secondary school @wilson formwork and rebar february 2, 2018 4 steel formwork and wall sleeves...

4
February 2, 2018 1 Completed and ongoing tasks: Below grade waterproofing ongoing. Concrete footings and foundation walls ongoing. Erection of elevator core walls ongoing. Installation of below grade utilities ongoing. Major structural steel in fabrication. Temporary electrical power was installed and generator removed from site. Construction activities next month: Continuation of concrete footings, foundation walls, and underground utilities. Start concrete slab on grade at basement level. Curtainwall material will be released for fabrication. Process related activities: Final Design and Construction Contract Award for full GMP was approved at the School Board meeting on January 18. See the link below for the presentation: https://www.boarddocs.com/vsba/arlington/Board.nsf/files/AUXRFU67B4D2/$file/F- 2%20Wilson%20Presentation-%20Final%20Design%20and%20GMP.pdf Construction workers parking has been in a nearby commercial garage since December 1, 2017. Secondary School @Wilson Community Newsletter (January 2018)

Upload: doannguyet

Post on 10-Apr-2018

216 views

Category:

Documents


2 download

TRANSCRIPT

February 2, 2018 1

Completed and ongoing tasks:

• Below grade waterproofing ongoing.

• Concrete footings and foundation walls ongoing.

• Erection of elevator core walls ongoing.

• Installation of below grade utilities ongoing.

• Major structural steel in fabrication.

• Temporary electrical power was installed and generator removed from site.

Construction activities next month:

• Continuation of concrete footings, foundation walls, and underground utilities.

• Start concrete slab on grade at basement level.

• Curtainwall material will be released for fabrication.

Process related activities:

• Final Design and Construction Contract Award for full GMP was approved at the School Board meeting

on January 18. See the link below for the presentation:

https://www.boarddocs.com/vsba/arlington/Board.nsf/files/AUXRFU67B4D2/$file/F-

2%20Wilson%20Presentation-%20Final%20Design%20and%20GMP.pdf

• Construction workers parking has been in a nearby commercial garage since December 1, 2017.

Secondary School @Wilson

Community Newsletter (January 2018)

February 2, 2018 2

B2 level soil final grading for slab on grade

B2 level retaining wall

February 2, 2018 3

Foundation rebar

Steel formwork and rebar

February 2, 2018 4

Steel formwork and wall sleeves