schedule execution metrics - nasa

43
Schedule Execution Metrics The value proposition for adding Baseline Realism, Baseline Progress and Forecast Realism to the Scheduler Analyst’s Toolkit June 2017

Upload: others

Post on 02-Jan-2022

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Schedule Execution Metrics - NASA

Schedule Execution MetricsThe value proposition for adding Baseline Realism,

Baseline Progress and Forecast Realism to the Scheduler Analyst’s Toolkit

June 2017

Page 2: Schedule Execution Metrics - NASA

BPO/CAAG/ECE

Abstract

In response to National Reconnaissance Office (NRO) Senior Management’s need for metrics that are leading indicators of program execution challenges, the NRO Cost and Acquisition Assessment Group (CAAG) Earned Value Management Center of Excellence (ECE) developed a suite of Schedule Execution Metrics. The metrics are now part of the NRO Corporate tool box for senior leadership decision support. The metrics are derived from the Contractor’s integrated master schedule to answer the questions:

• Is the contractor executing to the baseline plan?• Is the contractor ahead or behind in completing the planned activities?• Is the forecast realistic?

This briefing will define schedule execution metrics, explain how they are being used at NRO, and describe ongoing research tasks to establish thresholds and interpret the metrics.

2

Page 3: Schedule Execution Metrics - NASA

BPO/CAAG/ECE

Business Case for Schedule Execution Metrics at NRO

• What led to the creation of Schedule Execution Metrics (SEM)• We were tasked to create leading indicators to explain the true status of a program beyond the “green”

conditions of program level CPI and SPI, and to provide an early indicator of a potential rebaseline• We were asked to provide clean, simple, easy-to-understand metrics• Many detailed cost and technical metrics already exist are reviewed extensively. We chose to emphasize

schedule execution and schedule performance to fill a void. • JSCC Better EVMS Implementation Study II: Improving Value for Government PMs: Government PMs highly value

the Integrated Master Schedule, and refer to it as managing “heads and scheds”• We rebranded existing NAVAIR, NRO internal and other metrics and created new metrics to fully analyze

schedule performance. • Baseline Realism, work-off analysis (phasing of recovery), and other schedule execution metrics are used

extensively across NRO programs offices. We standardized terminology and created automated tools to put Schedule Execution Metrics in the Corporate Toolbox

• Measuring accomplishment against the contractor’s forecast is a fall back if there is a problem with the baseline plan

• Benefits of employing Schedule Execution Metrics at NRO• Excellent Insight on an Agile Program: The delta between baseline realism and baseline execution provided

insight into the magnitude of reprioritization work. The metrics indicated the contractor was efficiently delivering software functionality, but highlighted the impact of Government's reprioritization through agile software management, and alerted the customer of potential work in the backlog that might not be completed

• Better Insight Drives accountability When included in a suite of cost, schedule and technical metrics, schedule execution metrics isolated underlying schedule issues leading to corrective action targeted to keep the program on schedule including: assigning dedicated effectivity and test campaign leads, investing in the improvement of testing environments, more complete detail planning when ECP work is added to the contract.

3

Page 4: Schedule Execution Metrics - NASA

BPO/CAAG/ECE

How Schedule Execution Metrics can help Industry

The suite of Schedule Execution Metrics tells a more complete story• Provides feedback to the planning process

• Is the work really being performed as it was planned? How much can the plan deviate and still be useful as a plan (use of float, margin)?

• Identifies upcoming planning challenges• Are future activities in jeopardy of finishing late? Is there a bow wave of

activities on he horizon? • Highlights issues that are not necessarily identified by technical

metrics• How much effort is regularly being spent on activities that are already

more than 30d late?• Supplements typical schedule presentation

• Is accomplishment of tasks supporting the standard Gantt Chart view? Is there a potential impact to the critical path?

4

Page 5: Schedule Execution Metrics - NASA

BPO/CAAG/ECE

Challenges in Typical Schedule Reporting

5

SV CV VACProgram Level ↑ ↑ ↔

BUS ↑ ↑ ↑PAYLOAD ↑ ↑ ↑

Program-level Cumulative Schedule Variance can look favorable, even if there are execution challenges:• Historic performance can heavily

weight the indicator to “green”

Senior Leaders ask for leading indicators of execution challenges

0.0

0.1

0.2

0.3

0.4

0.5

0.6

0.7

0.8

0.9

1.0

Oct

-15

Jan-

16

Apr-

16

Jul-1

6

Oct

-16

Jan-

17

Apr-

17

Jul-1

7

Oct

-17

Jan-

18

Apr-

18

Jul-1

8

Oct

-18

Jan-

19

Apr-

19

Jul-1

9

Oct

-19

Jan-

20

Apr-

20

Jul-2

0

Perf

rom

ance

Inde

x

Schedule Data as of October 2016

PROGRAM X Executive View Baseline Realism (1 Mo)BLR (Mo) Projected BLR (Mo)

100% have BL FinFilter: All Tasks

Baseline Realism can provide an early indicator that a contractor is not performing the work as planned

Typically EVM Metrics provided to Senior Leadership

Schedule Execution Metrics can provide Additional Insight

Notional Data

Notional Data

EVMvs

SEM

Page 6: Schedule Execution Metrics - NASA

BPO/CAAG/ECE

Schedule Execution Metrics as part of the NRO Corporate Toolbox

6

Baseline Realism

Baseline Progress

Forecast Realism

Baseline Realism Moving Averages

Ability to Absorb Late Finishes

Distribution of Late Finishes

Schedule Workoffs

Baseline Execution Index

Others

Baseline Realism is one of many

metrics that can be used to assess

schedule performance

Schedule data and analysis is part of the

EVM data set

Page 7: Schedule Execution Metrics - NASA

BPO/CAAG/ECE

We recommend a combination of new and existing Schedule Execution Metrics to answer 3 critical questions

Question Metric/Analysis What it Means

Is the contractor executing the baseline plan?

Baseline Progress Prior to “time now” Activities completed early or on time / baseline activities planned finishes over a specified period of timeAfter “time now” Activities forecasted early or on time / baseline activities planned finishes over a specified period of time

Baseline Realism Prior to “time now” Assessment of the completions of specific baseline plan finishes over a specified period of timeAfter “time now” Assessment of the forecasted completions of specific baseline plan finishes over a specified period of time

Is the contractor ahead or behind?

Critical Path Verification

Identification of Critical Path activities to any specific deliverable or milestone

Critical Path Length Index

(Duration to a specific deliverable or milestone + float and margin) / duration to a specific deliverable or milestone

Schedule Margin Remaining

Schedule margin as percentage of remaining time to a deliverable or milestone

Is the forecast realistic?

Forecast Realism Prior to “time now” Number of tasks actually completed / number of tasks forecasted to finish in a previous IMS version of the IMSAfter “time now” Number of tasks forecasted to complete / number of tasks forecasted to finish in a previous IMS version of the IMS

Schedule Workoff Prior to “time now” Percentage of activities completed each month that are more than 30 days lateAfter “time now” Percentage of activities in the future that are forecasted to to be more than 30 days late

Total Float Consumption Index

(Actual Duration + Critical Path Total Float) / Actual Duration

Note: One or more specified period of time can be one to six months, or a cumulative value

Page 8: Schedule Execution Metrics - NASA

BPO/CAAG/ECE

Illustration - December 2016 Status

Notional

LegendBaseline

StartBaseline

FinishProgress (ending at forecast or actual finish)

Percent Complete

Early

Late

8

On plan finish, current period

Late, not finished

On plan finish, current period

Early finish, current period baseline

Late finish, current period

Early finish, current period

On plan finish, prior period

Assessment Window

Time Now

Page 9: Schedule Execution Metrics - NASA

BPO/CAAG/ECE

Illustration – Baseline Realism:On Plan Finishes for Activities with Baseline Finishes

within the assessment window

Monthly Baseline Realism = 4/6 = 0.6666% of the of the activities planned for completion in the assessment

window were completed during the assessment window.

Notional

1

4

9

Note : Cumulative Baseline Execution = 8/9 = 0.89

On plan finish, current period

On plan finish, current period

2

3

Assessment Window

Time Now

Page 10: Schedule Execution Metrics - NASA

BPO/CAAG/ECE

Illustration – Baseline Progress: On Plan & Early Finishes for Activities with Baseline Finishes

within the assessment window

Monthly Baseline Progress = 5/6 = 0.8383% of the activities planned for completion in the assessment window were

accomplished or before the time-now date.

Notional

1

2

3

4

Note : Cumulative Baseline Progress = 8/9 = 0.89

5

10

On plan finish, current period

Early finish, current period baseline

On plan finish, current period

Assessment Window

Time Now

Page 11: Schedule Execution Metrics - NASA

BPO/CAAG/ECE

Illustration – Baseline Execution:All On Plan, Early, & Late Finishes

within the assessment window

Monthly Baseline Execution = 6/6 = 1.00The pace of work is 100% of what it was planned to be during the assessment window, although the completed activities were not

necessarily the ones that were planned for completion.

Early finish, current period

Notional

1

2

6

Note : Cumulative Baseline Execution = 9/9 = 1.0011

3

45

Assessment Window

Time Now

Late finish, current period

On plan finish, current period

On plan finish, current period

Page 12: Schedule Execution Metrics - NASA

BPO/CAAG/ECE

Automated Tools versus Manual Analysis

Automated Tool in Use

Future Automated

Tool

Manual Analysis

Note: Data for Schedule Margin Metric can be Collected in Forecast Realism Tool

12

Page 13: Schedule Execution Metrics - NASA

BPO/CAAG/ECE

New Schedule Execution Metrics and how they compare widely available Baseline Execution Index (BEI)

13

Metric What it Tells You

Baseline Realism (BR)*

Is the baseline being accomplished the way it was planned (by specific period or cumulative to date)?How well the contractor can do the work in the manner identified in the Integrated Master Schedule?Low BR can be a potential early indicator of need to replan

BaselineProgress (BP)*

What is the progress to “time now” against the plan (by specific period or cumulative to date)?Differs from BR in that it includes prior finishes if the task was baselined within the assessment window. Does not count early finishes for activities baselined to finish after the assessment window..Most PMs will be most concerned with Cumulative BP and Critical Path management

Forecast Realism (FR)

Are forecasted tasks being accomplished as forecasted?Provides insight into contractor's ability to complete the activities forecasted for completion in previous IMS submissions

Baseline Execution Index (BEI)

Execution Pace - Significantly different from BR and BP in that BEI does not look at the order or the planBEI provides the actual pace of activities accomplished compared to the pace that was planned“BEI is the SPI of Schedule Execution Metrics” (BEI is based on activity finishes not dollars). Like SPI, BEI may not necessarily be a leading indicator. Unlike SPI, BEI does not give credit for partial completion

Note: Cumulative BR is equal to Cumulative BP

Page 14: Schedule Execution Metrics - NASA

BPO/CAAG/ECE

Interpreting Baseline Realism

Light Blue Bars represent the count of activity baseline finishesPrior to Time Now - Black Bars represent actual activity finishesAfter time now – Black Bars represent forecasted activity finishesSolid Red Line represents the percent of activity completions in the period they were baselined for completionDotted Red Line represents percent of activity completions forecasted to complete in the period they are baselined to be completedSolid Black Triangles represent Cumulative Baseline Realism (percent)White Triangles represent Forecasted Cumulative Baseline Realism (percent)

14

0

50

100

150

200

250

300

0.0

0.1

0.2

0.3

0.4

0.5

0.6

0.7

0.8

0.9

1.0

Oct

-15

Dec-

15Fe

b-16

Apr-

16Ju

n-16

Aug-

16O

ct-1

6De

c-16

Feb-

17Ap

r-17

Jun-

17Au

g-17

Oct

-17

Dec-

17Fe

b-18

Apr-

18Ju

n-18

Aug-

18O

ct-1

8De

c-18

Feb-

19Ap

r-19

Jun-

19Au

g-19

Oct

-19

Dec-

19Fe

b-20

Apr-

20Ju

n-20

Aug-

20

# Ac

tiviti

es in

Mon

th

Perf

rom

ance

Inde

x

Schedule Data as of November 2016

M2C2 (Nov 2016) Activity Baseline Realism (Cum/Cur)Monthly BL Fin Monthly Planning Window Finish

BLR (Mo) Projected BLR (Mo)

BLR (Cum) Projected Cum BLR

100% have BL FinFilter: All Tasks

Time nowNotional Data

Page 15: Schedule Execution Metrics - NASA

BPO/CAAG/ECE

Screen shots of Schedule Execution Metrics (1)

15

0

50

100

150

200

250

300

0.0

0.1

0.2

0.3

0.4

0.5

0.6

0.7

0.8

0.9

1.0

Oct

-15

Dec-

15Fe

b-16

Apr-

16Ju

n-16

Aug-

16O

ct-1

6De

c-16

Feb-

17Ap

r-17

Jun-

17Au

g-17

Oct

-17

Dec-

17Fe

b-18

Apr-

18Ju

n-18

Aug-

18O

ct-1

8De

c-18

Feb-

19Ap

r-19

Jun-

19Au

g-19

Oct

-19

Dec-

19Fe

b-20

Apr-

20Ju

n-20

Aug-

20

# Ac

tiviti

es in

Mon

th

Perf

rom

ance

Inde

x

Schedule Data as of October 2016

PROGRAM X Monthly Baseline RealismMonthly BL Fin Monthly Planning Window Finish BLR (Mo) Projected BLR (Mo)

100% have BL FinFilter: All Tasks

0

50

100

150

200

250

300

0.0

0.1

0.2

0.3

0.4

0.5

0.6

0.7

0.8

0.9

1.0

Oct

-15

Dec-

15Fe

b-16

Apr-

16Ju

n-16

Aug-

16O

ct-1

6De

c-16

Feb-

17Ap

r-17

Jun-

17Au

g-17

Oct

-17

Dec-

17Fe

b-18

Apr-

18Ju

n-18

Aug-

18O

ct-1

8De

c-18

Feb-

19Ap

r-19

Jun-

19Au

g-19

Oct

-19

Dec-

19Fe

b-20

Apr-

20Ju

n-20

Aug-

20

# Ac

tiviti

es in

Mon

th

Perf

rom

ance

Inde

x

Schedule Data as of October 2016

PROGRAM X Baseline Progress (Cum/Monthly)Monthly BL Fin Monthly EOT Finish BLP (Mo)

Projected BLP (Mo) BLP (Cum) Projected BLP (Cum)

100% have BL FinFilter: All Tasks

0

50

100

150

200

250

300

350

Oct

-15

Dec-

15Fe

b-16

Apr-

16Ju

n-16

Aug-

16O

ct-1

6De

c-16

Feb-

17Ap

r-17

Jun-

17Au

g-17

Oct

-17

Dec-

17Fe

b-18

Apr-

18Ju

n-18

Aug-

18O

ct-1

8De

c-18

Feb-

19Ap

r-19

Jun-

19Au

g-19

Oct

-19

Dec-

19Fe

b-20

Apr-

20Ju

n-20

Aug-

20

# M

onth

ly A

ctiv

ities

Schedule Data as of October 2016

PROGRAM X Forecasted Late FinishesCompleted Activities (Mo) Late Unfinished Activities (Mo) Future Planned Finishes (Mo)

100% have BL FinFilter: All Tasks

25% of all tasks currently projected to finish after the

status of OCT 2016 were baselined to finish prior to that

status date

0

200

400

600

800

1000

1200

1400

1600

0.0

0.1

0.2

0.3

0.4

0.5

0.6

0.7

0.8

0.9

Nov

-14

Dec-

14Ja

n-15

Feb-

15M

ar-1

5Ap

r-15

May

-15

Jun-

15Ju

l-15

Aug-

15Se

p-15

Oct

-15

Nov

-15

Dec-

15Ja

n-16

Feb-

16M

ar-1

6Ap

r-16

May

-16

Jun-

16Ju

l-16

Aug-

16Se

p-16

Oct

-16

Nov

-16

Dec-

16

# Ac

tiviti

es

Fore

cast

Rea

lsim

PROGRAM X - 6 Mo Forecast Realism# Forecasted Activities # Completed Activities 6 Mo Forecast Realism

Provides ratio of specific activiies actuallyaccomplished during the six--period window compared to the projected finishes from the

beginning of that window

Are activities being accomplished the way they were planned?

What is the “time now” progress against the plan?

What is the recovery plan for missed tasks?

How well is the contractor forecasting future finishes?

Baseline Realism Baseline Progress

Forecast RealismForecasted Late Finishes

Page 16: Schedule Execution Metrics - NASA

BPO/CAAG/ECE

14%

18%

68%

PROGRAM X - Activity Future DurationsCONTRACTED EXPANDED SAME

1554 ACTIVITIES < 100% COMPLETE AS OF

11/30/2016 (3712 TOTAL ACTIVITIES IN IMS)

DURATIONS COMPARED TO THOSE IDENTTIFIED ON

1/31/2016

0

50

100

150

200

250

300

350

400

0.0

0.2

0.4

0.6

0.8

1.0

1.2

1.4

1.6

Oct

-15

Dec-

15Fe

b-16

Apr-

16Ju

n-16

Aug-

16O

ct-1

6De

c-16

Feb-

17Ap

r-17

Jun-

17Au

g-17

Oct

-17

Dec-

17Fe

b-18

Apr-

18Ju

n-18

Aug-

18O

ct-1

8De

c-18

Feb-

19Ap

r-19

Jun-

19Au

g-19

Oct

-19

Dec-

19Fe

b-20

Apr-

20Ju

n-20

Aug-

20

Perf

rom

ance

Inde

x

Schedule Data as of November 2016

PROGRAM X Baseline Execution vs To-Complete Baseline Execution

Monthly BL Fin Monthly Finish BE (Cum)

Projected BE (Cum) BE (Mo) TC-BE

100% have BL FinFilter: All Tasks

51% difference between Cumulative BE (0.842) and To-Complete BEI (1.352) as of NOV 2016

Avg Dur for Completed Act: 25d Avg Dur for Future Act: 28d

52 52 52 52 50 50

35 35 35 35

15 158 8 8 8 7 7

73 73 73 73

53 51

0

10

20

30

40

50

60

70

80

9/30

/201

6

10/3

1/20

16

11/3

0/20

16

12/3

1/20

16

1/31

/201

7

2/28

/201

7

# Da

ys M

argi

n

IMS Status Dates

Schedule Margin ErosionSchedule Margin to MS1 Schedule Margin to MS2

Schedule Margin to MS3 Schedule Margin to MS4

0%

20%

40%

60%

80%

100%

0

50

100

150

200

250

300

350

400

Oct

-15

Dec

-15

Feb-

16

Apr-

16

Jun-

16

Aug-

16

Oct

-16

Dec

-16

Feb-

17

Apr-

17

Jun-

17

Aug-

17

Oct

-17

Dec

-17

Feb-

18

Apr-

18

Jun-

18

Aug-

18

Oct

-18

Dec

-18

Feb-

19

Apr-

19

Jun-

19

Aug-

19

Oct

-19

Dec

-19

Feb-

20

Apr-

20

Jun-

20

Aug-

20

% o

f Act

iviti

es M

ore

than

30d

Lat

e

# Ac

tiviti

es in

Mon

th

Schedule Data as of November 2016

Program X Schedule Workoffs% of Activity Completions > 30d Late (Mo) # Activities >30d Late (Mo)

# Activities Projected >30d Late (Mo) # Completed Activities (Mo)

# Projected Completed Activities (Mo) % of Activity Completions > 30d Late (Cum)

34% of All Activities are projected to be more than 30d Late

100% have BL FinFilter: All Tasks

Screen Shots of Schedule Execution Metrics (2)

16

How much effort is being spent on activities more than 30d late?

What is trending usage of Schedule Margin?

Is remaining work pace in line with how the work was planned?

Are activity durations changing (contracting or expanding)?

Schedule Workoffs Schedule Margin

Future DurationsTo-Complete Baseline Execution

Page 17: Schedule Execution Metrics - NASA

BPO/CAAG/ECE

ECE Schedule Execution Metric Capabilities

• Schedule Execution Metric methods are documented and have been presented over the last 6 months at NRO Scheduler’s Forum• Terminology has been Branded• Formulas have been vetted• Charts have been presented to senior management

• NRO Earned Value Center of Excellence (ECE) has developed tools automated calculation

• ECE is currently working to benchmark Schedule Execution Metrics to better interpret results with respect to historical experience

• ECE is encouraging COTS vendors to consider incorporating Schedule Execution Metrics into IMS and IPMR Analysis Tools

17

Page 18: Schedule Execution Metrics - NASA

BPO/CAAG/ECE

Ongoing Research to Interpret Metrics

• What level or trend in Baseline Realism is an early indicator of an OTB?

• Can Baseline Progress values less than a certain value be regularly associated with an overrun or use of schedule margin?

• What is an expected benchmark for Forecast Realism?

Factors to Consider

• Space Hardware versus Ground Software (in the Space and Ground community)

• Use of Schedule Margin, Management Reserve

• Follow-on effort versus New Development

18

Page 19: Schedule Execution Metrics - NASA

BPO/CAAG/ECE

Back-up

19

Page 20: Schedule Execution Metrics - NASA

BPO/CAAG/ECE

NRO Uses an Automated Tool to CalculateSchedule Execution Metrics

• Automated Data Entry and Chart Package Generation

• Microsoft Project Schedule, Microsoft Excel and Visual Basic

• Tool Outputs shown on following slides

20

Page 21: Schedule Execution Metrics - NASA

BPO/CAAG/ECE

PROGRAM XYZ - Schedule Finish DataCumulative to Date

Days Late/Early # Activities % of Total<-60 0 0%<-30 9 2%

>= -30 and <30 230 63%>30 6 2%>60 3 1%>90 0 0%

>120 0 0%

>150 0 0%

>180 0 0%NO BASELINE 116 32% 32% 32%

2%

63%

2%

2%0%

Based on historical data (before or equal to Status Date) AND

selected MS Project Filter

Notional Data

21

Page 22: Schedule Execution Metrics - NASA

BPO/CAAG/ECE

PROGRAM XYZ - Schedule Finish DataFuture Activities

Days Late/Early # Activities % of Total<-60 0 0%<-30 1 0%

>= -30 and <30 41 11%>30 2 1%>60 1 0%>90 4 1%

>120 1 0%

>150 0 0%

>180 0 0%NO BASELINE 340 87% 87% 87%

0%

11%

1%

2%1%

Based on future data (after Status Date) AND selected MS

Project Filter

Charts 3-5 provide an easy way to see if the future trends are

significantly different than historical data

Notional Data

22

Page 23: Schedule Execution Metrics - NASA

BPO/CAAG/ECE

PROGRAM XYZ - ACT Monthly Baseline Realism

0

20

40

60

80

100

120

140

160

0.0

0.1

0.2

0.3

0.4

0.5

0.6

0.7

0.8

0.9

1.0

Sep-

15N

ov-1

5Ja

n-16

Mar

-16

May

-16

Jul-1

6Se

p-16

Nov

-16

Jan-

17M

ar-1

7M

ay-1

7Ju

l-17

Sep-

17N

ov-1

7Ja

n-18

Mar

-18

May

-18

Jul-1

8Se

p-18

Nov

-18

Jan-

19M

ar-1

9M

ay-1

9Ju

l-19

Sep-

19N

ov-1

9Ja

n-20

Mar

-20

May

-20

Jul-2

0

# Ac

tiviti

es in

Mon

th

Perf

orm

ance

Inde

x

Schedule Data as of June 2016

PROGRAM XYZ ACT Monthly Baseline RealismMonthly BL Fin Monthly Planning Window Finish BLR (Mo) Projected BLR (Mo)

456 ACT require BL FinFilter: All Tasks

Number of Baseline Finishes per Month

Baseline Realism Index for 1 Month

(Historical)

Baseline Realism Index for 1 Month

(Projected)

IMS Status DateIMS Filter Identification of events without BL Finish Dates

Number of Actual/Projected Finishes per Month

Notional Data 23

Page 24: Schedule Execution Metrics - NASA

BPO/CAAG/ECE

PROGRAM XYZ - ACT Multi-View Baseline Realism

0.0

0.1

0.2

0.3

0.4

0.5

0.6

0.7

0.8

0.9

1.0

Sep-

15N

ov-1

5Ja

n-16

Mar

-16

May

-16

Jul-1

6Se

p-16

Nov

-16

Jan-

17M

ar-1

7M

ay-1

7Ju

l-17

Sep-

17N

ov-1

7Ja

n-18

Mar

-18

May

-18

Jul-1

8Se

p-18

Nov

-18

Jan-

19M

ar-1

9M

ay-1

9Ju

l-19

Sep-

19N

ov-1

9Ja

n-20

Mar

-20

May

-20

Jul-2

0

Perf

orm

ance

Inde

x

Schedule Data as of June 2016

PROGRAM XYZ Activity Multi-View Baseline RealismBLR (Mo) Projected BLR (Mo) BLR (3 Mo)

BLR (6 Mo) BLR (Cum) Projected Cum BLR

456 ACT require BL FinFilter: All Tasks

1 Mo BLR: 0.5 - 3 Mo BLR: 0.81 6 Mo BLR: 0.97 - Cum BLR: 0.97

Filter Used in MS Project

Identification of events without BL Finish Dates

IMS Status Date

Baseline Realism Index for 1 Month

(Historical)

Baseline Realism Index for 3 Months

(Historical)

Baseline Realism Index for 6 Months (Historical) – Not

Visible – Requires 6 months of data

Cumulative-to-Date Baseline Realism Index (Historical)

Cumulative-to-Date Baseline Realism Index (Projected)

Baseline Realism Index for 1 Month

(Projected)

Notional Data 24

Page 25: Schedule Execution Metrics - NASA

BPO/CAAG/ECE

PROGRAM XYZ - ACT Executive View Baseline Realism

0.00.10.20.30.40.50.60.70.80.91.0

Sep-

15

Dec-

15

Mar

-16

Jun-

16

Sep-

16

Dec-

16

Mar

-17

Jun-

17

Sep-

17

Dec-

17

Mar

-18

Jun-

18

Sep-

18

Dec-

18

Mar

-19

Jun-

19

Sep-

19

Dec-

19

Mar

-20

Jun-

20

Perf

orm

ance

Inde

x

Schedule Data as of June 2016

PROGRAM XYZ ACT Executive View Baseline Realism (1 Mo)

BLR (Mo) Projected BLR (Mo)

456 ACT require BL FinFilter: All Tasks

Filter Used in MS Project

Identification of events without BL Finish Dates

IMS Status Date

Baseline Realism Index for 1 Month

(Historical)

Baseline Realism Index for 1 Month

(Projected)

Notional Data 25

Page 26: Schedule Execution Metrics - NASA

BPO/CAAG/ECE

PROGRAM XYZ - ACT Baseline Progress (Cum/Monthly)

0

20

40

60

80

100

120

140

160

0.00.10.20.30.40.50.60.70.80.91.0

Sep-

15N

ov-1

5Ja

n-16

Mar

-16

May

-16

Jul-1

6Se

p-16

Nov

-16

Jan-

17M

ar-1

7M

ay-1

7Ju

l-17

Sep-

17N

ov-1

7Ja

n-18

Mar

-18

May

-18

Jul-1

8Se

p-18

Nov

-18

Jan-

19M

ar-1

9M

ay-1

9Ju

l-19

Sep-

19N

ov-1

9Ja

n-20

Mar

-20

May

-20

Jul-2

0

# Ac

tiviti

es in

Mon

th

Perf

orm

ance

Inde

x

Schedule Data as of June 2016

PROGRAM XYZ ACT Baseline Progress (Cum/Monthly)Monthly BL Fin Monthly EOT Finish BLP (Mo)

Projected BLP (Mo) BLP (Cum) Projected BLP (Cum)

456 ACT require BL FinFilter: All Tasks

Filter Used in MS Project

Identification of events without BL Finish Dates

IMS Status Date

Baseline Progress Index for 1 Month

(Historical)

Cumulative-to-Date Baseline Progress Index (Historical)

Cumulative-to-Date Baseline Progress Index (Projected)

Baseline Progress Index for 1 Month

(Projected)

Number of Actual/Projected Finishes per Month

Number of Baseline Finishes per Month

Notional Data 26

Page 27: Schedule Execution Metrics - NASA

BPO/CAAG/ECE

PROGRAM XYZ - ACT Monthly Baseline Progress

0.0

0.1

0.2

0.3

0.4

0.5

0.6

0.7

0.8

0.9

1.0

Sep-

15N

ov-1

5Ja

n-16

Mar

-16

May

-16

Jul-1

6Se

p-16

Nov

-16

Jan-

17M

ar-1

7M

ay-1

7Ju

l-17

Sep-

17N

ov-1

7Ja

n-18

Mar

-18

May

-18

Jul-1

8Se

p-18

Nov

-18

Jan-

19M

ar-1

9M

ay-1

9Ju

l-19

Sep-

19N

ov-1

9Ja

n-20

Mar

-20

May

-20

Jul-2

0

Perf

orm

ance

Inde

x

Schedule Data as of June 2016

PROGRAM XYZ ACT Monthly Baseline ProgressBLP (Mo) Projected BLP (Mo)

456 ACT require BL FinFilter: All Tasks

Filter Used in MS Project

Identification of events without BL Finish Dates

IMS Status Date

Baseline Progress Index for 1 Month

(Historical)

Baseline Progress Index for 1 Month

(Projected)

Notional Data 27

Page 28: Schedule Execution Metrics - NASA

BPO/CAAG/ECE

PROGRAM XYZ - ACT Baseline Execution

0

20

40

60

80

100

120

140

160

0.0

5.0

10.0

15.0

20.0

25.0

30.0

Sep-

15N

ov-1

5Ja

n-16

Mar

-16

May

-16

Jul-1

6Se

p-16

Nov

-16

Jan-

17M

ar-1

7M

ay-1

7Ju

l-17

Sep-

17N

ov-1

7Ja

n-18

Mar

-18

May

-18

Jul-1

8Se

p-18

Nov

-18

Jan-

19M

ar-1

9M

ay-1

9Ju

l-19

Sep-

19N

ov-1

9Ja

n-20

Mar

-20

May

-20

Jul-2

0

# Ac

tiviti

es in

Mon

th

Perf

orm

ance

Inde

x

Schedule Data as of June 2016

PROGRAM XYZ ACT Baseline ExecutionMonthly BL Fin Monthly Finish BE (Mo)

Projected BE (Mo) BE (Cum) Projected BE (Cum)

456 ACT require BL FinFilter: All Tasks

Accomplished ~152.3% of BL Plan ACT to date - All Remaining ACT represent 661% (increase) of ACT in BL Plan Scheduled to finish after JUN 2016

Filter Used in MS Project

Identification of events without BL Finish Dates

IMS Status Date

Baseline Execution Index for 1 Month

(Historical)

Cumulative-to-Date Baseline Execution Index (Historical)

Cumulative-to-Date Baseline Execution Index (Projected)

Baseline Execution Index for 1 Month

(Projected)

Number of Baseline Finishes per Month

Number of Actual/Projected Finishes per

Month

Notional Data 28

Page 29: Schedule Execution Metrics - NASA

BPO/CAAG/ECE

0

50

100

150

200

250

300

350

400

0.0

0.2

0.4

0.6

0.8

1.0

1.2

1.4

1.6

Oct

-15

Dec-

15Fe

b-16

Apr-

16Ju

n-16

Aug-

16O

ct-1

6De

c-16

Feb-

17Ap

r-17

Jun-

17Au

g-17

Oct

-17

Dec-

17Fe

b-18

Apr-

18Ju

n-18

Aug-

18O

ct-1

8De

c-18

Feb-

19Ap

r-19

Jun-

19Au

g-19

Oct

-19

Dec-

19Fe

b-20

Apr-

20Ju

n-20

Aug-

20

Perf

rom

ance

Inde

x

Schedule Data as of November 2016

PROGRAM X Baseline Execution vs To-Complete Baseline Execution

Monthly BL Fin Monthly Finish BE (Cum)

Projected BE (Cum) BE (Mo) TC-BE

100% have BL FinFilter: All Tasks

51% difference between Cumulative BE (0.842) and To-Complete BEI (1.352) as of NOV 2016

Avg Dur for Completed Act: 25d Avg Dur for Future Act: 28d

PROGRAM XYZ - ACT Baseline Executionvs To-Complete Baseline Execution

Filter Used in MS Project

Identification of events without BL Finish Dates

IMS Status Date

Baseline Execution Index

for 1 Month (Historical)

Cumulative-to-Date Baseline

Execution Index (Historical) Cumulative-to-Date Baseline

Execution Index (Projected)

To Complete Baseline Execution Index

Number of Baseline Finishes

per Month

Number of Actual/Projected Finishes per Month

Notional Data 29

Page 30: Schedule Execution Metrics - NASA

BPO/CAAG/ECE

PROGRAM XYZ - ACT Schedule Workoffs

0%

20%

40%

60%

80%

100%

0

50

100

150

200

250

300

350

400

Oct

-15

Dec

-15

Feb-

16

Apr-

16

Jun-

16

Aug-

16

Oct

-16

Dec

-16

Feb-

17

Apr-

17

Jun-

17

Aug-

17

Oct

-17

Dec

-17

Feb-

18

Apr-

18

Jun-

18

Aug-

18

Oct

-18

Dec

-18

Feb-

19

Apr-

19

Jun-

19

Aug-

19

Oct

-19

Dec

-19

Feb-

20

Apr-

20

Jun-

20

Aug-

20

% o

f Act

iviti

es M

ore

than

30d

Lat

e

# Ac

tiviti

es in

Mon

th

Schedule Data as of November 2016

Program X Schedule Workoffs% of Activity Completions > 30d Late (Mo) # Activities >30d Late (Mo)

# Activities Projected >30d Late (Mo) # Completed Activities (Mo)

# Projected Completed Activities (Mo) % of Activity Completions > 30d Late (Cum)

34% of All Activities are projected to be more than 30d Late

100% have BL FinFilter: All Tasks

Filter Used in MS Project

Identification of events without BL Finish Dates

IMS Status Date

Percentage of Completed Activities more than 30d Late During a Month

Number of Activities Forecasted to Complete

during Month

Cumulative Percentage of Completed Activities more than 30d Late

Number of Activities Completed during Month

Number of Activities Completed More than 30d Late during Month

Number of Activities Forecasted to Complete More than 30d

Late during Month

Notional Data 30

Page 31: Schedule Execution Metrics - NASA

BPO/CAAG/ECE

0

50

100

150

200

250

300

350

400O

ct-1

5N

ov-1

5D

ec-1

5Ja

n-16

Feb-

16M

ar-1

6Ap

r-16

May

-16

Jun-

16Ju

l-16

Aug-

16Se

p-16

Oct

-16

Nov

-16

Dec

-16

Jan-

17Fe

b-17

Mar

-17

Apr-

17M

ay-1

7Ju

n-17

Jul-1

7Au

g-17

Sep-

17O

ct-1

7N

ov-1

7D

ec-1

7Ja

n-18

Feb-

18M

ar-1

8Ap

r-18

May

-18

Jun-

18Ju

l-18

Aug-

18Se

p-18

Oct

-18

Nov

-18

Dec

-18

Jan-

19Fe

b-19

Mar

-19

Apr-

19M

ay-1

9Ju

n-19

Jul-1

9Au

g-19

Sep-

19O

ct-1

9N

ov-1

9D

ec-1

9Ja

n-20

Feb-

20M

ar-2

0Ap

r-20

May

-20

Jun-

20Ju

l-20

Aug-

20Se

p-20

# M

onth

ly A

ctiv

ities

Schedule Data as of November 2016

Program X Forecasted Late FinishesUnfinished BL Activities Completed Activities Future Planned Finishes

100% have BL FinFilter: All Tasks

27% of all tasks currrently projected to finish after the status of NOV 2016 were

baselined to finish prior to that status date

PROGRAM XYZ - ACT Forecasted Late Finishes

Filter Used in MS Project

Identification of events without BL Finish Dates

IMS Status Date

Activities that are Already Late and when they are currently Forecasted to by Complete

Number of Activities Completed during Month

Number of Activities Forecasted to Complete

during Month

Notional Data 31

Page 32: Schedule Execution Metrics - NASA

BPO/CAAG/ECE

PROGRAM XYZ - ACT Late Finish Assessment

0

500

1000

1500

2000

2500

3000

3500

4000O

ct-1

5N

ov-1

5D

ec-1

5Ja

n-16

Feb-

16M

ar-1

6Ap

r-16

May

-16

Jun-

16Ju

l-16

Aug-

16Se

p-16

Oct

-16

Nov

-16

Dec

-16

Jan-

17Fe

b-17

Mar

-17

Apr-

17M

ay-1

7Ju

n-17

Jul-1

7Au

g-17

Sep-

17O

ct-1

7N

ov-1

7D

ec-1

7Ja

n-18

Feb-

18M

ar-1

8Ap

r-18

May

-18

Jun-

18Ju

l-18

Aug-

18Se

p-18

Oct

-18

Nov

-18

Dec

-18

Jan-

19Fe

b-19

Mar

-19

Apr-

19M

ay-1

9Ju

n-19

Jul-1

9Au

g-19

Sep-

19O

ct-1

9N

ov-1

9D

ec-1

9Ja

n-20

Feb-

20M

ar-2

0Ap

r-20

May

-20

Jun-

20Ju

l-20

Aug-

20Se

p-20

Tota

l Num

ber o

f Act

iviti

es

Schedule Data as of November 2016

Program X Late Finish Assessment

STATUS DATE: NOV 2016 BL FINISH FINISH LATE FINISH

100% have BL FinFilter: All Tasks

Some future tasks may slip by as many as 337 calendar days before impacting the IMS completion date

Filter Used in MS Project

Identification of events without BL Finish Dates

IMS Status Date

Status Date

Actual/Forecasted Finishes

Baseline Finishes

Late Finishes

Notional Data 32

Page 33: Schedule Execution Metrics - NASA

BPO/CAAG/ECE

PROGRAM XYZ - ACT Baseline Realismvs Baseline Progress

0.0000.1000.2000.3000.4000.5000.6000.7000.8000.9001.000

Oct

-15

Dec

-15

Feb-

16

Apr-

16

Jun-

16

Aug-

16

Oct

-16

Dec

-16

Feb-

17

Apr-

17

Jun-

17

Aug-

17

Oct

-17

Dec

-17

Feb-

18

Apr-

18

Jun-

18

Aug-

18

Oct

-18

Dec

-18

Feb-

19

Apr-

19

Jun-

19

Aug-

19

Oct

-19

Dec

-19

Feb-

20

Apr-

20

Jun-

20

Aug-

20

Perf

rom

ance

Inde

x

Schedule Data as of November 2016

Program X Baseline Realism vs Baseline ProgressBLR (Mo) BLP (Mo) BLR (Cum) = BLP (Cum)

100% have BL FinFilter: All Tasks

Filter Used in MS Project

Identification of events without BL Finish Dates

IMS Status Date

Baseline Progress Index for 1 Month

(Historical)

Baseline Realism Index for 1 Month

(Historical)

Cumulative Baseline Progress/Realism Index

(Historical)

Notional Data 33

Page 34: Schedule Execution Metrics - NASA

BPO/CAAG/ECE

PROGRAM XYZ - ACT Baseline Realism (Cum/Cur)

020406080100120140160

0.00.10.20.30.40.50.60.70.80.91.0

Sep-

15N

ov-1

5Ja

n-16

Mar

-16

May

-16

Jul-1

6Se

p-16

Nov

-16

Jan-

17M

ar-1

7M

ay-1

7Ju

l-17

Sep-

17N

ov-1

7Ja

n-18

Mar

-18

May

-18

Jul-1

8Se

p-18

Nov

-18

Jan-

19M

ar-1

9M

ay-1

9Ju

l-19

Sep-

19N

ov-1

9Ja

n-20

Mar

-20

May

-20

Jul-2

0

# Ac

tiviti

es in

Mon

th

Perf

orm

ance

Inde

x

Schedule Data as of June 2016

PROGRAM XYZ Activity Baseline Realism (Cum/Cur)Monthly BL Fin Monthly Planning Window Finish

BLR (Mo) Projected BLR (Mo)

BLR (Cum) Projected Cum BLR

456 ACT require BL FinFilter: All Tasks

Filter Used in MS Project

Identification of events without BL Finish Dates

IMS Status Date

Number of Baseline Finishes per Month

Number of Actual/Projected Finishes per

Month

Baseline Realism Index for 1 Month

(Historical)

Baseline Realism Index for 1 Month

(Projected)

Cumulative-to-Date Baseline Realism Index (Historical)

Cumulative-to-Date Baseline Realism Index (Projected)

Notional Data 34

Page 35: Schedule Execution Metrics - NASA

BPO/CAAG/ECE

PROGRAM XYZ - ACT BR vs BP vs BE

0.0

5.0

10.0

15.0

20.0

25.0

30.0Se

p-15

Nov

-15

Jan-

16M

ar-1

6M

ay-1

6Ju

l-16

Sep-

16N

ov-1

6Ja

n-17

Mar

-17

May

-17

Jul-1

7Se

p-17

Nov

-17

Jan-

18M

ar-1

8M

ay-1

8Ju

l-18

Sep-

18N

ov-1

8Ja

n-19

Mar

-19

May

-19

Jul-1

9Se

p-19

Nov

-19

Jan-

20M

ar-2

0M

ay-2

0Ju

l-20

Perf

orm

ance

Inde

x

Schedule Data as of June 2016

PROGRAM XYZ ACT BLR vs BLP vs BEBLR (Mo) BLP (Mo) BE (Mo)

456 ACT require BL FinFilter: All Tasks

Filter Used in MS Project

Identification of events without BL Finish Dates

IMS Status Date

Baseline Realism Index for 1 Month

(Historical)

Baseline Execution Index for 1 Month

(Historical)

Baseline ProgressIndex for 1 Month

(Historical)

Notional Data 35

Page 36: Schedule Execution Metrics - NASA

BPO/CAAG/ECE

PROGRAM X - 1 Period ACT Forecast Realism

0

50

100

150

200

250

300

350

0.0

0.1

0.2

0.3

0.4

0.5

0.6

0.7

0.8

0.9

1.0

Feb-

16M

ar-1

6Ap

r-16

May

-16

Jun-

16Ju

l-16

Aug-

16Se

p-16

Oct

-16

Nov

-16

Dec-

16Ja

n-17

Feb-

17M

ar-1

7Ap

r-17

May

-17

Jun-

17Ju

l-17

Aug-

17Se

p-17

Oct

-17

Nov

-17

Dec-

17Ja

n-18

Feb-

18M

ar-1

8

# Ac

tiviti

es

Fore

cast

Rea

lsim

PROGRAM X - 1 Mo Activity Forecast Realism# Forecasted Activities # Completed Activities 1 Mo Activity Forecast Realism

Provides ratio of specific activiies actuallyaccomplished compared to the projected

Forecast Realism is assessment of the actual

completions to the projected completions (in this case ~125

of ~250 = ~.5)

These are completions in Nov 16 of SPECIFIC

events that were forecast were forecast to be

complete in the Oct 16 file

These are the projected completions for Dec 16 (using the Nov 16 file)

These are the projected completions for Nov 16 (using the Oct 16 file)

Note: This example uses Monthly Data and Status is EOM Nov 16

In this example, Contractor’s ability to forecast one month ahead ranges between 30% and 80% with average near

50%

Notional Data 36

Page 37: Schedule Execution Metrics - NASA

BPO/CAAG/ECE

PROGRAM X - 2 Period ACT Forecast Realism

0

100

200

300

400

500

600

700

0.0

0.1

0.2

0.3

0.4

0.5

0.6

0.7

0.8

0.9

1.0

Mar

-16

Apr-

16M

ay-1

6Ju

n-16

Jul-1

6Au

g-16

Sep-

16O

ct-1

6N

ov-1

6De

c-16

Jan-

17Fe

b-17

Mar

-17

Apr-

17M

ay-1

7Ju

n-17

Jul-1

7Au

g-17

Sep-

17O

ct-1

7N

ov-1

7De

c-17

Jan-

18Fe

b-18

Mar

-18

Apr-

18

# Ac

tiviti

es

Fore

cast

Rea

lsim

PROGRAM X - 2 Mo Activity Forecast Realism# Forecasted Activities # Completed Activities 2 Mo Activity Forecast Realism

Provides ratio of specific activiies actuallyaccomplished during the two--period window compared to the projected finishes from the

beginning of that window

Forecast Realism is assessment of the actual

completions to the projected completions (in this case ~275

of ~550 = ~.53)

These are the projected completions for Nov 16 through Dec 16 (using the Oct 16 file)

These are the projected completions for 2 months of data - Oct 16 through Nov 16 (using the Sep 16 file)

These are the projected completions for Dec 16 through Jan 17 (using the Nov 16 file)

These are completions Oct 16 through Nov 16 of SPECIFIC

events that were forecast were forecast to be complete in the Sep

16 file

In this example, Contractor’s ability to forecast two months ahead ranges between 45% and 80% with average near

55%

Note: 2 Period is calculated based on Forecast Finishes during the next two periods

Notional Data

37

Page 38: Schedule Execution Metrics - NASA

BPO/CAAG/ECE

PROGRAM X - 3 Period ACT Forecast Realism

0

100

200

300

400

500

600

700

800

900

0.0

0.1

0.2

0.3

0.4

0.5

0.6

0.7

0.8

0.9

1.0

Apr-

16M

ay-1

6Ju

n-16

Jul-1

6Au

g-16

Sep-

16O

ct-1

6N

ov-1

6De

c-16

Jan-

17Fe

b-17

Mar

-17

Apr-

17M

ay-1

7Ju

n-17

Jul-1

7Au

g-17

Sep-

17O

ct-1

7N

ov-1

7De

c-17

Jan-

18Fe

b-18

Mar

-18

Apr-

18M

ay-1

8

# Ac

tiviti

es

Fore

cast

Rea

lsim

PROGRAM X - 3 Mo Activity Forecast Realism# Forecasted Activities # Completed Activities 3 Mo Activity Forecast Realism

Provides ratio of specific activiies actuallyaccomplished during the three--period window

compared to the projected finishes from the beginning of that window

In this example, Contractor’s ability to forecast three months

ahead ranges between 50% and 80% with average near 60%

Note: 3 Period is calculated based on Forecast Finishes during the next three periods

Forecast Realism is assessment of the actual

completions to the projected completions (in this case ~325

of ~650 = ~.49)

These are the projected completions for Nov 16 through Jan 17 (using the Sep 16 file)

These are the projected completions for 3 months of data – Sep 16 through Nov 16 (using the Aug 16 file)

These are the projected completions for Dec 16 through Feb 17 (using the Nov 16 file)

These are completions Sep 16 through Nov 16 of SPECIFIC events that were forecast were forecast to

be complete in the Aug 16 file

Notional Data

38

Page 39: Schedule Execution Metrics - NASA

BPO/CAAG/ECE

PROGRAM X - 6 Period ACT Forecast Realism

0

200

400

600

800

1000

1200

1400

1600

0.0

0.1

0.2

0.3

0.4

0.5

0.6

0.7

0.8

0.9

1.0

Jul-1

6Au

g-16

Sep-

16O

ct-1

6N

ov-1

6De

c-16

Jan-

17Fe

b-17

Mar

-17

Apr-

17M

ay-1

7Ju

n-17

Jul-1

7Au

g-17

Sep-

17O

ct-1

7N

ov-1

7De

c-17

Jan-

18Fe

b-18

Mar

-18

Apr-

18M

ay-1

8Ju

n-18

Jul-1

8Au

g-18

# Ac

tiviti

es

Fore

cast

Rea

lsim

PROGRAM X - 6 Mo Activity Forecast Realism# Forecasted Activities # Completed Activities 6 Mo Activity Forecast Realism

Provides ratio of specific activiies actuallyaccomplished during the six--period window compared to the projected finishes from the

beginning of that window

In this example, Contractor’s ability

to forecast six months ahead

ranges between 65% and 75% with average near 65%

Note: 6 Period is calculated based on Forecast Finishes during the next six periods

These are the projected completions for 6 months of data – Jun 16 through Nov 16 (using

the May 16 file)

Forecast Realism is assessment of the actual

completions to the projected completions (in this case ~800 of ~1200 =

~.67)

These are the projected completions for Aug 16 through Dec 16 (using the Jul 16 file)

These are the projected completions for Sep 16 through Feb17 (using the Aug 16 file)

These are the projected completions for Oct 16 through Mar 17 (using the Sep 16 file)

These are the projected completions for Nov 16 through Apr 17 (using the Oct 16 file)

These are the projected completions for Dec 16 through May 17 (using the Nov 16 file)

These are the projected completions for Jul 16 through Dec 16 (using the Jun 16 file)

These are completions Jun 16 through Nov 16 of SPECIFIC events that were

forecast were forecast to be complete in the May 16 file

Notional Data

39

Page 40: Schedule Execution Metrics - NASA

BPO/CAAG/ECE

PROGRAM X - Activity Future Durations

14%

18%

68%

PROGRAM X - Activity Future DurationsCONTRACTED EXPANDED SAME

1554 ACTIVITIES < 100% COMPLETE AS OF

11/30/2016 (3712 TOTAL ACTIVITIES IN IMS)

DURATIONS COMPARED TO THOSE IDENTTIFIED ON

1/31/2016

Note: This chart is only available in FR_Activities

Identifies Future Activity durations are contracted

(shorter durations) compared to the first duration identified for

the activity in the IMS

Identifies Future Activity durations are expanded

(longer durations) compared to the first duration identified

for the activity in the IMS

Identifies Future Activity durations are the same when compared to the first duration identified for the

activity in the IMS

Notional Data 40

Page 41: Schedule Execution Metrics - NASA

BPO/CAAG/ECE

PROGRAM X - Future Completions (Activities)

6%

72%

22%

PROGRAM X - Activity Future CompletionsEARLIER LATER SAME

1554 ACTIVITIES < 100% COMPLETE AS OF

11/30/2016 (3712 TOTAL ACTIVITIES IN IMS)

COMPLETION DATES COMPARED TO THOSE

FORECASTED ON 1/31/2016

Identifies Future Activity completion dates earlier than the first completion date identified for

the activity in the IMSIdentifies Future Activity completion dates same as the first completion date identified

for the activity in the IMSIdentifies Future Activity

completion dates later than the first completion date identified

for the activity in the IMS

Notional Data

41

Page 42: Schedule Execution Metrics - NASA

BPO/CAAG/ECE

Illustration - Baseline Plan

Number of activities planned for completion in the assessment window (6) is the denominator for calculating Monthly Baseline Realism, Baseline Progress, and Baseline Execution

Notional

42

1

2

3

4

5

6

Time NowAssessment Window

Page 43: Schedule Execution Metrics - NASA