FOR OFFICIAL USE ONLY // REL TO USA ONLY SLIDE #: F-35 DOC #: 342121AS BRIEFED: 27 Oct 14
SECAF Brief
27 October 2014Lieutenant General Chris Bogdan, USAF
Program Executive OfficerF-35 Lightning II Program
PRATT & WHITNEY PROPRIETARY INFORMATION
FOR OFFICIAL USE ONLY // REL TO USA, GBR MOD, ITA MOD, NLD MOD, TUR MND, CAN DND, AUS DOD, DNK MOD, and NOR MOD SLIDE #: F-35 DOC #: 342121AS BRIEFED: 27 Oct 14
• Engine way ahead / impact• Production delivery update• LRIP 8 settlement (hand carried)• Dual Capable Aircraft• Noise Report• Aircraft availability• Canada update• IOC status
Agenda
FOR OFFICIAL USE ONLY // REL TO USA, GBR MOD, ITA MOD, NLD MOD, TUR MND, CAN DND, AUS DOD, DNK MOD, and NOR MOD SLIDE #: F-35 DOC #: 342121AS BRIEFED: 27 Oct 14
• Background:◦ Engine surge, fire occurred during take-off roll at Eglin AFB
(23 June)◦ USN, USAF, UK and NL grounded F-35 fleet (3 July)◦ Returned to flight using limited envelope and flight duration
times (14 July)• Engineering Analysis:
◦ Root Cause review completed on 10 Oct 14◦ Due to excessive rub between an engine fan component
and adjacent seal
• Root Cause Corrective Action
AF-27 Engine FailureIncident area
S1S2
Plate Seal Rub
PRATT & WHITNEY PROPRIETARY INFORMATION
FOR OFFICIAL USE ONLY // REL TO USA, GBR MOD, ITA MOD, NLD MOD, TUR MND, CAN DND, AUS DOD, DNK MOD, and NOR MOD SLIDE #: F-35 DOC #: 342121AS BRIEFED: 27 Oct 14
Root Cause Analysis1) Rub rig tests
◦ Replicated problem & verified acceptable bite size◦ Started 27 August; Completed 7 October
2) Evaluated and verified close down model◦ Key tools used to return SDD aircraft back to flight
3) Fault tree closure: complete◦ Rub rig test complete: 7 October◦ Probable root cause complete: 30 September◦ Root cause review completed: 10 October
Return to Flight1) Prioritized SDD aircraft for envelope
clearance◦ AF-2, CF-2, CF-5, BF-3, AF-6 & AF-7 have
expanded flight envelopes◦ CF-3 executing arrestment testing
2) SDD engine flight test break-in procedure ◦ Successful rub-in flights on AF-4
3) Pre-trench prototype design change◦ Test plan review
- Completed 21 Oct◦ Fly week of 27 October◦ Validate design safety
4) Production final redesign review◦ Six potential options: early November◦ Inspection interval evaluation (3 hr)
- Early November review
Engine Way Ahead
Other Actions1) Enterprise wide process for future mishaps2) PW contracting changes: retrofits and production cut-in solution at no cost to the Gov’t
Stator 2 Pre-trench
FOR OFFICIAL USE ONLY // REL TO USA, GBR MOD, ITA MOD, NLD MOD, TUR MND, CAN DND, AUS DOD, DNK MOD, and NOR MOD SLIDE #: F-35 DOC #: 342121AS BRIEFED: 27 Oct 14
Future JPO and Accident Investigation Communication Improvement
JPO
Service/PartnerAirworthiness
(AW) Authorities
Three Phased Approach:1. Establish guidelines to allow tech data to
flow from field to JPO/AW when incident occurs- Late October
2. Must update MOU/MOAs with relevant agencies to document processes with formal agreements- End of calendar year
3. Author Decision Memorandum with Partners to cover possible Partner incidents- End of calendar year
Must give decision makers technical data to insure fleet aircraft safety while protecting integrity of the safety investigation board
Interim Safety Board/Safety Investigation
Board
FOR OFFICIAL USE ONLY // REL TO USA, GBR MOD, ITA MOD, NLD MOD, TUR MND, CAN DND, AUS DOD, DNK MOD, and NOR MOD SLIDE #: F-35 DOC #: 342121AS BRIEFED: 27 Oct 14
Overview• LRIP 5 – 32 A/C (All DD250’d)
• LRIP 6 – 36 A/C (15 in Major Assembly, 21 in Flight & Ground Ops)
• LRIP 7 – 35 aircraft (25 in Component Assembly, 10 in Major Assembly)
• LRIP 8 – 43 aircraft (29 in Component Assembly)
Issues• LRIP 5 deliveries were ~3 months late to contract
◦ Primary driver: TR1 ICP hardware shortage◦ Last LRIP 5 delivery completed 26 Sept 14
• LRIP 6 deliveries (late to contract) but 1 month early to warfighter◦ Final assembly parts shortages (2 mos), 3i S/W delay (3 mos)◦ LRIP 6 is currently expected to start deliveries in late Oct 14◦ 18 F-35A’s in LRIP 6
- 14 to Luke AFB and 4 to Nellis AFB• LRIP 8 contract award in mid Nov 14
◦ Handshake completed◦ 19 F-35A’s (Hill AFB, Luke AFB, Nellis AFB)◦ Includes $60M warranty for F-35B bulkhead deficiencies
As of 22 Oct 14
Factory and Fleet Summary
F-35 Current Fleet Laydown
F-35 Production Overview
FOR OFFICIAL USE ONLY // REL TO USA, GBR MOD, ITA MOD, NLD MOD, TUR MND, CAN DND, AUS DOD, DNK MOD, and NOR MOD SLIDE #: F-35 DOC #: 342121AS BRIEFED: 27 Oct 14
• Hand carried
LRIP 8 Settlement
FOR OFFICIAL USE ONLY // REL TO USA ONLY SLIDE #: F-35 DOC #: 342121AS BRIEFED: 27 Oct 14
• Enterprise understands timing of F-35 and B61-12 and are in sync with criticality of DCA
• Exploring options to begin F-35 flights in 2015 to inform Bomb Assembly Baseline Design Review (2nd Qtr CY16) and Tail Kit Assembly Critical Design Review (1st Qtr CY16)
• OSD AT&L directed the Air Force to add funding in the FY17 POM◦ SAF/AQ to close with AF/A8 on the minimum funding profile◦ Funding required from USAF and cannot be absorbed by already allocated JPO resources◦ Effort is not early to need; staffers need to see Department/Service commitment to fund
JPO/OSD Dual Capable Aircraft Discussions
RDT&E
($M)
FY12 FY13 FY14 FY15 FY16 FY17 FY18 FY19 FY20 FY21 FY22 FY23 FY24 Total
USAF
Funded
9.97 0 0 15.61 5.00 0 0 0 0 0 0 0 0 0
USAF
Required
9.97 0 0 15.61 5.00 25.88 27.79 37.35 49.41 47.13 45.48 40.12 35.16 338.90
USAF
Delta
0.00 0 0 0 0 (25.88) (27.79) (37.35) (49.41) (47.13) (45.48) (40.12) (35.16) (308.32)
FOR OFFICIAL USE ONLY // REL TO USA, GBR MOD, ITA MOD, NLD MOD, TUR MND, CAN DND, AUS DOD, DNK MOD, and NOR MOD SLIDE #: F-35 DOC #: 342121AS BRIEFED: 27 Oct 14
• Products1. Two-Page Executive Summary2. Communications Plan3. Noise Report (marked appropriately – FOUO/Rel to Partners)
• Timeline◦ Tues PM, 28 Oct: PEO send Item of Interest Email to Senior DoD Leadership
- Includes Two-Page Executive Summary, Communications Plan and Noise Report◦ Wed AM, 29 Oct: Partners
- Two-Page Executive Summary, Communications Plan and Noise Report◦ Fri AM, 31 Oct: Congress
- Two-Page Executive Summary and Noise Report◦ Fri PM, 31 Oct: Press
- Two-Page Executive Summary
Noise ReportRoll Out Plan and Timeline
FOR OFFICIAL USE ONLY // REL TO USA, GBR MOD, ITA MOD, NLD MOD, TUR MND, CAN DND, AUS DOD, DNK MOD, and NOR MOD SLIDE #: F-35 DOC #: 342121AS BRIEFED: 27 Oct 14
F-35 Overall Availability Summary
Actions for NMCMActive: 91/118Investigating: 88/96
Engaging the FleetActive: **/123Investigating: **/123** Reaches into all three areas
Actions for NMCSActive: 19/118Investigating: 08/96
Actions for DepotActive: 8/118Investigating: 0/96
Path to 60% AVA◦ JPO established Readiness Cell and JPO/LM the Sustainment Improvement Project Review Team with a shared
goal to enable the F-35 to reach 60% AVA or greater across all variants by end of Calendar year 2014◦ Based on what we know today, we expect 50-55% AVA by end of CY14◦ Upcoming challenges of Depot mods for USMC IOC may delay achievement of 60% AVA until Jul 15
F-35 Availability
FOR OFFICIAL USE ONLY // REL TO USA & CAN DND SLIDE #: F-35 DOC #: 342121AS BRIEFED: 27 Oct 14
• Canada swaps 4 LRIP 7 aircraft in CY15; payback with LRIP 9 aircraft
• Progress to date:◦ AF concurred 4 aircraft swap is executable with 2 caveats:
- USAF F-35 IOC remains on schedule – “No flex left”- If other partners make similar request, it would be difficult to accommodate
• Next Steps:◦ Canada needs to deliver Letter of Intent with updated beddown plan to F-35 PEO
- ECD mid-November◦ Congressional Notification letter being staffed through JPO
- ECD late-November
Canadian Aircraft OptionsCurrent Status
FOR OFFICIAL USE ONLY // REL TO USA, GBR MOD, ITA MOD, NLD MOD, TUR MND, CAN DND, AUS DOD, DNK MOD, and NOR MOD SLIDE #: F-35 DOC #: 342121AS BRIEFED: 27 Oct 14
USAF IOC Status
Aug 16 IOC Dec 16 IOC Requirement / Get-well plan
JulAssessment
AugAssessment
OctAssessment
AugAssessment
Y Y Y G12 Aircraft∙ Delays in LRIP 6 deliveries, recovers by LRIP 8
Y Y Y GBlock 3i capability (Conduct basic CAS, interdiction, and limited SEAD/SEAD ops in a contested environment)•USAF Req’d DRs incorporated before IOC
Y Y Y Y/GAircraft modifications• USAF IOC Mod Requirements defined on 27 June 2014
G G G G JTD/FSD - on track• All required tech data planned to be in place
R Y Y* Y/G*ALIS• SW: SOU V2 phase 1 final increment to enable sub squadron reporting and Dynamic Routing was late to start but has now begun
Y Y Y Y/GUSRL MDF delivery •AOR 1 & 4 by Aug 16, AOR 2 & 3 by Dec 16
Updated 1 Oct 14
Partially Meets- No Blk Correction
Doesn’t Meet -or- Action Req’dRisk to MeetingGComplete On TrackB Y O R*ALIS baseline replan Nov 2014
662 days to go
FOR OFFICIAL USE ONLY // REL TO USA, GBR MOD, ITA MOD, NLD MOD, TUR MND, CAN DND, AUS DOD, DNK MOD, and NOR MOD SLIDE #: F-35 DOC #: 342121AS BRIEFED: 27 Oct 14
USAF IOC Status
Aug 16 IOC Dec 16IOC Requirement / Get-well plan
JulAssessment
AugAssessment
OctAssessment
AugAssessment
Y Y Y Y/GTraining• Pilot Training- 2B Software on track; Simulators for Hill AFB prioritized for delivery• Maintainer Training- on track
Y Y Y Y/G HMDS• 3iR4 SW build brings in Gen III, flight test underway
Y Y Y Y/GTesting/Certification• Weapons test planning ongoing• Spectrum certifications aligned with need dates
G G G GSpares• AV Base Spare Package funded / Deployable Spares Package projected to be in-
place
G G G G Lightning Support Team• Progressing well, no issues. Recommend no longer tracking
R/Y R/Y Y Y/G Support Equipment/AME • JPO has taken action to procure the required SE
662 days to go
Partially Meets- No Blk Correction
Doesn’t Meet -or- Action Req’dRisk to MeetingGComplete On TrackB Y O R
Updated 1 Oct 14
FOR OFFICIAL USE ONLY // REL TO USA, GBR MOD, ITA MOD, NLD MOD, TUR MND, CAN DND, AUS DOD, DNK MOD, and NOR MOD SLIDE #: F-35 DOC #: 342121AS BRIEFED: 27 Oct 14
Delivering the F-35 to the Warfighter