school overview

1
1 GROUND FFL 200 3 FIRST FFL 3950 0 Top Found -900 4 RING BEAM 2 7060 A 2 RING BEAM 1 3310 5 TOP OF STACK 8725 3520 3515 1060 152 1060 1 GROUND FFL 200 3 FIRST FFL 3950 0 Top Found -900 4 RING BEAM 2 7060 A B 2 RING BEAM 1 3310 5 TOP OF STACK 8725 A B C 3 4 5 D/GL/08 D/GL/10 D/GL/11 D/GL/09 12 D/GL/07 1 A110 94 m² CLASSROOM 4 33 m² ATRIUM 7000 7000 D/GL/14 W/GL/05 W/GL/06 W/GL/16 W/GL/15 6903 13987 6492 4600 1210 1210 808 3988 8315 300 1210 3340 1210 1810 TECHNICAL THESIS OF POST PRIMARY SCHOOL A1 SHEET Ross Boyce , Year 3 Architectural Technology, Dublin School of Architecture, D.I.T. 1 : 20 Section 2 1 GREEN ROOF BUILDUP : SEDUM BLANKET ON 20mm DRAINAGE MAT ON ROOT BARRIER ON UNDERLAY ON 100 PIR RIGID INSULATION ON VAPOUR BARRIER ON 18 PLY WOOD SUBSTRATE ON 44 X 150 SOFTWOOD JOISTS @ 400 C/C WITH 100 QUILTED INSULATION INFILL ON TWO 18 PLASTERBOARD SLABS WITH 3 SKIM FINISH. NOTE: VAPOUR BARRIER , UNDERLAY AND ROOT BARRIER ALL OVERLAPPED AND DRESSED UP ABOVE FINISHED ROOF LEVEL ONTO GLULAM BEAM AND PROTECTED WITH PRESSED ALUMINUM CAPPING . 850 X 100 GLULAM BEAM WITH TOP TAPERED TO CREATE FALL FOR ALUMINUM CAPPING. BOTTOM OF BEAM TO BE REBATED TO CREATE A DRIP. BEAM TO BE BOLTED BACK TO STRUCTURAL GLULAM AT 1METER INTERVALS 60 PIR RIGID INSULATION SANDWICHED BETWEEN BEAMS. 450 X 200 STRUCTURAL GLULAM BEAM 300 X 60 PEA GRAVEL DRAINAGE LAYER AROUND THE PERIMETER OF THE BUILDING. DOUBLE GLAZED ALU-CLAD TIMBER FRAMED WINDOW WITH THERMAL BREAKS BUILT INTO FRAME.. AND COBINATION OPENING SASH TINTED INSULATED GLAZING BOTTOM PANEL 18 PLASTERBOARD SLAB WITH 3 SKIM FINISH ON 50 X 75 TIMBER STUD PARTITION WITH 75 QUILTED INSULATION 650 X 100 EXPOSED GLULAM BEAM WITH TOP TAPERED TO CREATE FALL FOR ALUMINUM DRIP TRAY. BOTTOM OF BEAM TO BE REBATED TO CREATE A DRIP. BEAM TO BE BOLTED BACK TO STRUCTURAL GLULAM AT 1METER INTERVALS D.P.C. FITTED TO UNDERSIDE OF WINDOW FRAME AND DRESSED UNDER PRESSED ALUMINUM DRIP TRAY 60 PIR RIGID INSULATION SANDWICHED BETWEEN BEAMS. 450 X 200 STRUCTURAL GLULAM BEAM D.P.C. DRESSED AROUND ENTIRE WINDOW JAMB DOUBLE GLAZED ALU-CLAD TIMBER FRAMED WINDOW WITH THERMAL BREAKS BUILT INTO FRAME. TINTED INSULATED GLAZING BOTTOM PANEL 18 PLASTERBOARD SLAB WITH 3 SKIM FINISH ON 50 X 75 TIMBER STUD PARTITION WITH 75 QUILTED INSULATION D.P.C. FITTED TO UNDERSIDE OF WINDOW FRAME AND DRESSED UNDER PRESSED ALUMINUM DRIP TRAY 10 ACRYLIC RENDER ON EXTRUDED POLYSTYRENE INSULATION ON 150 X 190 THERMAL BLOCK. FLOOR CONSTRUCTION: 40 UNDERFLOOR HEATING SCREED ON 150 RIGID PIR INSULATION WITH 50 PERIMETER INSULATION ON RADON BARRIER ON 200 STRUCTURAL CONCRETE FLOOR ON 50 SAND BLINDING ON 250 HARDCORE 304 BASE FIRST FLOOR CONSTRUCTION: 150 X 22 HARDWOOD TIMBER FLOORING ON 25 MANORFLOOR TRI-BOARD ACOUSTIC FLOORING ( 9 CALCIUM SILICATE BOARD ON 8 MOISTURE RESISTANT MDF ON 9 FOAM ) ON 18 PLY WOOD SUBSTRATE ON 44 X 150 SOFTWOOD JOISTS A@ 400 C/C WITH 100 QUILTED INSULATION INFILL ON TWO 18 PLASTERBOARD SLABS WITH 3 SKIM FINISH. NOTE: 15MM SHADOW GAP AT THE JUNCTION BETWEEN CIELING SLAB AND EXPOSED GLULAM BEAMS 1 : 1 Structural 3D View 6 1 : 1 3D Section View 7 1 : 100 VENTILATION DETAIL 5 1 : 100 1 GROUND FFL 2 1 : 500 KEY PLAN 8 1 : 500 South Elevation 10 1 : 500 North Elevation 9 1 : 500 East Elevation 11 1 : 500 West Elevation 12 1 : 500 Key Section 1 13 1 : 500 Key Section 3 14 3 Parapet Detail 4 Floor To Wall Detail The initial brief from the architect was that she wanted the students to be able to read how the building was constructed and create an enviromentally friendly energy efficient school. This evolved finding a way to leave main structural elements such as the large glulam beams and brick peers exposed but yet eliminate cold bridging and achieve a sufficient U-Value of the main elements. We decided to utilise the large brick peers for natural stack ventilation as well as an area to transfer services from each level without the services being viable. The central atrium in each building is used to aid the ventilation as well as maintaining a link to the outside space. The idea was to orientate the three school buildings around a central courtyard area and divide the use of each building in such a way as to encourage movement of the students from one building to another during different stages of the day. The buildings have been designed to take advantage of as much solar gain as possible with largely glazed facades and optimal rotation of each building. An extensive green roof has been incorporated to reduce surface water run off around the site. In order to improve the buildability of the school, each building uses the same pallet of materials as well as the same construction techniques . This creates similar construction details throughout the three buildings and should improve the speed and efficiency of the build. Overall the build should perform with a high level of energy efficiency and create a comfortable learning environment for the students. 1 : 1500 Site Layout 15 GREEN ROOF BUILDUP : SEDUM BLANKET ON 20mm DRAINAGE MAT ON ROOT BARRIER ON UNDERLAY ON 100 PIR RIGID INSULATION ON VAPOUR BARRIER ON 18 PLY WOOD SUBSTRATE ON 44 X 150 SOFTWOOD JOISTS @ 400 C/C WITH 100 QUILTED INSULATION INFILL ON TWO 18 PLASTERBOARD SLABS WITH 3 SKIM FINISH. FIRST FLOOR CONSTRUCTION: 150 X 22 HARDWOOD TIMBER FLOORING ON 25 MANORFLOOR TRI-BOARD ACOUSTIC FLOORING (9 CALCIUM SILICATE BOARD ON 8 MOISTURE RESISTANT MDF ON 9 FOAM ) ON 18 PLY WOOD SUBSTRATE ON 44 X 150 SOFTWOOD JOISTS A@ 400 C/C WITH 100 QUILTED INSULATION INFILL ON TWO 18 PLASTERBOARD SLABS WITH 3 SKIM FINISH.

Upload: rossboyce

Post on 11-Feb-2017

163 views

Category:

Education


0 download

TRANSCRIPT

Page 1: School Overview

1 GROUND FFL

200

3 FIRST FFL

3950

0 Top Found

-900

4 RING BEAM 2

7060

A

2 RING BEAM 1

3310

5 TOP OF STACK

8725

3520

3515

1060

152

1060

1 GROUND FFL

200

3 FIRST FFL

3950

0 Top Found

-900

4 RING BEAM 2

7060

A B

2 RING BEAM 1

3310

5 TOP OF STACK

8725

A B C

3

4

5

D/GL/08

D/GL/10 D/GL/11

D/GL/09

12

D/GL/07

1

A110

94 m²CLASSROOM 4

33 m²ATRIUM

7000

7000

D/GL/14

W/GL/05

W/GL/06

W/GL/16

W/GL/15

6903

13987

6492

4600 1210 1210

808

3988

8315

300

1210

3340

1210

1810

TECHNICAL THESIS OF POST PRIMARY SCHOOL A1 SHEET

Ross Boyce , Year 3 Architectural Technology, Dublin School of Architecture, D.I.T.

1 : 20

Section 21

GREEN ROOF BUILDUP : SEDUMBLANKET ON 20mm DRAINAGEMAT ON ROOT BARRIER ONUNDERLAY ON 100 PIR RIGIDINSULATION ON VAPOURBARRIER ON 18 PLY WOODSUBSTRATE ON 44 X 150SOFTWOOD JOISTS @ 400 C/CWITH 100 QUILTED INSULATIONINFILL ON TWO 18PLASTERBOARD SLABS WITH 3SKIM FINISH.

NOTE: VAPOUR BARRIER , UNDERLAYAND ROOT BARRIER ALLOVERLAPPED AND DRESSED UPABOVE FINISHED ROOF LEVEL ONTOGLULAM BEAM AND PROTECTEDWITH PRESSED ALUMINUM CAPPING .

850 X 100 GLULAM BEAM WITH TOPTAPERED TO CREATE FALL FOR ALUMINUM CAPPING. BOTTOM OF BEAMTO BE REBATED TO CREATE A DRIP.BEAM TO BE BOLTED BACK TOSTRUCTURAL GLULAM AT 1METERINTERVALS

60 PIR RIGID INSULATIONSANDWICHED BETWEEN BEAMS.

450 X 200 STRUCTURAL GLULAMBEAM

300 X 60 PEA GRAVEL DRAINAGELAYER AROUND THE PERIMETEROF THE BUILDING.

DOUBLE GLAZED ALU-CLAD TIMBERFRAMED WINDOW WITH THERMALBREAKS BUILT INTO FRAME.. ANDCOBINATION OPENING SASH

TINTED INSULATED GLAZINGBOTTOM PANEL

18 PLASTERBOARD SLAB WITH 3SKIM FINISH ON 50 X 75 TIMBERSTUD PARTITION WITH 75QUILTED INSULATION

650 X 100 EXPOSED GLULAM BEAMWITH TOP TAPERED TO CREATE FALLFOR ALUMINUM DRIP TRAY.BOTTOM OF BEAM TO BE REBATEDTO CREATE A DRIP.BEAM TO BE BOLTED BACK TOSTRUCTURAL GLULAM AT 1METERINTERVALS

D.P.C. FITTED TO UNDERSIDE OFWINDOW FRAME AND DRESSEDUNDER PRESSED ALUMINUM DRIPTRAY

60 PIR RIGID INSULATIONSANDWICHED BETWEEN BEAMS.

450 X 200 STRUCTURAL GLULAMBEAM

D.P.C. DRESSED AROUND ENTIREWINDOW JAMB

DOUBLE GLAZED ALU-CLAD TIMBERFRAMED WINDOW WITH THERMALBREAKS BUILT INTO FRAME.

TINTED INSULATED GLAZINGBOTTOM PANEL

18 PLASTERBOARD SLAB WITH 3SKIM FINISH ON 50 X 75 TIMBERSTUD PARTITION WITH 75QUILTED INSULATION

D.P.C. FITTED TO UNDERSIDE OFWINDOW FRAME AND DRESSEDUNDER PRESSED ALUMINUM DRIPTRAY

10 ACRYLIC RENDER ONEXTRUDED POLYSTYRENEINSULATION ON 150 X 190THERMAL BLOCK.

FLOOR CONSTRUCTION: 40 UNDERFLOORHEATING SCREED ON 150 RIGID PIR INSULATIONWITH 50 PERIMETER INSULATION ON RADONBARRIER ON 200 STRUCTURAL CONCRETE FLOORON 50 SAND BLINDING ON 250 HARDCORE 304BASE

FIRST FLOOR CONSTRUCTION: 150 X 22HARDWOOD TIMBER FLOORING ON 25MANORFLOOR TRI-BOARD ACOUSTIC FLOORING (9 CALCIUM SILICATE BOARD ON 8 MOISTURERESISTANT MDF ON 9 FOAM ) ON 18 PLY WOODSUBSTRATE ON 44 X 150 SOFTWOOD JOISTS A@400 C/C WITH 100 QUILTED INSULATION INFILL ONTWO 18 PLASTERBOARD SLABS WITH 3 SKIMFINISH.

NOTE: 15MM SHADOW GAP AT THEJUNCTION BETWEEN CIELING SLAB ANDEXPOSED GLULAM BEAMS

1 : 1

Structural 3D View6

1 : 1

3D Section View7

1 : 100

VENTILATION DETAIL5

1 : 100

1 GROUND FFL2

1 : 500

KEY PLAN8

1 : 500

South Elevation10

1 : 500

North Elevation9

1 : 500

East Elevation11

1 : 500

West Elevation12

1 : 500

Key Section 113

1 : 500

Key Section 314

3 Parapet Detail

4 Floor To Wall Detail

The initial brief from the architect was that she wanted the studentsto be able to read how the building was constructed and create anenviromentally friendly energy efficient school. This evolved findinga way to leave main structural elements such as the large glulambeams and brick peers exposed but yet eliminate cold bridgingand achieve a sufficient U-Value of the main elements. Wedecided to utilise the large brick peers for natural stack ventilationas well as an area to transfer services from each level without theservices being viable. The central atrium in each building is used toaid the ventilation as well as maintaining a link to the outside space.The idea was to orientate the three school buildings around acentral courtyard area and divide the use of each building in such away as to encourage movement of the students from one buildingto another during different stages of the day. The buildings havebeen designed to take advantage of as much solar gain aspossible with largely glazed facades and optimal rotation of eachbuilding. An extensive green roof has been incorporated to reducesurface water run off around the site. In order to improve thebuildability of the school, each building uses the same pallet ofmaterials as well as the same construction techniques . Thiscreates similar construction details throughout the three buildingsand should improve the speed and efficiency of the build. Overallthe build should perform with a high level of energy efficiency andcreate a comfortable learning environment for the students.

1 : 1500

Site Layout15

GREEN ROOF BUILDUP : SEDUMBLANKET ON 20mm DRAINAGEMAT ON ROOT BARRIER ONUNDERLAY ON 100 PIR RIGIDINSULATION ON VAPOURBARRIER ON 18 PLY WOODSUBSTRATE ON 44 X 150SOFTWOOD JOISTS @ 400 C/CWITH 100 QUILTED INSULATIONINFILL ON TWO 18PLASTERBOARD SLABS WITH 3SKIM FINISH.

FIRST FLOOR CONSTRUCTION: 150 X 22HARDWOOD TIMBER FLOORING ON 25MANORFLOOR TRI-BOARD ACOUSTICFLOORING (9 CALCIUM SILICATE BOARD ON 8MOISTURE RESISTANT MDF ON 9 FOAM ) ON18 PLY WOOD SUBSTRATE ON 44 X 150SOFTWOOD JOISTS A@ 400 C/C WITH 100QUILTED INSULATION INFILL ON TWO 18PLASTERBOARD SLABS WITH 3 SKIM FINISH.