23
<Project Name> Capacity Plan Capacity Plan Bureau of Information Systems <Project Name> document.docx Page 1 of 23

Upload: hoangkien

Post on 10-May-2018

215 views

Category:

Documents


2 download

TRANSCRIPT

Page 1: SDLC Deliverable Templates - Pennsylvania … · Web viewOperational Data Store (ODS) (All Environments) Area Description Current Size Expected Increase for Report Period Estimated

<Project Name> Capacity Plan

Capacity Plan Bureau of Information Systems

<Project Name>

document.docx Page 1 of 18

Page 2: SDLC Deliverable Templates - Pennsylvania … · Web viewOperational Data Store (ODS) (All Environments) Area Description Current Size Expected Increase for Report Period Estimated

<Project Name> Capacity Plan

REVISION HISTORYDate Version Description Author

<dd/mm/yy> <x.x> <details> <name>

document.docx Page 2 of 18

Page 3: SDLC Deliverable Templates - Pennsylvania … · Web viewOperational Data Store (ODS) (All Environments) Area Description Current Size Expected Increase for Report Period Estimated

<Project Name> Capacity Plan

TABLE OF CONTENTS

1. Release Specific Questions 4

2. Application User Base 5

3. Transaction Volume (Production Only) 6

4. Business Intelligence Metrics (Production Only) 7

5. System Resources (All Environments) 8

6. Data Warehouse Databases (All Environments) 9

7. Operational Data Store (All Environments) 10

8. File Storage (All Environments) 11

9. Network Bandwidth (Production Only) 16

10. DGS Print Service (Production Only) 17

11. Enterprise Service Usage (Production Only) 18

document.docx Page 3 of 18

Page 4: SDLC Deliverable Templates - Pennsylvania … · Web viewOperational Data Store (ODS) (All Environments) Area Description Current Size Expected Increase for Report Period Estimated

<Project Name> Capacity Plan

1. RELEASE SPECIFIC QUESTIONS

The capacity reporting should be based on a review of the Critical Business Process (CBP); previously referred to as a Unit of Work. This review should focus on key business drivers, workload, and workload characterization (transactions, batch jobs). The capacity report should be based on changes or additions to this base as well as any anticipated environmental (i.e. new software products). This requirement applies equally to transactional application, business intelligence, enterprise service, and COTS products. Use the following format for the Capacity Report:

Release-Specific Questions

Area Description Comments

FunctionalityAre there any significant changes to the nature of this application in terms of how it will be used (e.g. workflow changes, new or modified queries, etc.)?

Batch ProcessWill there be changes to the application’s batch requirements? If so, what is the estimated impact to the existing batch process?

Interfaces and Services

Identify any new or expanded interfaces or service usage that could potentially increase cross platform application traffic and result in new usage of external applications.

Information Lifecycle Management (ILM)

Has an ILM strategy been defined for this application? If so, please describe. If not, please explain why not.

New SoftwareAre any new COTS products required? If so, please identify the product(s).

document.docx Page 4 of 18

Page 5: SDLC Deliverable Templates - Pennsylvania … · Web viewOperational Data Store (ODS) (All Environments) Area Description Current Size Expected Increase for Report Period Estimated

<Project Name> Capacity Plan

2. APPLICATION USER BASE

Application User Base (Production Only)

Area Description Current Environment Change Expected

Application User Base

Describe total application user base including business unit affiliation where possible.

Describe when application is expected to be available (i.e. time of day and day of week) and list peak usage period.

List concurrent DB sessions (ODP)

document.docx Page 5 of 18

Page 6: SDLC Deliverable Templates - Pennsylvania … · Web viewOperational Data Store (ODS) (All Environments) Area Description Current Size Expected Increase for Report Period Estimated

<Project Name> Capacity Plan

3. TRANSACTION VOLUME (PRODUCTION ONLY)

Transaction Volume (Production Only)

Area Description

Transaction Name

(add or delete rows as required)

Current Consumption

(Daily)

Expected Increase (Daily)

Transaction Volume

Is there any anticipated change in transaction volume or new transactions (where transaction is defined as a Critical Business Process or Unit of Work)?

document.docx Page 6 of 18

Page 7: SDLC Deliverable Templates - Pennsylvania … · Web viewOperational Data Store (ODS) (All Environments) Area Description Current Size Expected Increase for Report Period Estimated

<Project Name> Capacity Plan

4. BUSINESS INTELLIGENCE METRICS (PRODUCTION ONLY)

Business Intelligence Metrics (Production Only)

Area Description Current Expected Increase for Report Period

Estimated number for the Report

Period

Data Warehouse Metrics

Cognos – Number of Users 0

Cognos – Number of Reports

0

Cognos - Number of Cubes 0

Cognos – Number and Size of Output Versions

0

Cognos – Number of Dashboard Pages

0

Informatica - Number of ETL Processes

0

ODS Metrics

Cognos – Number of Users 0

Cognos – Number of Reports

0

Cognos - Number of Cubes 0

Cognos – Number and Size of Output Versions

0

Cognos – Number of Dashboard Pages

0

Informatica - Number of ETL Processes

0

document.docx Page 7 of 18

Page 8: SDLC Deliverable Templates - Pennsylvania … · Web viewOperational Data Store (ODS) (All Environments) Area Description Current Size Expected Increase for Report Period Estimated

<Project Name> Capacity Plan

5. SYSTEM RESOURCES (ALL ENVIRONMENTS)

System Resources (All Environments)

Area Description Comments

System Resources

Will there be changes to the application that may require additional processing capacity. If so, please estimate the percentage increase.

Development

Integration Test

System Acceptance Test

Test for Production

Training

Production

document.docx Page 8 of 18

Page 9: SDLC Deliverable Templates - Pennsylvania … · Web viewOperational Data Store (ODS) (All Environments) Area Description Current Size Expected Increase for Report Period Estimated

<Project Name> Capacity Plan

6. DATA WAREHOUSE DATABASES (ALL ENVIRONMENTS)

Data Warehouse Database (All Environments)

Area Description Current Size Expected Increase for Report Period

Estimated Total Size

Data Warehouse Database

Will there be any growth to the current size of the data warehouse database?

Development

Integration Test

System Acceptance Test

Load Test

Test for Production

Training

Production

document.docx Page 9 of 18

Page 10: SDLC Deliverable Templates - Pennsylvania … · Web viewOperational Data Store (ODS) (All Environments) Area Description Current Size Expected Increase for Report Period Estimated

<Project Name> Capacity Plan

7. OPERATIONAL DATA STORE (ALL ENVIRONMENTS)

Operational Data Store (ODS) (All Environments)

Area Description Current Size Expected Increase for Report Period

Estimated Total Size

Operational Data Store

(ODS) Database

Will there be any growth to the current size of the operational data store database?

Development

Integration Test

System Acceptance Test

Load Test

Test for Production

Training

Production

document.docx Page 10 of 18

Page 11: SDLC Deliverable Templates - Pennsylvania … · Web viewOperational Data Store (ODS) (All Environments) Area Description Current Size Expected Increase for Report Period Estimated

<Project Name> Capacity Plan

8. FILE STORAGE (ALL ENVIRONMENTS)

File System Storage (All Environments)

Area DescriptionServer Type (Web, Utility, Report)

(add or delete rows as required)

Current Size

Change Expected

File System Storage

(i.e. Non-Database)

Will there be any growth to the size of non-database server storage (e.g. application code, input files, log files, reports, etc.).

Development

Web Server

PWISDEVWEB02

Utility Server N/A

Report Server

PWISHBGCOG16

PWISSATRPT02

PWISDEVSRS10

FSWS

PWISDEVSOA10

Data Warehouse Servers

SOA Server

PWISDEVSOA10

iRep

Integration Test

Web Server

document.docx Page 11 of 18

Page 12: SDLC Deliverable Templates - Pennsylvania … · Web viewOperational Data Store (ODS) (All Environments) Area Description Current Size Expected Increase for Report Period Estimated

<Project Name> Capacity Plan

File System Storage (All Environments)

Area DescriptionServer Type (Web, Utility, Report)

(add or delete rows as required)

Current Size

Change Expected

PWISHBGINT04

Utility Server PWISINTAPP15

Report Server

PWISINTSRS15

FSWS

PWISDEVSOA10

Data Warehouse Servers

SOA Server

PWISDEVSOA10

iRep

Web Server

PWISSATWEB17

PWISSATWEB18

Utility Server

PWISSATAPP21

Report Server

PWISSATSRS25

PWISHBGCOG26

document.docx Page 12 of 18

Page 13: SDLC Deliverable Templates - Pennsylvania … · Web viewOperational Data Store (ODS) (All Environments) Area Description Current Size Expected Increase for Report Period Estimated

<Project Name> Capacity Plan

File System Storage (All Environments)

Area DescriptionServer Type (Web, Utility, Report)

(add or delete rows as required)

Current Size

Change Expected

PWISHBGCOG27

PWISSATRPT02

FSWS

PWISSATSOA20

PWISSATSOA21

Data Warehouse Server

SOA Servers

PWISSATSOA20

PWISSATSOA21

iRep

Test for Production

Web Server

PWISTFPWEB20

Utility Server

PWISTFPAPP23

Report Server

PWISTFPSRS20

FSWS

PWISSATSOA20

PWISSATSOA21

iRep

document.docx Page 13 of 18

Page 14: SDLC Deliverable Templates - Pennsylvania … · Web viewOperational Data Store (ODS) (All Environments) Area Description Current Size Expected Increase for Report Period Estimated

<Project Name> Capacity Plan

File System Storage (All Environments)

Area DescriptionServer Type (Web, Utility, Report)

(add or delete rows as required)

Current Size

Change Expected

Data Warehouse Servers

Web Service Servers

Training

Web Server

PWISTRNWEB01

Utility Server

PWISSATAPP21

Report Server

PWISTRNSRS29

FSWS

PWISSATSOA20

PWISSATSOA21

iRep

Data Warehouse Servers

SOA Servers PWISSATSOA20

PWISSATSOA21

Production

Web Server

PWISPRDWEB35

document.docx Page 14 of 18

Page 15: SDLC Deliverable Templates - Pennsylvania … · Web viewOperational Data Store (ODS) (All Environments) Area Description Current Size Expected Increase for Report Period Estimated

<Project Name> Capacity Plan

File System Storage (All Environments)

Area DescriptionServer Type (Web, Utility, Report)

(add or delete rows as required)

Current Size

Change Expected

PWISPRDWEB39

Utility Server

PWISPRDAPP30

Report Server

PWISPRDRPT30

PWISPRDSRS31

FSWS

PWISPRDFSW30

iRep

Data Warehouse Servers

Web Services Servers

document.docx Page 15 of 18

Page 16: SDLC Deliverable Templates - Pennsylvania … · Web viewOperational Data Store (ODS) (All Environments) Area Description Current Size Expected Increase for Report Period Estimated

<Project Name> Capacity Plan

9. NETWORK BANDWIDTH (PRODUCTION ONLY)

Network Bandwidth (Production Only)

Area Description Firewall ZoneCurrent

SizeChange Expected

Network Bandwidth

Will there be a major growth to the amount of Network Bandwidth (e.g. additional bandwidth over just normal web traffic, such as extensive binary image data).

User Zone

App Zone

Perimeter Zone

document.docx Page 16 of 18

Page 17: SDLC Deliverable Templates - Pennsylvania … · Web viewOperational Data Store (ODS) (All Environments) Area Description Current Size Expected Increase for Report Period Estimated

<Project Name> Capacity Plan

10. DGS PRINT SERVICE (PRODUCTION ONLY)

DGS Print Services (Production Only)

Area Description DGS Constraints Current Usage Change Expected

DGS Print Services

Will there be changes to the usage of DGS print services?

Bandwidth / Transfer Size

Transfer Time / Duration

Mail Insertion (Gunther, Pitney Bowes)

document.docx Page 17 of 18

Page 18: SDLC Deliverable Templates - Pennsylvania … · Web viewOperational Data Store (ODS) (All Environments) Area Description Current Size Expected Increase for Report Period Estimated

<Project Name> Capacity Plan

11. ENTERPRISE SERVICE USAGE (PRODUCTION ONLY)

Enterprise Service Usage (Production Only)

Area Description Enterprise Service Current Usage Change Expected

Enterprise Service Usage

Will there be any changes to the usage of existing enterprise services?

MCI.NET

MPI.NET

ELN

Provider Search Service

Submit Application Service

Enterprise Rate Service

Enterprise Correspondence Services

Rules Engine Services (Corticon)

Reporting Services (SSRS)

Address Validation / Geo-Specific Services

Self Registration Service

Authentication / Authorizations (CA Products)

document.docx Page 18 of 18