secondary beam production facility layout discussions sblnf meeting 5 th dec. 2012
DESCRIPTION
Secondary beam production facility layout discussions SBLNF meeting 5 th Dec. 2012. M. Calviani, A. Ferrari, R. Losito (EN/STI) H. Vincke (DGS/RP). Outline. Update on the conceptual functional layout Neutrino production area Annex services (“morgue”, hot handling area, etc.) - PowerPoint PPT PresentationTRANSCRIPT
Secondary beam production facility layout discussionsSBLNF meeting 5th Dec. 2012
M. Calviani, A. Ferrari, R. Losito (EN/STI)H. Vincke (DGS/RP)
2 MC - Updates on SBLNF secondary beam facility layout
Outline
Update on the conceptual functional layout Neutrino production area Annex services (“morgue”, hot handling area, etc.) Building sizes and requirements
Comparison with similar installations in USA/Japan
5th December 2012
3 MC - Updates on SBLNF secondary beam facility layout
Updates on the neutrino production area
Present solution adopts the “trench/chase” approach: ~20/25 meters long, for an internal size of ~3 meters
New proposition: Machine (cooling systems) rooms on the lateral/size to the
target area Depends on the size of the trench that can be excavated Impact on costs but reduced pipings
Morgue and local shielding storage lateral to the target area Hot handling cell located downstream the target vault Personnel access to the target building from upstream Shielding thickness adapted to radiation levels at 240 kW (MC,
link) Disclaimer: this proposition reflects requirements – it’s
not integrated with services groups (CV, EL, etc.)!
5th December 2012
4 MC - Updates on SBLNF secondary beam facility layout
Access conditions and H*(10) levels
No routine access to the target hall during operation Shielding should be designed to respect an H*(10) of < 15 mSv/h
on the target vault during operation at 240 kW Levels outside the building will have to be <0.5 mSv/h (non
designated)
5th December 2012
Decay pipe: 250 cm thick concrete
shielding 5 mSv/h at 10 m from beam axis –
DP possibly fenced on the surface Concrete/soil interface at ~30
mSv/h 5 mSv/h would require ~400
cm thick concrete5 mSv/h level
H*(10) (mSv/h)Z averaged middle DPVertical direction
5 MC - Updates on SBLNF secondary beam facility layout
Neutrino production area proposition
5th December 2012
6 MC - Updates on SBLNF secondary beam facility layout
Neutrino production area
proposition
5th December 2012
Shielding: There are
margins to reduce the H*(10) on the vault floor by adding concrete blocks
Chase size matched with a 3 m diameter DP
< 15 mSv/h
< 1 mSv/h < 10 mSv/h
Present configuration assume: Machine rooms & morgue excavated lateral to chase
7 MC - Updates on SBLNF secondary beam facility layout
Possible configuration of the “morgue”
Two possibilities could be envisaged for the radioactive material disposal area Ground level lateral from the main target vault
Less underground works Need significant shielding + complex transport?
Located in a separate trench lateral to the target chase Easier shielding in case of very hot objects (objects could reach
~Sv/h) Can be used also to temporary store shielding blocks More complex CE works to excavate the trench Could be used to prepare the shielded transport cask
Size will depend on assumptions on hot objects exchange rates & transport requirements – temporary storage?
5th December 2012
8 MC - Updates on SBLNF secondary beam facility layout
Neutrino production area
5th December 2012
9 MC - Updates on SBLNF secondary beam facility layout
Hot handling work cell possible configuration
Potential use of a “radioactive working cell”: Horn mechanical connection to the shielding module,
remote strip line clamp, waterline connection to horn, electrical connection to horn, target inspection
5th December 2012
Location? On the target vault floor,
downstream the chase shielding Easier manipulation and access
Concrete enclosure, w/ internal cameras for local inspection No lead glass window
Fron
t sid
e
10 MC - Updates on SBLNF secondary beam facility layout
He-vessel conceptual
He-vessel enclosure, 1 atm He-gas: Pros:
Reduce pion absorption Suppress 3H by ~25% wrt air Suppress NOx production and corrosion (factor of ~100x) Suppress 7Be, 41Ar, 32P, etc. sure benefits for global releases
See H. Vincke, link Cons:
Quite complicated to build – huge He volume to handle – need to guarantee leak tightness for feedthroughs
Expensive solution Target station & decay volume – unique volume No beam window required between TS and DP
5th December 2012
11 MC - Updates on SBLNF secondary beam facility layout
He-vessel conceptual
Configuration: Thick steel layer – ~20 m (L), 3 m (W), 8 m (H) Evacuation of the He-vessel required to remove air and
avoid condensation (i.e. corrosion) during operation Cooling channels might be needed to cool down the
vessel (~20/30 kW deposited) Air/water cooled?
Is a shutter separating the TS from the DP during access required?
In order to recuperate He during evacuation, need of external compartments
Total volume ~1100 m3 (480 TS + 620 DP) It’s urgent to study the viability of this option
vs. an open air circulation system5th December 2012
12 MC - Updates on SBLNF secondary beam facility layout
What needs to be cooled in the
chase? Target – possibly an He cooling system Horn/reflector – water cooling He-vessel circulation (*) – He cooling
system He-vessel plates (*) – water (or air?) cooling DP collimator (?) – water cooling Hadron Absorber – water cooling Upstream collimator/baffle – cooling not
needed?
5th December 2012
(*) with an open air atmosphere these would be probably exchanged for a forced air cooling loop
13 MC - Updates on SBLNF secondary beam facility layout
Decay pipe 3 or 3.5 m Ø ~90 meters
long volume (~110 m from target)
Shape cylindrical or parallelepiped (a-la-T2K)
What’s the level of the moraine/molasse interface? 1974 bore: close to TCC2,
waterbed in moraine at 20 m below ground level (431 m)
Molasse ~429 m (22 m from surface)
5th December 2012
Courtesy: J. Osborne
14 MC - Updates on SBLNF secondary beam facility layout
DP - geomembrane DP: high level of prompt dose rate over a large
distance risks of soil and water activation Geosynthetic barrier system: protect the
surrounding groundwater from any possible tritiated water escaping the decay region
5th December 2012
Separate barriers (LBNE approach): Geomembrane Geosynthetic clay
liner barrier Geonet leak
detection layerhttp://lbne2-docdb.fnal.gov:8080/0046/004623/006/CDR_Vol_5_MI-10CF_20120313.pdf
15 MC - Updates on SBLNF secondary beam facility layout
Hadron absorber area
5th December 2012
16 MC - Updates on SBLNF secondary beam facility layout
Hadron absorber area
5th December 2012
Pit1/HS Absorber cooling
mandatory – cooling station will be certainly quite hot (~50 kW power to dissipate)
Access limited for maintenance
Pit1 access requires local bunker due to material activation
Crane required
Pit2: Could potentially be even a barrack –
no RP issues foreseen (H. Vincke, link) No fixed crane required
Pit1/HS Pit2
17 MC - Updates on SBLNF secondary beam facility layout
FNAL NuMI configuration
NuMI target station deep underground (beam level ~50 meters below ground); target hall is ~40 meters deep
Facility adapted to handle 400 kW beam power Surface target service building to access the deeper vault
5th December 2012
Target hall = 53 m length, ~8 m wide
18 MC - Updates on SBLNF secondary beam facility layout
FNAL NuMI configuration
5th December 2012
19 MC - Updates on SBLNF secondary beam facility layout
JPARC/T2K configuration
JPARC has a surface target vault, with a beam axis located ~20 meters below ground level
Facility adapted to handle 750 kW (1.6 MW) beam power Several annex buildings are located on the surface
5th December 2012
20 MC - Updates on SBLNF secondary beam facility layout
JPARC/T2K configuration
5th December 2012
21 MC - Updates on SBLNF secondary beam facility layout
Conclusions
Updated secondary beam line functional specifications
Location of the morgue to be confirmed in collaboration with DGS/RP
Cooling station/hot service rooms location to be confirmed/discussed with DGS/RP and GS/SE, as the target vault/chase size depends on this as well
He-vessel certainly an advantage, but costs and technical complexity worth?
5th December 2012