Project Dates: June 28-July 19
SEAP/NREIP Student:Kristopher R. PriceSt. Mary’s Ryken High SchoolSenior Class of [email protected]
Mentor:Georg ContagAIR [email protected]
Project Objective and Research Approach:
- Audited and renamed several hundred files containing drawings related to parts or tools made by Sikorsky so that they referred to their contents by drawing number.
Results / Accomplishments / Next Steps:- Hundreds of Sikorsky drawings can now be
searched quickly by drawing number.
Distribution type Type
![Page 2: SEAP_NREIP_Quad_Chart_Kris Price1August final (2)](https://reader036.vdocument.in/reader036/viewer/2022071710/55ac33ba1a28abc74b8b479e/html5/thumbnails/2.jpg)
VH3D/VH60N CD Library Lab Logo
Project Dates: June 24- July 21
SEAP/NREIP Student:Kristopher R. PriceSt. Mary’s Ryken High SchoolSenior Class of [email protected]
Mentor:Georg ContagAIR [email protected]
Project Objective and Research Approach:
- Compile library of all Sikorsky files and drawings, contracts with Sikorsky, and part lists made by Sikorsky.
- CD’s were numbered and content was recorded in Excel.
Results / Accomplishments / Next Steps:- After organizing and recording contents of CD’s,
they were filed in 3-ring binders with printout of data lists.
- Identified gaps in data files. - Data will be used to support future aircraft
modifications and changes.
Distribution type Type
Binder 1 Binder 2
![Page 3: SEAP_NREIP_Quad_Chart_Kris Price1August final (2)](https://reader036.vdocument.in/reader036/viewer/2022071710/55ac33ba1a28abc74b8b479e/html5/thumbnails/3.jpg)
Computer Resources Life Cycle Management Plan (CRLCMP)
Project Dates: 24 July – 29 July 2013
SEAP Student:Kristopher R. PriceSt. Mary’s Ryken High SchoolSenior Class of [email protected]
Co-Mentors:Lorenda Walton, VH-3D Class Desk, AIR [email protected]
Project Objective and Research Approach:
The 20-year-old VH-3D & VH-60N Computer Resources management document does not reflect the current VH Fleet manuals nor management requirements and needs to be updated. I regenerated this document and corrected basic information in preparation for management update.
Results:
- Substantially corrected 174 page CRLCMP document and recreated necessary data to support next update phase.
- Program Office now able to distribute document across team for updates.
Distribution A
![Page 4: SEAP_NREIP_Quad_Chart_Kris Price1August final (2)](https://reader036.vdocument.in/reader036/viewer/2022071710/55ac33ba1a28abc74b8b479e/html5/thumbnails/4.jpg)
Support Equipment Data Audit
Project Dates: 13 May – 9 August 2013
NREIP Student:Kristopher R. PriceSt. Mary’s Ryken High SchoolSenior Class of [email protected]
Mentor:Mike CarterAIR 4.8Michael.l.carter1.ctr.navy.mil
Project Objective and Research Approach:- Identify whether Fleet HMX-1 manuals had
approved support equipment and highlight any unapproved equipment.
- Achieved by thorough audit of each manual side by side with the list of NAVAIR approved support equipment. If a piece of support equipment in a manual was not found in the list of approved equipment, the manual and section were added to a list for further analysis.
Results / Accomplishments:- Completed audit of three maintenance manuals. - Manuals will be updated with corrections.