April 2016 Monthly Report 1 MTACC-SAS
PMOC MONTHLY REPORT
Second Avenue Subway Phase 1 (MTACC-SAS) Project
Metropolitan Transportation Authority
New York, New York
Report Period April 1 to April 30, 2016
PMOC Contract No. DTFT6014D00017
Task Order No. 2, Project No. DC-27-5287, Work Order No. 2
Urban Engineers of New York, D. P.C., 2 Penn Plaza, Suite 1103, New York, New York 10121
PMOC Lead: Charles A. Halboth, PE, 212-736-9100; [email protected]
Length of time on project: Five years on project for Urban Engineers
April 2016 Monthly Report 2 MTACC-SAS
TABLE OF CONTENTS
TABLE OF CONTENTS ..............................................................................................................2
THIRD PARTY DISCLAIMER ...................................................................................................3
REPORT FORMAT AND FOCUS ..............................................................................................3
MONITORING REPORT ............................................................................................................3
1.0 PROJECT STATUS ............................................................................................................3
a. Procurement …………………………………………………………………………….. 3
b. Construction ......................................................................................................................... 3
c. Quality Assurance and Quality Control (QA/QC) ............................................................... 9
2.0 SCHEDULE DATA ...........................................................................................................11
3.0 COST DATA ......................................................................................................................22
4.0 RISK MANAGEMENT ....................................................................................................27
5.0 ELPEP ................................................................................................................................30
6.0 SAFETY AND SECURITY ..............................................................................................31
7.0 ISSUES AND RECOMMENDATIONS ..........................................................................32
APPENDICES
APPENDIX A – ACRONYMS
APPENDIX B – TABLES
Table 1 - Summary of Schedule Dates
Table 2 - Project Budget/Cost
Table 3 - Estimate at Completion
Table 4 - Allocation of Current Working Budget to Standard Cost Categories
Table 5 - Core Accountability Items
April 2016 Monthly Report 3 MTACC-SAS
THIRD PARTY DISCLAIMER
This report and all subsidiary reports are prepared solely for the Federal Transit Administration
(FTA). This report should not be relied upon by any party, except FTA or the project sponsor, in
accordance with the purposes as described below:
For projects funded through the FTA’s Full Funding Grant Agreement (FFGA) program, FTA
and its Project Management Oversight Contractor (PMOC) use a risk-based assessment process
to review and validate a project sponsor’s cost, budget, and schedule. This risk-based
assessment process is a tool for analyzing project development and management. Moreover, the
assessment process is iterative in nature; any results of an FTA or PMOC risk-based assessment
represent a “snapshot in time” for a particular project under the conditions known at that same
point in time. The status of any assessment may be altered at any time by new information,
changes in circumstances, or further developments in the project, including any specific
measures a sponsor may take to mitigate the risks to project costs, budget, and schedule, or the
strategy a sponsor may develop for project execution.
Therefore, the information in the monthly reports may change from month to month, based on
relevant factors for the current month and/or previous months.
REPORT FORMAT AND FOCUS
This monthly report is submitted in compliance with the terms of the Federal Transit
Administration (FTA) Contract No. DTFT6014D00017. Its purpose is to provide information
and data to assist the FTA as it continually monitors the Grantee’s technical capability and
capacity to execute a project efficiently and effectively, and hence, whether the Grantee
continues to be ready to receive federal funds for further project development.
This report covers the project management activities on the Second Avenue Subway (SAS)
Phase 1 Project managed by MTACC. MTA is the Grantee and financed by the FTA FFGA.
MONITORING REPORT
1.0 PROJECT STATUS
During April, 2016, the MTACC continued advancing SAS Phase 1 to meet a Revenue Service
Date (RSD) of December 30, 2016, within its Current Working Budget (CWB) of $4.451 billion
(exclusive of financing). The overall project is approximately 87.4% complete. Substantial
Completion has been achieved on three of the eight active construction contracts. Progress in
this reporting period is discussed below:
a. Procurement
Procurement of construction contractors for SAS – Phase 1 is complete. Three construction
contracts are currently in the closeout process.
b. Construction
As of April 30, 2016, there are eight (8) active construction contracts on the SAS Phase 1
Project. Construction progress on the active contracts during this period includes:
Contract C-26005 (C2A) 96th Street Site Work and Heavy Civil
Substantial Completion was achieved on November 5, 2013.
April 2016 Monthly Report 4 MTACC-SAS
Sign off of the final volume of the “As-Built” drawings was expected to be completed
by the end of the 1st Quarter 2016. The contractor was delayed due to incorporation
of the Department of Environmental Protection’s comments into the “As-Built”
drawings. This is the only action left and closeout is now anticipated by May 31,
2016.
Contract C-26010 (C2B) 96th Street Station Civil, Architectural, and MEP
The following near term milestones are associated with activities that are being accelerated to
achieve the December 30, 2016 Revenue Service Date:
ConEd’s completion of the forth electrical feeds which provide facility power to the
station.
Power distribution to the various rooms (breaker panels)
Milestone #14 is ongoing and reported as on schedule. The work has to be completed on
or before May 31, 2016 and includes:
Completion of all work required to perform Field Installation Acceptance
Tests on all electrical and mechanical systems including but not limited to:
o Permanent power to all equipment
o Battery backup for the UPS system
o Chilled water piping and equipment
o Cooling towers and dry coolers
o HVAC ductwork and insulation
o Chillers
o Air handling units
o Fan coil units
o Condenser water piping
o Sump pump equipment
o All work required to provide a controlled environment in rooms that house
electrical and mechanical system equipment
o Provide controlled environment through temporary means if equipment
necessary to provide the controlled environment is unavailable due to testing
Milestone #15 is ongoing and reported as on schedule. The work has to be completed by
May 31, 2016 and includes:
Completion of all work required to perform Field Installation Acceptance
Tests on Tunnel Station Smoke Management (TSSM) system including, but
not limited to:
o Structural elements of the two Ancillary structures
o Fans
o Variable Frequency Drives (VFDs)
o All associated duct work
o Dampers and supervisory panel and control cabinets,
o Permanent power to all equipment
o All work required to provide a controlled environment in rooms that house
TSSM system equipment
April 2016 Monthly Report 5 MTACC-SAS
o Provide controlled environment through temporary means if equipment
necessary to provide the controlled environment is unavailable due to testing
Milestone #16 is ongoing and reported as on schedule. The work has to be completed by
May 31, 2016 and includes:
Completion of all work required to perform Field Installation Acceptance Fire
and Life Safety Systems including, but not limited to:
o Fire protection sprinklers,
o Water mist system
o Fire extinguishers,
o Doors required to prevent the spread of fire
o Dry fire standpipe
o All work required to provide a controlled environment in rooms that house
Fire and Life Safety system equipment
o Provide controlled environment through temporary means if equipment
necessary to provide the controlled environment is unavailable due to testing
Contract C-26006 (C3) 63rd Street Station Rehabilitation
The focus of the work effort remains at Area 5 and the progress at Entrance #1;
Work trains are being regularly scheduled on the inactive track for final trash removal
and material delivery;
Area 5 (Reconstruction includes mezzanines and the deck plaza roof)
In Area 5 the contractor continues with cleanup and responding to the NYCT
inspection observation lists.
At the 6th Mezzanine, the ceiling panels and lighting are complete. In the Traction Elevators 1-4, controller tests are scheduled for May 1, 2016.
Arts-N-Design artwork installation is complete on the 6th Mezzanine and is
complete in Entrance #1.
Installation of granite pavers on the 6th Mezzanine is complete with the
exception of infills.
Entrances (#1, #2, #3, and #4)
At Entrance #1, the contractor is finalizing work in the Back-Of-House
(BOH) area.
At the Entrance #2, testing has resumed.
At Entrances #3 and #4, the lighting levels are being checked.
Platforms
The full height construction wall between the active and inactive platform
has been removed for a “softer” demising barrier until full wall removal at
the time of Revenue Service.
Site
The Plaza renovation is complete.
Contract C-26007 (C4B) 72nd Street Station Cavern Mining and Lining
Substantial Completion was achieved on January 14, 2014. Submittal of contract
closeout documentation is ongoing;
April 2016 Monthly Report 6 MTACC-SAS
The punchlist items, including correcting the deficiencies to the architectural finish
along the escalator incline at Entrance #2 are complete and the area has been turned
back over to the C4C contractor; and,
Similar corrective work will also be required on the Entrance #1 incline finish.
Contract C-26011 (C4C) 72nd Street Station – Station Finishes, MEP, Ancillary Buildings
and Entrances
Ancillary #2
Cable pulling at the street level EDR is 95% complete and the main cable pulling is
complete at the 2nd floor;
Electrical work is complete in the Ancillary #2 basement & sub-basement
FPRs;
ConEd inspection and testing was completed in the Sub-Basement and Basement
FPRs in both Ancillaries #1 & #2; and,
Installation of pipe risers from the street to the roof Cooling Towers & Dry
Coolers continues at Ancillary #2.
Entrance #2
Installation of the escalator steps is approximately 50% complete at Entrance #2 and
installation of the handrails continues.
Ancillary #1
2 Fan Motors have been delivered;
Concrete placement of the corner stair nears completion; and,
Installation of conduit risers from the street EDR to the 4th Floor Fan Control
Room continues.
Cavern Mezzanine (Public, North and South)
In the Public Mezzanine the W30 porcelain tile installation is complete with
exception of the Arts-N-Transit panels; and,
In the North & South Mezzanines, installation of equipment devices, BMS
(Building Management System) panels, etc. in the Fan/Chiller Rooms
continues.
Platform
Installation of the platform granite wall tiles at the stairs and escalators is
complete with exception of infill at the doors;
Installation of drive machines for the Platform to Mezzanine elevator
(Elevator #1) is complete; and,
Installation of conduit & lights in the platform service carriers continues.
Entrance #1
The escalator conduit installation and light fixture installation was completed and
approximately 90% of the scaffolding has been removed from the incline;
Installation of the escalators is scheduled to begin May 1, 2016; and,
On the outside at Escalator #12, components installation is ongoing.
April 2016 Monthly Report 7 MTACC-SAS
Entrance #3 (Elevator Bank)
3 of the drive machines have been installed in the Elevator Machine Room for the
traction elevators.
Schedule
At the end of April 2016, the energization of 1 permanent power feed was
accomplished by ConEd during a weekend outage. With this permanent power,
the project can proceed to complete all equipment power and systems testing.
Contract C-26008 (C5B) 86th Street Station Cavern Mining and Lining
Substantial Completion of all contract work was achieved on December 16, 2014.
The architectural finish corrections at Entrance #2 and Entrance #1 escalator inclines
has been completed and the areas turned back over to the C5C contractor.
Contract C-26012 (C5C) 86th Street Station Finishes, MEP Systems, Ancillary Buildings &
Entrances
Cavern (Public, North & South Mezzanines) The porcelain tile on the W30 wall in the Public Mezzanine continues on the
east wall. The west wall tile installation is complete except for the art panels.
All fans (north & south mezzanines) arrived at the site.
Installation of the transition ducts and silencers for the fans are complete in
the north and south mezzanines.
Third Party Testing continued in the FPRs (Facility Power Room).
Installation of dampers continued in the north & south mezzanines.
Entrance #1
Some rigging remains in place. The long escalators truss alignment and
components installation continues.
Entrance #2
At Escalators #8, #9 & #10 the alignment is complete. Removal of rigging is
complete. Work platforms have been installed over the escalators for finishing out
the escalator incline.
At the traction elevator installation of rails is underway.
Ancillary #1 At Ancillary #1 the building fit-out is continuing, including electrical, ductwork, C6
conduit, etc; and,
At Ancillary #1 the Cooling Tower has been set in place; the Dry Cooler will be
delivered in early May 2016.
Ancillary #2 The structure erection continues above street level; and,
At Ancillary #2 the equipment for 3 rooms was delivered.
Platform Installation of platform granite pavers is complete with the exception of
infill tiles. Granite tile installation at the platform on the
April 2016 Monthly Report 8 MTACC-SAS
escalators/stairways walls is complete with the exception of infill tiles at
doors; and,
C6 has completed the trackwork on the southbound side and the contractor resumed
Durasteel framing installation over the track.
Site
Street restoration, along 2nd Ave. continues with backfilling of ductbanks.
Schedule ConEd began their “Trip Checks” at the site.
The plan remains for permanent power energization to be accomplished first in the
South Mezzanine power rooms, with the north to follow.
Contract C-26009 (C6) Track, Power, Signals and Communication Systems
The Contractor’s current schedule indicates a Substantial Completion (SC) date of 12/12/2016.
This is 2 weeks earlier than the revised SC date of 12/31/2016 and 9 weeks earlier than the
December 2015 CPM update SC date of 2/21/2017. Near term acceleration milestones includes:
96th Street Station
Signal System buildout to allow Field Installation Acceptance Test (FIAT) to be
completed by 5/23/2016. Work includes but not limited to:
o Breakdown testing of all relays, ground detectors, transfer switches and other
components in the relay rooms and wayside
Power washing of rail
Cable pulling ongoing (data, telephone, communication)
Traction Power Substation buildout and FIATs to allow Con Edison high tension
power testing and energization.
86th Street Station
Signal System buildout to allow FIAT to be completed by 5/23/2016. Work includes
but not limited to:
o Breakdown testing of all relays, ground detectors, transfer switches and other
components in the relay rooms and wayside
o Signal System wide track circuit bulletin certification and code signal in-service
acceptance
Traction Power Substation buildout and FIATs to be completed by 5/9/2026 to allow
Con Edison high tension power testing and energization.
72nd Street Station
Signal System buildout to allow FIAT to be completed by 5/23/2016. Work includes
but not limited to:
o Breakdown testing of all relays, ground detectors, transfer switches and other
components in the relay rooms and wayside
Traction Power Substation buildout and FIATs to be completed to allow Con Edison
high tension power testing and energization.
63rd Street Station
Signal System buildout to allow FIAT to be completed by 5/23/2016. Work includes
April 2016 Monthly Report 9 MTACC-SAS
but not limited to:
o Installation, wiring, and breakdown testing of all relays, ground detectors, transfer
switches, and signal equipment
Communication Systems buildout to allow preliminary and pre-testing FIAT to be
completed by 5/31/2016
Traction Power Substation buildout and FIATs to be completed by 6/27/2016 to allow
Con Edison high tension power testing and energization.
Acceleration schedule
Acceleration milestones have been established to have all work and testing
through Final Systems Integrated Testing completed by 9/30/2016
c. Quality Assurance and Quality Control (QA/QC)
Status:
During April 2016, the Second Avenue Subway Quality Management team continued to conduct
Quality Meetings and Quarterly Quality Oversights of the Contractor with CCM, MTACC, and
PMOC participation. The Quality Management Team participated in the job progress meetings,
monitored quality matters in the field for each construction contract, reviewed and provided
comments for Quality Work Plans, and participated in Preparatory Phase Meetings for numerous
construction processes.
Observations:
C2B: The C2B Contractor’s Quality Manager has not met the dates he has committed to
complete action items. Among the actions that keep slipping are:
A Special Inspection Matrix has not been updated;
Submittal of certifications from the Special Inspection Agency for completed work
have not been received and;
Eight (8) nonconformance reports (NCRs) have been open for more than ten months.
The Contractor’s Corporate Quality Manager is now providing assistance to the contractor’s
Quality Manager. Some improvement has been noted but the 8 NCRs that have been open for
more than 10 months is a serious issue.
C5C: There are many issues on this contract that affect Quality. These include:
Submittals that have been returned for additional information have not been returned;
Preparation of new submittals for approval has been delayed;
The Quality Staff has been reduced from four to three;
There is insufficient supervision for field activities;
Performance of external Quality Audits are behind schedule;
The electrical subcontractor’s NCRs have not been processed for over three months;
Record drawings at 50% completion has been delayed;
Work is not ready for NYCT inspection;
Check lists for many activities are not submitted on CMS; and,
Work is progressing without Preparatory Phase Meetings being held.
April 2016 Monthly Report 10 MTACC-SAS
Contract Package C2B
Status:
Through April 30, 2016, a total of 163 NCRs have been issued. One
Hundred Thirty-Four (134) have been closed and 29 NCRs are open. In
April 2016, 13 new NCRs were written and 5 were closed. None of the
NCRs closed in April were for concrete that was out-of-specification.
Sixteen (16) of the 29 open NCRs are for concrete that was out-of-
specification.
Observation:
Bi-weekly Quality Management Meetings, as suggested by the PMOC,
are being held. Submittal of Daily Inspection Reports is still 2 weeks
behind.
Concerns and
Recommendations:
Eight (8) of the open 13 non-concrete NCRs have been open more than
ten months. Based on the PMOC’s suggestion, the contractor has
established closure dates with the assistance of their Corporate Quality
Director who is now actively involved in managing the quality effort.
All of the projected dates are in May 2016. Each month, the dates
continue to slip. The PMOC is concerned that the dates are not realistic.
The PMOC has suggested to the Corporate Quality Director that he
evaluate each open NCR and add a column to the NCR log with
comments explaining what actions are being taken to close it.
Contract Package C3
Status:
Through April 30, 2016, a total of 128 NCRs have been issued. One
hundred eighteen (118) have been closed and 7 are still open. In April
2016, one new NCR was written and none were closed.
Observation: Submittal of Daily Inspection Reports is current.
Concerns and
Recommendations: The PMOC has no concerns.
Contract Package C4C
Status:
Through April 30, 2016, a total of 227 NCRs have been issued. One
hundred sixty-three (163) have been closed and 64 NCRs are still open.
In April 2016, three (3) NCRs were written and none were closed.
Observation:
One hundred eighty-four (184) of the 227 NCRs are for concrete that
was out of specification. Two of the three NCRs generated in April
2016 were for concrete that was out of range for slump. Submittal of
Daily Inspection Reports is current.
Concerns and
Recommendations:
Forty-three (43) of the remaining 64 open NCRs are for concrete that
was out of specification.
Contract Package C5C
Status:
Through April 30, 2016, 181 NCRs have been issued. One Hundred
twenty-one (121) have been closed and 60 NCRs are still open. In April
2016, four new NCRs were written and 47 were closed.
April 2016 Monthly Report 11 MTACC-SAS
Observation:
Nine (9) of the 60 NCRs that are open are for concrete that is out of
specification. The contractor prepared and submitted a concrete
statistical analysis in April 2016. It was approved by the Engineer of
Record and all 47 of the NCRs closed in April 2016 were for concrete
that was out of specification. Submittal of Daily Inspection Reports is
one week behind.
Concerns and
Recommendations:
The PMOC continues to recommend that the contractor establish a
schedule for closing the 51 non-concrete NCRs. The PMOC also
recommends that effort be devoted to resolving the issues listed in the
beginning of this section.
Contract Package C6
Status:
Through April 30, 2016, a total of 60 NCRs have been issued. Forty-
one (41) NCRs have been closed and 19 are still open. In April 2016,
no new NCRs were written and none were closed.
Observation: Fourteen of the open NCRs are for concrete that was placed beyond the
90 minute time limit. Submittal of Daily Inspection Reports is current.
Concerns and
Recommendations:
The cause for the concrete NCRs that were placed beyond the 90 minute
time limit was due to trucks that were delayed getting to the site due to
heavy traffic. It is expected that about ten of the concrete NCRs will be
closed in May 2016.
Concerns and Recommendations:
Discussed under each Contract Package.
2.0 SCHEDULE DATA
Status:
The PMOC received updated P6 schedules for the four (4) active construction contracts on May
2, 2016. These schedules are updates of those included as part of each contract’s “Schedule
Acceleration Agreement”. Each schedule has been updated through April 1, 2016. MTACC is no
longer maintaining an Integrated Project Schedule (IPS). The last IPS monthly update modeled
the status of the project through February 1, 2016. Subsequent discussions will be based on the
schedule for each individual construction contractor.
The lack of an integrated project schedule complicates the assessment of overall project
contingency. Based on information presented at the March 23, 2016 C/S Meeting, the latest date
identified by the fragnet schedules for the start of Pre-Revenue Service Activities is September
14, 2016. This date is controlled by LAN/WAN installation, testing and subsequent Level 5 Fire
Alarm System testing. MTACC has also advanced its internal estimate of when it can achieve
RSD. MTACC’s internal target to commence revenue service is now December 1, 2016. This
effectively adds 30 CD of schedule float if the published RSD of December 30, 2016 is used.
April 2016 Monthly Report 12 MTACC-SAS
Based on the available schedule information, available schedule contingency is evaluated as
follows:
Dates
Contingency
(CD) MTACC Construction, Testing
Complete 09/01/16
NYCT Pre-Revenue Training, Testing
- 60 CD 11/01/16
MTACC RSD- (REVISED TARGET) 12/01/16 30 MTACC Contingency
ELPEP Threshold 07/03/17 214 Additional Contingency
FTA RSD 02/28/18 240
Minimum ELPEP
Contingency
484 TOTAL
Observations:
Contract schedules in the “P6” format provide more detail regarding the work required to
complete than the highly summarized “Netpoint” schedules. However, the value of the P6
schedules is also limited. Schedule float values cannot be relied upon as an indicator of schedule
“criticality”. In some cases, float values exceed project remaining duration. In other cases,
excessive use of constrained milestone date artificially increase negative float values.
C2B – 96th Street Station
Substantial general and architectural construction remains at street level, station
platform and mezzanine levels, Ancillary 2, Entrances 1, 2 and 3. The risk of
street-level work impacting the RSD is low. While some of this work may be
deferred until after RSD, a certain finish level is typically required for a station to
be deemed acceptable for passenger use;
A significant portion of FIAT (Level 2 and 3) testing is forecast to occur between
June 6, 2016 and June 17, 2016. Concentration of this type of activity may stress
available NYCT support resources;
With the exceptions of minor architectural and site restoration, all installation and
testing (through level 4) activities are forecast to complete before September 1,
2016; and,
Development of equipment test and acceptance procedures, O & M Manuals and
submittal of test results represent a very large number of activities within this
schedule.
C4C – 72nd Street Station
Availability of permanent power is forecast for April 30, 2016;
Development of test procedures, O & M Manuals and submittal of test results
represent a relatively few number of activities within this schedule. Development
of equipment test and acceptance procedures is not included;
April 2016 Monthly Report 13 MTACC-SAS
Some finish construction activities such as painting, flooring, cleanup, elevator and
escalator trim, and punchlist activities extend beyond September 1, 2016;
Completion and turnover of fire protection systems does not occur until September
29, 2016;
Testing of elevators is not completed until November 14, 2016;
Entrance 1 escalator testing is not completed until November 14, 2016;
Track drainage system testing is not complete until October 14, 2016;
TSSM testing is not complete until October 12, 2016; and,
PMOC assumes final O & M Manuals and systems training will not constrain
NYCT Pre-Revenue Testing and the subsequent RSD. A number of these activities
do not complete until November/December 2016.
C5C – 86th Street Station
Availability of permanent power is forecast for May 2, 2016;
Delivery of water mist system equipment will not be complete until May 4, 2016;
installation of this system is forecast for completion on May 30, 2016;
Ancillary 2 structural work is forecast to complete in late May 2016;
Final inspections and punchlist work are all “planned to occur between October 10,
2016 and December 26, 2016;
Development of equipment test and acceptance procedure are not included in this
schedule;
Limited interior and exterior architectural work, site restoration and system testing
activities are forecast beyond September 1, 2016; and,
This contractor appears to have interpreted the acceleration agreement to mean that
inspection and punchlist activities may extend beyond September 1, 2016. The
nature of these activities may create punchlist work potentially interfering with
NYCT pre-revenue testing at the platform and mezzanine levels.
C6 – Systems:
Activities within this schedule contain as much as -746 WD (nearly 3 years) of
schedule float. This is based on the ongoing linkages to original contract
milestones. It can be reasonably assumed this contractor is maintaining this
schedule in anticipation of pursuing a significant post-construction equitable
adjustment to its contract;
Fire alarm testing; and,
Installation and testing - police radio system.
The PMOC review indicates several potential issues with this schedule:
This schedule appears to substantially comply with the acceleration agreement in
that the planned completion of all virtually work is on or before September 1,
2016;
April 2016 Monthly Report 14 MTACC-SAS
Approximately 140 milestones have been added to the schedule, denoting the
completion of work by other contractors on which C6 work is dependent; and,
There are approximately 210 CD from the schedule data date of February 1, 2016,
to the construction complete milestone of September 1, 2016. The fact that nearly
25% of the activities in this schedule have negative float values which exceed this
value (negative float values extend to -735 WD) creates significant concern over
the validity of this schedule.
A lack of consistency in construction schedule development has been previously noted and
continues to limit schedule usefulness. A current example is the selective inclusion of equipment
test and acceptance procedure development and improvement. The C2B schedule includes this
work in great detail while it is almost completely absent from the C4C and C5C schedules.
Netpoint Summary Schedule:
The most recent “Netpoint” schedule provided to the PMOC had Data Dates in early April, 2016.
Based on these schedules, critical or near-critical schedule issues include the following:
Tunnel ventilation; 96th, 86th and 72nd Street Stations;
Fire Alarm – Life Safety Installation; 96th and 72nd Street Stations;
Vertical Transportation – Installation and Testing; 72nd Street Station;
FIAT (Level 3-> 4) Testing; 96th, 86th and 72nd Street Stations;
FIST (Level 5) Testing; 96th, 86th and 72nd Street Stations; and,
FIAT (Level 3-> 4) Testing (LAN/WAN); 96th, 86th, 72nd and 63rd Street
Stations.
Additional observations include:
At 96th Street, significant delays to the start of FIAT (Level 3->4) Testing are
indicated for all Fire Life Safety Systems. These schedules do not provide
sufficient information to evaluate the cause of the delay;
Permanent Power:
o At 72nd Street, the availability of permanent power had been forecast for April
15, 2016. There appears to be a discrepancy between the Netpoint and P6
schedules.
o At 86th Street, permanent power availability is indicated to be June 1, 2016, a
discrepancy between the Netpoint and P6 schedules.
The date when permanent power become available remains important as it is a
necessary predecessor to the start of almost all FIAT (Level 3->4) Testing;
At 72nd Street Station, timing of escalator installation and testing has become
increasingly compressed in the Oct. /Nov. 2016 time period. The current schedule
indicated the 48 hour operational test for escalators 6, 7 and 8 will not be
completed in time to support MTACC’s December 1, 2016 target RSD;
At 96th Street, the last Netpoint schedule received from MTACC (DD=3/21/16)
indicates a significant improvement in testing and completion of most systems.
April 2016 Monthly Report 15 MTACC-SAS
Completion of testing of HVAC systems control the completion of this schedule.
The schedule seems to indicate delays to the development of test procedures for
the UPS System and Ancillary 1. Schedule symbols in these fragnets are not
included in the Legend; however they most closely represent the symbol for
“delay”; and,
Remaining architectural construction and sitework is not included in any of the
schedules for the three new stations.
Milestone Summary: As a part of the “Schedule Acceleration Agreements”, MTACC
established revised milestones with each contractor for the work involved. These milestones are
summarized and updated in the following table:
72nd Street
MS Description Accel.
Agreement
Update
(04/01/16)
15 Contract C26009 Access. Turn over communication room 5012 and
lube oil room 2006. 03/15/16 03/15/16A
16 Summit all preliminary O&M manuals, and all procedures for FIAT,
SIST and FIST tests. 04/30/16 05/01/16
17 Complete all work required for Con Edison to energize the Facility
Power substations including. 04/30/16 04/30/16
18 Complete all work and testing required to complete permanent
power distribution. 05/31/16 06/01/16
19
Complete all installations, controls, pretests, finishes and
environmental controls for the TSSM rooms at Ancillary 2 to start
FIAT (Levels 3/4) testing of the TSSM system at Ancillary 2.
05/31/16 05/30/16
20
Complete all installations, controls, pretests, finishes and
environmental controls for the TSSM rooms at Ancillary 1 to start
FIAT (Levels 3/4) testing.
06/15/16 06/16/16
21 Complete all installations and pretests for the HVAC rooms to start
FIAT (Levels 3/4) testing (Ancillary 2) 05/31/16 05/31/16
22 Complete all installations and pretests for the HVAC rooms to start
FIAT (Levels 3/4) testing (Ancillary 1) 06/15/16 06/15/16
23 Complete all work and pretests required to start FIAT (Levels 3/4)
on the Fire and Life Safety systems. 07/01/16 07/01/16
24 Complete all work and pretests required to start FIAT (Levels 3/4)
on the Water Mist Fire and Life Safety systems. 07/01/16 07/01/16
25
Complete all work and testing through FSIT (Levels 5a/b), including
2 weeks dedicated to performing FSIT over the WAN in
coordination with the C26009 Contractor (Level 5b).
09/30/16 09/30/16
26 Complete all work and testing through FSIT (Levels 5a/b) for
Escalators at Entrance 1 and Elevators at Entrance 3. 11/01/16 11/01/16
April 2016 Monthly Report 16 MTACC-SAS
86th Street
MS Description Accel.
Agreement
Update
(04/01/16)
15 Complete all work required for Con Edison to complete energization
to provide permanent Facility Power. 04/30/16 05/02/16
16 Complete Installation and Preparation for Level 3/4 Testing of
HVAC Systems 05/31/16 05/31/16
17 Complete Installation and Preparation for Level 3/4 Testing of
TSSM 05/25/16 05/31/16
18 Complete Installation and Preparation for Level 3/4 Testing of Fire
And Life Safety Systems 05/26/16 06/02/16
19 Complete all installation and testing – elevators and escalators 09/01/16 08/30/16
20
Complete all work and testing through FSIT, including 2 weeks
dedicated to performing FSIT via WAN in coordination with the
C26009 (Level 5b).
08/31/16 09/01/16
96th Street
MS Description Accel.
Agreement
Update
(04/01/16)
12 Complete all Work required for Con Edison to energize the South
Facility Power Substation at 96th Street. 02/29/16 02/29/16A
13
Provide permanent power to the communication rooms for
Milestone 6, the signal rooms for Milestone 7, the traction power
rooms for Milestone 8, the station service center for Milestone 9 and
the other rooms for Milestone 10.
03/31/16 04/13/16
14 Complete Preparations and Installation of Electrical and Mechanical
Systems to Start FIAT (Level 3,4) Testing 05/31/16 06/13/16
15 Complete all work required to commence FIAT (Level 3,4) on the
TSSM system 05/31/16 05/26/16
16 Complete all work required to commence all FIAT (Level 3,4) on
the Fire and Life Safety systems 05/31/16 05/31/16
17 Complete Level 5a Testing for HVAC, and Fire and Life Safety 07/31/16 07/28/16
18 Complete all work required to commence FIAT on all escalators and
elevators 07/31/16 07/28/16
19 Complete Level 5b Testing for All Systems; Complete ALL Work 08/31/16 08/30/16
Systems
MS Description Accel.
Agreement
Update
(04/01/16)
6 72nd Street: Complete all installation and testing required for ConEd
to inspect and start trip-checks. 05/02/16 04/25/16
7 96th Street: Complete all installation and testing required for ConEd
to inspect and start trip-checks. 04/04/16 03/22/16
8 86th Street: Complete all installation and testing required for ConEd
to inspect and start trip-checks. 05/09/16 05/08/16
9 Complete All Traction Power Installation and FIAT (Level 3/4)
testing 06/27/16 06/27/16
April 2016 Monthly Report 17 MTACC-SAS
Systems
MS Description Accel.
Agreement
Update
(04/01/16)
10
Complete installation of Trackwork and the Third Rail for Tracks S1
& S2 including submittal of complete scans demonstrating a
contractually compliant installation.
05/30/16 05/27/16
11 Complete all Field Installation Acceptance Tests (FIAT) of the
Signal System at 72nd Street. 05/23/16 04/23/16
12 Complete all Field Installation Acceptance Tests (FIAT) of the
Signal System at 96th Street. 05/23/16 05/22/16
13 Complete all Field Installation Acceptance Tests (FIAT) of the
Signal System at 86th Street. 07/18/16 07/17/16
14
Complete all Field Installation Acceptance Tests (FIAT) of the
Signal System at 63rd Street and existing tie-in rooms at various
locations.
05/30/16 05/25/16
15 Complete all remaining signal system work and testing required 05/23/16 05/07/16
16 63rd Comms. Systems: Complete all work and pre-testing required
to perform Field Installation Acceptance Tests 05/31/16 05/31/16
17 72nd Comms. Systems: Complete all work and pre-testing required
to perform Field Installation Acceptance Tests 06/13/16 06/13/16
18 86th Comms. Systems: Complete all work and pre-testing required
to perform Field Installation Acceptance Tests 06/27/16 06/27/16
19 96th Comms. Systems: Complete all work and pre-testing required
to perform Field Installation Acceptance Tests 06/20/16 06/20/16
20
The Contractor shall complete all work and testing through Final
Systems Integrated Testing of all systems over the Local Area
Network (LAN) and overall Wide Area Network (WAN), such that
the LAN/ WAN is available for Final Systems Integrated Testing by
the Station Contractors.
06/06/16 06/06/16
21 Complete all other work required to start Pre-Revenue Service
Training 09/30/16 09/30/16
Activity Progress Monitoring:
Progress evaluation is a comparison of actual achievement versus planned achievement through a
given time period. Using the acceleration schedules incorporated with each of the acceleration
agreements, the PMOC has tabulated the number of activities forecast to be completed per
month. Updated schedule provide actual activities achieved per month and revised forecasts for
incomplete activities. Activity information is expressed in % complete to account for incidental
activity additions and deletions.
April 2016 Monthly Report 18 MTACC-SAS
Tabular and graphic summaries of this information follow:
Date
Planned
%
Complete
Actual %
Complete
Forecast %
Complete
Jan-16 5.7% 0.6%
Feb-16 22.7% 1.3%
Mar-16 42.2% 7.3% 7.3%
Apr-16 59.9%
31.7%
May-16 72.9%
54.0%
Jun-16 82.2%
70.1%
Jul-16 89.0%
80.8%
Aug-16 93.6%
91.2%
Sep-16 96.2%
96.2%
Oct-16 97.9%
97.8%
Nov-16 99.0%
98.8%
Dec-16 99.8%
99.9%
Jan-17 100.0%
100.0%
Feb-17 100.0%
100.0%
April 2016 Monthly Report 19 MTACC-SAS
This very simple analysis indicates that, according to the updated contractor schedules,
significantly fewer activities have been achieved by the four “accelerated” construction contracts
than planned.
“Earned Value” Analysis:
In its periodic reports to the FTA, MTACC details the Budgeted Cost of Work Scheduled
(BCWS) versus the Budgeted Cost of Work Performed (BCWP) for each active construction
contract. At a summary level, the resulting “S-curves” compare planned versus actual
performance and can provide insight into performance trends and schedule forecasts. For each
active construction contract, the following table compares the planned vs. actual monthly level of
achievement in terms of value earned by completed construction work. This “earned value” can
be used to estimate the variance in planned vs actual schedule performance. January 2016 is the
latest month for which this information is available.
Value Earned through - March-16
Contract $
(x100K)
Plan $
Earned
Actual $
Earned
Plan
Month
for
Actual $
Earned
Months
Ahead
(+) or
Behind
(-)
Const.
Comp
Date
Est. Const.
Complete
Date
C2B $324 $324 $286 Apr-15 -8.1 9/1/16 5/3/17
C3 $176 $176 $170 Sep-13 -27.4 9/1/16 03/1/17
C4C $258 $255 $211 Mar-15 -9.7 9/1/16 6/18/17
C5C $208 $202 $170 Aug-15 -4.1 9/1/16 1/1/17
C6 $261 $253 $208 Jun-15 -6.2 9/1/16 3/5/17
TOTAL $1,227 $1,210 $1,044 Apr-15 -8.2 9/1/16 5/5/17
Cost Variance = Plan $ Earned – Actual $ Earned
= $1,210M - $1,044M = $166M
This summary level analysis suggests the following:
1. Had the work progressed according to baseline “plans”, an additional $166M worth of
original contract work would have been performed on or before March 31, 2016.
2. MTACC’s acceleration plan requires that $166M of baseline construction be completed over
the next 4 months. This does not include change order work or the value of the acceleration
agreements.
3. If the current rate of progress can be maintained, the C4C, C5C and C6 contracts appear to be
progressing at a rate that can achieve goal of the acceleration effort.
4. Based on current schedule assumptions, NYCT will require a minimum 2 months for pre-
revenue testing after all construction is complete. This results in a forecast RSD of July 5,
2017, absent significant schedule improvement.
ELPEP/SMP Compliance: MTACC is no longer using the IPS “master schedule” approach to
manage time on the project. The “Netpoint fragnet” system being used provides individual
summarized schedule fragnets for select work on four remaining construction contracts. This
April 2016 Monthly Report 20 MTACC-SAS
approach is not contained within the SAS Schedule Management Plan. It is the opinion of the
PMOC that MTACC is not in compliance with its schedule management plan.
Concerns and Recommendations:
1. Schedule data reviewed by the PMOC is somewhat inconclusive. Based on data provided
by MTACC:
a. Acceleration milestone forecast dates are being maintained.
b. Far fewer activities than forecast by the “acceleration schedules” are actually being
completed.
c. The rate at which contractors are realizing base contract revenue (Burn Rate) has
achieved a rate sufficient to complete the respective contracts on or around
September 1, 2016 for the first time.
2. These observations suggest contractors may be concentrating on “accelerated” work
associated with the milestones and neglecting other contract work. This scenario has been
previously observed during earlier periods of schedule acceleration.
3. MTACC has focused its schedule acceleration efforts on operating systems, generally
assuming there is always time to catch up on architectural and finish work. This approach
should be reviewed periodically to be sure certain work has not been deferred so long that
it cannot be completed without impact.
4. The total price due for each agreement is apportioned among new schedule milestones.
a. Contractors will complete the work for each milestone within 30 days of the date
established in order to receive the milestone payment.
b. Contractors have a second chance to earn the milestone payment if the contactor is
able to "catch-up" in time to meet the date required for pre-revenue training and
testing.
c. If a contractor misses a milestone date (plus 30 days) and misses the pre-revenue
service testing and training date (plus 30 days), the contractor will not be entitled
to the milestone payment.
d. The MTA may decide to pay a contractor for an otherwise missed milestone if
Revenue Service commences in or before December 2016.
PMOC is concerned that payment terms are so favorable to the contractors that
significant work may be deferred by a significant time, creating unforeseen impacts to
system testing and the RSD.
5. Review of contractor “acceleration schedules” indicates varying degrees of schedule
planning in the development of equipment and system testing procedures and acceptance
criteria.
C2B – development of test procedures incorporated in schedule in detail.
C4C – development of test procedures not included in schedule.
C5C - development of test procedures not included in schedule.
C6 - development of test procedures not included in schedule.
April 2016 Monthly Report 21 MTACC-SAS
The presence of a plan for this work provides some level of confidence the work will be
completed in a timely manner, particularly when actual month-to-month progress appears
limited.
April 2016 Monthly Report 22 MTACC-SAS
3.0 COST DATA
Based upon financial expenditures reported by the MTACC through April 30, 2016, SAS Phase
1 is approximately 87.4% complete. The completion status of the individual construction
contracts through April 30, 2016, also based upon reported expenditures through that date, is as
follows:
C26002 (Tunnel Boring) – 100.0%;
C26005 (96th Street Station) – 100.0%;
C26010 (96th Street Station) – 92.8%;
C26013 (86th Street Station) – 100%;
C26008 (86th Street Station) – 99.6%;
C26012 (86th Street Station) – 85.3%;
C26006 (63rd Street Station) – 96.9%;
C26007 (72nd Street Station) – 99.9%;
C26011 (72nd Street Station) – 83.5% ; and,
C26009 (Systems) – 79.9%.
Aggregate Construction percentage complete:
100% of all construction has been bid;
100% of all construction is under contract;
93.1% of base contract construction (excluding AWOs) is complete; and,
93.6% of all construction is complete.
Based upon cost data received from the MTACC for the period through April 30, 2016:
Value of construction reported in place this period = $37,073,611;
Estimated value of construction remaining = $186,028,339 (base contract only);
Target construction completion = September 1, 2016;
Number of months remaining = 4; and,
Avg. required construction expenditure to achieve target date = $45,608,948/MO.
Soft Cost expenditures (not including real estate, OCIP, etc.) reported this period by the MTACC
totaled $2.76M; expenditures were spread through all of the project management and technical
support categories. This lower-than-usual expenditure is partially due to the lack of any expense
recorded against Construction Management. It also appears that additional MTA staff costs
attributable to support of the schedule acceleration have yet to be charged to the project.
At current expenditure levels, the available budget should be sufficient through 2016. Significant
expenditure beyond 2016 however, may require the transfer of additional funds from
contingency. Any significant construction delays beyond December 2016 may also require
additional contingency transfer.
April 2016 Monthly Report 23 MTACC-SAS
Cost Growth: The value of AWOs reported by the MTACC/NYCT in April 2016 is summarized
as follows:
Executed AWOs AWO Exposure
Apr-16 $261,292,038 $351,402,566
Mar-16 $242,149,840 $342,552,667
Δ $19,142,198 $8,849,899
Δ 7.91% 2.58%
The changes in AWO Exposure for each construction contract are summarized as follows:
Const.
Pkg.
AWO Exposure
Apr-16 Mar-16 Period ∆ Changes this Period
Complete
Packages $47,612,118 $47,612,118 $0
Final values for Packages C1 and C5A as
reported by MTACC.
C2A $47,615,409 $47,615,409 $0 No change reported this period.
C2B $59,195,482 $59,240,668 -$45,187
Net increase is based on revised estimates for
AWO #s 121, 151, 178, 207, 215, 222, 224,
225, 228 and initial estimates for AWO #s
187, 203, 227, and 231.
C3 $40,533,864 $39,383,057 $1,150,807
Net increase is based on revised estimates for
AWO #s 190, 223, 260, 267, 271, 272, 275,
276, 277, 278, 279, 280, 282 through 291, and
initial estimates for AWO # 292 through 302.
C4B $1,325,639 $1,325,639 $0 No change reported this period.
C4C $66,906,970 $60,089,406 $6,817,564
Net increase is based on revised estimates for
AWO # 25, 80, 115, 118, 159, 160, 164, 182,
197, 210, 221 through 231 and initial estimates
for AWO #s 23, 50, 199, 232, 233, 234, 237,
238, 239, and 240.
C5B $26,280,122 $26,280,122 $0 No change reported this period.
C5C $30,765,404 $29,890,264 $875,140
Net increase is based on revised estimates for
AWO #s 6, 26, 33, 46, 79, 88, 90, 95, 96, 127,
133, and 150 and initial estimates for AWO #s
23, 48, 106, 124, 143, 161, 162, 167, and 168.
C6 $31,167,559 $31,115,984 $51,575
Net increase is based on revised estimates
for AWO #s 3, 46, 107, 131, 134, 135, 146,
171, 185, and 189 and initial estimates for
AWO #s 162, 167, and 197.
$351,402,566 $342,552,667 $8,849,899
April 2016 Monthly Report 24 MTACC-SAS
The changes in Executed AWO Value are summarized as follows:
Const.
Pkg.
Executed AWOs
Apr-16 Mar-16 Period ∆ Changes this Period
Complete
Packages $47,612,118 $47,612,118 $0
Final values for Packages C1 and C5A as
reported by MTACC.
C2A $47,615,409 $47,615,409 $0 No change reported this period.
C2B $49,550,183 $35,122,183 $14,428,000 Increase is based on execution of AWO #s
89, 145, 206, 207, 208, 214, 223, and 230.
C3 $28,078,288 $27,992,088 $86,200 Increase is based on execution of AWO # 42,
92, 288.
C4B $1,325,639 $1,325,639 $0 No change reported this period.
C4C $32,741,399 $30,089,999 $2,651,400
Increase is based on execution of AWO #s
94, 160, 172, 173, 174, 194, 195, 207, 214,
216, 217, 220, 225, 229, and 230.
C5B $21,586,813 $21,586,813 $0 No change reported this period.
C5C $7,714,904 $6,113,306 $1,601,598
Increase is based on execution of
AWO #s 21, 23, 25, 73, 85, 86, 105, 138,
144, and 150.
C6 $25,067,285 $24,692,285 $375,000 Increase is based on execution of
AWO #s 107, 131, 134, 171, and 185.
$261,292,038 $242,149,840 $19,142,198
April 2016 Monthly Report 25 MTACC-SAS
As of April 30, 2016, the status of Additional Work Orders (AWOs) for each construction
contract on Phase 1 of the Second Avenue Subway Project is summarized as follows:
Contract /
(Package)
%
Complete Award
Exposure Executed
$ % of
Award $
% of
Award
C26002 (1) 100.00% $337,025,000 $41,086,647 12.19% $41,086,647 12.19%
C26005 (2A) 100.00% $325,000,000 $47,615,409 14.65% $47,615,409 14.65%
C26010 (2B) 85.04% $324,600,000 $59,195,482 18.24% $49,550,183 15.26%
C26006 (3) 94.71% $176,450,000 $40,533,864 22.97% $28,078,288 15.91%
C26007 (4B) 99.93% $447,180,260 $1,325,639 0.30% $1,325,639 0.30%
C26011 (4C) 73.36% $258,353,000 $66,906,970 25.90% $32,741,399 12.67%
C26013 (5A) 100.00% $34,070,039 $6,525,471 19.15% $6,525,471 19.15%
C26008 (5B) 99.63% $301,860,000 $26,280,122 8.71% $21,586,813 7.15%
C26012 (5C) 64.84% $208,376,000 $30,765,404 14.76% $7,714,904 3.70%
C26009(6) 69.51% $261,900,000 $31,167,559 11.90% $25,067,285 9.57%
TOTAL TO DATE $2,674,814,299 $351,402,566 13.14% $261,292,038 9.77%
To date, $2,488,785,960 (93.1%) worth of all base contract construction work has been
completed. As a percentage of work completed, the AWO exposure for these contracts is 14.1%
and the executed AWO percentage is 10.5%.
The PMOC notes that total AWOs currently exceed the original AWO budget. The PMOC also
notes that exposure values are not included in a significant number of logged AWOs. Based on
current AWO trends, the final AWO value is estimated at approximately $350 million. MTACC
maintains an AWO forecast at completion that includes input from its Risk Registers. The
MTACC AWO EAC Forecast through March, 2016, is $359,227,269. This value is somewhat
greater than the PMOC’s AWO forecast and will be used as part of the overall contingency/EAC
analysis.
April 2016 Monthly Report 26 MTACC-SAS
Cost Contingency: Based upon the MTACC Current Working Budget, expenditures as of April
30, 2016, reported by the MTACC and the current AWO Exposure analyses, the PMOC has
developed the following contingency analysis:
Contingency Analysis
Current @ Completion
Phase 1 Budget $4,451,000,000 $4,451,000,000
Construction Awards $2,674,814,299 $2,674,814,299
Soft Cost Expended $1,176,630,126 $1,176,630,126
Soft Cost Forecast to Complete $200,024,639 $200,024,639
Add'l Soft Cost - Schedule Acceleration
$25,000,000
AWO Exposure $299,046,313 $359,227,269
Total Contingency $100,484,623 $15,303,667
Reserved Contingency $100,484,623 $15,303,667
Notes:
(1) AWO Exposure @ Completion incorporates MTACC’s latest “risk-informed” forecast
through March 2016
(2) Total Contingency = Reserved Contingency = total budget balance after forecast
expenditures;
(3) Minimum Available Contingency required by ELPEP is approximately $45,000,000 (100%
Construction Bid, 85% Construction Complete).
Conclusions based upon this analysis include:
(1) At the April 21, 2016 Quarterly Meeting with FTA, MTACC stated that “soft costs” to
support the schedule acceleration effort could be as high as $25M. This preliminary
estimate may be conservative, however given the limited contingency remaining, PMOC
recommends MTACC incorporate that additional $708M of local funds committed
through the amended FFGA into the project cost management system to cover potential
additional costs in excess of available contingency.
(2) Available contingency currently conforms to ELPEP limits.
ELPEP/CMP Compliance: The SAS Project Team maintains an EAC for all construction
costs, which is updated monthly. Revision #10 of the Project Cost Estimate, which includes a
complete forecast of remaining soft costs has been prepared, incorporated and updated as the
project CWB. It is the opinion of the PMOC that SAS Phase 1 is in substantial compliance with
the metrics, deliverables, and overall goals enumerated for Cost Management in the Enterprise
Level Project Execution Plan (ELPEP), dated January 15, 2010 (Section IV. b, page 8), and as
further described by the Cost Management Plan (CMP).
April 2016 Monthly Report 27 MTACC-SAS
4.0 RISK MANAGEMENT
Status
The major risk challenging the SAS Project Team at this time is schedule; senior MTA
management has advised that the current goal for construction completion and the start of
Revenue Service is December 1, 2016. Secondary risk involves the possibility that additional
schedule acceleration (or delay mitigation) costs could threaten the completion of the project
within MTACC’s Current Working Budget of $4.451B.
At this stage of the project, these risks are well understood by senior SAS managers and their
mitigation is the focus of almost all project management activity. As such, regular monthly risk
management meetings and reports are somewhat redundant and are not currently scheduled.
Observation and Analysis:
The goal of MTACC’s “schedule acceleration initiative” is to complete all third-party
construction, testing, and acceptance activities by September 1, 2016. This will create additional
time for NYCT operational testing and final “debugging” necessary for Revenue Service to start
no later than December 30, 2016. The acceleration of the construction schedule can be
considered a mitigation strategy directed at recovering time lost through previous delays and
mitigating delays forecast by the project schedule and other project management tools.
Risks can be classified as either management and organizational risk or technical and
coordination risk. Major risks within each of these categories are summarized as follows:
Management and Organizational Risks
Risk Status
1.
MTACC’s ability to implement its schedule
acceleration program through compression
of construction schedules.
MTACC appears to have successfully
avoided this risk.
2.
Design and scope changes requested by
NYCT during the late stages of
construction.
During March 2016, 48 new AWOs were
executed. During April 2016, 43 new AWOs
were executed. Preliminary review of these
AWOs suggests they conform to the
“operations and life safety” criteria noted by
MTACC.
3.
Availability of NYCT staff to support
testing, commissioning and final acceptance
of work performed by SAS contractors
Additional NYCT staff to support testing and
acceptance of the work have been and will be
made available to support project needs.
4.
Availability of NYCT staff to conduct code
compliance and final inspection of
constructed facilities.
A consultant has been procured and will
provide supplemental staff to support NYCT
code compliance inspection activities.
MTACC has noted this effort involves over
1400 individual rooms. At the March and
April 2016 Cost & Schedule meetings,
PMOC has requested documentation of the
status of this effort. No information has been
provided by MTACC to date.
5. MTACC’s system testing and approval The projects current method of referencing
April 2016 Monthly Report 28 MTACC-SAS
Management and Organizational Risks
Risk Status process has deviated from its Facilities
System Test Program as a means of
supporting the accelerated construction and
testing schedule.
tests as specific “Levels” is not defined in the
Facilities Systems Test Program (FSTP)
(Volume 1 –Management Plan). The FSTP
also states that there will be a Systems
Acceptance Phase (SAP) which will occur
after substantial completion (completion of
FAT, FIAT, SIST and FSIT). During this
phase, the systems and subsystems will be
operated to demonstrate that all interfaces
and systems are functioning as designed and
intended. After successful completion of this
phase, acceptance certificates will be issued
by NYCT. Schedules published by MTACC
do not reflect the testing process as
documented in the FSTP.
6.
MTACC’s ability to manage the change
order process in a timely manner to avoid
contractor delay.
PMOC has observed a general increase in the
number of AWOs executed over the past
several months. Additional resources have
apparently had an impact on volume of
AWOs processed.
Technical and Coordination Risks
Risk Status
1.
Critical communication systems: fire alarm
system and police radio installation, testing,
commissioning and acceptance.
Schedules made available by MTACC
currently indicate these work elements will
be completed in time to support the
scheduled RSD. 2. Permanent facility power – all stations
3. Traction Power – all stations
4. Installation, testing, commissioning and
acceptance of elevators and escalators.
5. Watermist system.
In addition to these risks, the PMOC considers the overall capability and readiness of the SAS
Project Team (MTACC and its consultants and contractors) to implement an aggressive schedule
acceleration initiative to be a significant risk.
As the number of field installation activities decreases, the next major “phase” of work involves
system testing and commissioning. The following table summarizes the SAS Project Team’s
progress during January and February 2016 in developing test procedures and acceptance criteria
necessary for the performance of the actual equipment testing and acceptance.
April 2016 Monthly Report 29 MTACC-SAS
Level 3/4 (FIAT) Level 5 (FIST) Level 6 (FSIT/SIT)
Mar-16 Apr-16 Δ Mar-16 Apr-16 Δ Mar-16 Apr-16 Δ
63rd Street
Required 65 65 0 30 30 0 9 9 0
Submitted 65 65 0 30 30 0 9 6 -3
Approved 60 65 5 17 25 8 5 6 1
% Complete 100% 83% 67%
72nd Street
Required 60 55 -5 31 26 -5 13 13 0
Submitted 39 55 16 24 26 2 4 7 3
Approved 15 29 14 2 2 0 2 1 -1
% Complete 53% 8% 8%
86th Street
Required 60 62 2 14 14 0 9 9 0
Submitted 39 62 23 0 2 2 0 0 0
Approved 20 42 22 0 0 0 0 0 0
% Complete 68% 0% 0%
96th Street
Required 59 61 2 13 13 0 8 8 0
Submitted 59 59 0 0 0 0 0 0 0
Approved 41 44 3 0 0 0 0 0 0
% Complete 72% 0% 0%
This tabulation raises the following concerns:
With the exception of 63rd Street, the level of completion of procedure
development for each level is reasonably consistent across the contracts.
Progress over the period represented by this table was limited.
Progress in the development of testing and acceptance criteria and procedures has
been and continues to be minimal at all three of the new SAS stations.
Completion and approval of all test procedures is not a criterion restraining the
start of testing at any level. However a large number of incomplete or unapproved
test procedures increases the risk of delay significantly.
Conclusions
Significant risks remain for both the successful execution of MTACC’s accelerated construction
schedule as well as overall achievement of Revenue Service on December 30, 2016. Recent
improvements in the rate of construction progress must be maintained throughout the next four
months. Significant improvements in preparation for systems testing and acceptance must be
achieved over the next several months in order for these efforts to be successful.
MTACC has effectively managed numerous cost/schedule risks over the construction phase of
SAS. In many instances, MTACC has chosen to proactively manage the project schedule
through directed acceleration at costs equal or less than costs that would be incurred by passive
acceptance of commensurate delay costs. In these instances, the risk management process has
been instrumental in identifying potential cost/schedule risks to the project and developing
mitigation strategies. The PMOC anticipates use of this process will be an important component
of MTACC’s overall schedule acceleration initiative.
April 2016 Monthly Report 30 MTACC-SAS
5.0 ELPEP
The most recent ELPEP Quarterly Review Meeting was held on March 3, 2016. The next
ELPEP Quarterly Review Meeting with MTACC, FTA-RII, SAS and the ESA project, and the
PMOC is scheduled for June 16, 2016. With respect to SAS, the current status of each of the
main ELPEP components is summarized as follows:
Technical Capacity and Capability (TCC): MTACC has resolved all remaining
FTA/PMOC comments and has issued the final revised PMP. MTACC is not
planning any further updates to the SAS PMP;
Schedule Management Plan (SMP): MTACC’s position is that the SAS
management processes remain ELPEP compliant. The PMOC does not concur
with this assessment. PMOC notes the ELPEP Conformance/Compliance checklist
indicates the IPS is updated on a monthly basis. As noted at the March and April,
2016 Cost & Schedule Meetings, the SAS Project Team is no longer maintaining
the IPS. Refer to Section 2.0 of this report for further discussion.
Cost Management Plan (CMP): Comments on the ESA/SAS Cost Management
Plan (CMP) were received on June 2, 2015. MTACC and the PMOC have held
meetings to resolve remaining issues. MTACC’s position is that the SAS
management processes remain ELPEP compliant;
Risk Mitigation Capacity Plan (RMCP) and Risk Management Plan (RMP):
MTACC’s position is that the SAS management processes remain ELPEP
compliant; and,
The SAS Project Team has implemented the principles and requirements embodied in the
ELPEP. The procedural changes triggered by the ELPEP have become an integral part of
the management of the project and give the FTA/PMOC greater insight into the risk, cost,
and schedule elements of the project.
April 2016 Monthly Report 31 MTACC-SAS
6.0 SAFETY AND SECURITY
Each construction contractor continued implementation of the Safety Requirements as specified
in Section 01 11 50 of the General Requirements.
As of March 31, 2015, a total of 12,758,777 construction hours have been logged on the project
with 100 lost time and 179 recordable incidents documented. The total hours and incidents
equates to a Lost Time Rate (LTR) of 1.57 and a Recordable Rate (REC) of 4.37. The LTR is
below and the REC is above the US Bureau of Labor Statistics (BLS) national rates (Heavy &
Civil construction) of 1.8 and 3.2 respectively. Although the REC is above the BLS national
rate, it continues to show a downward trend.
Safety and Security Certification: Safety and Security Certification Requirements are specified
in Section 01 77 12 of the General Requirements for each station and system contract. The
certifiable elements of the SAS project have been identified and the subsequent breakdown of the
certifiable elements into a list of certifiable items (CIL) has been completed. Technical Working
Group (TWG) meetings are ongoing with each station contractor and the system contractor to
review the test status of the certifiable items. Documentation supporting verification (Body of
Evidences) of a certifiable item is being accumulated and entered into the database. Status
meetings are held quarterly with the FTA and the PMOC in order to provide updates. Status
meetings are held monthly with the PMOC in attendance and the FTA is briefed quarterly.
April 2016 Monthly Report 32 MTACC-SAS
7.0 ISSUES AND RECOMMENDATIONS
Schedule Acceleration Initiative: MTACC’s schedule acceleration initiative results in the
establishment of September 1, 2016, as a new intermediate milestone at which time most
construction installation and testing activities are to be completed and NYCT Pre-Revenue
Testing is scheduled to commence.
The analysis of schedule data presented by MTACC provides a mixed view of
project progress. Milestone dates are apparently being met, yet overall
performance indicators suggest schedules are not being achieved.
In managing this accelerated schedule, MTACC has chosen the traditional
approach of focusing on the installation and testing of the mechanical and
electrical systems; assuming that any remaining architectural construction can be
completed at the end by applying as much labor as may be required.
Data evaluated combined with general observation of the work sites suggests the
mechanical, electrical and systems work may be receiving priority attention at the
expense of the other, currently less critical, architectural and general construction.
PMOC recommends MTACC periodically review the progress of remaining
architectural construction as well as punchlist work to verify that sufficient
progress is being made to provide satisfactory conditions in passenger spaces to
allow opening or about the RSD.
Certification for Revenue Service: MTACC has revised significant elements of its Facilities
Systems Test Program (FSTP) to support the goals of the accelerated schedule. Upon completion
of all testing, the procedures followed, approvals received and documentation assembled is likely
to be significantly different that that stipulated by the current plan. In that scenario, the PMOC
questions what the responsible individuals or the MTA as an organization will reference as a
baseline or standard against which it is “certifying” SAS, Phase 1 as being safe for revenue
service.
Budget/Cost Management: Current forecasts indicate approximately $15M of contingency
available at the end of SAS Phase 1 construction. This forecast may underestimate certain
remaining construction and post-construction risks.
In the amended FFGA (ref. page 2) MTACC Grantee agreed to contribute additional state and
local funds in the amount of $708,000,000 to ensure sufficient funds to complete the project.
The PMOC recommends that some or all of this local obligation be made available and
incorporated into the project cost management system to ensure subsequent decisions can be
made without constraint of available funding.
April 2016 Monthly Report A-1 MTACC-SAS
APPENDIX A – ACRONYMS
ARRA American Recovery and Reinvestment Act
AWO Additional Work Orders
BLS Bureau of Labor Statistics
CBH Circuit Breaker House
CCM Consultant Construction Manager
CD Calendar Days
CIL Certifiable Items List
CMP Cost Management Plan
CSSR Contact Status Summary Report
CPRB Capital Program Review Board
CWB Current Working Budget
CY Cubic Yards
DCB Detailed Cost Breakdown
EAC Estimate at Completion
ELPEP Enterprise Level Project Execution Plan
FIAT Field Installation Acceptance Test
FFGA Full Funding Grant Agreement
FSIT Final Systems Integrated Testing
FSTP Facilities System Integrated Testing
FTA Federal Transit Administration
GO General Outage
IPS Integrated Project Schedule
LAN Local Area Network
LTR Lost Time Rate
MO Month
MPT Maintenance and Protection of Traffic
MTA Metropolitan Transportation Authority
MTACC Metropolitan Transportation Authority – Capital Construction
N/A Not Applicable
NYCT New York City Transit
NYSPTSB New York State Public Transportation Safety Board
April 2016 Monthly Report A-2 MTACC-SAS
OSS NYCT Office of System Safety
PEP Project Execution Plan
PMOC Project Management Oversight Contractor (Urban Engineers)
PMP Project Management Plan
PQM Project Quality Manual
QA Quality Assurance
RAMP Real Estate Acquisition Management Plan
REC Recordable Rate
RMCP Risk Mitigation Capacity Plan
RMP Risk Management Plan
ROD Revenue Operations Date
ROW Right of Way
RSD Revenue Service Date
SAS Second Avenue Subway
SCC Standard Cost Category
SIST Simulated Integrated System Testing
SMP Schedule Management Plan
SSCC Safety and Security Certification Committee
SSOA State Safety Oversight Agency
SSPP System Safety Program Plan
TBD To Be Determined
TCC Technical Capacity and Capability
TPSS Traction Power Substation
TWG Technical Working Group
WAN Wide Area Network (WAN)
WBS Work Breakdown Structure
WD Work Days
April 2016 Monthly Report B-1 MTACC-SAS
APPENDIX B – TABLES
Table 1 - Summary of Schedule Dates
FFGA
(March 2015)
Forecast Completion
Grantee PMOC
Begin Construction January 1, 2007 March 20, 2007A March 20, 2007A
Construction Complete August, 2016 September 1, 2016 October 2017
Revenue Service February 28, 2018 December 30, 2016 February 2018
A = Actual
Table 2 - Project Budget/Cost
FFGA FFGA
Amend
MTA Current
Working Budget
(CWB)
Expenditures as of
April 30, 2016
$ Millions % of
Total
Obligated
($ Millions) 3/17/2015 $ Millions
% of
Total $ Millions
% of
Total
Grand Total Cost 4,866.614 100 4,572.942 5,574.614 5,267.614 100 3,889.065 73.83
Financing Cost 816.614 16.78 816.614 816.614 15.50
Total Project Cost 4,050.000 83.22 4,572.942 4,758.000 4,451.00 84.50 3,889.065 73.83
Total Federal 1,350.693 27.75 1,063.942 1,373.893* 1,350.693 24.60 1,180.877 22.42
Total FTA share 1,300.000 96.25 990.049 1,3000.000 1,300.000 23.68 1,180.877 22.42
5309 New Starts
share 1,300.000 100 990.049 1,3000.000 1,300.000 23.68 1,106.984 21.02
Total FHWA share 50.693 3.75 73.893 73.893 50.693 0.96 73.893 1.40
CMAQ 48.233 95.15 71.433 71.433 48.233 0.88 71.433 1.35
Special
Highway
Appropriation 2.460 4.85 2.460 2.460 2.460 0.04 2.460 0.05
Total Local share 2,699.307 55.47 3,509.000** 3,384.107 3,509.000 ** 63.92 2,708.188 51.41
State share 450.000 16.67 100.000 450.000 8.20
Agency share 2,249.307 83.33 1,145.782 3,059.000 55.72
City share 0 0 0 0
* Obligated and expended amounts obtained from the Transportation Electronic Award Management (TEAM) system and
MTACC’s Grant Management Department.
** Current MTA Board approved budget.
April 2016 Monthly Report B-2 MTACC-SAS
Table 3 - Estimate at Completion
Category Current Working
Budget
EAC Forecast
Total Construction $2,674,814,299 $3,034,041,568.00
Engineering Services Subtotal $622,862,000 $681,088,115.00
Third Party Expenses $554,086,273 $562,086,000.00
TA Expenses $131,160,085 $158,480,650.00
Contingency $468,077,343
Total $4,451,000,000 $4,435,696,333
Table 4 - Allocation of Current Working Budget to Standard Cost Categories
Std. Cost
Category
(SCC)
Description
FFGA FFGA
Amended
MTA’s Current
Working Budget
(January 2008) (March, 2015) (December, 2015)
10 Guideway & Track Elements $612,404,000 $195,346,781 $622,478,000
20 Stations, Stops, Terminals, Intermodal $1,092,836,000 $1,666,605,679 $1,277,642,000
30 Support Facilities $0 $0 $0
40 Site Work & Special Conditions $276,229,000 $793,118,232 $524,561,000
50 Systems $322,707,000 $250,379,966 $250,134,000
60 ROW, Land, Existing Improvements $240,960,000 $281,500,000 $281,500,000
70 Vehicles $152,999,000 $0 $0
80 Professional Services $796,311,000 $1,026,608,168 $1,185,742,929
90 Unallocated Contingency $555,554,000 $544,441,174 $308,942,010
Subtotal $4,050,000,000 $4,758,000,000 $4,451,000,000
Financing Cost $816,614,000 $816,614,000 $816,614,000
Total Project $4,866,614,000 $5,574,614,000 $5,267,614,000
April 2016 Monthly Report B-3 MTACC-SAS
Table 5 - Core Accountability Items
Project Status: Original at FFGA Current* ELPEP**
Cost Cost Estimate $4,050 million $4,451 million $4,980 million
Contingency
Unallocated
Contingency $555.554 million $100 million $45 million
Total Contingency
(Allocated plus
Unallocated)
$555.554 million $100 million
(April 2016) $45 million
Schedule Revenue Service Date June 30, 2014 December 30, 2016 February 28, 2018
Total Project
Percent
Complete
Based on
Expenditures 87.4%
Based on Earned
Value N/A
Major Issue Status Comments
Construction Schedule Acceleration Open
MTACC’s decision to accelerate the
construction schedule to allow NYCT
pre-Revenue Testing to commence on
09/01/16 results in concerns over
additional cost and the ultimate ability to
achieve this goal.
Construction Quality and
Operational Readiness Open
MTACC has deviated from established
organizational and project procedures as
part of its schedule acceleration effort.
PMOC is concerned that these deviations
may result in reduced construction
quality and incomplete systems testing.
Date of Next Quarterly Meeting: TBD (Tentatively July 21, 2106)
* MTACC’s Current Working Budget
** Enterprise Level Project Execution Plan (ELPEP), reflecting median level of risk mitigation
Financial data based upon MTACC reporting through 4/30/2016