Page 1: SDC Migration Project Status Report January 2012

SDC Migration Project

Status ReportJanuary 2012

Page 2: SDC Migration Project Status Report January 2012

Status

• Project funding reduced from $59M to $24M

– $24M consists of construction bond fund savings – can only be used for SDC improvements and assets

• Re-setting project strategy, scope, budget, and schedule to align with new funding constraint

– Requires different approach and infrastructure design

– All procurements on hold pending new plan and design

– Private Cloud procurement on hold pending review by TSB (meeting not yet scheduled)

Page 3: SDC Migration Project Status Report January 2012

Project Reset Activities• Assess priorities and options• Identify priorities that can be funded through existing or

alternate revenue sources• Develop phased migration plan that

– Reduces risk and maximizes available funds– Relieves OB2 over-capacity problems– Generates revenue from SDC– Meets minimum facility, security, and network requirements– Supports the State’s IT transformation initiative (Utility

Computing)– Positions the SDC as the primary data center anticipating

eventual OB2 shutdown– Minimizes disruption and rework over time

Page 4: SDC Migration Project Status Report January 2012

Next Steps (Jan – Feb 2012)

• Complete budget analysis• Complete migration alternatives analysis• Determine migration phases: logical groupings of

systems determined by dependencies, risks, benefits, complexity, equipment life-cycle, impact, cost

• Re-design core network and security to support migration phases

• Define new schedule, charter, investment plan• Restart selected procurements and other activities to

implement new plan

Page 5: SDC Migration Project Status Report January 2012

SDC Migration Project

Questions?