schedule execution metrics - nasa
TRANSCRIPT
![Page 1: Schedule Execution Metrics - NASA](https://reader030.vdocument.in/reader030/viewer/2022013018/61d0de80adf91148a83a4f5b/html5/thumbnails/1.jpg)
Schedule Execution MetricsThe value proposition for adding Baseline Realism,
Baseline Progress and Forecast Realism to the Scheduler Analyst’s Toolkit
June 2017
![Page 2: Schedule Execution Metrics - NASA](https://reader030.vdocument.in/reader030/viewer/2022013018/61d0de80adf91148a83a4f5b/html5/thumbnails/2.jpg)
BPO/CAAG/ECE
Abstract
In response to National Reconnaissance Office (NRO) Senior Management’s need for metrics that are leading indicators of program execution challenges, the NRO Cost and Acquisition Assessment Group (CAAG) Earned Value Management Center of Excellence (ECE) developed a suite of Schedule Execution Metrics. The metrics are now part of the NRO Corporate tool box for senior leadership decision support. The metrics are derived from the Contractor’s integrated master schedule to answer the questions:
• Is the contractor executing to the baseline plan?• Is the contractor ahead or behind in completing the planned activities?• Is the forecast realistic?
This briefing will define schedule execution metrics, explain how they are being used at NRO, and describe ongoing research tasks to establish thresholds and interpret the metrics.
2
![Page 3: Schedule Execution Metrics - NASA](https://reader030.vdocument.in/reader030/viewer/2022013018/61d0de80adf91148a83a4f5b/html5/thumbnails/3.jpg)
BPO/CAAG/ECE
Business Case for Schedule Execution Metrics at NRO
• What led to the creation of Schedule Execution Metrics (SEM)• We were tasked to create leading indicators to explain the true status of a program beyond the “green”
conditions of program level CPI and SPI, and to provide an early indicator of a potential rebaseline• We were asked to provide clean, simple, easy-to-understand metrics• Many detailed cost and technical metrics already exist are reviewed extensively. We chose to emphasize
schedule execution and schedule performance to fill a void. • JSCC Better EVMS Implementation Study II: Improving Value for Government PMs: Government PMs highly value
the Integrated Master Schedule, and refer to it as managing “heads and scheds”• We rebranded existing NAVAIR, NRO internal and other metrics and created new metrics to fully analyze
schedule performance. • Baseline Realism, work-off analysis (phasing of recovery), and other schedule execution metrics are used
extensively across NRO programs offices. We standardized terminology and created automated tools to put Schedule Execution Metrics in the Corporate Toolbox
• Measuring accomplishment against the contractor’s forecast is a fall back if there is a problem with the baseline plan
• Benefits of employing Schedule Execution Metrics at NRO• Excellent Insight on an Agile Program: The delta between baseline realism and baseline execution provided
insight into the magnitude of reprioritization work. The metrics indicated the contractor was efficiently delivering software functionality, but highlighted the impact of Government's reprioritization through agile software management, and alerted the customer of potential work in the backlog that might not be completed
• Better Insight Drives accountability When included in a suite of cost, schedule and technical metrics, schedule execution metrics isolated underlying schedule issues leading to corrective action targeted to keep the program on schedule including: assigning dedicated effectivity and test campaign leads, investing in the improvement of testing environments, more complete detail planning when ECP work is added to the contract.
3
![Page 4: Schedule Execution Metrics - NASA](https://reader030.vdocument.in/reader030/viewer/2022013018/61d0de80adf91148a83a4f5b/html5/thumbnails/4.jpg)
BPO/CAAG/ECE
How Schedule Execution Metrics can help Industry
The suite of Schedule Execution Metrics tells a more complete story• Provides feedback to the planning process
• Is the work really being performed as it was planned? How much can the plan deviate and still be useful as a plan (use of float, margin)?
• Identifies upcoming planning challenges• Are future activities in jeopardy of finishing late? Is there a bow wave of
activities on he horizon? • Highlights issues that are not necessarily identified by technical
metrics• How much effort is regularly being spent on activities that are already
more than 30d late?• Supplements typical schedule presentation
• Is accomplishment of tasks supporting the standard Gantt Chart view? Is there a potential impact to the critical path?
4
![Page 5: Schedule Execution Metrics - NASA](https://reader030.vdocument.in/reader030/viewer/2022013018/61d0de80adf91148a83a4f5b/html5/thumbnails/5.jpg)
BPO/CAAG/ECE
Challenges in Typical Schedule Reporting
5
SV CV VACProgram Level ↑ ↑ ↔
BUS ↑ ↑ ↑PAYLOAD ↑ ↑ ↑
Program-level Cumulative Schedule Variance can look favorable, even if there are execution challenges:• Historic performance can heavily
weight the indicator to “green”
Senior Leaders ask for leading indicators of execution challenges
0.0
0.1
0.2
0.3
0.4
0.5
0.6
0.7
0.8
0.9
1.0
Oct
-15
Jan-
16
Apr-
16
Jul-1
6
Oct
-16
Jan-
17
Apr-
17
Jul-1
7
Oct
-17
Jan-
18
Apr-
18
Jul-1
8
Oct
-18
Jan-
19
Apr-
19
Jul-1
9
Oct
-19
Jan-
20
Apr-
20
Jul-2
0
Perf
rom
ance
Inde
x
Schedule Data as of October 2016
PROGRAM X Executive View Baseline Realism (1 Mo)BLR (Mo) Projected BLR (Mo)
100% have BL FinFilter: All Tasks
Baseline Realism can provide an early indicator that a contractor is not performing the work as planned
Typically EVM Metrics provided to Senior Leadership
Schedule Execution Metrics can provide Additional Insight
Notional Data
Notional Data
EVMvs
SEM
![Page 6: Schedule Execution Metrics - NASA](https://reader030.vdocument.in/reader030/viewer/2022013018/61d0de80adf91148a83a4f5b/html5/thumbnails/6.jpg)
BPO/CAAG/ECE
Schedule Execution Metrics as part of the NRO Corporate Toolbox
6
Baseline Realism
Baseline Progress
Forecast Realism
Baseline Realism Moving Averages
Ability to Absorb Late Finishes
Distribution of Late Finishes
Schedule Workoffs
Baseline Execution Index
Others
Baseline Realism is one of many
metrics that can be used to assess
schedule performance
Schedule data and analysis is part of the
EVM data set
![Page 7: Schedule Execution Metrics - NASA](https://reader030.vdocument.in/reader030/viewer/2022013018/61d0de80adf91148a83a4f5b/html5/thumbnails/7.jpg)
BPO/CAAG/ECE
We recommend a combination of new and existing Schedule Execution Metrics to answer 3 critical questions
Question Metric/Analysis What it Means
Is the contractor executing the baseline plan?
Baseline Progress Prior to “time now” Activities completed early or on time / baseline activities planned finishes over a specified period of timeAfter “time now” Activities forecasted early or on time / baseline activities planned finishes over a specified period of time
Baseline Realism Prior to “time now” Assessment of the completions of specific baseline plan finishes over a specified period of timeAfter “time now” Assessment of the forecasted completions of specific baseline plan finishes over a specified period of time
Is the contractor ahead or behind?
Critical Path Verification
Identification of Critical Path activities to any specific deliverable or milestone
Critical Path Length Index
(Duration to a specific deliverable or milestone + float and margin) / duration to a specific deliverable or milestone
Schedule Margin Remaining
Schedule margin as percentage of remaining time to a deliverable or milestone
Is the forecast realistic?
Forecast Realism Prior to “time now” Number of tasks actually completed / number of tasks forecasted to finish in a previous IMS version of the IMSAfter “time now” Number of tasks forecasted to complete / number of tasks forecasted to finish in a previous IMS version of the IMS
Schedule Workoff Prior to “time now” Percentage of activities completed each month that are more than 30 days lateAfter “time now” Percentage of activities in the future that are forecasted to to be more than 30 days late
Total Float Consumption Index
(Actual Duration + Critical Path Total Float) / Actual Duration
Note: One or more specified period of time can be one to six months, or a cumulative value
![Page 8: Schedule Execution Metrics - NASA](https://reader030.vdocument.in/reader030/viewer/2022013018/61d0de80adf91148a83a4f5b/html5/thumbnails/8.jpg)
BPO/CAAG/ECE
Illustration - December 2016 Status
Notional
LegendBaseline
StartBaseline
FinishProgress (ending at forecast or actual finish)
Percent Complete
Early
Late
8
On plan finish, current period
Late, not finished
On plan finish, current period
Early finish, current period baseline
Late finish, current period
Early finish, current period
On plan finish, prior period
Assessment Window
Time Now
![Page 9: Schedule Execution Metrics - NASA](https://reader030.vdocument.in/reader030/viewer/2022013018/61d0de80adf91148a83a4f5b/html5/thumbnails/9.jpg)
BPO/CAAG/ECE
Illustration – Baseline Realism:On Plan Finishes for Activities with Baseline Finishes
within the assessment window
Monthly Baseline Realism = 4/6 = 0.6666% of the of the activities planned for completion in the assessment
window were completed during the assessment window.
Notional
1
4
9
Note : Cumulative Baseline Execution = 8/9 = 0.89
On plan finish, current period
On plan finish, current period
2
3
Assessment Window
Time Now
![Page 10: Schedule Execution Metrics - NASA](https://reader030.vdocument.in/reader030/viewer/2022013018/61d0de80adf91148a83a4f5b/html5/thumbnails/10.jpg)
BPO/CAAG/ECE
Illustration – Baseline Progress: On Plan & Early Finishes for Activities with Baseline Finishes
within the assessment window
Monthly Baseline Progress = 5/6 = 0.8383% of the activities planned for completion in the assessment window were
accomplished or before the time-now date.
Notional
1
2
3
4
Note : Cumulative Baseline Progress = 8/9 = 0.89
5
10
On plan finish, current period
Early finish, current period baseline
On plan finish, current period
Assessment Window
Time Now
![Page 11: Schedule Execution Metrics - NASA](https://reader030.vdocument.in/reader030/viewer/2022013018/61d0de80adf91148a83a4f5b/html5/thumbnails/11.jpg)
BPO/CAAG/ECE
Illustration – Baseline Execution:All On Plan, Early, & Late Finishes
within the assessment window
Monthly Baseline Execution = 6/6 = 1.00The pace of work is 100% of what it was planned to be during the assessment window, although the completed activities were not
necessarily the ones that were planned for completion.
Early finish, current period
Notional
1
2
6
Note : Cumulative Baseline Execution = 9/9 = 1.0011
3
45
Assessment Window
Time Now
Late finish, current period
On plan finish, current period
On plan finish, current period
![Page 12: Schedule Execution Metrics - NASA](https://reader030.vdocument.in/reader030/viewer/2022013018/61d0de80adf91148a83a4f5b/html5/thumbnails/12.jpg)
BPO/CAAG/ECE
Automated Tools versus Manual Analysis
Automated Tool in Use
Future Automated
Tool
Manual Analysis
Note: Data for Schedule Margin Metric can be Collected in Forecast Realism Tool
12
![Page 13: Schedule Execution Metrics - NASA](https://reader030.vdocument.in/reader030/viewer/2022013018/61d0de80adf91148a83a4f5b/html5/thumbnails/13.jpg)
BPO/CAAG/ECE
New Schedule Execution Metrics and how they compare widely available Baseline Execution Index (BEI)
13
Metric What it Tells You
Baseline Realism (BR)*
Is the baseline being accomplished the way it was planned (by specific period or cumulative to date)?How well the contractor can do the work in the manner identified in the Integrated Master Schedule?Low BR can be a potential early indicator of need to replan
BaselineProgress (BP)*
What is the progress to “time now” against the plan (by specific period or cumulative to date)?Differs from BR in that it includes prior finishes if the task was baselined within the assessment window. Does not count early finishes for activities baselined to finish after the assessment window..Most PMs will be most concerned with Cumulative BP and Critical Path management
Forecast Realism (FR)
Are forecasted tasks being accomplished as forecasted?Provides insight into contractor's ability to complete the activities forecasted for completion in previous IMS submissions
Baseline Execution Index (BEI)
Execution Pace - Significantly different from BR and BP in that BEI does not look at the order or the planBEI provides the actual pace of activities accomplished compared to the pace that was planned“BEI is the SPI of Schedule Execution Metrics” (BEI is based on activity finishes not dollars). Like SPI, BEI may not necessarily be a leading indicator. Unlike SPI, BEI does not give credit for partial completion
Note: Cumulative BR is equal to Cumulative BP
![Page 14: Schedule Execution Metrics - NASA](https://reader030.vdocument.in/reader030/viewer/2022013018/61d0de80adf91148a83a4f5b/html5/thumbnails/14.jpg)
BPO/CAAG/ECE
Interpreting Baseline Realism
Light Blue Bars represent the count of activity baseline finishesPrior to Time Now - Black Bars represent actual activity finishesAfter time now – Black Bars represent forecasted activity finishesSolid Red Line represents the percent of activity completions in the period they were baselined for completionDotted Red Line represents percent of activity completions forecasted to complete in the period they are baselined to be completedSolid Black Triangles represent Cumulative Baseline Realism (percent)White Triangles represent Forecasted Cumulative Baseline Realism (percent)
14
0
50
100
150
200
250
300
0.0
0.1
0.2
0.3
0.4
0.5
0.6
0.7
0.8
0.9
1.0
Oct
-15
Dec-
15Fe
b-16
Apr-
16Ju
n-16
Aug-
16O
ct-1
6De
c-16
Feb-
17Ap
r-17
Jun-
17Au
g-17
Oct
-17
Dec-
17Fe
b-18
Apr-
18Ju
n-18
Aug-
18O
ct-1
8De
c-18
Feb-
19Ap
r-19
Jun-
19Au
g-19
Oct
-19
Dec-
19Fe
b-20
Apr-
20Ju
n-20
Aug-
20
# Ac
tiviti
es in
Mon
th
Perf
rom
ance
Inde
x
Schedule Data as of November 2016
M2C2 (Nov 2016) Activity Baseline Realism (Cum/Cur)Monthly BL Fin Monthly Planning Window Finish
BLR (Mo) Projected BLR (Mo)
BLR (Cum) Projected Cum BLR
100% have BL FinFilter: All Tasks
Time nowNotional Data
![Page 15: Schedule Execution Metrics - NASA](https://reader030.vdocument.in/reader030/viewer/2022013018/61d0de80adf91148a83a4f5b/html5/thumbnails/15.jpg)
BPO/CAAG/ECE
Screen shots of Schedule Execution Metrics (1)
15
0
50
100
150
200
250
300
0.0
0.1
0.2
0.3
0.4
0.5
0.6
0.7
0.8
0.9
1.0
Oct
-15
Dec-
15Fe
b-16
Apr-
16Ju
n-16
Aug-
16O
ct-1
6De
c-16
Feb-
17Ap
r-17
Jun-
17Au
g-17
Oct
-17
Dec-
17Fe
b-18
Apr-
18Ju
n-18
Aug-
18O
ct-1
8De
c-18
Feb-
19Ap
r-19
Jun-
19Au
g-19
Oct
-19
Dec-
19Fe
b-20
Apr-
20Ju
n-20
Aug-
20
# Ac
tiviti
es in
Mon
th
Perf
rom
ance
Inde
x
Schedule Data as of October 2016
PROGRAM X Monthly Baseline RealismMonthly BL Fin Monthly Planning Window Finish BLR (Mo) Projected BLR (Mo)
100% have BL FinFilter: All Tasks
0
50
100
150
200
250
300
0.0
0.1
0.2
0.3
0.4
0.5
0.6
0.7
0.8
0.9
1.0
Oct
-15
Dec-
15Fe
b-16
Apr-
16Ju
n-16
Aug-
16O
ct-1
6De
c-16
Feb-
17Ap
r-17
Jun-
17Au
g-17
Oct
-17
Dec-
17Fe
b-18
Apr-
18Ju
n-18
Aug-
18O
ct-1
8De
c-18
Feb-
19Ap
r-19
Jun-
19Au
g-19
Oct
-19
Dec-
19Fe
b-20
Apr-
20Ju
n-20
Aug-
20
# Ac
tiviti
es in
Mon
th
Perf
rom
ance
Inde
x
Schedule Data as of October 2016
PROGRAM X Baseline Progress (Cum/Monthly)Monthly BL Fin Monthly EOT Finish BLP (Mo)
Projected BLP (Mo) BLP (Cum) Projected BLP (Cum)
100% have BL FinFilter: All Tasks
0
50
100
150
200
250
300
350
Oct
-15
Dec-
15Fe
b-16
Apr-
16Ju
n-16
Aug-
16O
ct-1
6De
c-16
Feb-
17Ap
r-17
Jun-
17Au
g-17
Oct
-17
Dec-
17Fe
b-18
Apr-
18Ju
n-18
Aug-
18O
ct-1
8De
c-18
Feb-
19Ap
r-19
Jun-
19Au
g-19
Oct
-19
Dec-
19Fe
b-20
Apr-
20Ju
n-20
Aug-
20
# M
onth
ly A
ctiv
ities
Schedule Data as of October 2016
PROGRAM X Forecasted Late FinishesCompleted Activities (Mo) Late Unfinished Activities (Mo) Future Planned Finishes (Mo)
100% have BL FinFilter: All Tasks
25% of all tasks currently projected to finish after the
status of OCT 2016 were baselined to finish prior to that
status date
0
200
400
600
800
1000
1200
1400
1600
0.0
0.1
0.2
0.3
0.4
0.5
0.6
0.7
0.8
0.9
Nov
-14
Dec-
14Ja
n-15
Feb-
15M
ar-1
5Ap
r-15
May
-15
Jun-
15Ju
l-15
Aug-
15Se
p-15
Oct
-15
Nov
-15
Dec-
15Ja
n-16
Feb-
16M
ar-1
6Ap
r-16
May
-16
Jun-
16Ju
l-16
Aug-
16Se
p-16
Oct
-16
Nov
-16
Dec-
16
# Ac
tiviti
es
Fore
cast
Rea
lsim
PROGRAM X - 6 Mo Forecast Realism# Forecasted Activities # Completed Activities 6 Mo Forecast Realism
Provides ratio of specific activiies actuallyaccomplished during the six--period window compared to the projected finishes from the
beginning of that window
Are activities being accomplished the way they were planned?
What is the “time now” progress against the plan?
What is the recovery plan for missed tasks?
How well is the contractor forecasting future finishes?
Baseline Realism Baseline Progress
Forecast RealismForecasted Late Finishes
![Page 16: Schedule Execution Metrics - NASA](https://reader030.vdocument.in/reader030/viewer/2022013018/61d0de80adf91148a83a4f5b/html5/thumbnails/16.jpg)
BPO/CAAG/ECE
14%
18%
68%
PROGRAM X - Activity Future DurationsCONTRACTED EXPANDED SAME
1554 ACTIVITIES < 100% COMPLETE AS OF
11/30/2016 (3712 TOTAL ACTIVITIES IN IMS)
DURATIONS COMPARED TO THOSE IDENTTIFIED ON
1/31/2016
0
50
100
150
200
250
300
350
400
0.0
0.2
0.4
0.6
0.8
1.0
1.2
1.4
1.6
Oct
-15
Dec-
15Fe
b-16
Apr-
16Ju
n-16
Aug-
16O
ct-1
6De
c-16
Feb-
17Ap
r-17
Jun-
17Au
g-17
Oct
-17
Dec-
17Fe
b-18
Apr-
18Ju
n-18
Aug-
18O
ct-1
8De
c-18
Feb-
19Ap
r-19
Jun-
19Au
g-19
Oct
-19
Dec-
19Fe
b-20
Apr-
20Ju
n-20
Aug-
20
Perf
rom
ance
Inde
x
Schedule Data as of November 2016
PROGRAM X Baseline Execution vs To-Complete Baseline Execution
Monthly BL Fin Monthly Finish BE (Cum)
Projected BE (Cum) BE (Mo) TC-BE
100% have BL FinFilter: All Tasks
51% difference between Cumulative BE (0.842) and To-Complete BEI (1.352) as of NOV 2016
Avg Dur for Completed Act: 25d Avg Dur for Future Act: 28d
52 52 52 52 50 50
35 35 35 35
15 158 8 8 8 7 7
73 73 73 73
53 51
0
10
20
30
40
50
60
70
80
9/30
/201
6
10/3
1/20
16
11/3
0/20
16
12/3
1/20
16
1/31
/201
7
2/28
/201
7
# Da
ys M
argi
n
IMS Status Dates
Schedule Margin ErosionSchedule Margin to MS1 Schedule Margin to MS2
Schedule Margin to MS3 Schedule Margin to MS4
0%
20%
40%
60%
80%
100%
0
50
100
150
200
250
300
350
400
Oct
-15
Dec
-15
Feb-
16
Apr-
16
Jun-
16
Aug-
16
Oct
-16
Dec
-16
Feb-
17
Apr-
17
Jun-
17
Aug-
17
Oct
-17
Dec
-17
Feb-
18
Apr-
18
Jun-
18
Aug-
18
Oct
-18
Dec
-18
Feb-
19
Apr-
19
Jun-
19
Aug-
19
Oct
-19
Dec
-19
Feb-
20
Apr-
20
Jun-
20
Aug-
20
% o
f Act
iviti
es M
ore
than
30d
Lat
e
# Ac
tiviti
es in
Mon
th
Schedule Data as of November 2016
Program X Schedule Workoffs% of Activity Completions > 30d Late (Mo) # Activities >30d Late (Mo)
# Activities Projected >30d Late (Mo) # Completed Activities (Mo)
# Projected Completed Activities (Mo) % of Activity Completions > 30d Late (Cum)
34% of All Activities are projected to be more than 30d Late
100% have BL FinFilter: All Tasks
Screen Shots of Schedule Execution Metrics (2)
16
How much effort is being spent on activities more than 30d late?
What is trending usage of Schedule Margin?
Is remaining work pace in line with how the work was planned?
Are activity durations changing (contracting or expanding)?
Schedule Workoffs Schedule Margin
Future DurationsTo-Complete Baseline Execution
![Page 17: Schedule Execution Metrics - NASA](https://reader030.vdocument.in/reader030/viewer/2022013018/61d0de80adf91148a83a4f5b/html5/thumbnails/17.jpg)
BPO/CAAG/ECE
ECE Schedule Execution Metric Capabilities
• Schedule Execution Metric methods are documented and have been presented over the last 6 months at NRO Scheduler’s Forum• Terminology has been Branded• Formulas have been vetted• Charts have been presented to senior management
• NRO Earned Value Center of Excellence (ECE) has developed tools automated calculation
• ECE is currently working to benchmark Schedule Execution Metrics to better interpret results with respect to historical experience
• ECE is encouraging COTS vendors to consider incorporating Schedule Execution Metrics into IMS and IPMR Analysis Tools
17
![Page 18: Schedule Execution Metrics - NASA](https://reader030.vdocument.in/reader030/viewer/2022013018/61d0de80adf91148a83a4f5b/html5/thumbnails/18.jpg)
BPO/CAAG/ECE
Ongoing Research to Interpret Metrics
• What level or trend in Baseline Realism is an early indicator of an OTB?
• Can Baseline Progress values less than a certain value be regularly associated with an overrun or use of schedule margin?
• What is an expected benchmark for Forecast Realism?
Factors to Consider
• Space Hardware versus Ground Software (in the Space and Ground community)
• Use of Schedule Margin, Management Reserve
• Follow-on effort versus New Development
18
![Page 19: Schedule Execution Metrics - NASA](https://reader030.vdocument.in/reader030/viewer/2022013018/61d0de80adf91148a83a4f5b/html5/thumbnails/19.jpg)
BPO/CAAG/ECE
Back-up
19
![Page 20: Schedule Execution Metrics - NASA](https://reader030.vdocument.in/reader030/viewer/2022013018/61d0de80adf91148a83a4f5b/html5/thumbnails/20.jpg)
BPO/CAAG/ECE
NRO Uses an Automated Tool to CalculateSchedule Execution Metrics
• Automated Data Entry and Chart Package Generation
• Microsoft Project Schedule, Microsoft Excel and Visual Basic
• Tool Outputs shown on following slides
20
![Page 21: Schedule Execution Metrics - NASA](https://reader030.vdocument.in/reader030/viewer/2022013018/61d0de80adf91148a83a4f5b/html5/thumbnails/21.jpg)
BPO/CAAG/ECE
PROGRAM XYZ - Schedule Finish DataCumulative to Date
Days Late/Early # Activities % of Total<-60 0 0%<-30 9 2%
>= -30 and <30 230 63%>30 6 2%>60 3 1%>90 0 0%
>120 0 0%
>150 0 0%
>180 0 0%NO BASELINE 116 32% 32% 32%
2%
63%
2%
2%0%
Based on historical data (before or equal to Status Date) AND
selected MS Project Filter
Notional Data
21
![Page 22: Schedule Execution Metrics - NASA](https://reader030.vdocument.in/reader030/viewer/2022013018/61d0de80adf91148a83a4f5b/html5/thumbnails/22.jpg)
BPO/CAAG/ECE
PROGRAM XYZ - Schedule Finish DataFuture Activities
Days Late/Early # Activities % of Total<-60 0 0%<-30 1 0%
>= -30 and <30 41 11%>30 2 1%>60 1 0%>90 4 1%
>120 1 0%
>150 0 0%
>180 0 0%NO BASELINE 340 87% 87% 87%
0%
11%
1%
2%1%
Based on future data (after Status Date) AND selected MS
Project Filter
Charts 3-5 provide an easy way to see if the future trends are
significantly different than historical data
Notional Data
22
![Page 23: Schedule Execution Metrics - NASA](https://reader030.vdocument.in/reader030/viewer/2022013018/61d0de80adf91148a83a4f5b/html5/thumbnails/23.jpg)
BPO/CAAG/ECE
PROGRAM XYZ - ACT Monthly Baseline Realism
0
20
40
60
80
100
120
140
160
0.0
0.1
0.2
0.3
0.4
0.5
0.6
0.7
0.8
0.9
1.0
Sep-
15N
ov-1
5Ja
n-16
Mar
-16
May
-16
Jul-1
6Se
p-16
Nov
-16
Jan-
17M
ar-1
7M
ay-1
7Ju
l-17
Sep-
17N
ov-1
7Ja
n-18
Mar
-18
May
-18
Jul-1
8Se
p-18
Nov
-18
Jan-
19M
ar-1
9M
ay-1
9Ju
l-19
Sep-
19N
ov-1
9Ja
n-20
Mar
-20
May
-20
Jul-2
0
# Ac
tiviti
es in
Mon
th
Perf
orm
ance
Inde
x
Schedule Data as of June 2016
PROGRAM XYZ ACT Monthly Baseline RealismMonthly BL Fin Monthly Planning Window Finish BLR (Mo) Projected BLR (Mo)
456 ACT require BL FinFilter: All Tasks
Number of Baseline Finishes per Month
Baseline Realism Index for 1 Month
(Historical)
Baseline Realism Index for 1 Month
(Projected)
IMS Status DateIMS Filter Identification of events without BL Finish Dates
Number of Actual/Projected Finishes per Month
Notional Data 23
![Page 24: Schedule Execution Metrics - NASA](https://reader030.vdocument.in/reader030/viewer/2022013018/61d0de80adf91148a83a4f5b/html5/thumbnails/24.jpg)
BPO/CAAG/ECE
PROGRAM XYZ - ACT Multi-View Baseline Realism
0.0
0.1
0.2
0.3
0.4
0.5
0.6
0.7
0.8
0.9
1.0
Sep-
15N
ov-1
5Ja
n-16
Mar
-16
May
-16
Jul-1
6Se
p-16
Nov
-16
Jan-
17M
ar-1
7M
ay-1
7Ju
l-17
Sep-
17N
ov-1
7Ja
n-18
Mar
-18
May
-18
Jul-1
8Se
p-18
Nov
-18
Jan-
19M
ar-1
9M
ay-1
9Ju
l-19
Sep-
19N
ov-1
9Ja
n-20
Mar
-20
May
-20
Jul-2
0
Perf
orm
ance
Inde
x
Schedule Data as of June 2016
PROGRAM XYZ Activity Multi-View Baseline RealismBLR (Mo) Projected BLR (Mo) BLR (3 Mo)
BLR (6 Mo) BLR (Cum) Projected Cum BLR
456 ACT require BL FinFilter: All Tasks
1 Mo BLR: 0.5 - 3 Mo BLR: 0.81 6 Mo BLR: 0.97 - Cum BLR: 0.97
Filter Used in MS Project
Identification of events without BL Finish Dates
IMS Status Date
Baseline Realism Index for 1 Month
(Historical)
Baseline Realism Index for 3 Months
(Historical)
Baseline Realism Index for 6 Months (Historical) – Not
Visible – Requires 6 months of data
Cumulative-to-Date Baseline Realism Index (Historical)
Cumulative-to-Date Baseline Realism Index (Projected)
Baseline Realism Index for 1 Month
(Projected)
Notional Data 24
![Page 25: Schedule Execution Metrics - NASA](https://reader030.vdocument.in/reader030/viewer/2022013018/61d0de80adf91148a83a4f5b/html5/thumbnails/25.jpg)
BPO/CAAG/ECE
PROGRAM XYZ - ACT Executive View Baseline Realism
0.00.10.20.30.40.50.60.70.80.91.0
Sep-
15
Dec-
15
Mar
-16
Jun-
16
Sep-
16
Dec-
16
Mar
-17
Jun-
17
Sep-
17
Dec-
17
Mar
-18
Jun-
18
Sep-
18
Dec-
18
Mar
-19
Jun-
19
Sep-
19
Dec-
19
Mar
-20
Jun-
20
Perf
orm
ance
Inde
x
Schedule Data as of June 2016
PROGRAM XYZ ACT Executive View Baseline Realism (1 Mo)
BLR (Mo) Projected BLR (Mo)
456 ACT require BL FinFilter: All Tasks
Filter Used in MS Project
Identification of events without BL Finish Dates
IMS Status Date
Baseline Realism Index for 1 Month
(Historical)
Baseline Realism Index for 1 Month
(Projected)
Notional Data 25
![Page 26: Schedule Execution Metrics - NASA](https://reader030.vdocument.in/reader030/viewer/2022013018/61d0de80adf91148a83a4f5b/html5/thumbnails/26.jpg)
BPO/CAAG/ECE
PROGRAM XYZ - ACT Baseline Progress (Cum/Monthly)
0
20
40
60
80
100
120
140
160
0.00.10.20.30.40.50.60.70.80.91.0
Sep-
15N
ov-1
5Ja
n-16
Mar
-16
May
-16
Jul-1
6Se
p-16
Nov
-16
Jan-
17M
ar-1
7M
ay-1
7Ju
l-17
Sep-
17N
ov-1
7Ja
n-18
Mar
-18
May
-18
Jul-1
8Se
p-18
Nov
-18
Jan-
19M
ar-1
9M
ay-1
9Ju
l-19
Sep-
19N
ov-1
9Ja
n-20
Mar
-20
May
-20
Jul-2
0
# Ac
tiviti
es in
Mon
th
Perf
orm
ance
Inde
x
Schedule Data as of June 2016
PROGRAM XYZ ACT Baseline Progress (Cum/Monthly)Monthly BL Fin Monthly EOT Finish BLP (Mo)
Projected BLP (Mo) BLP (Cum) Projected BLP (Cum)
456 ACT require BL FinFilter: All Tasks
Filter Used in MS Project
Identification of events without BL Finish Dates
IMS Status Date
Baseline Progress Index for 1 Month
(Historical)
Cumulative-to-Date Baseline Progress Index (Historical)
Cumulative-to-Date Baseline Progress Index (Projected)
Baseline Progress Index for 1 Month
(Projected)
Number of Actual/Projected Finishes per Month
Number of Baseline Finishes per Month
Notional Data 26
![Page 27: Schedule Execution Metrics - NASA](https://reader030.vdocument.in/reader030/viewer/2022013018/61d0de80adf91148a83a4f5b/html5/thumbnails/27.jpg)
BPO/CAAG/ECE
PROGRAM XYZ - ACT Monthly Baseline Progress
0.0
0.1
0.2
0.3
0.4
0.5
0.6
0.7
0.8
0.9
1.0
Sep-
15N
ov-1
5Ja
n-16
Mar
-16
May
-16
Jul-1
6Se
p-16
Nov
-16
Jan-
17M
ar-1
7M
ay-1
7Ju
l-17
Sep-
17N
ov-1
7Ja
n-18
Mar
-18
May
-18
Jul-1
8Se
p-18
Nov
-18
Jan-
19M
ar-1
9M
ay-1
9Ju
l-19
Sep-
19N
ov-1
9Ja
n-20
Mar
-20
May
-20
Jul-2
0
Perf
orm
ance
Inde
x
Schedule Data as of June 2016
PROGRAM XYZ ACT Monthly Baseline ProgressBLP (Mo) Projected BLP (Mo)
456 ACT require BL FinFilter: All Tasks
Filter Used in MS Project
Identification of events without BL Finish Dates
IMS Status Date
Baseline Progress Index for 1 Month
(Historical)
Baseline Progress Index for 1 Month
(Projected)
Notional Data 27
![Page 28: Schedule Execution Metrics - NASA](https://reader030.vdocument.in/reader030/viewer/2022013018/61d0de80adf91148a83a4f5b/html5/thumbnails/28.jpg)
BPO/CAAG/ECE
PROGRAM XYZ - ACT Baseline Execution
0
20
40
60
80
100
120
140
160
0.0
5.0
10.0
15.0
20.0
25.0
30.0
Sep-
15N
ov-1
5Ja
n-16
Mar
-16
May
-16
Jul-1
6Se
p-16
Nov
-16
Jan-
17M
ar-1
7M
ay-1
7Ju
l-17
Sep-
17N
ov-1
7Ja
n-18
Mar
-18
May
-18
Jul-1
8Se
p-18
Nov
-18
Jan-
19M
ar-1
9M
ay-1
9Ju
l-19
Sep-
19N
ov-1
9Ja
n-20
Mar
-20
May
-20
Jul-2
0
# Ac
tiviti
es in
Mon
th
Perf
orm
ance
Inde
x
Schedule Data as of June 2016
PROGRAM XYZ ACT Baseline ExecutionMonthly BL Fin Monthly Finish BE (Mo)
Projected BE (Mo) BE (Cum) Projected BE (Cum)
456 ACT require BL FinFilter: All Tasks
Accomplished ~152.3% of BL Plan ACT to date - All Remaining ACT represent 661% (increase) of ACT in BL Plan Scheduled to finish after JUN 2016
Filter Used in MS Project
Identification of events without BL Finish Dates
IMS Status Date
Baseline Execution Index for 1 Month
(Historical)
Cumulative-to-Date Baseline Execution Index (Historical)
Cumulative-to-Date Baseline Execution Index (Projected)
Baseline Execution Index for 1 Month
(Projected)
Number of Baseline Finishes per Month
Number of Actual/Projected Finishes per
Month
Notional Data 28
![Page 29: Schedule Execution Metrics - NASA](https://reader030.vdocument.in/reader030/viewer/2022013018/61d0de80adf91148a83a4f5b/html5/thumbnails/29.jpg)
BPO/CAAG/ECE
0
50
100
150
200
250
300
350
400
0.0
0.2
0.4
0.6
0.8
1.0
1.2
1.4
1.6
Oct
-15
Dec-
15Fe
b-16
Apr-
16Ju
n-16
Aug-
16O
ct-1
6De
c-16
Feb-
17Ap
r-17
Jun-
17Au
g-17
Oct
-17
Dec-
17Fe
b-18
Apr-
18Ju
n-18
Aug-
18O
ct-1
8De
c-18
Feb-
19Ap
r-19
Jun-
19Au
g-19
Oct
-19
Dec-
19Fe
b-20
Apr-
20Ju
n-20
Aug-
20
Perf
rom
ance
Inde
x
Schedule Data as of November 2016
PROGRAM X Baseline Execution vs To-Complete Baseline Execution
Monthly BL Fin Monthly Finish BE (Cum)
Projected BE (Cum) BE (Mo) TC-BE
100% have BL FinFilter: All Tasks
51% difference between Cumulative BE (0.842) and To-Complete BEI (1.352) as of NOV 2016
Avg Dur for Completed Act: 25d Avg Dur for Future Act: 28d
PROGRAM XYZ - ACT Baseline Executionvs To-Complete Baseline Execution
Filter Used in MS Project
Identification of events without BL Finish Dates
IMS Status Date
Baseline Execution Index
for 1 Month (Historical)
Cumulative-to-Date Baseline
Execution Index (Historical) Cumulative-to-Date Baseline
Execution Index (Projected)
To Complete Baseline Execution Index
Number of Baseline Finishes
per Month
Number of Actual/Projected Finishes per Month
Notional Data 29
![Page 30: Schedule Execution Metrics - NASA](https://reader030.vdocument.in/reader030/viewer/2022013018/61d0de80adf91148a83a4f5b/html5/thumbnails/30.jpg)
BPO/CAAG/ECE
PROGRAM XYZ - ACT Schedule Workoffs
0%
20%
40%
60%
80%
100%
0
50
100
150
200
250
300
350
400
Oct
-15
Dec
-15
Feb-
16
Apr-
16
Jun-
16
Aug-
16
Oct
-16
Dec
-16
Feb-
17
Apr-
17
Jun-
17
Aug-
17
Oct
-17
Dec
-17
Feb-
18
Apr-
18
Jun-
18
Aug-
18
Oct
-18
Dec
-18
Feb-
19
Apr-
19
Jun-
19
Aug-
19
Oct
-19
Dec
-19
Feb-
20
Apr-
20
Jun-
20
Aug-
20
% o
f Act
iviti
es M
ore
than
30d
Lat
e
# Ac
tiviti
es in
Mon
th
Schedule Data as of November 2016
Program X Schedule Workoffs% of Activity Completions > 30d Late (Mo) # Activities >30d Late (Mo)
# Activities Projected >30d Late (Mo) # Completed Activities (Mo)
# Projected Completed Activities (Mo) % of Activity Completions > 30d Late (Cum)
34% of All Activities are projected to be more than 30d Late
100% have BL FinFilter: All Tasks
Filter Used in MS Project
Identification of events without BL Finish Dates
IMS Status Date
Percentage of Completed Activities more than 30d Late During a Month
Number of Activities Forecasted to Complete
during Month
Cumulative Percentage of Completed Activities more than 30d Late
Number of Activities Completed during Month
Number of Activities Completed More than 30d Late during Month
Number of Activities Forecasted to Complete More than 30d
Late during Month
Notional Data 30
![Page 31: Schedule Execution Metrics - NASA](https://reader030.vdocument.in/reader030/viewer/2022013018/61d0de80adf91148a83a4f5b/html5/thumbnails/31.jpg)
BPO/CAAG/ECE
0
50
100
150
200
250
300
350
400O
ct-1
5N
ov-1
5D
ec-1
5Ja
n-16
Feb-
16M
ar-1
6Ap
r-16
May
-16
Jun-
16Ju
l-16
Aug-
16Se
p-16
Oct
-16
Nov
-16
Dec
-16
Jan-
17Fe
b-17
Mar
-17
Apr-
17M
ay-1
7Ju
n-17
Jul-1
7Au
g-17
Sep-
17O
ct-1
7N
ov-1
7D
ec-1
7Ja
n-18
Feb-
18M
ar-1
8Ap
r-18
May
-18
Jun-
18Ju
l-18
Aug-
18Se
p-18
Oct
-18
Nov
-18
Dec
-18
Jan-
19Fe
b-19
Mar
-19
Apr-
19M
ay-1
9Ju
n-19
Jul-1
9Au
g-19
Sep-
19O
ct-1
9N
ov-1
9D
ec-1
9Ja
n-20
Feb-
20M
ar-2
0Ap
r-20
May
-20
Jun-
20Ju
l-20
Aug-
20Se
p-20
# M
onth
ly A
ctiv
ities
Schedule Data as of November 2016
Program X Forecasted Late FinishesUnfinished BL Activities Completed Activities Future Planned Finishes
100% have BL FinFilter: All Tasks
27% of all tasks currrently projected to finish after the status of NOV 2016 were
baselined to finish prior to that status date
PROGRAM XYZ - ACT Forecasted Late Finishes
Filter Used in MS Project
Identification of events without BL Finish Dates
IMS Status Date
Activities that are Already Late and when they are currently Forecasted to by Complete
Number of Activities Completed during Month
Number of Activities Forecasted to Complete
during Month
Notional Data 31
![Page 32: Schedule Execution Metrics - NASA](https://reader030.vdocument.in/reader030/viewer/2022013018/61d0de80adf91148a83a4f5b/html5/thumbnails/32.jpg)
BPO/CAAG/ECE
PROGRAM XYZ - ACT Late Finish Assessment
0
500
1000
1500
2000
2500
3000
3500
4000O
ct-1
5N
ov-1
5D
ec-1
5Ja
n-16
Feb-
16M
ar-1
6Ap
r-16
May
-16
Jun-
16Ju
l-16
Aug-
16Se
p-16
Oct
-16
Nov
-16
Dec
-16
Jan-
17Fe
b-17
Mar
-17
Apr-
17M
ay-1
7Ju
n-17
Jul-1
7Au
g-17
Sep-
17O
ct-1
7N
ov-1
7D
ec-1
7Ja
n-18
Feb-
18M
ar-1
8Ap
r-18
May
-18
Jun-
18Ju
l-18
Aug-
18Se
p-18
Oct
-18
Nov
-18
Dec
-18
Jan-
19Fe
b-19
Mar
-19
Apr-
19M
ay-1
9Ju
n-19
Jul-1
9Au
g-19
Sep-
19O
ct-1
9N
ov-1
9D
ec-1
9Ja
n-20
Feb-
20M
ar-2
0Ap
r-20
May
-20
Jun-
20Ju
l-20
Aug-
20Se
p-20
Tota
l Num
ber o
f Act
iviti
es
Schedule Data as of November 2016
Program X Late Finish Assessment
STATUS DATE: NOV 2016 BL FINISH FINISH LATE FINISH
100% have BL FinFilter: All Tasks
Some future tasks may slip by as many as 337 calendar days before impacting the IMS completion date
Filter Used in MS Project
Identification of events without BL Finish Dates
IMS Status Date
Status Date
Actual/Forecasted Finishes
Baseline Finishes
Late Finishes
Notional Data 32
![Page 33: Schedule Execution Metrics - NASA](https://reader030.vdocument.in/reader030/viewer/2022013018/61d0de80adf91148a83a4f5b/html5/thumbnails/33.jpg)
BPO/CAAG/ECE
PROGRAM XYZ - ACT Baseline Realismvs Baseline Progress
0.0000.1000.2000.3000.4000.5000.6000.7000.8000.9001.000
Oct
-15
Dec
-15
Feb-
16
Apr-
16
Jun-
16
Aug-
16
Oct
-16
Dec
-16
Feb-
17
Apr-
17
Jun-
17
Aug-
17
Oct
-17
Dec
-17
Feb-
18
Apr-
18
Jun-
18
Aug-
18
Oct
-18
Dec
-18
Feb-
19
Apr-
19
Jun-
19
Aug-
19
Oct
-19
Dec
-19
Feb-
20
Apr-
20
Jun-
20
Aug-
20
Perf
rom
ance
Inde
x
Schedule Data as of November 2016
Program X Baseline Realism vs Baseline ProgressBLR (Mo) BLP (Mo) BLR (Cum) = BLP (Cum)
100% have BL FinFilter: All Tasks
Filter Used in MS Project
Identification of events without BL Finish Dates
IMS Status Date
Baseline Progress Index for 1 Month
(Historical)
Baseline Realism Index for 1 Month
(Historical)
Cumulative Baseline Progress/Realism Index
(Historical)
Notional Data 33
![Page 34: Schedule Execution Metrics - NASA](https://reader030.vdocument.in/reader030/viewer/2022013018/61d0de80adf91148a83a4f5b/html5/thumbnails/34.jpg)
BPO/CAAG/ECE
PROGRAM XYZ - ACT Baseline Realism (Cum/Cur)
020406080100120140160
0.00.10.20.30.40.50.60.70.80.91.0
Sep-
15N
ov-1
5Ja
n-16
Mar
-16
May
-16
Jul-1
6Se
p-16
Nov
-16
Jan-
17M
ar-1
7M
ay-1
7Ju
l-17
Sep-
17N
ov-1
7Ja
n-18
Mar
-18
May
-18
Jul-1
8Se
p-18
Nov
-18
Jan-
19M
ar-1
9M
ay-1
9Ju
l-19
Sep-
19N
ov-1
9Ja
n-20
Mar
-20
May
-20
Jul-2
0
# Ac
tiviti
es in
Mon
th
Perf
orm
ance
Inde
x
Schedule Data as of June 2016
PROGRAM XYZ Activity Baseline Realism (Cum/Cur)Monthly BL Fin Monthly Planning Window Finish
BLR (Mo) Projected BLR (Mo)
BLR (Cum) Projected Cum BLR
456 ACT require BL FinFilter: All Tasks
Filter Used in MS Project
Identification of events without BL Finish Dates
IMS Status Date
Number of Baseline Finishes per Month
Number of Actual/Projected Finishes per
Month
Baseline Realism Index for 1 Month
(Historical)
Baseline Realism Index for 1 Month
(Projected)
Cumulative-to-Date Baseline Realism Index (Historical)
Cumulative-to-Date Baseline Realism Index (Projected)
Notional Data 34
![Page 35: Schedule Execution Metrics - NASA](https://reader030.vdocument.in/reader030/viewer/2022013018/61d0de80adf91148a83a4f5b/html5/thumbnails/35.jpg)
BPO/CAAG/ECE
PROGRAM XYZ - ACT BR vs BP vs BE
0.0
5.0
10.0
15.0
20.0
25.0
30.0Se
p-15
Nov
-15
Jan-
16M
ar-1
6M
ay-1
6Ju
l-16
Sep-
16N
ov-1
6Ja
n-17
Mar
-17
May
-17
Jul-1
7Se
p-17
Nov
-17
Jan-
18M
ar-1
8M
ay-1
8Ju
l-18
Sep-
18N
ov-1
8Ja
n-19
Mar
-19
May
-19
Jul-1
9Se
p-19
Nov
-19
Jan-
20M
ar-2
0M
ay-2
0Ju
l-20
Perf
orm
ance
Inde
x
Schedule Data as of June 2016
PROGRAM XYZ ACT BLR vs BLP vs BEBLR (Mo) BLP (Mo) BE (Mo)
456 ACT require BL FinFilter: All Tasks
Filter Used in MS Project
Identification of events without BL Finish Dates
IMS Status Date
Baseline Realism Index for 1 Month
(Historical)
Baseline Execution Index for 1 Month
(Historical)
Baseline ProgressIndex for 1 Month
(Historical)
Notional Data 35
![Page 36: Schedule Execution Metrics - NASA](https://reader030.vdocument.in/reader030/viewer/2022013018/61d0de80adf91148a83a4f5b/html5/thumbnails/36.jpg)
BPO/CAAG/ECE
PROGRAM X - 1 Period ACT Forecast Realism
0
50
100
150
200
250
300
350
0.0
0.1
0.2
0.3
0.4
0.5
0.6
0.7
0.8
0.9
1.0
Feb-
16M
ar-1
6Ap
r-16
May
-16
Jun-
16Ju
l-16
Aug-
16Se
p-16
Oct
-16
Nov
-16
Dec-
16Ja
n-17
Feb-
17M
ar-1
7Ap
r-17
May
-17
Jun-
17Ju
l-17
Aug-
17Se
p-17
Oct
-17
Nov
-17
Dec-
17Ja
n-18
Feb-
18M
ar-1
8
# Ac
tiviti
es
Fore
cast
Rea
lsim
PROGRAM X - 1 Mo Activity Forecast Realism# Forecasted Activities # Completed Activities 1 Mo Activity Forecast Realism
Provides ratio of specific activiies actuallyaccomplished compared to the projected
Forecast Realism is assessment of the actual
completions to the projected completions (in this case ~125
of ~250 = ~.5)
These are completions in Nov 16 of SPECIFIC
events that were forecast were forecast to be
complete in the Oct 16 file
These are the projected completions for Dec 16 (using the Nov 16 file)
These are the projected completions for Nov 16 (using the Oct 16 file)
Note: This example uses Monthly Data and Status is EOM Nov 16
In this example, Contractor’s ability to forecast one month ahead ranges between 30% and 80% with average near
50%
Notional Data 36
![Page 37: Schedule Execution Metrics - NASA](https://reader030.vdocument.in/reader030/viewer/2022013018/61d0de80adf91148a83a4f5b/html5/thumbnails/37.jpg)
BPO/CAAG/ECE
PROGRAM X - 2 Period ACT Forecast Realism
0
100
200
300
400
500
600
700
0.0
0.1
0.2
0.3
0.4
0.5
0.6
0.7
0.8
0.9
1.0
Mar
-16
Apr-
16M
ay-1
6Ju
n-16
Jul-1
6Au
g-16
Sep-
16O
ct-1
6N
ov-1
6De
c-16
Jan-
17Fe
b-17
Mar
-17
Apr-
17M
ay-1
7Ju
n-17
Jul-1
7Au
g-17
Sep-
17O
ct-1
7N
ov-1
7De
c-17
Jan-
18Fe
b-18
Mar
-18
Apr-
18
# Ac
tiviti
es
Fore
cast
Rea
lsim
PROGRAM X - 2 Mo Activity Forecast Realism# Forecasted Activities # Completed Activities 2 Mo Activity Forecast Realism
Provides ratio of specific activiies actuallyaccomplished during the two--period window compared to the projected finishes from the
beginning of that window
Forecast Realism is assessment of the actual
completions to the projected completions (in this case ~275
of ~550 = ~.53)
These are the projected completions for Nov 16 through Dec 16 (using the Oct 16 file)
These are the projected completions for 2 months of data - Oct 16 through Nov 16 (using the Sep 16 file)
These are the projected completions for Dec 16 through Jan 17 (using the Nov 16 file)
These are completions Oct 16 through Nov 16 of SPECIFIC
events that were forecast were forecast to be complete in the Sep
16 file
In this example, Contractor’s ability to forecast two months ahead ranges between 45% and 80% with average near
55%
Note: 2 Period is calculated based on Forecast Finishes during the next two periods
Notional Data
37
![Page 38: Schedule Execution Metrics - NASA](https://reader030.vdocument.in/reader030/viewer/2022013018/61d0de80adf91148a83a4f5b/html5/thumbnails/38.jpg)
BPO/CAAG/ECE
PROGRAM X - 3 Period ACT Forecast Realism
0
100
200
300
400
500
600
700
800
900
0.0
0.1
0.2
0.3
0.4
0.5
0.6
0.7
0.8
0.9
1.0
Apr-
16M
ay-1
6Ju
n-16
Jul-1
6Au
g-16
Sep-
16O
ct-1
6N
ov-1
6De
c-16
Jan-
17Fe
b-17
Mar
-17
Apr-
17M
ay-1
7Ju
n-17
Jul-1
7Au
g-17
Sep-
17O
ct-1
7N
ov-1
7De
c-17
Jan-
18Fe
b-18
Mar
-18
Apr-
18M
ay-1
8
# Ac
tiviti
es
Fore
cast
Rea
lsim
PROGRAM X - 3 Mo Activity Forecast Realism# Forecasted Activities # Completed Activities 3 Mo Activity Forecast Realism
Provides ratio of specific activiies actuallyaccomplished during the three--period window
compared to the projected finishes from the beginning of that window
In this example, Contractor’s ability to forecast three months
ahead ranges between 50% and 80% with average near 60%
Note: 3 Period is calculated based on Forecast Finishes during the next three periods
Forecast Realism is assessment of the actual
completions to the projected completions (in this case ~325
of ~650 = ~.49)
These are the projected completions for Nov 16 through Jan 17 (using the Sep 16 file)
These are the projected completions for 3 months of data – Sep 16 through Nov 16 (using the Aug 16 file)
These are the projected completions for Dec 16 through Feb 17 (using the Nov 16 file)
These are completions Sep 16 through Nov 16 of SPECIFIC events that were forecast were forecast to
be complete in the Aug 16 file
Notional Data
38
![Page 39: Schedule Execution Metrics - NASA](https://reader030.vdocument.in/reader030/viewer/2022013018/61d0de80adf91148a83a4f5b/html5/thumbnails/39.jpg)
BPO/CAAG/ECE
PROGRAM X - 6 Period ACT Forecast Realism
0
200
400
600
800
1000
1200
1400
1600
0.0
0.1
0.2
0.3
0.4
0.5
0.6
0.7
0.8
0.9
1.0
Jul-1
6Au
g-16
Sep-
16O
ct-1
6N
ov-1
6De
c-16
Jan-
17Fe
b-17
Mar
-17
Apr-
17M
ay-1
7Ju
n-17
Jul-1
7Au
g-17
Sep-
17O
ct-1
7N
ov-1
7De
c-17
Jan-
18Fe
b-18
Mar
-18
Apr-
18M
ay-1
8Ju
n-18
Jul-1
8Au
g-18
# Ac
tiviti
es
Fore
cast
Rea
lsim
PROGRAM X - 6 Mo Activity Forecast Realism# Forecasted Activities # Completed Activities 6 Mo Activity Forecast Realism
Provides ratio of specific activiies actuallyaccomplished during the six--period window compared to the projected finishes from the
beginning of that window
In this example, Contractor’s ability
to forecast six months ahead
ranges between 65% and 75% with average near 65%
Note: 6 Period is calculated based on Forecast Finishes during the next six periods
These are the projected completions for 6 months of data – Jun 16 through Nov 16 (using
the May 16 file)
Forecast Realism is assessment of the actual
completions to the projected completions (in this case ~800 of ~1200 =
~.67)
These are the projected completions for Aug 16 through Dec 16 (using the Jul 16 file)
These are the projected completions for Sep 16 through Feb17 (using the Aug 16 file)
These are the projected completions for Oct 16 through Mar 17 (using the Sep 16 file)
These are the projected completions for Nov 16 through Apr 17 (using the Oct 16 file)
These are the projected completions for Dec 16 through May 17 (using the Nov 16 file)
These are the projected completions for Jul 16 through Dec 16 (using the Jun 16 file)
These are completions Jun 16 through Nov 16 of SPECIFIC events that were
forecast were forecast to be complete in the May 16 file
Notional Data
39
![Page 40: Schedule Execution Metrics - NASA](https://reader030.vdocument.in/reader030/viewer/2022013018/61d0de80adf91148a83a4f5b/html5/thumbnails/40.jpg)
BPO/CAAG/ECE
PROGRAM X - Activity Future Durations
14%
18%
68%
PROGRAM X - Activity Future DurationsCONTRACTED EXPANDED SAME
1554 ACTIVITIES < 100% COMPLETE AS OF
11/30/2016 (3712 TOTAL ACTIVITIES IN IMS)
DURATIONS COMPARED TO THOSE IDENTTIFIED ON
1/31/2016
Note: This chart is only available in FR_Activities
Identifies Future Activity durations are contracted
(shorter durations) compared to the first duration identified for
the activity in the IMS
Identifies Future Activity durations are expanded
(longer durations) compared to the first duration identified
for the activity in the IMS
Identifies Future Activity durations are the same when compared to the first duration identified for the
activity in the IMS
Notional Data 40
![Page 41: Schedule Execution Metrics - NASA](https://reader030.vdocument.in/reader030/viewer/2022013018/61d0de80adf91148a83a4f5b/html5/thumbnails/41.jpg)
BPO/CAAG/ECE
PROGRAM X - Future Completions (Activities)
6%
72%
22%
PROGRAM X - Activity Future CompletionsEARLIER LATER SAME
1554 ACTIVITIES < 100% COMPLETE AS OF
11/30/2016 (3712 TOTAL ACTIVITIES IN IMS)
COMPLETION DATES COMPARED TO THOSE
FORECASTED ON 1/31/2016
Identifies Future Activity completion dates earlier than the first completion date identified for
the activity in the IMSIdentifies Future Activity completion dates same as the first completion date identified
for the activity in the IMSIdentifies Future Activity
completion dates later than the first completion date identified
for the activity in the IMS
Notional Data
41
![Page 42: Schedule Execution Metrics - NASA](https://reader030.vdocument.in/reader030/viewer/2022013018/61d0de80adf91148a83a4f5b/html5/thumbnails/42.jpg)
BPO/CAAG/ECE
Illustration - Baseline Plan
Number of activities planned for completion in the assessment window (6) is the denominator for calculating Monthly Baseline Realism, Baseline Progress, and Baseline Execution
Notional
42
1
2
3
4
5
6
Time NowAssessment Window
![Page 43: Schedule Execution Metrics - NASA](https://reader030.vdocument.in/reader030/viewer/2022013018/61d0de80adf91148a83a4f5b/html5/thumbnails/43.jpg)