S1 & S2 Seat Matrix & delivery Status S1 Seats Status Ground Floor 22 Admin seats, installation under progress. 1 st Floor 989 450 handed over and ready to occupy. Balance under snagging. 2 nd Floor 615 Work stations installed, ready for snagging. 3 rd Work stations installed substantially, S2 Seats Status Ground Floor 22 Admin seats, installation under progress. 1 st Floor 988 Ready for snagging. 2 nd Floor 986 Work stations available at site, installation under progress. Seats will be ready by July. TCS Confidential 3 3 rd Floor 1,187 Work stations installed substantially, Seats will be ready by July. 4 th floor 1,244 Work stations available at site, installation to start. Seats will be ready by August. 5 th Floor 1,176 Work stations available at site, installation to start. Seats will be ready by September. 6 th Floor 1,174 Awaiting work stations. Seats will be ready by October. Total 6,407 3 rd Floor 1214 Work stations partially available at site, installation under progress. Seats will be ready by August. 4 th floor 1243 Work stations partially available at site, installation under progress. Seats will be ready by September. 5 th Floor 1175 Awaiting work stations. Seats will be ready by October - November. 6 th Floor 1173 Awaiting work stations. Seats will be ready by December. Total 6801

Upload: ravi-shankar-kolluru

Post on 28-Sep-2015

2 views

Category:

Documents


0 download

DESCRIPTION

seat matrix

TRANSCRIPT

  • S1 & S2 Seat Matrix & delivery Status

    S1 Seats Status

    Ground

    Floor22

    Admin seats, installation under

    progress.

    1st

    Floor989

    450 handed over and ready to occupy.

    Balance under snagging.

    2nd

    Floor615

    Work stations installed, ready for

    snagging.

    3rd Work stations installed substantially,

    S2 Seats Status

    Ground

    Floor22 Admin seats, installation under progress.

    1st Floor 988 Ready for snagging.

    2nd

    Floor986

    Work stations available at site,

    installation under progress. Seats will be

    ready by July.

    TCS Confidential3

    3rd

    Floor1,187

    Work stations installed substantially,

    Seats will be ready by July.

    4th floor 1,244Work stations available at site,

    installation to start. Seats will be ready

    by August.

    5th

    Floor1,176

    Work stations available at site,

    installation to start. Seats will be ready

    by September.

    6th

    Floor1,174

    Awaiting work stations. Seats will be

    ready by October.

    Total 6,407

    3rd Floor 1214Work stations partially available at site,

    installation under progress. Seats will be

    ready by August.

    4th floor 1243Work stations partially available at site,

    installation under progress. Seats will be

    ready by September.

    5th Floor 1175Awaiting work stations. Seats will be

    ready by October - November.

    6th Floor 1173Awaiting work stations. Seats will be

    ready by December.

    Total 6801