schedule of completion
TRANSCRIPT
-
7/30/2019 Schedule of Completion
1/1
(FOR THE PROPOSED DEALERSHIP FOR SMIPL TWO WHEELERS)
6-May-13 13-May-13 20-May-13 27-May-13 3-Jun-13 10
1.1 Negotiation & finalisation of Price
1.2 Payment & Registration of documents
1.3 Taking possession of the Building
1.1 Preparation or drawing
1.2 Submission of Drawing & Suzuki Approval
1.3 Clarification/Objections Showroom and Workshop
1.4 Corrected Drawing Showroom and Workshop
1.5 Approval by Suzuki Showroom and Workshop
Resignation to old Company
Getting no dues from old Company4
STATUTORY OBLIGATION CONVERSION OF PRESENT FIRM TO A PVT LTD COMPANY
2.1 Submission to Govt./Authority
2.2 Approval by Govt./Authority
3.1 Design Modification of Showroom and Workshop
3.2 Internal structural modification work Completion3.3 Mezzanine Floor Erection (if required)
3.7 Doors & Window frames
4.1 Final Location of Points SR,WS & SP
4.2 Electric conduting
4.3 Wiring of the Dealership
4.4 Location of sanitary & water points
4.5 Laying of pipelines
4.6 Laying of drainage pipes
5.1 Flooring Showroom and Workshop
5.2 Skirting Showroom and Workshop
5.3 Order to supplier for Show Room
5.4 Installation of False Ceiling
5.5 Walls - Internal Showroom and Workshop
5.6 Walls - external Showroom and Workshop
5.7 Walls POP - Showroom and Workshop
5.8 Tilling Showroom and Workshop
5.9 Sanitary ware fitting Showroom and Workshop
Manpower 5.10 Recruitment of Managers Showroom and Workshop
6.1 Painting Showroom and Workshop
6.2 Electrical Fixtures Showroom and Workshop
6.3 Front glass fitting
6.4 Furniture preparation Showroom and Workshop
6.5 Surroundings Showroom and Workshop
6.6 Landscaping of the Site
7.1 Payment to Suzuki for External & Internal CI Tools
7.2 Preparation of foundation of the Pylon
7.3 Installation of Pylon and Signage's
7.4 Commissioning of CI Tools
7.4
Placing of order Showroom facility and Workshop tools,
Pneumatic Lines and Spare part section racks
7.5 Receipt, Assembly Showroom and Workshop tools
7.6 Installation of Showroom and Workshop tools
7.7 Procurement of Server and Client PCs.
7.8 DMS Installation
7.9 Recruitment of DMS Operator
11 Dry Run of Dlrship 8.1 Printing of Formats, Stationary
9.1 Launch Schedule finalisation
9.2 Invitation to guests
9.3 advance for initial spares and vehicles lifting
9.4 Inauguration AD FINALIZATION
9.5 Arrangements for Sale of Vehicles
Date
Note: Please Affix Not Applicable (N/A) for the activities not required and also may add activities if required other than the given ones.
Major Activity Minor Activity
1 Purchase of Building and
development(Compulsary
unless already owned)
SCHEDULE OF WORK IMPLEMENTATION
Date of CompletionS. No
10 External Signs
Sales Tool Workshop
Tools and Equipments
8 Flooring
False Ceiling
Plastering
Toilet/Pantry
Preparation, Approval and
Finalisation of Drawing &LAYOUTS
2
CLEARENCE OF DOCS
FROM OLD
ESTABLISHMENT
3
Approval by local
authorities Including
pollution norms
Dealer Signature & Stamp:
DMS
12 Launch
9
External Development
6 Changes in the Internal
Structure
7 Electrical & Plumbing
5
Exteriors, Finishing