within the allocated time.
N/A This condition is considered outside of the audit period
(construction pre-2014).
Noted.
ENVIRONMENTAL EXEMPTION COMPLIANCE AUDIT REPORT Project No. 41101534 SASOL SECUNDA COMPLEX: MATERIALS MANAGEMENT
WSP May 2019
Page 9
REF: COMMITMENT COMPLIANCE FINDING RECOMMENDATION
2.02 In case of closure the site, the Dept shall evaluate, monitor
and approve the closure and rehabilitation of the site N/A The Auditor noted that there are no plans to close or decommission
the RMM site at this stage.
None.
3. CONSTRUCTION AND OPERATION
3.01 There should be a single controlled entrance to prevent
unauthorised entry. C The Auditor noted that there is a single entry point of access to the
RMM. The access point is security control. All visitors are
required to report to the security office and are issued with an
access permit.
All material delivered to the RMM must be accompanied by the
relevant documentation such as the “Declaration of Scrap and
Dispatch to RMM”. In addition, certain material is required to be
oil free and will require a decontamination certificate. Examples of
both the Declaration of Scrap and Decontamination certificates
were provided to the auditor.
Evidence:
— 3.01_Declaration of scrap example
— Photographic proof provided
Signage displayed at the access gate
None.
ENVIRONMENTAL EXEMPTION COMPLIANCE AUDIT REPORT Project No. 41101534 SASOL SECUNDA COMPLEX: MATERIALS MANAGEMENT
WSP May 2019
Page 10
REF: COMMITMENT COMPLIANCE FINDING RECOMMENDATION
Single controlled entrance to the RMM
3.02 The site must be adequately fenced. C The Auditor noted that the RMM is adequately fenced. The
perimeter is patrolled by security.
Evidence:
— Photographic evidence provided
Adequate Fencing around the site
None.
ENVIRONMENTAL EXEMPTION COMPLIANCE AUDIT REPORT Project No. 41101534 SASOL SECUNDA COMPLEX: MATERIALS MANAGEMENT
WSP May 2019
Page 11
REF: COMMITMENT COMPLIANCE FINDING RECOMMENDATION
3.03 The floors where the material will be stockpiled should be
bunded. C The Auditor noted that there are no bund walls within the RMM.
However, the materials stored on site include vehicles, engines,
electric motors, transformers, air conditioners, zink plates,
conveyor belts, plastic pallrings etc. Materials are stored on
concrete, in waste skips, on pallets (and strapped) or on sleepers.
The Auditor was advised that all items are required to be oil free
prior to acceptance. Items were an oil leak is identified are stored
on drip trays.
It was noted that no scrap is stored on site; it is taken directly to the
scrap dealer.
Evidence:
— Onsite Check – Secondary containment measures:
Storage on Pallets
None
ENVIRONMENTAL EXEMPTION COMPLIANCE AUDIT REPORT Project No. 41101534 SASOL SECUNDA COMPLEX: MATERIALS MANAGEMENT
WSP May 2019
Page 12
REF: COMMITMENT COMPLIANCE FINDING RECOMMENDATION
Vehicles stored on concrete slab
Storage on concrete slab
ENVIRONMENTAL EXEMPTION COMPLIANCE AUDIT REPORT Project No. 41101534 SASOL SECUNDA COMPLEX: MATERIALS MANAGEMENT
WSP May 2019
Page 13
REF: COMMITMENT COMPLIANCE FINDING RECOMMENDATION
Storage undercover with impermeable floor
Storage within skips
3.04 A leachate management plan for the site should be
established N/A Due to the nature of the material stored and the temporary storage
timeframes, the site is unable to produce leachate.
In addition, the Section 20 Directions from the DWS classify the
facility as a GSB- site, which would not produce leachate.
None.
ENVIRONMENTAL EXEMPTION COMPLIANCE AUDIT REPORT Project No. 41101534 SASOL SECUNDA COMPLEX: MATERIALS MANAGEMENT
WSP May 2019
Page 14
REF: COMMITMENT COMPLIANCE FINDING RECOMMENDATION
Evidence:
— 1.03_EX_Direction_16.2.7.C121.B.028_2005-03-17
3.05 The quality of surface and ground water should be
monitored. C Groundwater:
JMA Consulting is an independent contractor appointed to
complete sampling and bi-annual reporting for Sasol. The Auditor
verified that the Groundwater Quality Report compiled by JMA
Consulting. Report number: JMA/Prj6129 Rev-01; Dated:
November 2018 included groundwater monitoring of boreholes
established for the RMM. The RMM has 6 groundwater
monitoring boreholes, 4 of which are monitored biannually.
Surface Water:
The Auditor was provided with evidence that stormwater is
monitored on site during the rainy season.
Sasol conduct weekly surface water sampling across the Sasol
Secunda Complex as verified by the Weekly RESM Monitoring
Spreadsheet.
Sasol monitor the Bossiespruit, Brandspruit Kleinspruit, Klipspruit
and Trichardspruit,
Evidence:
— Sasol Compliance Statement – Water
— 3.05_RESM Weekly Monitoring_2004-2019
— GWMonitor Report Nov 2017 Final_Prj6129rev-01_2018-11-
20
— Groundwater – Boreholes:
None.
ENVIRONMENTAL EXEMPTION COMPLIANCE AUDIT REPORT Project No. 41101534 SASOL SECUNDA COMPLEX: MATERIALS MANAGEMENT
WSP May 2019
Page 15
REF: COMMITMENT COMPLIANCE FINDING RECOMMENDATION
Monitoring boreholes established at the RMM
— Surface Water – RESM Points:
Location of the RESM monitoring points monitored on a
continuous basis
3.06 Storm water drainage should be established to manage
runoff from the site. C The stormwater plan for the RMM is outlined in the Sasol
IWWMP (dated 18 September 2015) and states the following:
“Wastewater from the washing bay, and stormwater run-off arising
at the washing bay is routed from the Redundant Materials Yard
and exit the site towards the north. For the remainder of the area,
None
ENVIRONMENTAL EXEMPTION COMPLIANCE AUDIT REPORT Project No. 41101534 SASOL SECUNDA COMPLEX: MATERIALS MANAGEMENT
WSP May 2019
Page 16
REF: COMMITMENT COMPLIANCE FINDING RECOMMENDATION
stormwater runoff follows the topography. Two (2) small
stormwater collection pits were excavated, one to the north and
one to the east of the Redundant Materials Yard, to serve as a
collection point to obtain samples that will give an indication of
the stormwater quality. Seepage from the Quarry Dam (part of the
Brandspruit Mine of Sasol Mining) impacts on the RMM area,
which give rise to elevated sulphate concentrations observed in
samples taken from the northern stormwater collection pit.
To provide additional storage space for Green Coke, a storage pad
was constructed with concrete walls, which slopes towards the
north-east. The pad is divided into two (2) sections, with the
higher portion used to store the Green Coke, and the lower portion
used to collect run-off from the stored Green Coke. Any runoff
that collects in the lower portion is analysed, and if the quality is
deemed acceptable, it is discharged to the Bossie Spruit via a
sediment trap.”
Additional recommendations regarding the management and
monitoring of the seepage from Quarry Dam were made on 24
November 2016. The Auditor has been informed that these
recommendations have been implemented.
Evidence:
— IWWMP SIC 2015 Final_2018-05-15
— 3.06_EX_Storm water management report_RMM_2016-11-
24
— On-site Check:
ENVIRONMENTAL EXEMPTION COMPLIANCE AUDIT REPORT Project No. 41101534 SASOL SECUNDA COMPLEX: MATERIALS MANAGEMENT
WSP May 2019
Page 17
REF: COMMITMENT COMPLIANCE FINDING RECOMMENDATION
Stormwater Drains
3.07 If any changes need to be made to the infrastructure this dept
must be informed 30 days in advance to be able to decide
whether the changes need authorisation.
N/A The Auditor was informed that no changes have been made to the
RMM since establishment.
None.
ENVIRONMENTAL EXEMPTION COMPLIANCE AUDIT REPORT Project No. 41101534 SASOL SECUNDA COMPLEX: MATERIALS MANAGEMENT
WSP May 2019
Page 18
REF: COMMITMENT COMPLIANCE FINDING RECOMMENDATION
4. AIR POLLUTION
4.01 Air pollution should be handled as indicated by the relevant
authorities. N/A The nature of the material stored will not result in any air
emissions. It is noted that the activities undertaken at the RMM do
not constitute activities that would require an AEL
Sasol makes use of an integrated approach to air quality
management as governed by National Environmental
Management: Air Quality Act. Sasol works closely with the local
authority and operates units in line with the relevant AEL and
minimum legal emission requirements.
Evidence:
— Fugitive Emission Monitoring Plan_2018-10-18 updated
None.
5. WATER POLLUTION
5.01 It is the responsibility of the applicant and the relevant
contractor on the site to prevent any pollution of surface as
well as ground water.
C The Auditor has noted that the IWWMP aims to identify the
activities related to Sasol’s operations within the context of the
receiving environment (with a focus on water resource protection),
identify the risks associated with these operations, and
subsequently manage these risks by means of an action plan
committed to by Sasol management.
The Auditor noted the following precautions that have been put in
place to prevent surface and ground water pollution:
— Concrete floors are utilised where required;
— A Works Instruction for the Disposal of recyclable and other
redundant materials, assets and equipment (Document
Number: SCSS-MM-000008) has been compiled for the
facility, which requires:
— Material to be oil free prior to acceptance at the RMM;
None
ENVIRONMENTAL EXEMPTION COMPLIANCE AUDIT REPORT Project No. 41101534 SASOL SECUNDA COMPLEX: MATERIALS MANAGEMENT
WSP May 2019
Page 19
REF: COMMITMENT COMPLIANCE FINDING RECOMMENDATION
— Loads to be inspected visually prior to acceptance, in the
event that material is not suitable or adequately cleaned,
material is sent back.
— A decontamination certificate to accompany items where
required.
— Drip trays are utilised where required;
Surface and Ground Water monitoring is in place as described
under Condition 3.5 above. Overall water quality mostly falls
within the SANS 241 water quality standard.
Evidence:
— IWWMP SIC 2015 Final_2018-05-15
— 3.01_Declaration of scrap example
— Sasol Compliance Statement – Water
— 3.05_RESM Weekly Monitoring_2004-2019
— GWMonitor Report Nov 2017 Final_Prj6129rev-01_2018-11-
20
— Onsite Check:
Vehicles stored on concrete slab
ENVIRONMENTAL EXEMPTION COMPLIANCE AUDIT REPORT Project No. 41101534 SASOL SECUNDA COMPLEX: MATERIALS MANAGEMENT
WSP May 2019
Page 20
REF: COMMITMENT COMPLIANCE FINDING RECOMMENDATION
Storage on concrete slab
Storage within skips
6. WASTE MANAGEMENT
6.01 All waste generated during the construction and/or operation
of the site shall be stored, handled and disposed of in an C The Auditor notes that the construction period for the development
of the township is outside of the Audit Period.
None.
ENVIRONMENTAL EXEMPTION COMPLIANCE AUDIT REPORT Project No. 41101534 SASOL SECUNDA COMPLEX: MATERIALS MANAGEMENT
WSP May 2019
Page 21
REF: COMMITMENT COMPLIANCE FINDING RECOMMENDATION
environmentally acceptable way and as directed by this
Department or any other relevant authority.
All waste generated as a result of the RMM operations is managed
as outlined in Sasol’s Waste Management Procedure (SGR-SHE-
000017).
The Auditor viewed the Waste Management procedure that is in
place, and this provides an approach to manage waste in line with
the internationally accepted waste hierarchy, whereby disposal to
land is considered the last management option to undertake once
avoidance, re-use, recycling, recovery and treatment options have
been considered / eliminated. The procedure further details waste
disposal and management through characterisation and
classification that is detailed in site specific waste registers.
Evidence:
— Waste Management Procedure_SGR-SHE-
000017_Rev10_2017-09
7. RISK ASSESSMENT
7.01 Risk assessment should be handled as indicated by relevant
authorities. C The Auditor was informed that no directions have been forth
coming from the authorities in this regard.
Sasol advised the Auditor that it has a Governance SHE Risk and
Assurance department that assesses environmental risks and drives
implementation by business.
The SHE Environment department facilitates Environmental Risk
Assessments per business entity to ensure that gaps are addressed
through implementation of mitigation measures via the Integrated
Management System. Sasol further addresses all Key Undesirable
Events (KUEs) from a group perspective.
A Procedure was viewed by the Auditor that defines the
requirements, responsibilities, and the process to be followed in the
management, execution, and control of environmental risk
assessments.
The Auditor noted the following risk assessments to be specific to
the RMM:
None.
ENVIRONMENTAL EXEMPTION COMPLIANCE AUDIT REPORT Project No. 41101534 SASOL SECUNDA COMPLEX: MATERIALS MANAGEMENT
WSP May 2019
Page 22
REF: COMMITMENT COMPLIANCE FINDING RECOMMENDATION
— Environmental Risk Assessment – Redundant Materials
Management (03 November 2015);
— Emergency Plan for the RMM
Evidence:
— 7.01_ERA-SCSS-RMM-BvdM 2015-11-03
— 7.01_Emergency Management Plan
8. REPORTING
8.01 Records relating to compliance / non-compliance with the
conditions of this Authorization must be kept in good order.
Such records must be made available to this Department
within 7 work days from the date of a written request for
them.
N/A Prior to the introduction of the 7 April 2014 amendment to the
Environmental Impact Assessment (EIA) regulations, no audit
against this Exemption was required. However, this Audit
represents the second audit for this Exemption. WSP undertook an
initial audit of the facility in 2016.
The Auditor was advised that all records relating to compliance are
stored on the Sasol Sharepoint.
Evidence:
— 5.01_EX_Storm water management report_RMM_2016-11-
24
8.02 Non-compliance with or any deviations from the conditions
of this Authorization is regarded as an offence and after
reasonable provision has been made for remedial action, will
be dealt with in terms of S 29,30 and 31A of the Act
N/A Noted. Sasol has confirmed to the Auditor that no communications
have been received from the Authorities regarding non-
compliances.
None.
8.03 Any complaints regarding the development must be brought
to the attention of this Department within 24 hours after
receiving the complaint.
C All environmental complaints received from interested and
affected parties, both internal and external to the organisation, are
recorded in a complaints register that is available and the
Environmental department. Complaints are investigated and
reported in line with the procedure and as per legal requirements.
None.
ENVIRONMENTAL EXEMPTION COMPLIANCE AUDIT REPORT Project No. 41101534 SASOL SECUNDA COMPLEX: MATERIALS MANAGEMENT
WSP May 2019
Page 23
REF: COMMITMENT COMPLIANCE FINDING RECOMMENDATION
Environmental complaints contact details are communicated to
internal and external stakeholders.
A procedure relating to complaints from stakeholders (SGR-SHE-
000022) has been implemented at the Sasol Secunda Complex.
The complaints and/or incidents register verified by the auditors
confirmed that no complaints have been logged regarding the
RMM during the audit period.
Evidence:
— Sasol Compliance Statement – Complaints
— Environmental complaints procedure_SGR-SHE-
000022_Rev04_2015-08
— Environmental complaints procedure_SGR-SHE-
000022_Rev05_2019-01
— Environmental Complaints Register_2019-02-18
8.04 A complaints register must be kept up to date for inspection
by members of this Department C The complaints and/or incidents register verified by the auditors
confirmed that no complaints have been logged regarding the
RMM during the audit period.
Evidence:
— Sasol Compliance Statement – Complaints
— Environmental complaints procedure_SGR-SHE-
000022_Rev04_2015-08
— Environmental complaints procedure_SGR-SHE-
000022_Rev05_2019-01
— Environmental Complaints Register_2019-02-18
None.
ENVIRONMENTAL EXEMPTION COMPLIANCE AUDIT REPORT Project No. 41101534 SASOL SECUNDA COMPLEX: MATERIALS MANAGEMENT
WSP May 2019
Page 24
5 SUMMARY OF THE AUDIT FINDINGS
5.1 ENVIRONMENTAL EXEMPTION
The audit findings have been summarised into the following categories: compliance, non-compliance and not
applicable. The overall audit findings concerning compliance to the Exemption conditions are as listed in Table
3 below.
Table 3: Summary of Exemption Compliance Audit Findings
SECTION OF THE EXEMPTION NO. COMMITMENTS C NC N/A
GENERAL CONDITIONS 6 1 0 5
ESTABLISHMENT OF ENTERPRISE 2 0 0 2
CONSTRUCTION AND OPERATION 7 5 0 2
AIR POLLUTION 1 0 0 1
WATER POLLUTION 1 1 0 0
WASTE MANAGEMENT 1 1 0 0
RISK ASSESSMENT 1 1 0 0
REPORTING 4 2 0 2
Total Count 23 11 0 12
Total Percentage 48% 0% 52%
Percentage Compliance with Applicable Conditions 100%
Figure 2 illustrates the number/count contribution of the findings of the Exemption per section while Figure 3
presents the total proportion of compliance for the facility.
ENVIRONMENTAL EXEMPTION COMPLIANCE AUDIT REPORT Project No. 41101534 SASOL SECUNDA COMPLEX: MATERIALS MANAGEMENT
WSP May 2019
Page 25
Figure 2: Number/Count contribution of findings made to the Exemption conditions per Section
Figure 3: Overall count findings on compliance to the Exemption conditions
0
1
2
3
4
5
6
7
8
Sectional Count Contribution
C
NC
N/A
11
0
12
Total Compliance
C
NC
N/A
ENVIRONMENTAL EXEMPTION COMPLIANCE AUDIT REPORT Project No. 41101534 SASOL SECUNDA COMPLEX: MATERIALS MANAGEMENT
WSP May 2019
Page 26
Figure 4 illustrates the percentage contribution of the findings of the Exemption conditions. Figure 5 presents
the total percentage compliance for the facility.
Figure 4: Percentage contribution of findings made to the Exemption conditions per Section
Figure 5: Overall percentage findings on compliance to the Exemption conditions
0102030405060708090
100
Sectional Percentage Contribution
C
NC
N/A
48%
0%
52%
Total Percentage Compliance
C
NC
N/A