sce’s smart grid update - ieeegrouper.ieee.org/groups/td/dist/da/doc/bobyinger--sce smart...
TRANSCRIPT
SCE’s Smart Grid Update
Bob YingerSouthern California Edison
October 15, 2007
2
Southern California Edison
50,000 square miles~23,000 MW peak demand4.7 million customers11 million people served845 cities and communities
3
SCE Smart Grid Activities
Generation
Transmission & Sub-transmission
Distribution
Customer
Advanced Metering, Demand Response, and Distributed Resources
Substation Automation
Distribution Automation
SCADA and Phasor Measurements
4
Phasor Measurement UnitProvides
Real-time system monitoring for reliability and post event analysisControl for system components (e.g. FACTS, HVDC) Integration with existing SCADA/ EMS systemsInfo. to avoid blackouts like ones in the Northeast and WestSituational awareness on event locations and severityInfo. to facilitate system restoration after disturbance
SCE is working with WECC members and SCE neighbors like APS, SRP, PG&E, LADWP and WAPA for data exchange
5
Phase Angles: July 24, 2006 event
6
Old Substation Automation
ModBus Plus Token Ring Loop
MODICON QUANTUM PLC
ABB DPU
ABB TPUDNP 3.0
Dedicated 1200 baud
4 wire circuit
PricomHMI
Momentum PLCInterface for
Bank temp., Battery Charger etc.
SELSEL
SELSEL
SELSEL
SEL-2030
7
New Sub. Auto. Objectives
Open System local networkEthernet/ ModBusMulti-vendor equipmentSupport future standards (IEC 61850)Topology supports interfacing with legacy systems
Dedicated HMI Local ControlRemote SCADA control
Gateway for ‘beyond SCADA’ dataSecurable pathway
8
E-Grid Network
Power Management System
DNP 3.0Dedicated 1200
baud4 wire circuit
ETHERNET 10/100 Managed Switches (Modbus TCP/IP & IEC 61850)
IED IntegrationOptimate PanelGetaway Riser Temperature Battery ChargerWeather Station (Temp&Hum.)
Real Time SCADA
Non-Scada128 KbpsTCP/IP
MODICON QUANTUM PLC
MODICON MOMENTUM PLC
ABB DPU2000R 5.xx and Ethernet TPU
ABB OCIDPU 2000R
Router / Switch
Firewall
ABB OCIDPU 2000RABB OCI
DPU 2000RABB OCIDPU 2000R
ABB DPU 2000R
GE L-90
GE C-60
GE UR Relays
GATEWAYINTEGRATOR / OPC
SERVER
SEL Relays
SEL-311LSELSEL-311LSEL
IED Read Anywhere
DNA Server
SEL-387SELSEL-387SEL
PricomHMI
DAC Node
Outage Management
SystemGIS
App Node
WS Node
ABB TPU
SCE Admin
IBUS
XC Node
Distributed Control Monitoring
System
SubstationEnterprise /
SCA
DA
GE T-60GE C-30
GE D-60GE F-60 CB Monitors
Transformer Monitors Distribution Lines
IED Read Anywhere
New Substation Automation
9
Distribution Automation
Distribution Switches (2773)On 1611 of 4300 circuits
Sub-transmission Switches (57)66 kV and 115 kV
Automatic Reclosers (984)Circuit Alarms (324)Capacitor Controls (8273 of 9500)Remote Fault Indicators (148)Load Survey meters (8500)Large Customer meters (4500)
10
Distribution Automation
New applications:Vacuum Fault InterruptersAutomated P/E (Auto Transfer)Automated Distribution RegulatorsIntelligent Fault IndicatorsDistribution Automatic Restoration SystemNetwork Protectors
11
Distribution Automation
All distribution automation presently accomplished through the use of CellNetUtilinet radios
Spread spectrum, peer-to-peerSome meter reading/ load survey functions will be replaced by Advanced Metering (SmartConnect™)
12
The Circuit of the Future (CoF)
SCE has identified a need to come up with new ideas to build more reliable and efficient distribution circuits
Provide customers with better serviceImprove safetyReduce costs
13
Location of CoFNew circuitWill serve approximately 2,000 customersOverhead / Underground facilitiesNew hardware and protection schemesHigh speed communicationsApproximately 23,000 amps fault duty
14
CoF Features
Circuit Tie Switch
Circuit Tie Switch
Sweetwater 12KV
Northpark
12KVM
Typ. Load Transformer
ShandinSubstation
Tie RCS
RCI2
Tie RCS
Fiber Optic Duct temp Monitoring
SystemSolid State
Fault Current Limiter
TieRCS
RAR
DistributedGeneration
G
USAT
RCI3RCI
1
SCADA System Gateway
Comm.
Fiber
SEL 2100Logic Processor
RCI = Remote Controlled Fault InterrupterRCS = Remote Controlled SwitchRAR = Remote Automatic Recloser
Circuit Tie Switch
Multi-Stage Capacitor Banks
15
CoF Schedule
Initial operation began on August 14, 2007Entering testing phaseFuture phases will test other advanced devices
2008 – Fault current limiter, multi-stage cap2009 and beyond – other new concepts
16
DOE Advanced Protection
Advanced protection methods on the Circuit of the Future (CoF)Three tasks over 3 years:
Evaluation of new protection scheme on CoFDesign and evaluation of protection scheme with fault current limiter on CoFDevelop and test advanced fault location, sensing and prediction methods on CoF
17
New Protection Scheme
RCI RCI
RCI
Block Trip
Typical Time OvercurrentProtection betweenSub and RAR
Tie RCS
Tie RCS
Tie RCS
FAULT
Logic Processor
Trip
Block TripRAR
Trip
18
Distributed Generation/ Storage
Interconnection point for dist. generation or storage on CoFInvestigate distributed gen/storage (plug-in-hybrid) Benefits:
Supplement the feeder during high load conditionsVoltage/ VAR support
19
SmartConnect (Advanced Metering Infrastructure)
Enable Energy Smart CustomersIntegrated information from utilityPayment options (e.g., pre-payment)Outage & service condition informationSupport rate option innovations
Manage Distributed ResourcesEconomic dispatch of load resourcesDispatch of load for grid managementIntelligent net metering
Operational EfficienciesField communication links to distributionRevenue cycle improvementsSituational data in near real-timeWholesale - retail markets integration
Built with the future in mindUpgradeable WAN/HAN communicationsLeverage open architecture principles in system design Future customer service offerings
SCE seeks to leverage a 2-way communications infrastructure with 5 million intelligent metering devices on our distribution network to create lasting value for our customers and our operations
20
SmartConnect Program Phases
Business Process
Design &Proof of Concept
Beta Development
& Pilot
Business
DeploymentPre Deployment
Meter Trade & Feasibility Studies
Conceptual Processes & Systems Reqs
Business Process
AIM Requirements,
“Design” & Proof of Concept
Beta Product Field Pilot
Business Case in Chief
Full
Activities
Meter Trade & Feasibility Studies
Cost/Benefit Analyses
12/2005 1/2007 1/2008 1/2009 7/2012
Business Process
Design &Proof of Concept
Beta Development
& Pilot
Business
Application
Meter Trade & Feasibility Studies
Conceptual Processes & Systems Reqs
Business Process
AIM Requirements,“Design” &
Proof of Concept
Beta Product Field Pilot
Meter Trade & Feasibility Studies
Cost/Benefit Analyses
Phase II12 Mos.
Phase I Phase III BPhase III APhase IIPhase I Phase III BPhase III APhase IIPhase I Phase III BPhase III APhase IIPhase I13 Mos.
Phase III B42 Mos.
Phase III A12 Mos.
Final Business CaseDesign & System Dev
AMI Program will use a multi-phased approach to development and deployment of a next generation advanced metering infrastructure over a 6 ½ year timeframe.
21
SCE Smart Grid Program Goals
Provide advanced visualization for operators and plannersProvide information for maintenanceImplement advanced protection techniquesBetter outage detection/ quicker restorationBetter load management abilitiesIncreased distributed generation and storageBetter grid and cyber securityImprove safety
22
What Needed to Accomplish
Integrate “islands of automation”Standardize protocols for communications and data transferConstruct common databasesInstall advanced sensorsImprove cross-system communicationsImplement advanced hardwareProvide system-wide view of security