February 2, 2018 1
Completed and ongoing tasks:
• Below grade waterproofing ongoing.
• Concrete footings and foundation walls ongoing.
• Erection of elevator core walls ongoing.
• Installation of below grade utilities ongoing.
• Major structural steel in fabrication.
• Temporary electrical power was installed and generator removed from site.
Construction activities next month:
• Continuation of concrete footings, foundation walls, and underground utilities.
• Start concrete slab on grade at basement level.
• Curtainwall material will be released for fabrication.
Process related activities:
• Final Design and Construction Contract Award for full GMP was approved at the School Board meeting
on January 18. See the link below for the presentation:
https://www.boarddocs.com/vsba/arlington/Board.nsf/files/AUXRFU67B4D2/$file/F-
2%20Wilson%20Presentation-%20Final%20Design%20and%20GMP.pdf
• Construction workers parking has been in a nearby commercial garage since December 1, 2017.
Secondary School @Wilson
Community Newsletter (January 2018)