    SCM445 Name Shashank Mallepula

    SAP ASSIGNMENT# 3

    Assigned # 039

    Material Requirements Planning Exercise

    Learning Objective: The purpose of this exercise is to demonstrate the materials requirement planning (MRP)

    functionality in the SAP R/3 system. This assignment will utilize the data that you created in assignment #2. As a

    first step, a small test problem will be solved manually to determine planned order releases by carrying out MRPcalculations as learned in class and similar to homework assignments in chapter 6. The problem is solved in a

    traditional way with weekly time buckets. This problem is then implemented in the SAP R/3 software. Results

    obtained in SAP R/3 are compared with those obtained by hand calculations.

    The main steps in this exercise are outlined below.

    1. Solve the MRP calculations for materials X100-01-xxxx; X200-01-xxxx; and X300-03-xxxx.

    2. Modify the MRP parameters on 5 material masters3. Create planned independent requirements for the finished product.

    4. View MRP stock/Reqmts list for the finished goods product5. Adjust the stock quantity for material X300-03-xxxx6. Run Master Production Scheduling and MRP for the finished product. (Multi-level explosion)7. View MRP Stock/Reqmts list

    8. Verify the MRP results with those obtained with hand calculations.

    REMEMBER: Everywhere that xxxx is referenced, you should be using your personal FOUR digit SAP number

    assigned for course SCM445

    STEP 1

    Solve the Test Problem

    Calculate Planned Order Releases formaterials X100-01-xxxx; X200-01-xxxx; and X300-03-xxxx . Relevantdata on independent requirements (forecast), BOM, and material master data are given below.

    We will run SAP/R3 MRP processing for the entire product structure (10 materials), but your manual calculations

    will only need to be completed for 3 of the materials as specified above.

    Independent requirements (demand) for product X100-01-xxxx are given below:

    Period Independent Requirements

    Week 47/2013 100

    Week 48/2013 150

    Week 49/2013 120Week 50/2013 180

  • 7/30/2019 SCM445SAP3vSPR13

    2/6

    Some Relevant Material Master Data

    Material Lot Size Lead time Procurement type Remarks

    X100-01-xxxx LFL 1 week

    (5 days)

    In-house

    production

    Finished

    Product

    X200-01-xxxx LFL 1 week

    (5 days)

    In-house

    production

    Semi-finished Product

    X300-03-xxxx Fixed lot size of

    200

    1 week(5 days)

    In-houseproduction

    Semi-finished Product

    Complete the following table:

    MRP CALCULATIONS

    Week No. 44 45 46 47 48 49 50 51Gross Requirements for X100-

    01-xxxx

    100 150 120 180

    Scheduled receipts 0 0 0 0 0 0 0 0

    ProjectedAvailableBalance(initial PAB=0)

    Planned Order Releases

    Gross Requirements for X200-

    01-xxxx

    Scheduled receipts 0 0 0 0 0 0 0 0

    ProjectedAvailableBalance

    (initial PAB=0)

    Planned Order Releases

    Gross Requirements for X300-

    03-xxxx

    Scheduled receipts 0 0 0 0 0 0 0 0

    ProjectedAvailableBalance

    (initial PAB=110)

    Planned Order Releases

    X100-01-xxxx

    Tuaca Light

    X200-01-xxxx

    Styrene BackAssembly

    X200-02-xxxx

    Formed Face

    X200-03-xxxx

    Three prongcord

    X200-04-xxxx

    Light Bulb

    X300-02-xxxx

    Metal HeatShield

    X300-04-xxxx

    LampholderAssembly

    X300-03-xxxx

    Formed Back

    X400-01-xxxx

    White styrenesheet

    X300-01-xxxx

    Clear screenedface

  • 7/30/2019 SCM445SAP3vSPR13

    3/6

    STEP 2

    Modify Material Master MRP Data for the following five materials

    1. Execute SAP transaction code MM02

    You are now going to eliminate the safety stock that currently exists for your finished goods material and you willalso view the number of days that the MRP Planning fence is set to.

    Enter your material number X100-01-xxxx

    Click the green check mark

    Select views MRP1 and MRP2

    Click the green check mark

    Enter plant: 3000

    Enter location: 0001

    Click the green check mark

    You are now in the MRP1 view

    Q.1 What is the value ofPlanning Time Fence? 10

    Click the MRP2 view (tab)

    ChangeIn-House Production time from 1 day to 5 days.

    Save changes (click on )

    A message in the bottom left will confirm the changes have been made

    2. Execute SAP transaction code MM02 (you are already there just enter new material)

    For the following material, you are going to change the lot size from lot for lot to fixed; set the fixed order

    quantity to 200; and change the lead time to 5 (days).

    Enter your material number X300-03-xxxx

    Click the green check mark

    Select views MRP1 and MRP2 Click the green check mark

    Enter plant: 3000

    Enter location: 0001

    Click the green check mark

    You are now in the MRP1 view

    ChangeLot Size to FX(fixed order quantity instead of LFL)

    Change Fixed Lot Size to 200

    Click the MRP2 view (tab)

    ChangeIn-house production time to 5 (five) days

    Save changes (click on )

    A message in the bottom left will confirm the changes have been made

    3. Execute SAP transaction code MM02 (you are already there just enter new material)

    For the following raw material, you are going to set the maximum order quantity to 70.

    Enter your material number X300-02-xxxx

    Click the green check mark

    Select view MRP1

    Click the green check mark

    Enter plant: 3000

  • 7/30/2019 SCM445SAP3vSPR13

    4/6

    Enter location: 0001

    Click the green check mark

    You are now in the MRP1 view

    ChangeMaximum Lot Size to 70

    Save changes (click on )

    A message in the bottom left will confirm the changes have been made

    4. Execute SAP transaction code MM02 (you are already there just enter new material)

    For the following raw material, you are going to set the minimum order quantity to 250.

    Enter your material number X400-01-xxxx

    Click the green check mark

    Select view MRP1

    Click the green check mark

    Enter plant: 3000

    Enter location: 0001

    Click the green check mark

    You are now in the MRP1 view ChangeMinimum Lot Size to 250

    Save changes (click on )

    A message in the bottom left will confirm the changes have been made

    5. Execute SAP transaction code MM02 (you are already there just enter new material)

    For the following material, you are going to change the lead time to 5 (days).

    Enter your material number X200-01-xxxx

    Click the green check mark

    Select view MRP2

    Click the green check mark

    Enter plant: 3000

    Enter location: 0001

    Click the green check mark

    You are now in the MRP2 view

    ChangeIn-house production time to 5 (five) days

    Save changes (click on )

    STEP 3

    Execute SAP Transaction code MD61.

    This transaction will allow you to create planned independent requirements for your finished product.

    Enter material X100-01-xxxx

    Change planning period to W (week)

    Set FROMdate to 11/14/2013

    Set TO date to 12/31/2013

    Click green check mark

    You are now in the Planning Table view

    In W47/2013 enter quantity: 100

  • 7/30/2019 SCM445SAP3vSPR13

    5/6

    In W48/2013 enter quantity: 150

    In W49/2013 enter quantity: 120

    In W50/2013 enter quantity: 180

    Save changes (click on )

    A message in bottom left will confirm the schedule has been created

    STEP 4

    At this point, you have created material masters, BOM, and entered independent demands for your finished goods

    material. You will now run the MRP Stock /Requirements list for the finished goods material.

    Run SAP transaction MD04.

    Enter material: X100-01-xxxx

    Enter plant: 3000

    Click green check mark

    Q.2 What is the projected available balance (available qty) at the end of day 12/9/2013? 550-

    Think about this PAB quantity we created the independent requirements, but we did not yet run MRP to generate

    orders to support the requirements. If we do not run MRP and create replenishments, on 12/9/2013 we will have alarge negative balance which will represent the Tuaca Lights that we still owe our customers. However, this will not

    be the case because we are going to run MRP and build the Tuaca Lights to ship to our customers.

    STEP 5Create initial inventory balance for material X300-03-xxxx

    Run transaction MB1C

    Field Data

    Document Date Todays date

    Posting Date Todays dateMovement type 561

    Plant 3000

    Storage Location 0001

    From the menu on top of screen select:

    Movement type Receipt Init.stck entry (own) To unrestricted

    You will get multiple warning messages (lower left) continue to hit enter (green check) until the next screen

    appears which will allow you to enter material and quantity:

    Now enterMaterial Quantity

    X300-03-xxxx 110

    Hit green check mark (enter) wait for processing!

    SAVE.

    STEP 6

    You will now run a multi-level MRP explosion that will start with your finished goods material (X100-01-xxxx) and

    will continue through the entire product structure.

    Run SAP transaction MD41. (MPS/MRP multi-level explosion)

    Enter material X100-01-xxxx

    Enter plant 3000

    MRP control parameters (should be set OK but verify)

  • 7/30/2019 SCM445SAP3vSPR13

    6/6

    o Processing keyNETCH, Create pur. Req. 3, Schedule lines 3, Create MRP list 1, Planning mode 1,

    Scheduling 1

    SelectAlso plan unchanged components

    Click green check mark (enter)

    Click green check mark again (confirming values)

    You will get the results of the MRP explosion do not worry about this screen, simply exit the transaction

    and go back to the Easy Menu.

    STEP 7

    1) Run SAP transaction MD04 for material X100-01-xxxx and plant 3000.

    Review this screen very carefully!! Note all field names, including the Available Qty (projected available quantity)

    field. Note the first line with todays date that has Stock is the current sock on-hand quantity. Each row will

    show Independent requirements (the need) and the planned orders that were generated to satisfy them. Note the start

    date for the planned orders is backed off from the order due date based on the material lead time.

    For the planned order that is due on 11/25/2013:

    Q.3. What is the planned order start date? 11/21/2013 (hint: hit the magnifying glass icon to the left of the order)

    Q.4 For the order due on 12/02/2013, what is the planned order quantity? 120

    Q.5 What is the available quantity at the end of the day on 12/02/2013? 0 (look CLOSELY at the MD04 screen to

    answer this question think about it)

    2) Run SAP transaction MD04 for material X300-02-xxxx and plant 3000.

    Again, review this screen very carefully and understand the impact of setting the maximum lot size to 70.

    Q.6 How many planned orders were created that are due on 11/08/2013? (I am looking for the NUMBER of

    orders, NOT the total order quantity) 2

    Be sure that you understand why multiple orders were created on 11/08/2013!!!

    3) Run SAP transaction MD04 for material X400-01-xxxx and plant 3000.

    Again, review this screen very carefully and understand the impact of setting the minimum lot size to 250.

    Q.7 What is the Available Qty at the end of the day on 11/06/2013? 100

    STEP 8

    One at a time, run SAP transaction MD04 for materials X100-01-xxxx, X200-01-xxxx, X300-03-xxxx and X00-01-

    xxxx. Now verify the results of the MRP planning with your manual calculations that you performed in step 1. The

    planned order releases and the available quantity (PAB) should match up EXACTLY.

    In addition to comparing these four materials with your manual calculations, you should also compare your MD04

    results with one or two of your classmates. (You can optionally compare your answers with materials X100-01-

    X01, X200-01-X01, X300-03-X01 and X400-01-X01).

    When viewing the MD04 transaction for each of these materials, if something is not correct, you will need to findthe problem. You should review lead times and ordering parameters. When you find the problem, change the

    material (fix the parameter) and then run MRP again.

    In addition to your answer sheet quiz, my grading will also consist of my review of your material (MD04)

    requirements / replenishments for all materials.

    GREAT WORK!!!!