section 03000-1 - tech specs 05-29-2015

129
SECTION 03000 - TECHNICAL REQUIREMENTS SUPPLEMENTAL TECHNICAL SPECIFICATIONS SECTION 03000-1 NE 28TH AVENUE DRA COMPONENT PROJECT - PART 1 SECTION 3100-1 GENERAL 1. This section covers supplemental technical specifications not covered in the standard specifications. 2. The City of Ocala "General Conditions for Construction", Volume I and "Standard Specifications for Water and Sewer Construction", Volume III, along with FDOT Standard Specifications for Road and Bridge Construction, latest edition, shall govern the execution of this Component Project - Part 1 as specified and amended by these Contract Documents. 3. Valve boxes used for locate wire terminals (material specification 479-03-06-02) shall have lid furnished with the word "STORM" on the cover to indicate the use of the locate wire system for stormwater. 4. Provided hereinafter is the Geotechnical Report for the project site as provided by Geo-Technologies Inc (Geo-Tech) dated April 23, 2014, Project No. 13- 4583.04.2. 5. Provided hereinafter is the Geotechnical Report for the project site as provided by Geo-Technologies, Inc. (Geo-Tech) dated April 8, 2013, Project No. 13- 4583.04.1 6. Provided hereinafter is the Individual Permit No. 111331-4 for the NE 28th Avenue DRA as issued by the St. Johns River Water Management District dated November 26, 2014 for the construction of a stormwater management system as described in these project documents.

Upload: others

Post on 18-May-2022

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: SECTION 03000-1 - Tech Specs 05-29-2015

SECTION 03000 - TECHNICAL REQUIREMENTS

SUPPLEMENTAL TECHNICAL SPECIFICATIONS

SECTION 03000-1 NE 28TH AVENUE DRA

COMPONENT PROJECT - PART 1

SECTION 3100-1 GENERAL

1. This section covers supplemental technical specifications not covered in the

standard specifications.

2. The City of Ocala "General Conditions for Construction", Volume I and "Standard

Specifications for Water and Sewer Construction", Volume III, along with FDOT

Standard Specifications for Road and Bridge Construction, latest edition, shall

govern the execution of this Component Project - Part 1 as specified and

amended by these Contract Documents.

3. Valve boxes used for locate wire terminals (material specification 479-03-06-02)

shall have lid furnished with the word "STORM" on the cover to indicate the use

of the locate wire system for stormwater.

4. Provided hereinafter is the Geotechnical Report for the project site as provided

by Geo-Technologies Inc (Geo-Tech) dated April 23, 2014, Project No. 13-

4583.04.2.

5. Provided hereinafter is the Geotechnical Report for the project site as provided

by Geo-Technologies, Inc. (Geo-Tech) dated April 8, 2013, Project No. 13-

4583.04.1

6. Provided hereinafter is the Individual Permit No. 111331-4 for the NE 28th

Avenue DRA as issued by the St. Johns River Water Management District dated

November 26, 2014 for the construction of a stormwater management system as

described in these project documents.

Page 2: SECTION 03000-1 - Tech Specs 05-29-2015

SECTION 3200-1 CONCRETE

1. General

Provide labor and materials necessary to install cast-in-place concrete complete.

2. Submittals

Submit concrete mix design with details of aggregate and admixtures used.

Certified test results must be submitted for each mix design used. Submit

concrete tickets from concrete supplier after every concrete placement.

3. Concrete Mix Design

Concrete compressive strength, F'C: 4,000 psi at 28 days, pipe encasements,

thrust blocks, supports. Concrete compressive strength, F'C: 3,000 psi at 28 days,

sidewalks, driveways.

Proportions: Water-Cement Ratio - ratio will control the amount of total water

added to concrete. Maximum 0.44 by weight.

Admixtures: Air Content - range of two (2) percent to four (4) percent. Test in

accordance with ASTM C231.

Slump Range at Site: Three (3) inches to five (5) inches.

4. Proportions of Mix

A. Mixture Proportioning, Normal Weight Concrete

Trial batches shall contain materials proposed to be used in the project.

Trial mixtures having proportions, consistencies, and air content suitable

for the work shall be made based on methodology described in ACI 211.1,

using at least three (3) different water-cement ratios. Trial mixes shall be

proportioned to produce concrete strengths specified. In the case where

ground iron blast-furnace slag is used, the weight of the slag will be

substituted in the equations for the term P which is used to denote the

weight of pozzolan. Trial mixtures shall be designed for maximum

permitted slump and air content. The temperature of concrete in each

trial batch shall be reported. For each water-cement ratio at least three

(3)test cylinders for each test age shall be made and cured in accordance

with ASTM C192. They shall be tested at seven (7) and 28 days in

accordance with ASTM C39. From these test results a curve shall be

plotted showing the relationship between water-cement ratio and

strength.

Page 3: SECTION 03000-1 - Tech Specs 05-29-2015

B. Average Strength

In meeting the strength requirements specified, the selected mixture

proportion shall produce an average compressive strength exceeding the

specified strength by the amount indicated below. Where a concrete

production facility has test records, a standard deviation shall be

established. Test records from which a standard deviation is calculated

shall represent materials, quality control procedures, and conditions

similar to those expected; shall represent concrete produced to meet a

specified strength or strengths within 1,000 psi of that specified for

proposed work; and shall consist of at least 30 consecutive tests. A

strength test shall be the average of the strengths of two (2) cylinders

made from the same sample of concrete and tested at 28 days or at

other test age designated for determination of the specified strength.

1. Required average compressive strength used as the basis for

selection of concrete proportions shall be the larger of the

specified strength plus the standard deviation multiplied by 1.34

or the specified strength plus the standard deviation multiplied by

2.33 minus 500.

2. Where a concrete production facility does not have test records

meeting the above requirements but does have a record based on

15 to 29 consecutive tests, a standard deviation may be

established as the product of the calculated standard deviation

and a modification factor from the following table:

(1) NUMBER OF TESTS MODIFICATION FACTOR FOR

STANDARD DEVIATION

Less than 15 See Note

15 1.16

20 1.08

25 1.03

30 or more 1.00

(1) Interpolate for intermediate numbers of tests.

NOTE: When a concrete production facility does not have field

strength test records for calculation of standard deviation or the

number of tests is less than 15, the required average strength shall

be:

Page 4: SECTION 03000-1 - Tech Specs 05-29-2015

The specified strength plus 1,200 for specified strengths of 3,000 to

5,000 psi.

5. Sampling and Testing

Sampling and testing of concrete is the responsibility of the City. All other

sampling and testing including cement, aggregate, admixture and curing

compound testing shall be the responsibility of the Contractor. The Contractor

shall cooperate with the City and/or his representatives in regard to all sampling

and testing activities.

A. Aggregates

Aggregates for normal weight concrete shall be sampled and tested in

accordance with ASTM C33. Lightweight aggregate shall be sampled

and tested in accordance with

ASTM C330. Gradation tests shall be performed on the first day and

every other day thereafter during concrete construction.

B. Sampling of Concrete

Samples of concrete for air, slump, unit weight, and strength tests shall

be taken in accordance with ASTM C172.

1. Air Content

Tests for air content shall be performed in accordance with ASTM

C173 or C231. A minimum of one (1) test per day shall be

conducted.

2. Slump

At least two (2) slump tests shall be made on randomly selected

batches of each mixture of concrete during each day’s concrete

placement. Tests shall be performed in accordance with ASTM

C143.

3. Unit Weight

Tests for unit weight of lightweight concrete shall be performed in

accordance with ASTM C567. Tests shall be conducted on each

batch sampled for strength tests and on random samples taken

for each 75 cubic yards of concrete placed. The unit weight of

fresh concrete shall not vary more than two (2) pounds per cubic

Page 5: SECTION 03000-1 - Tech Specs 05-29-2015

foot from the corresponding unit weight of the approved

proportions.

C. Evaluation and Acceptance of Concrete

1. Frequency of Testing

Samples for strength tests of each class of concrete placed each

day shall be taken not less than once a day, nor less than once for

each 150 cubic yards of concrete, nor less than once for each

5,000 square feet of surface area for slabs or walls. If this

sampling frequency results in less than five (5) strength tests for a

given class of concrete, tests shall be made from at least five (5)

randomly selected trucks or from each truck if fewer than five

truck loads are used. Field cured specimens for determining form

removal time or when a structure may be put in service shall be

made in numbers directed to check the adequacy of curing and

protection of concrete in the structure. The specimens shall be

removed from the molds at the age of 24 hours and shall be cured

and protected, in-so-far as practicable, in the same manner as

that given to the portion of the structure the samples represent.

2. Testing Procedures

Cylinders and beams for acceptance tests shall be molded and

cured in accordance with ASTM C31. Cylinders shall be tested in

accordance with ASTM C39 and beams shall be tested in

accordance with ASTM C78. A strength test shall be the average

of the strengths of two (2) cylinders made from the same sample

of concrete and tested at 28 days or at another specified test age.

3. Evaluation of Results

Concrete specified on the basis of compressive strength will be

considered satisfactory if the averages of all sets of three (3)

consecutive strength test results equal or exceed the specified

strength and no individual strength test result falls below the

required strength by more than 500 pounds per square inch.

4. Investigation of Low-Strength Test Results

When any strength test of standard-cured test cylinder falls below

the specified strength requirement by more than 500 pounds per

square inch, or if tests of field-cured cylinders indicate

deficiencies in protection and curing, steps shall be taken to

Page 6: SECTION 03000-1 - Tech Specs 05-29-2015

assure that load-carrying capacity of the structure is not

jeopardized. Non-destructive testing in accordance with ASTM

C597, C803, or C805 may be permitted by the Engineer to

determine the relative strengths at various locations in the

structure as an aid in evaluating concrete strength in place or for

selecting areas to be cored. Such tests, unless properly calibrated

and correlated with other test data, shall not be used as a basis

for acceptance or rejection. When strength of concrete in place is

considered potentially deficient, cores shall be obtained and

tested in accordance with ASTM C42. At least three (3)

representative cores shall be taken from each member or area of

concrete in place that is considered potentially deficient. The

location of cores shall be determined by the Engineer to least

impair the strength of the structure. If the concrete in the

structure will be dry under service conditions, the cores shall be

air dried (60° to 80°F, relative humidity less than 60%) for seven

days before testing and shall be tested dry. If the concrete in the

structure will be more than superficially wet under service

conditions, the cores shall be tested after moisture conditioning in

accordance with ASTM C42. Concrete in the area represented by

the core testing will be considered adequate if the average

strength of the cores is equal to or at least 85% of the specified

strength requirement and if no single core is less than 75% of the

specified strength requirement. If the core tests are inconclusive

or impractical to obtain, or if structural analysis does not confirm

the safety of the structure, load tests may be directed by the

Engineer in accordance with the requirements of ACI 318.

Concrete work evaluated by structural analysis or by results of a

load test and found deficient shall be corrected in a manner

satisfactory to the Engineer. All investigations, testing, load tests,

and correction of deficiencies shall be approved by the Engineer

and shall be performed at the expense of the Contractor.

6. Storage of Materials

Cement and pozzolan shall be stored in weather tight buildings, bins, or silos,

which will exclude moisture and contaminants. Aggregate stockpiles shall be

arranged and used in a manner to avoid excessive segregation and to prevent

contamination with other materials or with other sizes of aggregates.

Reinforcing bars and accessories shall be stored above the ground on platforms,

skids or other supports. Other materials shall be stored in such a manner as to

avoid contamination and deterioration. Admixtures which have been in storage

at the project site for longer than six (6) months or which have been subjected to

freezing shall not be used unless retested and proven to meet the specified

requirements.

Page 7: SECTION 03000-1 - Tech Specs 05-29-2015

7. Admixtures

Admixtures shall conform to the following:

Accelerating Admixture:

Air-Entraining Admixture:

Flowing Concrete Admixture:

Water-Reducing or Retarding

Admixture:

ASTM C494, Type C or E; or calcium chloride

conforming to D98.

ASTM C260

ASTM C1017, Type 1 or 2

ASTM C494, Type A, B, D, F, or G

8. Aggregates

A. Abrasive Aggregates

Fifty-five percent, minimum, aluminum oxide or silicon-dioxide abrasive

ceramically bonded together to form a homogenous material sufficiently

porous to provide a good bond with portland paste; or factory-graded

emery aggregate consisting of not less than 45% aluminum oxide and

25% ferric oxide. The aggregate shall be well graded from particles

retained on the No. 30 sieve to particles passing the No. 8 sieve.

B. Normal Weight Aggregate

ASTM C33. Grading requirement for coarse aggregate shall conform to

size number 57.

9. Cementitious Materials

Cementitious materials shall each be of one type and from one source when

used in concrete which will have surfaces exposed in the finished structure.

Cementitious materials shall conform to ASTM C150, Type I or II.

10. Curing Materials

Curing materials shall conform to the following:

Impervious Sheets: ASTM C171, type optional, except that polyethylene film, if

used, shall be white opaque.

Membrane-Forming Compounds: ASTM C309, Type 1-D, Class A and B.

Page 8: SECTION 03000-1 - Tech Specs 05-29-2015

11. Embedded Items

Embedded items shall be of the size indicated and stainless steel unless

otherwise noted, or as needed for the application.

12. Non-Shrink Grout

Non-shrink grout shall conform to CRF C621 and shall be a formulation suitable

for the application.

13. Vapor Barrier

Vapor barrier shall be polyethylene sheeting with a minimum thickness of six (6)

mils or other equivalent material having a vapor permeance rating not exceeding

0.5 perms as determined in accordance with ASTM E96.

14. Water

Water shall be potable, except that non-potable water may be used if it

produces mortar cubes having seven (7) and 28 day strengths at least 90% of the

strength of similar specimens made with water from a municipal supply. The

strength comparison shall be made on mortars, identical except for mixing water,

prepared and tested in accordance with ASTM C109. Water for curing shall not

contain any substance injurious to concrete, or which causes staining.

15. Forms

A. Forms shall be used for all concrete masonry, including footings. Forms

shall be so constructed and placed that the resulting concrete will be of the

shape, lines, dimensions, appearance, and to the elevations indicated on the

drawings.

B. Forms for all exposed exterior and interior concrete walls shall be

plywood with "A" veneer exterior on casting side. Rustications shall be at the

location and to the details shown on the Drawings. Moldings for chamfers and

rustications shall be milled and planed smooth.

C. Forms shall be made of wood, metal or other approved material. Wood

forms shall be constructed of sound lumber or plywood of suitable dimensions,

free from knotholes and loose knots; where used for exposed surfaces, boards

shall be dressed and matched. Plywood shall be sanded smooth and fitted with

tight joints between panels. Metal forms shall be of an approved type for the

Page 9: SECTION 03000-1 - Tech Specs 05-29-2015

class of work involved and of the thickness and design required for rigid

construction.

D. Edges of all form panels in contact with concrete shall be flush within

1/32" and forms for plans surfaces shall be such that the concrete will be planed

within 1/16" in four (4) feet. Forms shall be tight to prevent the passage of

mortar and water and grout.

E. Forms for walls shall have removable panels at the bottom for cleaning,

inspection, and scrubbing-in of bonding paste. Forms for walls of considerable

height shall be arranged with tremies and hoppers for placing concrete in a

manner that will prevent segregation and accumulation of hardened concrete on

the forms or reinforcements above the fresh concrete.

F. Molding or bevels shall be placed to produce a three (3) quarter inch

chamfer on all exposed projecting corners, unless otherwise shown on the

drawings. Similar chamfer strips shall be provided at horizontal and vertical

extremities of all wall placements to produce "clean" separation between

successive placements as called for on the plans.

G. Forms shall be sufficiently rigid to withstand vibration, to prevent

displacement or sagging between supports, and constructed so the concrete will

not be damaged by their removal. The Contractor shall be entirely responsible

for their adequacy.

H. Forms, including new pre-oiled forms, shall be oiled before reinforcement

is placed, with an approved non-staining oil or liquid for coating having a

non-paraffin base.

I. Before form material is re-used, all surfaces in contact with concrete shall

be thoroughly cleaned and all damaged places repaired, all projecting nails

withdrawn, all protrusions smoothed and in the case of wood, forms pre-oiled.

J. Form ties encased in concrete shall be designed so that after removal of

the projecting part, no metal shall be within 1 1/2" of the face of the concrete.

That part of the tie to be removed shall be at least one (1) inch diameter or be

provided with wood or metal cone at least one (1) foot in diameter and 1 1/2"

LONG. Form ties in concrete exposed to view shall be the cone-washer type

equal to the Richmond "Tyscru". Ties for water-holding structures shall have an

integral water stop that is tightly fitted to the tie at midpoint. Through bolts or

common wire shall not be used for form ties.

Page 10: SECTION 03000-1 - Tech Specs 05-29-2015

16. Preparation of Surfaces

Surfaces to receive concrete shall be clean and free from frost, ice, mud, and

water. Conduit and other similar items shall be in place and clean of any

deleterious substance.

A. Foundations: Flowing water shall be diverted without washing over

freshly deposited concrete. Rock foundations shall be cleaned by high velocity

air-water jets, sandblasting, or other approved methods. Debris and loose, semi-

detached or unsound fragments shall be removed. Rock surfaces shall be moist

but without free water when concrete is placed. Semiporous subgrades for

foundations and footing shall be damp when concrete is placed. Pervious

subgrades shall be sealed by blending impervious material with the top six (6)

inches of the in-place pervious material or by covering with an impervious

membrane.

B. Vapor Barrier: Subgrades for slabs under buildings shall be covered with

a vapor barrier. Vapor barrier edges shall be lapped at least four (4) inches and

ends shall be lapped not less than six (6) inches. Patches and lapped joints shall

be sealed with pressure- sensitive adhesive or tape not less than two (2) inches

wide and compatible with the membrane.

C. Preparation of Previously Placed Concrete: Concrete surfaces to which

other concrete is to be bonded shall be roughened in an approved manner that

will expose sound aggregate uniformly without damaging the concrete. Laitance

and loose particles shall be removed. Surfaces shall be moist but without free

water when concrete is placed.

17. Installation of Embedded Items

Embedded items shall be free from oil, loose scale or rust, and paint. Embedded

items shall be installed at the locations indicated and required to serve the

intended purpose. Voids in sleeves, slots and inserts shall be filled with readily

removable material to prevent the entry of concrete.

18. Batching, Mixing, and Transporting Concrete

Ready-mixed concrete shall be batched, mixed and transported in accordance

with ASTM C94, except as otherwise specified. Truck mixers, agitators, and non-

agitating units shall comply with the TMMB "Truck Mixer and Agitator

Standards". Plant equipment and facilities shall conform to NRMCA

"Certification of Ready Mixed Concrete Production Facilities." Site-mixed

concrete shall be mixed in accordance with ACI 301. On-site plant shall conform

Page 11: SECTION 03000-1 - Tech Specs 05-29-2015

to the requirements of the Concrete Plant Standards of the Concrete Plan

Manufacturers Bureau.

A. Admixtures: Admixtures shall be batched within an accuracy of three

percent (3%). Where two or more admixtures are used in the same batch, they

shall be batched separately and must be compatible. Retarding admixture shall

be added within one minute after addition of water is complete or in the first

quarter of the required mixing time, whichever is first. Superplasticizing

admixtures shall be added as recommended by manufacturer. Concrete that

shows evidence of total collapse or segregation caused by the use of admixture

shall be removed from the site.

B. Control of Mixing Water: No water from the truck system or elsewhere

shall be added after the initial introduction of mixing water for the batch except

when on arrival at the job site, the slump of the concrete is less than that

specified. Water added to bring the slump within the specified range shall not

change the total water in the concrete to a point that the approved water-

cement ratio is exceeded. The drum shall be turned an additional 30 revolutions,

or more if necessary, until the added water is uniformly mixed into the concrete.

Water shall not be added to the batch at any later time.

19. Conveying Concrete

Concrete shall be conveyed from mixer to forms as rapidly as possible and within

the time interval specified in paragraph 20.01 Concrete Placement by methods

which will prevent segregation or loss of ingredients.

A. Chutes: When concrete can be placed directly from a truck mixer or

other transporting equipment, chutes attached to this equipment may be used.

Separate chutes will not be permitted except when specifically approved.

B. Buckets: Bucket design shall be such that concrete of the required slump

can be readily discharged. Bucket gates shall be essentially grout tight when

closed. The bucket shall provide means for positive regulation of the amount

and rate of deposit of concrete in each dumping position.

C. Belt Conveyors: Belt conveyors may be used when approved. Belt

conveyors shall be designed for conveying concrete and shall be operated to

assure a uniform flow of concrete to the final place of deposit without

segregation or loss of mortar. Conveyors shall be provided with positive means

for preventing segregation of the concrete at transfer points and point of

placement.

Page 12: SECTION 03000-1 - Tech Specs 05-29-2015

D. Pumps: Concrete may be conveyed by positive displacement pumps

when approved. Pump shall be the piston or squeeze pressure type. Pipeline

shall be steel pipe or heavy duty flexible hose. Inside diameter of the pipe shall

be at least three times the maximum size of the coarse aggregate. Distance to

be pumped shall not exceed the limits recommended by the pump manufacturer.

Concrete shall be supplied to the pump continuously. When pumping is

completed, the concrete remaining in the pipeline shall be ejected without

contaminating the concrete in place. After each use, the equipment shall be

thoroughly cleaned. Flushing water shall be wasted outside the forms.

20. Concrete Placement

Mixed concrete which is transported in truck mixers or agitators or concrete

which is truck mixed, shall be discharged within 1 1/2 hours or before the drum

has revolved 300 revolutions, whichever comes first after the introduction of the

cement to the aggregates. These limitations may be waived by the Engineer if

the concrete is of such slump after the 1 1/2 hour time or 300 revolution limit

has been reached that it can be placed, without the addition of water to the

batch. When the concrete temperature exceeds 85°F, the time shall be reduced

to 45 minutes. Concrete shall be placed within 15 minutes after it has been

discharged from the truck.

A. Placing Operation: Concrete shall be handled from mixer to forms in a

continuous manner until the approved unit of operation is completed. Adequate

scaffolding, ramps, and walkways shall be provided so that personnel and

equipment are not supported by in-place reinforcement. Placing will not be

permitted when the sun, heat, wind, or limitations of facilities furnished by the

Contractor prevent proper consolidation, finishing and curing. Concrete shall be

deposited as close as possible to its final position in the forms, and there shall be

no vertical drop greater than eight (8) foot except where suitable equipment is

provided to prevent segregation and where specifically authorized. Depositing

of the concrete shall be so regulated that it will be effectively consolidated in

horizontal layers not more than 12" thick, except that all slabs shall be placed in

a single layer. Concrete to receive other construction shall be screeded to the

proper level to avoid excessive shimming or grouting.

B. Consolidation: Immediately after placing, each layer of concrete shall be

consolidated by internal vibrators, except for slabs four (4) inches or less. The

vibrators shall at all times be adequate in effectiveness and number to properly

consolidate the concrete; a spare vibrator shall be kept at the job site during all

concrete placing operations. The vibrators shall have a frequency of not less

than 8,000 vibrations per minute, and the head diameter and amplitude shall be

appropriate for the concrete mixture being placed. Vibrators shall be inserted

vertically at uniform spacing over the area of placement. The distance between

Page 13: SECTION 03000-1 - Tech Specs 05-29-2015

insertions shall be approximately 1 1/2 times the radius of action of the vibrator

so that the area being vibrated will overlap the adjacent just-vibrated area by a

few inches. The vibrator shall penetrate rapidly to the bottom of the layer and

at least six (6) inches into the preceding layer if there is such. Vibrator shall be

held stationary until the concrete is consolidated and then withdrawn slowly.

The use of form vibrators must be specifically approved. Vibrators shall not be

used to transport concrete within the forms. Slabs four (4) inches and less in

thickness shall be consolidated by properly designed vibrating screeds or other

approved technique. Excessive vibration of lightweight concrete resulting in

segregation and flotation of coarse aggregate shall be avoided.

C. Cold Weather Requirements: Special protection measures, approved by

the Engineer, shall be used if freezing temperatures are anticipated before the

expiration of the specified curing period. The ambient temperature of the air

where concrete is to be placed and the temperature of surfaces to receive

concrete shall be not less than 40°F. The temperature of the concrete when

placed shall be not less than 50°F, nor more than 75°F. Heating of the mixing

water or aggregates will be required to regulate the concrete placing

temperature. Materials entering the mixer shall be free from ice, snow, or

frozen lumps. Salt, chemicals or other materials shall not be incorporated in the

concrete to prevent freezing. Upon written approval, calcium chloride or

chemical admixture conforming to ASTM C494, Type C or E, may be used. The

amount of calcium chloride shall not exceed 2% by weight of the cement, and it

shall be batched in solution form. Calcium chloride shall not be used where

concrete will be in contact with aluminum of zinc-coated items, or where sulfate

resistant or prestressed concrete is specified.

21. Construction Joints

Construction joints shall be located as indicated or approved. Where concrete

work is interrupted by weather, end of work shift or other similar type of delay,

location and type of construction joint shall be subject to approval of the

Engineer. Unless otherwise indicated and except for slabs on grade, reinforcing

steel shall extend through construction joints. Construction joints in slabs on

grade shall be keyed or doweled as shown. Concrete columns, walls, or piers

shall be in place at least two (2) hours, or until the concrete is no longer plastic,

before placing concrete for beams, girders, or slabs thereon. In walls having

door or window openings, lifts shall terminate at such levels as to conform to

structural requirements or architectural details. Where horizontal construction

joints are required, a strip of one (1) inch square-edge lumer, bevelled and oiled

to facilitate removal, shall be tacked to the inside of the forms at the

construction joint. Concrete shall be placed to a point one (1) inch above the

underside of the strip. The strip shall be removed one (1) hour after the

concrete has been placed, and any irregularities in the joint line shall be leveled

Page 14: SECTION 03000-1 - Tech Specs 05-29-2015

off with a wood float, and all laitance shall be removed. Prior to placing

additional concrete, horizontal construction joints shall be prepared as specified

in paragraph PREPARATIONS OF SURFACES.

22. Finishing Concrete

A. Formed Surfaces

Repair of Surface Defects: For all finish classes (i.e. Classes A, B, C, and D),

surface defects shall be repaired within 24 hours after the removal of

forms. Honeycombed and other defective areas shall be cut back to solid

concrete or to a depth of not less than one (1) inch, whichever is greater.

Edges shall be cut perpendicular to the surface of the concrete. The

prepared areas shall be dampened and brush-coated with neat cement

grout. The repair shall be made using mortar consisting of not more than

1:2½, cement:sand. The mixed mortar shall be allowed to stand to stiffen

(approximately 45 minutes), during which time the mortar shall be

intermittently re-mixed without the addition of water. After the mortar

has attained the stiffest consistency that will permit placing, the patching

mix shall be thoroughly tamped into place by means approved by the

Engineer, and finished slightly higher than the surrounding surface. For

Class B finished surfaces the cement used in the patching mortar shall be

a blend of job cement and white cement proportioned to produce a

finished repair surface matching, after curing, the color of adjacent

surfaces. Holes left after the removal of form ties shall be cleaned and

filled with patching mortar. Holes lift by the removal of tie rods shall be

reamed and filled by dry-packing. Repaired surface shall be cured as

required for adjacent surfaces. The temperature of concrete, mortar

patching material, and ambient air shall be above 50° F white making

repairs and during the curing period. Concrete with defects which affect

the strength of the member or with excessive honeycombs will be

rejected, or the defects shall be corrected as directed.

B. Unformed Surfaces

1. Float Finish: Slabs to receive a steel towel finish and slabs, where

indicated shall be given a float finish. Screeding shall be followed

immediately by darbying or bull floating before bleeding water is present,

to bring the surface to a true, even plane. After the concrete has

stiffened to permit the operation and the water sheen has disappeared, it

shall be wood floated. Lightweight concrete of concrete that portrays

stickiness shall be finished with a magnesium float in lieu of a wood float,

and lift free of ridges and other projections.

Page 15: SECTION 03000-1 - Tech Specs 05-29-2015

2. Trowel Finish: Slabs, where indicated, shall be given a trowel finish

immediately following floating. Surfaces shall be troweled to produce

smooth, dense slabs free from blemishes including trowel marks. In lieu

of hand finishing, an approved power finishing machine may be used in

accordance with the directions of the machine manufacturer. A final

hard steel troweling shall be done by hand.

3. Broom Finish: After floating, slabs where indicated shall be lightly

troweled, and then broomed with a fiber-bristle brush in a direction

transverse to that of the main traffic.

C. Finish Schedule

Area Finish

Slabs and floors of structures or buildings

exposed to view. Slabs and floors of

below grade pits and vaults and

equipment pads.

Wall tops and exposed edges.

Exposed edges of slab and floors. Exterior

concrete slabs, drives, and sidewalks.

Light Broom

¾" Chamfer

Broom Finish

23. Curing and Protection

A. General: All concrete shall be cured by an approved method for the

period of time given below:

Concrete with Type I, II, IP or IS cement...........…........…...7 days

Concrete with Type I or Type II cement Blended with Pozzolan..7 days

Immediately after placement, concrete shall be protected from premature

drying extremes in temperatures, rapid temperature change, mechanical injury

and injury from rain and flowing water. Air and forms in contact with concrete

shall be maintained at a temperature above 50°F for the first three (3) days and

at a temperature above 32°F for the remainder of the specified curing period.

Exhaust fumes from combustion heating units shall be vented to the outside of

the enclosure and heaters and ducts shall be placed and directed so as not to

cause areas of overheating and drying of concrete surfaces or create fire hazards.

All materials and equipment needed for adequate curing and protection shall be

available and at the site prior to placing concrete. No fire or excessive heat shall

be permitted near or in direct contact with the concrete at any time. Curing

Page 16: SECTION 03000-1 - Tech Specs 05-29-2015

shall be accomplished by any of the following methods, or combination thereof,

as approved.

B. Moist Curing: Concrete to be moist-cured shall be maintained

continuously wet for the entire curing period. If water or curing materials used

stains or discolors concrete surfaces which are to be permanently exposed, the

concrete surfaces shall be cleaned. When wooden forms are left in place during

curing, they shall be kept wet at all times. If the forms are removed before the

end of the curing period, curing shall be carried out as on unformed surfaces,

using suitable materials. Horizontal surfaces shall be cured by ponding, by

covering with a 2" minimum thickness of continuously saturated sand, or by

covering with waterproof paper, polyethylene sheet, polyethylene-coated burlap

or saturated burlap.

C. Membrane Curing: Membrane curing shall not be used on surfaces that

are to receive any subsequent treatment depending on adhesion or bonding to

the concrete; except a styrene acrylate or chlorinated rubber compound meeting

ASTM C309, Class B requirements may be used for surfaces which are to be

painted or are to receive bituminous roofing or waterproofing, or floors that are

to receive adhesive applications of resilient flooring. The curing compound

selected shall be compatible with any subsequent paint, roofing, waterproofing

or flooring specified. Membrane curing compound shall not be used on surfaces

that are maintained at curing temperatures with free steam. Curing compound

shall be applied to formed surfaces immediately after the forms are removed

and prior to any patching or other surface treatment except the cleaning of loose

sand, mortar, and debris from the surface. Surfaces shall be thoroughly

moistened with water and the curing compound shall be applied to slab surfaces

as soon as the bleeding water has disappeared, with the tops of joints being

temporarily sealed to prevent entry of the compound and to prevent moisture

loss during the curing period. Compound shall be applied in a one-coat

continuous operation by mechanical spraying equipment, at a uniform coverage

in accordance with the manufacturer's printed instructions.

Concrete surfaces which have been subjected to rainfall with three hours after

curing compound has been applied shall be re-sprayed by the method and at the

coverage specified. On surfaces permanently exposed to view, the surface shall

be shaded from direct rays of the sun for the duration of the curing period.

Surfaces coated with curing compound shall be kept free of foot and vehicular

traffic, and from other sources of abrasion and contamination during the curing

period.

Page 17: SECTION 03000-1 - Tech Specs 05-29-2015

24.01 Concrete Reinforcing Steel

Contractor shall furnish and install, complete, reinforcing steel.

Submit detailed shop drawings for approval, showing placing drawing for steel

reinforcement, and bar bending details. Submit certified copy of mill test on

reinforcing steel showing physical and chemical analyses.

A. Deformed Billet-Steel Reinforcing Bars

ASTM A615, grade 60 reinforcing bars. Tie wires for reinforcement shall

be 16 gauge or heavier, black annealed wire.

B. Bar Supports and Spacers

Pre-cast concrete bar supports for reinforcing in concrete placed on

grade.

Plastic protected bar supports for beams and walls.

C. Installation

Bend all bars cold.

Notify the Engineer when reinforcing is ready for inspection and allow

sufficient time for this inspection prior to placing concrete.

Clean reinforcement of any loose mill scale, oil, or other contaminants.

Install in accordance with approved shop drawings.

Stagger splices in adjacent bars and tie every other intersection on mats

to hold bars at required spacing.

Minimum concrete cover of reinforcement shall be three (3) inches to

bottom reinforcing for slabs on grade, three (3) inches where concrete is

cast directly against earth, two (2) inches for all other reinforcing bars

including for beams and walls.

Lap splices for reinforcing steel shall be 48 bar diameters, but not less

than 12".

Unless permitted by the Engineer do not cut reinforcing bars in the field.

Page 18: SECTION 03000-1 - Tech Specs 05-29-2015

24. Concrete Patching

Patching material shall be certified by manufacturer, prior to use, that it contains

no corrosion causing chemicals.

Develop patching techniques and mixes with grout manufacturer. Dress surface

of patches that will remain exposed to view to match color and texture of

concrete.

Patching of concrete shall provide an acceptable and structurally sound surface

finish uniform in appearance until acceptable.

Patch all tie holes, defective concrete areas, honeycombed areas, and rock

pocket areas out to sound concrete with non-shrink, non-metallic grout. Use

approved bonding agent on horizontal patches prior to placing grout.

SECTION 3300-1 EARTHWORK

1. General

Provide labor and materials necessary to complete clearing, grubbing,

preparation of site, removal and disposal of all debris and unsuitable material,

excavation, trenching, backfill, preparation of subgrades, protection of adjacent

property, grading, and other work required to complete the earthwork indicated

on the plans.

2. Surface Preparation

All areas to be occupied by permanent construction or fill areas shall be cleared

of all trees, roots, brush, and other objectionable materials and debris. All

stumps shall be grubbed. Subgrades shall be cleaned and stripped of all surface

vegetation, sod, or organic topsoil. All waste materials shall be properly disposed

of by the CONTRACTOR.

3. Excavation

Excavation shall provide adequate working space and clearances for the work to

be performed. Excavation and trenching shall include the removal and handling

of materials excavated or removed.

Page 19: SECTION 03000-1 - Tech Specs 05-29-2015

4. Preservation of Trees

No trees shall be removed outside excavated or filled areas unless their removal

is authorized by the OWNER. Trees left standing shall be adequately protected

from damage by construction activities.

5. Dewatering

Dewatering equipment shall be provided to remove and dispose of all surface

water entering excavations, trenches, or other areas of the work.

6. Sheeting and Shoring

Excavations and trenches shall be supported or sloped as necessary to prevent

caving or sliding.

7. Drainage Maintenance

Install silt fences, hay bales, and other protective measures to prevent sediment

from washing out on roadways and existing drainage structures.

SECTION 3400-1 STRUCTURAL STEEL, MISCELLANEOUS METALS, AND GRATINGS

1. General

Furnish all labor, materials, equipment, and incidentals required to install

structural steel, aluminum items, anchors, fasteners, and other miscellaneous

metal items as shown on the drawings and specified herein.

2. Coordination

The work of this section shall be completely coordinated with the work of other

sections. Verify at the site, both the dimensions, and work of other trades

adjoining items of work in this section before fabrication and installation of items

herein specified.

Furnish to the pertinent trades, all items included under this section that are to

be built into the work of other sections.

3. Shop Drawings and Samples

Detailed fabrication and erection drawings, as provided for in the General

Conditions, showing sizes of members, methods of assembly, anchorage, and

Page 20: SECTION 03000-1 - Tech Specs 05-29-2015

connection to other members shall be submitted to ENGINEER for review before

fabrication.

Samples shall be submitted at the request of ENGINEER for concurrent review

with shop drawings.

4. Field Measurements

Field measurements shall be taken at the site prior to shop drawing submittal

and fabrication to verify or supplement indicated dimensions and to ensure

proper fitting of all items. Items rejected due to improper fit shall be replaced at

no additional cost to CITY.

5. Reference Specifications

Unless otherwise specified, materials shall conform to the following:

Aluminum (Extruded Shapes)

Aluminum (Extruded Pipe)

Aluminum Bars (Structural)

Stainless Steel Bolts, Fasteners

Stainless Steel Plate & Sheet, Wire

6063 T5 (Aluminum alloy)

6063 T6 (Aluminum alloy)

6061 T6 (Aluminum alloy)

AISI, Type 316

AISI, Type 316

6. Structural Steel

A. Materials shall be stainless steel as specified on the contract plans.

B. The design, fabrication, and erection of all structural stainless steel work shall

be subject to the latest editions of the published standards listed hereinafter

as they apply:

1. Latest editions of the American Institute of Steel Construction (AISC)

Specifications for the Design, Fabrication, and Erection of Structural

Steel for Buildings.

2. AISC Code of Standard Practice.

3. American Welding Society, Structural Welding Code, AWS D1.1.

4. Standard Building Code.

5. Local Codes and Regulations.

6. In case of a conflict between the referenced specification and the

project specification, the more stringent specification shall govern.

A. All welding in shop and field shall be performed by welders certified in

accordance with the provisions of American Welding Society D1.1.

Page 21: SECTION 03000-1 - Tech Specs 05-29-2015

Qualification test reports, bearing witness certification of an independent

laboratory or inspection service shall be submitted to ENGINEER. If a welder

is not engaged in the process of welding for a period of three (3) or more

months, welder shall be re-qualified before permitted to weld. Welding shall

be in accordance with the Structural Welding Requirements of the AWS D1.1-

84 and shall only be done where shown, or specified. Welding terms shall be

interpreted in accordance with AWS 24-79 Standard of the AWS. All welding

shall be done only by certified welders using approved welding procedures

and proper safety and welding equipment.

7. Aluminum Items

Aluminum items shall be sized to meet load and deflection requirements and

shall be Reliance Steel Products Company, McNichols, Diamondback, IKG

Industries, Alloy 6061-T6, or equal. Clamps and bolts used for attaching

aluminum to supporting members shall be stainless steel. Hardware shall be as

recommended by the manufacturer.

8. Anchors, Bolts, and Fastening Devices

A. Anchors, bolts, etc., shall be furnished as necessary for installation of the

work of this section. Unless otherwise indicated, use stainless steel for all

anchors, bolts, and other fastening devices.

B. Compound masonry anchors shall be of the type shown or required and shall

be equal to Star Slug in compounded masonry anchors manufactured by Star

Expansion Industries, equal by Phillips Drill Co., Rahlplug, or equal. Anchors

shall be minimum "two-unit" type.

C. Unless otherwise noted, expansion bolts shall be Wej-it "Ankr-Tite", Phillips

Drill Co., "Wedge Anchors", Hilti "Kwik-Bolt", or equal. When the length of

bolt is not called for on the Drawings, the length of bolt provided shall be

sufficient to place the wedge portion of the bolt a minimum of 1" behind the

reinforcing steel within the concrete. Material shall be as noted on the

Drawings. If not listed, use stainless steel.

D. All anchors, bolts, and fastening devices shall be stainless steel when

contacting aluminum.

9. Access Hatches

Access hatches shall be provided for all openings in the top slab for the wet well.

Each hatch shall include an access frame complete with hinge and slide bar

equipped covers. Each wet well hatch frame and cover shall be constructed of

Page 22: SECTION 03000-1 - Tech Specs 05-29-2015

aluminum and designed for a live load of 300 pounds per square foot. Hatches

shall be watertight. Hatch doors shall be of aluminum check plate with

reinforcing ribs to meet design criteria. All hardware shall be stainless steel.

Hatches shall be as manufactured by Halliday Products, Bilco Company, or equal.

10. Installation

A. Unless otherwise specified, structural stainless steel shall be fabricated in

accordance with the requirement of the AISC Specifications for the Design,

Fabrication, and Erection of Structural Steel for Buildings. All members shall

fit closely together and shall be straight and true, and the finished work shall

be free from burrs, bends, twists, and open joints. Materials for welding shall

be of the best available and in accordance with the recommendations of the

manufacturer of the material to be welded.

B. Structural Stainless Steel Installation Tolerances: Erect individual pieces so

that the deviation from plumb, level, and alignment shall not exceed 1:500. If

tolerances required by equipment manufacturers or referenced standards

are stricter than the above, then the strictest tolerance shall govern.

C. All miscellaneous metal work shall be formed true to detail, with clean,

straight, sharply defined profiles and smooth surfaces of uniform color and

texture and free from defects impairing strength of durability.

D. All stainless steel surfaces to come in contact with exposed concrete or

masonry shall receive protective coating of an approved heavy bitumastic

trowelling mastic applied in accordance with the manufacturer's instructions

prior to installation.

E. Where aluminum contacts a dissimilar metal, apply a heavy brush coat of

zinc-chromate primer followed by two coats of aluminum metal and masonry

paint to the dissimilar metal.

F. Where aluminum contacts masonry or concrete, apply a heavy coat of

approved alkali resistant paint to the masonry or concrete.

G. Assembly and installation shall be in accordance with manufacturer’s written

recommendations.

Page 23: SECTION 03000-1 - Tech Specs 05-29-2015

SECTION 3500-1 ALUMINUM FENCING

PART - 1 - GENERAL

1.01 SCOPE OF WORK:

Provide all labor, materials, equipment and supervision necessary to

complete the installation of:

Aluminum Fence;

Aluminum Gate(s);

Excavation and backfill of support posts;

Concrete anchoring of posts;

And other accessories and equipment

as specified herein or illustrated on the Drawings.

1.02 RELATED SECTIONS:

Section 03300 - Cast In Place Concrete

1.03 SCOPE:

Furnish all tools, equipment, materials, machinery, appurtenances and

labor unless otherwise specified to clear and grub for, excavate for, erect

and install fence posts, extra length posts, aluminum fence sections and

components, Aluminum gate(s), corner posts, hardware, and all

accessories along the lines shown on or reasonably inferred from the

drawings. If any items for a complete job are omitted or not shown, the

Contractor shall furnish and install the same without cost to the Owner.

1.04 REFERENCES:

A. Aluminum Association (AA)

(1) ASD-1 – Aluminum Standards and Design

(2) DAF-45 – Designation System for Aluminum Finishes

B. American Society for Testing and Materials (ASTM)

(1) ASTM A 276 – Standard Specification for Stainless Steel Bars and

Shapes.

(2) ASTM B 117 – Standard Practice for Operating Salt Spray (Fog)

Apparatus.

Page 24: SECTION 03000-1 - Tech Specs 05-29-2015

(3) ASTM B 221 – Specification for Aluminum-Alloy Extruded Bars,

Rods, Wire Shapes and Tubes.

(4) ASTM B 429 – Specification for Aluminum-Alloy Extruded

Structural Pipe and Tube.

(5) ASTM D 523 – Standard Test Method for Specular Gloss.

(6) ASTM D 1654 – Standard Test Method for Evaluation of Painted or

Coated Specimens Subjected to Corrosive Environments.

(7) ASTM D 2247 – Standard Practice for Testing Water Resistance of

Coatings in 100% Relative Humidity.

(8) ASTM D 2794 – Impact Resistance Test (Rating up to 160 inch lbs.)

(9) ASTM D 3359B – Adhesion by Tape Test (Rating = 5B)

(10) ASTM D 3363 – Film Hardness by Pencil Test (Rating = 2H)

(11) ASTM D 968 – Abrasion Resistance.

C. American Architectural Manufacturers Association (AAMA)

(1) AAMA 2605 – Voluntary Specification, Performance

Requirements and Test Procedures for Superior Performing

Organic Coatings on Aluminum Extrusions and Panels

(2) AAMA 2604 – Voluntary Specification, Performance

Requirements and Test Procedures for Pigmented Organic

Coatings on Aluminum Extrusions and Panels

1.05 SUBMITTALS:

A. Submit under requirements of Section 01 300.

B. Manufacturer's data sheets on each product to be used, including:

1. Preparation instructions and recommendations.

2. Storage and handling requirements and

recommendations.

3. Installation methods.

C. Shop Drawings: Indicate plan layout, spacing of components, post

foundation dimensions, hardware anchorage, gates, and schedule of

components.

D. Selection Samples: For each finish product specified, two complete

sets of color chips representing manufacturer's full range of available

Page 25: SECTION 03000-1 - Tech Specs 05-29-2015

colors and patterns.

E. Verification Samples: For each finish product specified, two samples,

minimum size 6 inches (150 mm) square; representing actual product,

color, and patterns.

1.06 QUALITY ASSURANCE:

A. Manufacturer Qualifications: Company specializing in manufacturing

Products specified in this section with minimum five years

documented experience.

1.07 DELIVERY, STORAGE, AND HANDLING:

A.Transport, handle, store, and protect products so that they are in

undamaged condition when installed.

B. Store products in manufacturer's unopened packaging to protect

prefinished aluminum surfaces until ready for installation.

C. Store components off the ground in a dry covered area, protected

from adverse weather conditions.

1.08 PROJECT CONDITIONS:

A. Maintain environmental conditions (temperature, humidity, and

ventilation) within limits recommended by manufacturer for optimum

results. Do not install products under environmental conditions

outside manufacturer's absolute limits.

1.09 WARRANTY:

A. Manufacturer's Warranty:

1. Fence manufacturer shall provide Aluminum Fencing lifetime-

limited warranty (“warranty”) against defects in workmanship.

Manufacturer shall also warrant the powder coated finish will not

chip, crack, or flake. The warranty may not be transferable and

may only be valid to the original purchaser. The warranty on

commercial installations of fences that are purchased by other

than a natural person, shall be limited to a period of thirty (30)

years.

PART - 2 - PRODUCTS

2.01 MANUFACTURERS:

A. Acceptable Manufacturer: Alumi-Guard, Inc., Brooksville, FL 34604;

Ameristar Fence Products, Tulsa, OK 74158; Stevens Pipe & Steel,

Page 26: SECTION 03000-1 - Tech Specs 05-29-2015

LLC Melborne, FL 32904

B. Substitutions: With Owner and Engineer approval only.

C. Requests for substitutions will be considered in accordance with

Special Provisions Section 00800.

2.02 MATERIALS:

A. Components:

1. Posts: Aluminum extrusions of 6005-T5 alloy in accordance

with ASTM B 221.

2. Pickets: Aluminum extrusions of 6063-T52 alloy in

accordance with ASTM B 221.

3. Channel: Aluminum extrusions of 6005-T5 alloy in

accordance with ASTM B 221.

B. Fasteners:

1. Screws of 410 and 18-8 stainless steel conforming to ASTM

A276, with self-drilling head.

2. Screws painted to match the finish of fence.

C. Accessories:

1. Post caps, wall brackets, scrolls, finials, flanges and other

miscellaneous hardware fabricated of aluminum or other

non-ferrous metal castings.

D. Concrete: Types specified in Sections 03300 – Cast-in Place Concrete.

E. Concrete: ASTM C94/C94M, Option A; Portland Cement; minimum

3,000 psi (17 MPa) strength at 28 days.

2.03 ORNAMENTAL FENCING:

A. Fencing General:

1. Municipal Grade:

a. Aluminum Channel Sections: 1-1/2 inch deep and 1 inch

wide with top 0.055 inch and sidewalls 0.082 inch wall

thickness. With decorative top corner.

b. Pickets 3/4 inch by 3/4 inch with a 0.050 inch wall

thickness.

2. Post Length:

a. As required to allow setting of post into the ground with

approximately 1-3/4 inches (305 mm) between bottom of

panel and ground.

B. Ornamental Fencing:

Page 27: SECTION 03000-1 - Tech Specs 05-29-2015

1. Style: Flat top rail and bottom rail, flush

a. Grade:

1) Municipal.

b. Channels:

1) 3 Channel.

c. Municipal Picket:

1) Standard: 3.875 inches spacing.

2) 0.75” x 0.75” x .05” wall thickness.

d. Panel Length: Inside posts.

1) Municipal Nominal 91.75 inches

e. Line Posts:

1) 2-1/2 inches by 2-1/2 inches.

2) 0.075 inch wall thickness.

f. Gate Post:

1) 4 inches by 4 inches.

2) 0.125 inch wall thickness.

g. Panel Height:

1) 72 inches.

C. Ornamental Gates: Provide to match ornamental style specified.

1. Height:

a. 72 inches.

2. Opening Width: Inside posts.

a. Nominal size opening as shown on construction plans to

conform to gate and accessory installation.

3. Hardware: Shall be furnished as noted or listed on the plans and

consist of one or more of the following accessory components:

a. Self-Closing Hinges.

b. Gravity Latch.

c. Lock bolt for one leaf of double gates.

d. Single Hole Lock Box.

e. Double Hole Lock Box.

f. Magna-Latch.

2.04 FINISH:

A. Fence and Accessory Finish:

1. SuperDurable Polyester Powder Coating: High performance

polyester, medium gloss, applied to over 2 mils thickness and

complying with AAMA 2604.

2. Fluoropolymers: Superior performance polyester power coating,

medium gloss, applied to 3-4 mils thickness and complying with

AAMA 2605.

Page 28: SECTION 03000-1 - Tech Specs 05-29-2015

B. Color: Color shall be dark bronze unless otherwise specified and

noted on the plans. Manufacturer shall be capable of providing the

following colors if specified by Owner:

1. Black

2. White

3. Dark Bronze

4. Hunter Green

5. Beige

6. Light Bronze

7. Gray

C. Performance:

1. Meet or exceed a 4000 hour salt spray test.

2. SuperDurable: Polyester Powder Coating: High performance

polyester, medium gloss, applied to over 2 mils thickness and

complying with AAMA 2604.

3. Fluoropolymers: Superior performance polyester power coating,

medium gloss, applied to 3-4 mils thickness and complying with

AAMA 2605.

4. Meets or exceeds ASTM D 3359 adhesion test.

2.05 FABRICATION:

A. Stringers, (Horizontal rails) shall be punched to allow pickets to

pass through the top of the rail. The number of stringers shall vary

with the style, height and strength as determined by manufacturer.

B. Pickets, shall be fastened to stringers mechanically with stainless

steel TEK screws on one side of the stringer only.

C. Posts, shall be pre-punched to allow the stringers to slide in and be

attached with stainless steel TEK. Cast aluminum post caps shall be

affixed to all posts.

D. Gates, shall be fabricated using the same components as for the

complete fencing system. Walk gates shall have adjustable self-

closing hinges and will be self-latching.

E. Assembled 3-Channel 72” high fence panels/sections shall support

a min. vertical load of 270 lbs. at midspan. 36” high sections shall

support a min. vertical load of 500 lbs. at midspan.

Page 29: SECTION 03000-1 - Tech Specs 05-29-2015

PART - 3 - EXECUTION

3.01 LINE AND GRADE:

Contractor shall stakeout accurate location of posts, corners and angles

prior to installation and following the finish grading operation.

3.02 EXAMINATION:

A. Do not begin installation until substrates have been properly

prepared.

B. If substrate preparation is the responsibility of another installer,

notify Architect of unsatisfactory preparation before proceeding.

3.03 PREPARATION:

A. Clean surfaces thoroughly prior to installation.

B. Prepare the grade and remove surface irregularities, if any, which

may cause interference with the installation of aluminum fence.

C. If preparation and condition is the responsibility of another

installer, notify Architect of unsatisfactory preparation before

proceeding.

3.04 INSTALLATION:

A. Install in accordance with manufacturer's instructions.

B. Excavate holes for posts to diameter and spacing indicated on

Drawings without disturbing underlying materials.

C. Provide excavation for post length to suit local conditions for

proper anchorage and stability.

D. Center and align posts in excavated holes to required depth. Place

concrete around posts, and vibrate or tamp for consolidation. Re-

check vertical and top alignment of posts, verify they are plumb

and level. Make necessary corrections if needed before concrete

hardens.

E. If fence is deck mounted on existing hard surfaces. Set posts

plumb, to tolerances specified. Locate mounting locations prior to

start of work. Avoid mounting over expansion or control joints.

Use non-corrosive fasteners suitable for the material to which it is

to be mounted.

Page 30: SECTION 03000-1 - Tech Specs 05-29-2015

F. Insert notched stringers into pre-punched posts and fasten with

stainless steel TEK screws.

G. Support gates from gate posts. Do not attach hinged side of gate

from building wall.

H. Provide concrete center drop for drop rod retainers at center of

double gate openings.

I. Install gates plumb, level and secure for full opening without

interference. For double gates, install drop rod. Adjust all

hardware for smooth operation.

3.05 ERECTION TOLERANCES:

A. Maximum Variation From Plumb: 1/4 inch.

B. Maximum Offset From Indicated Position: 1 inch.

C. Minimum distance from property line: 6 inches.

3.06 CLEANING:

A. Leave immediate work area neat at end of each work day.

B. Clean jobsite of excess materials; scatter excess material from

post hole excavations uniformly away from posts. Remove excess

material if required.

C. Clean aluminum fence with mild household detergent and clean

water rinse well. Mortar should be removed from exposed posts

and other fencing material using a 10% solution of muriatic acid

followed immediately by several rinses with clean water.

D. Touch up scratched surfaces using materials recommended by

manufacturer. Match touchup paint color to fence finish.

3.07 PROTECTION:

A. Protect installed products until completion of project.

B. Touch-up, repair or replace damaged products before Substantial

Completion.

3.03 GATES:

Page 31: SECTION 03000-1 - Tech Specs 05-29-2015

Gates shall be swing, single or double, as noted on the drawings. They

shall be complete with latches, stops, keepers, hinges, and braces. The

latch assembly shall be capable of being locked with a padlock.

SECTION 3550-1 HDPE LINER

PART 1 - GENERAL

1.01 SCOPE OF WORK:

Furnish and install a flexible membrane lining as shown on engineering or

contractor supplied drawings. All work shall be done in strict accordance

with the drawings and related specifications and the membrane lining

manufacturer's recommendations.

It is the intent of these specifications to insure a quality finished product

as described on the plans and specifications and shall be the

responsibility of the contractor to take whatever measures shall be

deemed necessary to insure that this requirement shall have been met.

All interested governmental agencies shall provide inspection services

throughout the installation procedure or provide written acceptance of

the installation after final inspection.

1.02 APPLICABLE SECTIONS:

3200-1 Earthwork

1.03 SUBMITTALS:

Six (6) copies of all submittal documentation is required for approval prior

to construction.

Certified test results showing that the liner sheeting meets or exceeds the

specification are required.

1. List of material properties.

2. Copy of quality control certificates issued by the resin supplier

stating that the resin meets the specification requirements.

3. Copy of quality control certificates for the geomembrane

including a Statement certifying no recycled polymer and no more

Page 32: SECTION 03000-1 - Tech Specs 05-29-2015

than 10% rework of the same type of material is added to the

resin (product run may be recycled).

The CONTRACTOR/INSTALLER shall furnish the following information to

the ENGINEER and OWNER for approval/acceptance prior to installation:

1. Installation layout drawings

a. Must show proposed panel layout including field seams and

details.

b. Must be approved prior to installing the geomembrane

2. Approved drawings will be for concept only and actual panel

placement will be determined by site conditions.

3. Installer’s Geosynthetic Field Installation Quality Assurance Plan

Pre installation submittals may be requested from CONTRACTOR /

INSTALLER at ENGINEER or Owners option for the following

documentation:

A list of completed facilities, totaling a minimum of 2,000,000

square feet for which the installer has installed polyethylene

geomembrane. For each installation, the following information

shall be provided:

a. Name and purpose of facility, location, and date of installation.

b. Name of owner, design engineer, manufacturer, and name

and telephone number of contact at the facility who can

discuss the project.

c. Thickness and quantity of the installed geomembrane.

d. Resume of the field installation supervisor and master seamer.

Upon completion of all geomembrane installation the CONTRACTOR /

INSTALLER shall submit the following documentation to the ENGINEER

prior to final acceptance of installation:

1. Certificate stating the geomembrane has been installed in

accordance with the Contract Documents.

2. Original and 5 copies of all Material and installation warranties.

Page 33: SECTION 03000-1 - Tech Specs 05-29-2015

3. As-built drawings showing actual geomembrane placement and

seams including typical anchor trench detail.

4. Copy of seam testing report and results.

1.04 QUALIFICATION OF CONTRACTOR WORK ACTIVITIES:

A. Manufacturing : The manufacturer shall have at least five (5) years

continuous experience in the manufacture of polyethylene

geomembrane and/or experience totaling 10,000,000 square feet

of manufactured polyethylene geomembrane. Membrane shall be

manufactured by GSE Lining Technology, Inc, Agru America,

Solmax International, or approved equal.

B. Installation : The installation contractor shall be the manufacturer

or a dealer trained to install the manufacturer's geomembrane.

Installation shall be performed under the constant direction of a

field installation supervisor who shall remain on site and be

responsible, throughout the liner installation, for liner layout,

seaming, testing, repairs, and all other activities by the Installer.

The field installation supervisor shall have installed or supervised

the installation of a minimum of 2,000,000 square feet of

polyethylene geomembrane and be certified by the liner

manufacturer. Seaming shall be performed under the direction of

a master seamer (who may also be the field installation supervisor)

who has seamed a minimum of 2,000,000 square feet of

polyethylene geomembrane, using the same type of seaming

apparatus specified for this project. The field installation

supervisor and/or master seamer shall be present whenever

seaming is performed.

1.05 WARRANTY:

A written Warranty shall be obtained from the manufacturer (for all

material) and the installation contractor (for workmanship). These

documents shall warrant both the quality of the material and

workmanship for a specified duration of time. The Contractor shall

warrant all labor for a minimum of 2 years. The manufacturer shall

provide a written warrant for the material for a minimum of 15 years.

Material shall be warranted, on a pro-rata basis against Manufacturer’s

defects for a specified 15 year period from the date of geomembrane

installation.

Page 34: SECTION 03000-1 - Tech Specs 05-29-2015

PART 2 - PRODUCTS

2.01 DESCRIPTION OF LINING MATERIALS:

1. The geomembrane shall be High-Density Polyethylene (HDPE) or

Linear Low Density Polyethylene (LLDPE).

2. Gasket material shall be neoprene, closed cell medium, 1/4 inch thick,

2 inches wide with adhesive on one side, as supplied by Poly-Flex, Inc.,

or other compatible gasket materials as required

3. Metal battens or banding and hardware shall be stainless steel.

4. Water cut-off mastic shall be Neoprene Flashing Cement as supplied

by Poly-Flex, Inc., or as required.

5. Sealant shall be General Electric Silicone, RTV 103, or equivalent.

2.02 GEOMEMBRANE RAW MATERIALS:

The geomembrane shall be manufactured of polyethylene resins

produced in the United States and shall be compounded and

manufactured specifically for the intended purpose. The resin

manufacturer shall certify each lot for the following properties.

The natural polyethylene resin without the carbon black shall meet the

following requirements:

Property Test Method HDPE

Requirements

LLDPE (VFPE)

Requirements

Density, g/cc ASTM D 1505 or ASTM D 792 0.935 - 0.940 0.915 - 0926

Melt Index, g/10 min. ASTM D 1238 Condition E < 0.4 < 0.6

2.03 ROLLS:

The geomembrane shall be a minimum 22.0 ft seamless width. Carbon

black shall be added to the resin if the resin is not compounded for ultra-

violet resistance. Do not exceed a combined maximum total of 1 percent

by weight of additives other than carbon black.

Geomembrane shall be free of holes, pinholes as verified by on-line

electrical detection, bubbles, blisters, excessive contamination by foreign

matter, and nicks and cuts on roll edges.

All liner sheets produced at the factory shall be inspected prior to

shipment for compliance with the physical property requirements listed.

Page 35: SECTION 03000-1 - Tech Specs 05-29-2015

Extrudate Rod or Bead;

1. Extrudate material shall be made from same type resin as the

geomembrane.

2. Additives shall be thoroughly dispersed.

3. Materials shall be free of contamination by moisture or foreign matter.

Page 36: SECTION 03000-1 - Tech Specs 05-29-2015

SMOOTH HDPE GEOMEMBRANE

TESTED PROPERTY TEST METHOD FREQUENCY MINIMUM AVERAGE VALUE

30 mil 40 mil 60 mil 80 mil 100 mil

Thickness, (minimum

average) mil (mm) Lowest

individual reading (-10%)

ASTM D 5199

every roll 30

(0.75)

27

40

(1.00)

36

60

(1.50)

54

80

(2.00)

72

100

(2.50) 90

(2.30) Density, g/cm3 ASTM D 1505 200,000 0.94 0.94 0.94 0.94 0.94

Tensile Properties (each

direction) Strength at

Break, lb/in-width (N/mm)

Strength at Yield, lb/in-

ASTM D 6693,

Type IV

Dumbell, 2 ipm

20,000

lb 120 (21)

66 (11)

700

152

(26)

84 (14)

243 (42)

132 (23)

700

327 (57)

177 (30)

700

410 (71)

212 (37)

700 Tear Resistance, lb (N) ASTM D 1004 45,000 lb 21 (93) 28 42 58 73 (324)

Puncture Resistance, lb (N) ASTM D 4833 45,000 lb 65 85 125 160 195 (867) Carbon Black Content, %

(Range)

ASTM D 1

603*/421 8

20,000 lb 2.0 -

3.0

2.0 - 3.0 2.0 -

3.0

2.0 -

3.0

2.0 - 3.0

Carbon Black Dispersion ASTM D 5596 45,000 lb Note(1)

Note(1)

Note(1)

Note(1)

Note(1)

Notched Constant Tensile

Load, hr

ASTM D 5397,

Appendix

200,000

lb

1000 1000 1000 1000 1000

Oxidative Induction Time, min ASTM D 3895,

200°C; O2, 1

200,000

lb

>140

>140

>140

>140

>140

TYPICAL ROLL DIMENSIONS

Roll Length(2)

, ft (m) 1,120

(341)

870

(265)

560

(171)

430

(131) 340 (104)

Roll Width(2)

, ft (m) 22.5 (6.9) 22.5

(6.9)

22.5

(6.9)

22.5

(6.9) 22.5 (6.9)

Roll Area, ft2 (m

2) 25,20

0

19,575

(1,819

12,60

0

9,67

5

7,650

(711)

NOTES:

• (1)

Dispersion only applies to near spherical agglomerates. 9 of 10 views shall be

Category 1 or 2. No more than 1 view from Category 3.

• (2)

Roll lengths and widths have a tolerance of ± 1%.

Page 37: SECTION 03000-1 - Tech Specs 05-29-2015

TEXTURED HDPE GEOMEMBRANE

NOTES:

• (1)

Dispersion only applies to near spherical agglomerates. 9 of 10 views

shall be Category 1 or 2. No more than 1 view from Category 3.

• (2)

NCTL for GSE I-ID Textured is conducted on representative smooth

membrane samples.

• (3)

Roll lengths and widths have a tolerance of ± 1%.

TESTED PROPERTY TEST METHOD FREQUENCY MINIMUM AVERAGE VALUE

Thickness, (minimum

average) mil (mm) Lowest

ASTM D 5994

every roll 30

(0.75)

40

(1.00)

60

(1.50)

80

(2.00)

100

(2.50) Density, g/cm

3 ASTM D 1505 200,000 lb 0.94 0.94 0.94 0.94 0.94

Tensile Properties (each

direction) Strength at

Break, lb/in-width

(N/mm) Strength at Yield,

ASTM D 6693, Type

IV Dumbell, 2 ipm

G.L. 2.0 in (51 mm)

20,000 lb 66 (11)

68 (11)

100

75

(13)

90

115 (20)

132 (23)

100

155 (27)

177 (31)

100

230 (40)

225 (39)

100

Tear Resistance, lb (N) ASTM D 1004 45,000 lb 24 (106) 32 (142) 45 (200) 60 (266) 75 (333)

Puncture Resistance, lb (N) ASTM D 4833 45,000 lb 65 (289) 95 (422) 130 160 190

Carbon Black Content, % ASTM D 1 20,000 lb 2.0 - 3.0 2.0 - 3.0 2.0 - 3.0 2.0 - 3.0 2.0 - 3.0

Carbon Black Dispersion ASTM D 5596 45,000 lb Note(1)

Note(1)

Note(1)

Note(1)

Note(1)

Asperity Height, mil (mm) ASTM D 7466 second roll 16 (0.40) 18

(0.45)

18

(0.45)

18

(0.45)

18 (0.45)

Notched Constant Tensile

Load(2)

, hr

ASTM D 5397,

Appendix

200,000 lb 1000 1000 1000 1000 1000

Oxidative Induction Time,

min ASTM D 3895, 200°

C; O , 1 atm

200,000 lb >140 >140 >140 >140 >140

TYPICAL ROLL DIMENSIONS

Roll Length(3)

, ft (m) Double-Sided Textured

Single-Sided Textured

830

(253)

700

(213)

520

(158)

400

(122)

330 (101)

250 (76) Roll Width

(3), ft (m) 22.5

(6.9)

22.5

(6.9)

22.5

(6.9)

22.5

(6.9)

22.5

(6.9) Roll Area, ft2 (m

2) Double-Sided

Textured

18,675

(1,735)

18,900

15,750

(1,463)

14,625

11,700

(1,087)

9,450

9,000

(836)

7,200

7,425

(690)

5,625

Page 38: SECTION 03000-1 - Tech Specs 05-29-2015

PART 3 - EXECUTION

3.01 MATERIAL PACKAGING, LABELING, DELIVERY, STORGAE AND HANDLING:

A. Packaging and Labeling - HDPE geomembrane material shall be packed

around a core in roll form. The core on which the rolls of geomembrane

are wound shall be at least 6.0 inches in diameter. The core should have

sufficient inside diameter such that fork lift stingers can be used for

lifting and movement. The cores should be sufficiently strong that the

roll should not cause buckling of the cores nor flattening of the rolls.

Each roll of geomembrane delivered to the site shall be labeled by the

MANUFACTURER. The label will identify:

1. manufacturer’s name

2. product identification

3. thickness

4. roll dimensions (length & width)

5. date manufactured

6. roll number

B. Delivery- Rolls of liner will be prepared to ship by appropriate means

to prevent damage to the material and to facilitate off-loading.

C. Storage- The on-site storage location for geomembrane material

acceptable to Owner and provided by the CONTRACTOR, shall protect

the geomembrane from punctures, abrasions and excessive dirt and

moisture and should have the following characteristics:

1. level (no wooden pallets)

2. smooth

3. dry

4. protected from theft and vandalism

5. adjacent to the area being lined

D. Handling- Materials are to be handled so as to prevent damage.

3.02 INSTALLATION:

Installation shall be performed by an authorized Installation Contractor who

has previously installed a minimum 2,000,000 sq. ft. of this material or by a

Contractor who has a full-time, on-site representative of the fabricator to

monitor the installation. The surface (substrate) to receive the liner shall be

smooth and free of sharp objects that could puncture the lining. All

vegetation must be removed. A soil sterilant may be required at the

discretion of the Engineer. The geomembrane lining shall be placed over

the prepared surfaces to be lined in such a manner as to assure minimum

Page 39: SECTION 03000-1 - Tech Specs 05-29-2015

handling. The panels shall be placed in such a manner as to minimize field

seaming. Horizontal field seams on slopes shall be kept to a minimum.

The membrane shall be sealed to all concrete structures and other openings

through the lining in accordance with details shown on the construction

drawings submitted by the Contractor, approved by the Engineer and the

manufacturer. Factory fabricated pipe seals shall be used to seal all pipes

penetrating the liner. Any portion of the lining damaged during installation

shall be removed or repaired by using an additional piece of membrane as

specified herein. The liner shall be installed in a relaxed condition and shall

be free of stress or tension upon completion of the installation. Stretching

the liner to fit is not permissible.

3.03 DEPLOYMENT:

A. Assign each panel a simple and logical identifying code. The coding

system shall be subject to approval and shall be determined at the job

site.

B. Visually inspect the geomembrane during deployment for

imperfections and mark faulty or suspect areas.

C. Deployment of geomembrane panels shall be performed in a manner

that will comply with the following guidelines:

1. Geomembranes shall be installed according to site-specific

specifications.

2. Unroll geomembrane using methods that will not damage

geomembrane and will protect underlying surface from damage

(spreader bar, protected equipment bucket).

3. Place ballast (commonly sandbags) on geomembrane which will

not damage geomembrane to prevent wind uplift.

4. Personnel walking on geomembrane shall not engage in activities

or wear shoes that could damage it. Smoking will not be

permitted on the geomembrane.

5. Do not allow heavy vehicular traffic directly on geomembrane.

Rubber-tired ATV’s and trucks are acceptable if wheel contact is

less than 8 psi.

6. Protect geomembrane in areas of heavy traffic by placing

protective cover over the geomembrane.

D. Sufficient material (slack) shall be provided to allow for thermal

expansion and contraction of the material.

Page 40: SECTION 03000-1 - Tech Specs 05-29-2015

3.04 FIELD SEAMING:

Approved seaming processes are fusion and extrusion welding. On side

slopes, seams shall be oriented in the general direction of maximum

slope, i.e., oriented down, not across the slope. In corners and odd-

shaped geometric locations, the number of field seams shall be

minimized.

No base T-seam shall be closer than 5 feet from the toe of the slope.

Seams shall be aligned with the least possible number of wrinkles and

"fishmouths". If a fishmouth or wrinkle is found, it shall be relieved and

cap-stripped.

A. Seam Overlap

Geomembrane panels must have a finished minimum overlap of 4

inches for fusion welding and 6 inches for extrusion welding. Cleaning

solvents may not be used unless the product is approved by the liner

manufacturer.

B. Seaming Equipment and Accessories

Welding equipment and accessories shall meet the following

requirements:

1. Gauges showing temperatures in apparatus such as extrusion

welder or fusion welder shall be present.

2. An adequate number of welding apparatus shall be available to

avoid delaying work.

3. Power source must be capable of providing constant voltage under

combined line load.

Approved equipment for field seaming are fusion welders and

extrusion fillet welders.

1. Fusion Welder, 110 Volt (220 Volt).

2. Extrusion Welder, 220 Volt.

3. High-speed, 10,000 rpm, 41/2 inch side grinder with 80-grit discs.

4. 6.5 KW Generator, single-phase with 110/200 Volt Outputs.

5. Power Cord, minimum S.O. type, 12 gauge O.S.H.A. approved

electrical cord with O.S.H.A. approved twist-type plugs and

connections.

6. Vacuum Box Test Equipment for non-destructive seam testing.

7. Air pressure test equipment for non-destructive seam testing.

8. Field Tensiometer, capable of performing quantitative shear and

Page 41: SECTION 03000-1 - Tech Specs 05-29-2015

peel tests.

C. Test Seams

Field test seams shall be conducted on the liner to verify that seaming

conditions are satisfactory. Test seams shall be conducted at the

beginning of each seaming period and at least once each 4 hours, for

each seaming apparatus and personnel used that day.

All test seams shall be made in contact with the subgrade. Welding

rod used for extrusion welding shall have the same properties as the

resin used to manufacture the geomembrane. The test seam samples

shall be 10 feet long for fusion welding and 3 feet long for extrusion

welding with the seam centered lengthwise. Five specimens shall be

cut from each end of the test seams by the inspector. The inspector

shall use a tensiometer to test 5 specimens for shear and 5 specimens

for peel. Each specimen shall be one inch wide with a grip separation

of 4 inches plus the width of the seam. The seam shall be centered

between the clamps. The rate of grip separation shall be 2 inches per

minute. Test results for seam strength properties shall be the average

of five specimens. Four out of five specimens shall pass seam

acceptance criteria. Shear and peel tests shall return in Film Tearing

Bond (FTB), which is a failure in ductile mode of one of the bonded

sheets by tearing prior to complete separation in the bonded area. If

a test seam fails to meet field seam specifications, the seaming

apparatus and/or seamer shall not be used for seaming until the

deficiencies are corrected and a successful test seam is achieved.

D. Non-Destructive Seam Testing

The installer should non-destructively test all field seams over their

full length.

3.05 BACKFILL OF ANCHOR TRENCH:

The anchor trench shall be backfilled by the earthwork contractor. Trench

backfill material shall be placed and compacted in accordance with the

project specifications. Care shall be taken when backfilling the trenches

to prevent any damage to the geomembrane. If damage occurs, it shall

be repaired prior to backfilling.

Page 42: SECTION 03000-1 - Tech Specs 05-29-2015

3.06 LINING BASE MATERIAL:

A base shall be prepared on the bottom and slopes of the area to be

lined. This base shall be free of all sharp objects, roots, grass and

vegetation. Unsuitable material found during the pre-installation

inspection by the installer shall be removed prior to the installation of the

liner.

The base (subgrade) material shall be native materials or materials

obtained from a borrow source compacted to a minimum 95%

compaction.

Foreign materials, vegetation, protrusions, voids, cracks and other

penetrating or raised sources shall by removed from the sloping areas as

well as the base. Loose rocks, rubble and other foreign matter shall be

collected and deposited in the appropriate site out of the area to be

lined. The excavated and filled areas shall be trimmed to elevations and

contours shown on the drawings and shall be smooth, uniform and free

of all foreign matter, vegetation and sudden changes in grade.

A pre-installation inspection shall be called for and ALL interested parties,

including governmental agencies, shall be present for this

inspection. Any parties not participating in this inspection shall be

construed as accepting the site preparation and will acknowledge this de

facto acceptance in writing at the appropriate time

3.07 FINAL SUBGRADE PREPARATION:

The sub grade shall be prepared immediately prior to the placing of the

liner. The surface on which the liner is to be placed is to be firm, clean,

dry and smooth. Anchor trench excavation and any structure seal

preparation should be completed before the lining installation begins.

3.08 LINING INSTALLATION:

A continuous sheet of liner shall be installed throughout the installation

site as according to the drawings. The lining shall be placed over the

prepared surfaces to be lined in such a manner as to assure a minimum

of handling. The sheets shall be of prescribed lengths and widths and

shall be placed in such a manner as to minimize field seams. Only those

pieces of fabric that can be installed and anchored in place during the

workday shall be unpacked and placed in position.

Page 43: SECTION 03000-1 - Tech Specs 05-29-2015

Sandbags and or other suitable weights may be used as required to hold

the lining in position during the installation. The weights shall not have

any sharp edges, which may snag or otherwise penetrate the liner fabric.

Care should be taken to keep the seam areas as clean as possible. It may

be necessary to wipe down the edges prior to heat-sealing the panels

together.

No materials or equipment shall be dragged across the face of the liner

nor shall the workmen while installing the liner subject the liner to

abuse. All installation party members shall wear soft-soled shoes or

boots while working on the surface of the liner.

Lining sheets shall be closely fit around all penetrations through the

liner. Lining to concrete seals shall be affected with mechanical anchors

as shown on drawings. All piping, structures and irregular projections

shall be sealed and flashed with the fabricated boots or other approved

sealing methods.

3.09 FIELD QUALITY ASSURANCE

A. MANUFACTURER and INSTALLER shall participate in and conform to

all terms and requirements of the Owner’s quality assurance of this

specification. CONTRACTOR shall be responsible for assuring this

participation.

B. Quality assurance requirements are as specified in this Section and in

the Field Installation Quality Assurance Manual if it is included in the

contract.

C. Field Testing

1. Non-destructive testing may be carried out as the seaming

progresses or at completion of all field seaming.

a. Vacuum Testing

1) Shall be performed in accordance with ASTM D 5641,

Standard Practice for Geomembrane Seam Evaluation by

Vacuum Chamber.

b. Air Pressure Testing

1) Shall be performed in accordance with ASTM D 5820,

Standard Practice for Pressurized Air Channel Evaluation of

Dual Seamed Geomembranes.

c. Spark Testing (if conductive layer is specified)

1) Shall be performed accordance with ASTM D 7240 Standard

Practice for Leak Location using Geomembranes with an

Insulating Layer in Intimate Contact with a Conductive Layer

Page 44: SECTION 03000-1 - Tech Specs 05-29-2015

via Electrical Capacitance Technique (Conductive

Geomembrane Spark Test).

d. Other approved methods.

2. Destructive Testing (may be performed by Owner’s independent

CONSULTANT with assistance from INSTALLER)

a. Location and Frequency of Testing

1) Collect destructive test samples at a frequency of one per

every 500 lineal feet of seam length.

2) Test locations will be determined after seaming.

3) Exercise Method of Attributes as described by GRI GM-14

(Geosynthetic Research Institute, http://www.geosynthetic-

institute.org) to minimize test samples taken.

b. Sampling Procedures are performed as follows:

1) INSTALLER shall cut samples at locations designated by the

CONSULTANT as the seaming progresses in order to obtain

field laboratory test results before the geomembrane is

covered.

2) CONSULTANT will number each sample, and the location will

be noted on the installation as-built.

3) Samples shall be twelve (12) inches wide by minimal length

with the seam centered lengthwise.

4) Cut a 2-inch wide strip from each end of the sample for field-

testing.

5) Cut the remaining sample into two parts for distribution as

follows:

a) One portion for INSTALLER, 12-inches by 12 inches

b) One portion for the Third Party laboratory, 12-inches by

18-inches

c) Additional samples may be archived if required.

6) Destructive testing shall be performed in accordance with

ASTM D 6392, Standard Test Method for Determining the

Integrity of Non-Reinforced Geomembrane Seams Produced

Using Thermo-Fusion Methods.

7) INSTALLER shall repair all holes in the geomembrane

resulting from destructive sampling.

8) Repair and test the continuity of the repair in accordance

with these Specifications.

3. Failed Seam Procedures

a. If the seam fails, INSTALLER shall follow one of two options:

1) Reconstruct the seam between any two passed test locations.

Page 45: SECTION 03000-1 - Tech Specs 05-29-2015

2) Trace the weld to intermediate location at least 10 feet

minimum or where the seam ends in both directions from

the location of the failed test.

b. The next seam welded using the same welding device is

required to obtain an additional sample, i.e., if one side of the

seam is less than 10 feet long.

c. If sample passes, then the seam shall be reconstructed or

capped between the test sample locations.

d. If any sample fails, the process shall be repeated to establish

the zone in which the seam shall be reconstructed.

3.10 REPAIR PROCEDURES

A. Remove damaged geomembrane and replace with acceptable

geomembrane materials if damage cannot be satisfactorily repaired.

B. Repair any portion of unsatisfactory geomembrane or seam area

failing a destructive or non-destructive test.

C. INSTALLER shall be responsible for repair of defective areas.

D. Agreement upon the appropriate repair method shall be decided

between CONSULTANT and INSTALLER by using one of the following

repair methods:

1. Patching- Used to repair large holes, tears, undispersed raw

materials and contamination by foreign matter.

2. Abrading and Re-welding- Used to repair short section of a seam.

3. Spot Welding- Used to repair pinholes or other minor, localized

flaws or where geomembrane thickness has been reduced.

4. Capping- Used to repair long lengths of failed seams.

5. Flap Welding- Used to extrusion weld the flap (excess outer

portion) of a fusion weld in lieu of a full cap.

6. Remove the unacceptable seam and replace with new material.

E. The following procedures shall be observed when a repair method is

used:

1. All geomembrane surfaces shall be clean and dry at the time of

repair.

2. Surfaces of the polyethylene which are to be repaired by extrusion

welds shall be lightly abraded to assure cleanliness.

3. Extend patches or caps at least 6 inches for extrusion welds and 4

inches for wedge welds beyond the edge of the defect, and around

all corners of patch material.

Page 46: SECTION 03000-1 - Tech Specs 05-29-2015

F. Repair Verification

1. Number and log each patch repair (performed by CONSULTANT).

2. Non-destructively test each repair using methods specified in this

Specification.

3.10 QUALITY OF WORKMANSHIP:

All joints, on completion of work, shall be tightly bonded. Any lining surface

showing injury due to scuffing, penetration by foreign objects, or distress

from rough subgrade, shall, as directed by the Engineer, be replaced or

covered and sealed with an additional layer of PVC of the proper size. A

Fabricator Field Service Representative will be required during the liner

installation and shall inspect and certify that the installation was performed

in accordance with the manufacturer's recommendations. The Contractor

will bear the expense of the Field Service Representative.

3.11 WARRANTY:

Geomembrane material warranty shall be furnished to Owner following

completion of installation. Warranty shall be for a minimum of 15 years for

all materials. Installer warranty for all seams and installation workmanship

shall be for a minimum 2-year duration following completion of material

installation and delivery of field installation reports, samples and materials

warranty to Owner.

3.12 GEOMEMBRANE ACCEPTANCE:

The installer shall retain all ownership and responsibility for the

geomembrane until acceptance by the owner.

Final acceptance is when all of the following conditions are met:

1. Installation is finished.

2. Verification of the adequacy of all filled seams and repairs,

including associated testing, is complete.

3. Delivery of certified original warranty.

PART 4 - MEASUREMENT AND PAYMENT

A. Payment for geomembrane installation will be as per contract unit

price per square foot, as measured parallel to liner surface, including

designed anchor trench material and is based upon net lined area.

Page 47: SECTION 03000-1 - Tech Specs 05-29-2015

B. Net lined area is defined to be the true area of all surfaces to be lined

plus designed burial in all anchor trenches, rubsheets, and sacrificial

layers.

C. Prices shall include full compensation for furnishing all labor, material,

tools, equipment, and incidentals.

D. Prices also include doing all the work involved in performing

geomembrane installation and testing completely as shown on the

drawing, as specified herein, and as directed by the ENGINEER.

SECTION 3600-1 SIMPLEX SUBMERSIBLE PUMP STATION

PART 1 - GENERAL

1.01 SCOPE OF WORK:

The Contractor shall furnish and install ONE (1) SIMPLEX stormwater

pumping station as shown and specified, including all necessary

components and equipment to provide a complete and functional facility.

In addition to the specifications shown herein the pumping station shall

conform to the requirements of the local utility and/or government

having jurisdiction over the construction.

The equipment system shall include one (1) submersible non-clog pumps

with 3" solids handling capacity, stainless steel pump rail guides,

discharge elbows and rail supports, access frame with aluminum access

covers, pump lifting chains with hooks, stainless steel cable holder, NEMA

4X fiberglass weather proof control panel, non-mercury switch level

controls, and station valves, pipe, fittings, concrete wet well, and

miscellaneous related items of equipment.

All equipment for the system shall be furnished by one (1) company to

insure complete component compatibility and operation.

1.02 QUALITY ASSURANCE:

A. Acceptance tests: Services of manufacturers representative for

start up certification.

B. Manufacturer's successful experience in manufacture, operation

and servicing of equipment of type, size, quality performance and

reliability, equal to that specified.

Page 48: SECTION 03000-1 - Tech Specs 05-29-2015

1.03 REFERENCES:

A. American National Standards Institute (ANSI)

B. American Society of Mechanical Engineers (ASME)

C. National Sanitation Foundation (NSF)

1.04 SUBMITTALS:

A. Contractor shall submit to the Engineer two (2) hard copies and

one (1) CD or other acceptable file transfer media, a copy of the

descriptive or product data submittals in PDF (Portable Document

Format) file format. The Contractor may submit up to four (4)

additional hard copies which will be returned to the Contractor, if

Contractor desires returned hard copies. The Engineer will retain

two (2) hard copy sets. Contractor submittals provided shall

include certified Shop Drawings and performance data regarding

pump, structure, controls and appurtenances characteristics

including:

1. Pump and Motor Data:

a. Outline dimensions and weight

b. Manufacturers Pump Information Sheet (including

Pump Model and Impeller number(size), efficiency,

power factor, NPSH, and variable speed conditions)

c. Operating and maintenance instructions and parts

list.

d. Operating and nameplate data

e. Pump performance curve with GPM, TDH, HP, and

operating range data for variable speed operation.

f. Certification Statement that motors and cable are

suitable for use with variable frequency drives.

2. Access Equipment:

a. Access frame and cover details, Grating and/or

Hatch equipment

3. Structural :

a. Outline dimensions and openings.

Page 49: SECTION 03000-1 - Tech Specs 05-29-2015

b. Concrete wetwell reinforcement and anti-

floatation characteristics.

4. Controls Data:

a. Manufacturer's size and type, circuit diagram.

b. Enclosure (NEMA rating and locking mechanism)

c. Operating data, float switch controls, radio

transmitter

B. If equipment proposed substantially differs from arrangement

indicated, prepare and submit detailed drawings for review

showing all mechanical, electrical and structural changes, at no

additional compensation.

1.05 DELIVERY, STORAGE AND HANDLING:

A. Shipping:

1. Ship equipment, material and spare parts complete,

except where partial disassembly is required by

transportation regulations or for protection of

components.

2. Pack spare parts in containers bearing labels clearly

designating contents and pieces of equipment for which

intended.

3. Deliver spare parts at same time as pertaining equipment.

Delivery to Owner after completion of work.

B. Receiving:

1. Assume responsibility for equipment material and spare

parts just before unloading from carrier at site.

2. Inspect and inventory items upon delivery to site.

3. Unload, haul and store items.

Page 50: SECTION 03000-1 - Tech Specs 05-29-2015

4. Pay all demurrage charges if failed to promptly unload

items.

1.06 DESIGN CRITERIA:

The pump shall have operating capacities and conditions as specified

herein. Motor horsepower, voltage and Phase requirements are as

indicated in this specification. The pump shall be non-overloading

throughout the entire range of operation without employing service

factor. The pump shall reserve a minimum service factor of 1.15. The

performance curve submitted for approval shall state in addition to head

and capacity performance, the pump efficiency, solid handling capability,

and reflect motor service factor.

Design Flow: 300 GPM

Design Head: 34 ft. TDH

HP: 5 HP

Voltage: 230V, 3 Ph

PART 2 - PRODUCTS

2.01 DESCRIPTION:

Submersible sewage pumping station assembled with pumps, piping,

valves, controls, panels, instruments and appurtenances. Pump

manufacturers shall be Flygt, Gorman-Rupp, or an equivalent pump and

characteristics approved by the Engineer.

2.02 MATERIALS:

A. Submersible Pump/Motor Construction

Submersible pump shall be designed to pump sewage,

stormwater, heavy sludge and other fibrous materials without

injurious damage during operation. Pump shall be capable of

handling raw, unscreened sewage at least three (3) inches in

diameter.

The pump motor shall be guaranteed to run in a totally, partially,

or non-submerged condition continuously for a period of twenty-

four (24) hours without injurious damages.

Page 51: SECTION 03000-1 - Tech Specs 05-29-2015

Pump shall have two (2) mechanical seals with an oil chamber

between the seals. All pump fasteners shall be stainless steel. The

pump motor-shaft shall be stainless steel.

Seal of the pump at the discharge flange, shall be a positive, leak

proof system and shall be guaranteed not to leak.

Pump discharge assembly shall have the manufacturer’s name,

model number, serial number, impeller size and other pertinent

data marked on a metal plate.

Motor shall have non-overloading characteristics and shall not

overload anywhere on the operating curve. The motors shall have

a name plate with the revolutions per minute, horsepower,

voltage, amperage, the manufacturer’s name and model number

clearly marked on the nameplate.

Motor shall operate on 3 PHASE power only, unless otherwise

specifically approved by engineer.

The pump shall be equipped with a seal leak detection probe and

warning system. There shall be an electric probe or failure sensor

installed in the seal chamber between the two tandem

mechanical seals. If the lower seal fails, contaminants which

enter the seal chamber shall be detected by the sensor and send a

signal to operate a warning light located on the pump control

panel.

Pump shall be equipped with heat sensor. The heat sensor shall

be low resistance, bi-metal disc temperature sensitive. It shall be

mounted directly on the stator windings and sized to open at 120

degrees centigrade and automatically reset at 30-35 degrees

centigrade differential. The sensors shall be connected in series

with motor starter coil so that the starter shall be equipped with

three leg overload heaters so all normal overloads are protected

by the starter.

B. Discharge Piping

Minimum 4" D.I.P. discharge piping with 90 degree fitting, check

and gate valves, basket strainer, and spool piece, shall be installed

as shown on the construction plans.

Page 52: SECTION 03000-1 - Tech Specs 05-29-2015

C. Access Frame and Cover

Access cover shall be single leaf hinged as specified on the

construction plans. The access assembly shall be furnished for the

wet well. The access frame cover shall be capable of bearing a

300 lb/ft2 live load. Access frame cover shall be fabricated of

aluminum. Frame shall support guide rails and stainless steel

cable holder. Hinged cover shall be provided with lifting handle

and safety latch to hold cover in the open position. Locking hasp

shall be furnished for the cover. Door and frame are to be

installed integral with the concrete wetwell pad. Frame and

access cover shall be as manufactured by Halliday products, Inc.;

Bilco Hatch, Inc. , or approved equal. The entrance hatch shall be

constructed and fabricated to comply with applicable OSHA

standards. All surfaces in contact with concrete shall have a shop

coat of zinc chromatic primer, approved alkali resistant paint or

other approved protective coating. Cover must be compatible

with pump and guide rail system.

The contractor shall provide a pad lock for the wetwell cover. The

pad lock shall be Masters or equal.

D. Electrical Control Panel

The simplex pump panel shall be standard duty type. The

complete unit shall be housed in a NEMA-4X (Fiberglass or type

304 stainless steel) enclosure with provisions for padlocking the

door, and a dead front inner door for mounting controls. All

exterior hardware and hinges shall be 304 stainless steel. All

exterior mounted equipment accessories shall be constructed of

corrosion resistant materials such as stainless steel or aluminum.

Panel shall be mounted two concrete posts unless otherwise

approved, and include ground fault protection and lightning

arrestor.

Mounted on the exterior side of the panel shall be the main

circuit breaker with provisions for locking in an ON or OFF position.

The Control Panel shall be fully tested prior to installation and

include the following components:

1. The panel shall have a BQ frame normal breaker and a BQ

frame emergency breaker for main breaker disconnect with

Page 53: SECTION 03000-1 - Tech Specs 05-29-2015

handles through the inner door and a mechanical interlock on

the handles to insure that only one breaker is in the “on”

position at a time. No fuses shall be permitted inside the

control panel, only resetable circuit breakers. All breakers and

starters shall be Square D Company, or approved equal.

2. Pump motor shall be provided with a NEMA rate across the

line starter with individual quick-trip overload protection on

each leg. Overloads shall be capable of either manual or

automatic reset and shall have a manual trip button to

facilitate testing of the overload mechanism. A reset button

shall be provided on the door for each overload. Starter coils

and contacts shall be easily replaceable with standard hand

tools. Start and run capacitors shall be mounted inside the

control panel and not in the pump motor(s).

3. A rotary type, three position selector switch for HAND-OFF-

AUTOMATIC operation and a run light for the pump shall be

on the inner door.

4. Wire shall be minimum #14 gauge in wire duct, wire marked

and fully accessible. Wiring shall be labeled, color coded or

numbered.

5. Relays and control wiring shall be rated NEMA 300 volt, Furnas

Electric Class 46, or approved equal. Power terminal blocks

shall meet 600 volt creepage and clearance requirements of

NEMA and UL for general industrial control equipment and

panel boards. Control circuit terminal blocks shall be rated 300

volts as NEMA general industrial control devices.

6. Elapsed Time Meters; The panel shall have a non-reset type

elapsed time meter for pump starter mounted on the inner

door to record the accumulated running time of the pump.

Elapsed time meter for the clock shall record in hours and

1/10 of an hour.

7. Surge/Lightning Suppressors: The control panel and all

electrical circuits shall be equipped with transient voltage

surge suppressors (TVSS) to protect these items from the

effects of lightning induced currents, substation switching

transients and internally generated transients resulting from

inductive and or capacitive load switching. Lightning

Arrestor/Surge Suppressor shall be Silicon Type N. A surge

Page 54: SECTION 03000-1 - Tech Specs 05-29-2015

suppressor shall be installed on the control panel, float level

switches and pump per the manufacturer’s instructions.

Conductors between the suppressor and the point of

attachment to the panel board shall be kept as short and

straight as possible. Suppressors shall have a maximum single

current withstand rating and pulse life rating appropriate for

the intended installation and shall be housed in an enclosure

that is compatible with the system being protected.

8. Phase Monitor: The Station electrical components shall be

protected against all electrical inequities. Phase monitor relay

shall be as manufactured by Diversified Electronics, Evansville,

Ind., Model #SLA 230 ASA, including surge capacitor as

required unit will automatically restore when normal

conditions are restored.

9. Control panel shall come equipped with 24-hour time switch

as manufactured by Intermatic, Inc. Model #FM1STUZ-120U or

approved equivalent. Time switch shall restrict duration that

pump is permitted to run. Maximum run time of the pump

allowed by the timer shall be set at 20 minutes and shall be

capable of being altered by Owner's personnel.

10. Control panel shall come equipped with Model DR9011

Transmitter as manufactured by Wilkerson Instruments, Inc.

mounted to the DIN rails within the panel. The transmitter

shall receive 10-30 VDC power source and transmit RF signal

through coaxial cable to site antenna.

11. Pump Controller shall be model SC1000 as manufactured by

Motor Protection Electronics, Inc. The Controller shall control

up to three pumps to perform liquid level control. The

Controller shall be capable of alternating the pumps, and shall

provide lag pump delays and high and low level alarms, and shall

perform both pump-down and pump-up operation.

a) The Controller shall be standard “off the shelf” equipment

with published literature and fully tested hardware and

operating program. The Controller must be field

configurable from the front of the unit, and require no

special tools or software to set-up or operate.

b) The Controller shall be a microcontroller-based device and

not require a battery to maintain the operating program.

All set-up values shall be stored in non-volatile memory.

Page 55: SECTION 03000-1 - Tech Specs 05-29-2015

c) The Controller shall be UL listed as Industrial Control

Equipment, UL 508.

d) A numerical level display shall be provided on the front of

the unit. It shall have a 3 digit, 7 segment LED display and

show levels in feet and tenths of feet. All setup parameter

values shall be viewed or changed from the front of the

Controller.

e) The Controller shall not require an external power supply or

any external I/O modules to be a fully functioning unit. An

analog input (4-20mA) with zero and span adjustments shall

be provided for the wet-well level input.

f) Relay outputs shall be provided as standard for high and low

level alarms and for the control of up to three pumps.

g) The Controller shall have adjustable lag pump(s) delay.

h) All electrical connections, for power or I/O, shall be by quick

disconnect phoenix style connectors.

i) The Controller shall have 12 discrete inputs. The inputs

shall be transient protected and be programmable for the

following functions:

- Pump disable with HOA in OFF, or pump fault

- External Alternator Selector Switch

- All Pump Disable – for connection to Phase Monitor

- Limit number of pump called to run on emergency

power

- Alternation by External Time Clock

- Freeze wet well level during a bubbler tube purge

- Pump disable upon low level – for connection to low

level float switch

- Float switch backup

- Low Level Pump Cutoff

- Start Flush Cycle

- Inputs for user selectable SCADA functions

j) If not being used, the ten conductance level probe inputs

shall be available for use as ten additional discrete SCADA

inputs.

k) Troubleshooting features shall include a fault indicator on

the front of the unit and retrievable fault codes that aid in

diagnosing most common problems.

l) Status of all of the discrete inputs shall also be viewable

from the front of the unit.

m) A level simulation feature shall also be available from the

front of the unit. The Controller shall automatically return to

monitoring wetwell level after sixty seconds, if left in

simulation mode.

Page 56: SECTION 03000-1 - Tech Specs 05-29-2015

Menu selectable First-On/First-Off or First-On/Last-Off

alternation sequences shall be available.

Menu selectable alternation modes shall include:

• Standard Alternation

• Jockey pump (Pump 1 stays on when other pumps turn

on)

• Jockey Pump (Pump 1 turns off when other pumps turn

on)

• Split alternation (Pumps 1&2, Pumps 3)

• Fixed sequence (Pump 1 always lead)

• Stepped on/off (Only one pump runs at a time)

n) Pump disable discrete inputs shall cause the alternation

routine to skip over disabled pumps.

o) The Controller shall remember which pump was in the

lead position during a power outage.

p) An RS232 serial port with the Modbus RTU protocol shall

be provided for SCADA. Programming shall be in place to

collect and transmit the station status, and to allow for the

remote control of the pumps.

q) The Pump On/Off levels, high level alarm, and low level

alarm setup values shall be viewable and changeable from

a remote location.

r) Pump elapsed time meters shall be viewable and

resettable remotely, and shall be stored in non-volatile

memory during a power outage.

s) The Controller shall contain a discrete input for connection

to an external time clock to force pump alternation.

t) The Controller shall have a parameter setting to allow the

analog input level to be a 4-20mA signal from a transducer

or an input from a conductance level probe.

u) The Controller shall have a parameter setting to select the

number of pumps to control.

v) The Controller shall have a parameter setting to select the

number of pumps to run at one time.

w) The Controller shall have a parameter setting to select the

number of pumps allowed to run while on generator

power.

x) The Controller shall pave parameters for calibrating the

zero and span of the level input signal.

Page 57: SECTION 03000-1 - Tech Specs 05-29-2015

y) The Controller shall have a fault code register to aid in

troubleshooting.

z) All connections to the Controller shall be made to

removable, “Phoenix” style combination connector/plugs.

aa) The Controller shall also have parameters to allow level

probe to be a back-up to the analog transducer input.

bb) The Controller must shall have a connector for a

conductance level probe with ten sensor points.

cc) The Controller shall have a parameter to select the level

probe type by the distance between the electrodes.

dd) The Controller shall have a choice of impedance settings

for use with a conductance probe.

ee) The Controller shall have a level offset parameter to

enable the transducer or conductance level probe to be

placed off the bottom of the wetwell, while maintaining an

accurate representation of the wetwell depth.

ff) The Controller shall be able to perform float back-up using

two to six floats.

gg) The Controller’s unused output relays shall be able to be

programmed through SCADA for additional control uses.

hh) The Controller shall be able to perform an automatic flush

cycle to reduce sludge build up within the wetwell.

ii) The Controller shall contain a flow calculator that provides

the following:

• Latest Inflow Rate

• Average Daily Flow (Average of the last 7 days)

• Pump Outflow Rate (Latest Rate for each pump)

The Controller shall contain the ability to perform the following SCADA

features:

Monitor the status of:

• Wetwell Level

• All Discrete Inputs

• Pump On, Pump Off, High and Low Alarm Levels

• Individual Pump Disable Status

• All Pump Disable Status

• Float Backup Status

• On Generator Status

• Level Probe Backup Status

• Pump Forced On Status

• ETMs

• Relay Remote Control Status

Page 58: SECTION 03000-1 - Tech Specs 05-29-2015

• Forced Alternation Status

• Pump Run Status

• Pump Forced On Status

• Current Lead Pump Status

• Level Probe Electrode Status

• Fault Code Status

• Last Fault Code Status

• Internal 5V Power Supply Status

• Internal 24V Power Supply Status

• Controller Program Revision Number

• Flow Calculator, Latest Inflow rate

• Flow Calculator, Average Daily Flow

• Flow Calculator, Outflow Rate per Pump

• Flow calculator, Daily Inflow Total for last 7 days

Control:

• Remotely Change Pump On, Pump Off, High and Low

Alarm Levels

• Remotely Reset ETM’s

• Remotely Force Pumps On

• Remotely Disable Pumps

• Remotely Force Alternation

• Remotely Select Lead Pump

• Remotely Reset Fault Code Register

• Remotely Reset Last Fault Code Register

• Remotely Control Unused Relays

Fault Codes:

The following Fault Codes shall be available for Controller

Troubleshooting:

• Communication Fault

• Parameter Setup Faults

• Normal Operation Disabled

• Pump Operation on Float Backup

• All Pump Disable

• Backup Float Out-of-Sequence

• Level Probe Fault

• Level Probe Out-of-Sequence

• Flow calculator Setup fault

The Controller shall offer the following optional features:

Page 59: SECTION 03000-1 - Tech Specs 05-29-2015

4-20mA Analog Level input may be ordered as an isolated

input.

An optional Ethernet Port that will perform both Modbus TCP

and Modbus RTU protocols.

The SC1000 Controller is to be manufactured by Motor

Protection Electronics of Apopka, Florida, (407) 299-3825.

E. General Electrical

All wiring and grounding shall conform to NEC and Local electrical

codes.

Conduit shall enter the pump station wetwell and terminate with

fiber bushing. No splices will be allowed in the wetwell or conduit.

All control and motor cords shall be continuous from the motor to

the control panel terminal.

Electrical control panel shall be grounded with a copper ground

rod installed in accordance with NEC.

Electrical service entrance shall include a meter socket and

disconnect. All local electric power service company and

applicable electrical codes for meter sizing and installation shall

be complied with. Service meter and disconnect shall be

mounted on the opposite side of the control panel installation

and be for underground service only. Conductor wire and conduit

size shall be in accordance with NEC and copper wire.

Control panel shall have a laminated schematic diagram and a

laminated equipment list (listing the manufacturer and model of

all electrical components housed within the control panel)

attached to the inside surface of the front door. A typed directory

indicating equipment controlled and/or monitored by the panel,

electrician that installed the panel, electrician that assembled the

panel and the date the panel was installed shall be attached to

the inside of the surface front door.

F. Non-Mercury Float Switch Level Controls

Non-Mercury float switch level controls shall be single pole Model

ENM-10 as manufactured by Flygt or equal. Float switches shall

have a snap action switch activated by a steel ball rolling back and

forth within a switching tube in a polypropylene plastic float

housing. Switches shall be mounted on a standard stainless steel

Page 60: SECTION 03000-1 - Tech Specs 05-29-2015

rack accessible from the hatch cover and in a place that does not

interfere with the removal of the pump. Switches shall be set up

as indicated on the construction plans. Switch shall actuate when

the longitudinal axis of the float is horizontal, and deactuate when

the liquid level falls 1” below the actuation level. The float shall

have a chemical resistant polypropylene casting with a firmly

bonded electrical cable protruding. One end of the cable shall be

permanently connected to the enclosed switch and the entire

assembly encapsulated to form a completely water tight and

impact resistant switch unit.

G. Operation of the System

Upon wet well sump level rise, higher float switch for pump “ON”

level shall energize and start the pump. With the pump operating,

the wet well level shall lower to the lower float switch for pump

“OFF” setting and the pump shall stop. If the liquid level continues

to rise, the third level switch, high-level float shall be energized

and shall send signal to the DR9011 Transmitter, which shall relay

the signal from the simplex pump station to the Cameo Pond

Stormwater Pump Station DR9021 Receiver to shut off all pumps

at the triplex pump station. The control panel shall also be

equipped with a 24-hour timing device for the pump to operate

for specified durations throughout the day as determined by City

of Ocala Department of Public Works.

All level switches shall be adjustable, for level setting, from the

surface.

H. Wetwell and Accessories

The wet well shall be sized as illustrated on the construction plans.

Wetwell shall be constructed of reinforced precast concrete as

further specified herein.

Reinforced concrete meeting “Standard Specifications for Precast

Reinforced Concrete Manholes”, ASTM C-478-75, latest revision.

Cement used in reinforced concrete composition shall be Type II

acid resistant cement used for sanitary construction. Concrete

shall attain a minimum compressive strength of 4000 psi at

twenty-eight (28) days. Wall joints shall be tongue and groove

and so spaced that no piping shall pass through the wet well at a

joint. Joints shall be laid full with cement mortar, sealed with

double ring “RAM-NEK” or equal, and shall have no voids or other

Page 61: SECTION 03000-1 - Tech Specs 05-29-2015

imperfections, and shall be entirely watertight upon completion

of construction.

Openings in the walls of the wet well for the passage of pipes may

be made by the manufacturer at the time of fabrication or may be

made in the field by the contractor, if desired. If holes are made

in the field, their maximum dimension shall not exceed 1-1/2

times the outside diameter of the pipe passing through the

opening. Reinforced steel in the wall shall be cut cleanly and in no

circumstances will cut ends by bent so as to turn to the inside or

outside surface. Openings so made shall be thoroughly filled with

non-shrinking grout after installation of the pipes and special care

shall be taken to insure a watertight connection at these points.

A Flexible water tight pipe boot shall be used for all main line pipe

penetrations into the wet well when PVC piping is utilized.

The concrete base upon which the wet well rests shall be

constructed of Type II 4000 psi concrete, reinforced to comply

with ASTM C-478. The reinforced concrete top of the wet well

will be constructed of Type II 4000 psi concrete, reinforced to

comply with ASTM C-478 and with a rectangular opening for

access to the wet well. The pump and/or accessories shall be

secured to the concrete base in accordance with the

manufacturer’s recommendations.

Minimum design for adequacy of base and top slab reinforcement

is for AASHTO H-20 truck loading.

The supporting soil shall be compacted to support the wetwell

with a factor of safety of two (2).

I. Piping, Valves and Accessories

Pump station main line piping shall be Ductile Iron Pipe (D.I.P.)

with Flanged joints unless otherwise specified by Engineer.

Flanges shall either be welded or threaded to the connecting

pipes. All fasteners inside the wetwell shall be stainless steel.

Check valve shall be flanged end swing check valve with outside

lever arm and spring, as manufactured by Clow Valve Co., Mueller

Co., or approved equal. Reference City of Ocala Water and Sewer

Construction Manual Specification 493.5.11.3

Page 62: SECTION 03000-1 - Tech Specs 05-29-2015

Gate valve shall be resilient wedge flanged end gate valve with full

port opening with handwheel operator, as manufactured by Clow

Valve Co., Mueller Co., or approved equal.

A one quarter inch (¼”) NPT tap, nipple and WIKA Stainless steel

body pressure gauge with HYETT model 42MW diaphragm seal

and ½” Apollo 76-100 series stainless steel shut off ball valve or

approved equal.

PART 3 - EXECUTION

3.01 INSTALLATION:

Structure installation shall be to line and grade as indicated on the plans.

Foundation preparation for the wetwell shall obtain a minimum 98%

compaction and be leveled on a bead of gravel. Backfill around all

structures to a density sufficient to not allow noticeable settlement.

Dewatering and/or sheeting to facilitate pump station installation shall

be included in the contractor scope of work. Wetwell may be installed “In

the Wet” with engineer approval.

Contractor shall protect all adjacent structures and equipment, if existing,

and work to reduce excessive open cut and overnight open excavations.

Installation of equipment, piping, and valves shall be in strict

conformance with manufacturer's recommendations, plans, and

specifications.

Electrical equipment shall be installed by a state licensed electrician.

Contractor shall coordinate with local power company to facilitate

permanent electrical hookup.

3.02 ACCEPTANCE TESTS:

A. After installation of equipment and after completion of services of

manufacturer's representative, operate unit under normal

operating conditions to demonstrate its ability to operate

continuously without vibration or overheating and to perform its

specified function satisfactorily within five (5) percent of rating.

Failure to meet aforementioned requirement is cause for

rejection.

Page 63: SECTION 03000-1 - Tech Specs 05-29-2015

B. Correct defects and defective equipment promptly or replace at

no additional expense to Owner. Make final adjustments

necessary to place equipment in satisfactory working order at

time of above tests.

3.03 SPARE PARTS:

Deliver to owner spare upper and lower mechanical seals of the pump.

3.04 WARRANTY:

The pump manufacturer shall warrant all equipment supplied for a

minimum of three (3) years from the date of acceptance.

Page 64: SECTION 03000-1 - Tech Specs 05-29-2015

SECTION 03000-2 CAMEO WATERSHED STORMWATER FORCEMAIN

COMPONENT PROJECT - PART 2

SECTION 3100-2 GENERAL

1. This section covers supplemental technical specifications not covered in the

standard specifications.

2. The City of Ocala "General Conditions for Construction", Volume I and "Standard

Specifications for Water and Sewer Construction", Volume III, along with FDOT

Standard Specifications for Road and Bridge Construction, latest edition, shall

govern the execution of this Component Project - Part 2 as specified and

amended by these Contract Documents.

3. Air Release Valve assembly shall be installed above ground within plastic housing

as shown on the drawings. Valve shall conform to material specification 499-10-

99-02 for 2" plastic Air Release Valve.

4. Valve boxes used for locate wire terminals (material specification 479-03-06-02)

shall have lid furnished with the word "STORM" on the cover to indicate the use

of the locate wire system for stormwater.

Page 65: SECTION 03000-1 - Tech Specs 05-29-2015

SECTION 03000-3 CAMEO POND STORMWATER PUMP STATION

COMPONENT PROJECT - PART 3

SECTION 3100-3 GENERAL

1. This section covers supplemental technical specifications not covered in the

standard specifications.

2. The City of Ocala "General Conditions for Construction", Volume I and "Standard

Specifications for Water and Sewer Construction", Volume III, along with FDOT

Standard Specifications for Road and Bridge Construction, latest edition, shall

govern the execution of this Component Project - Part 3 as specified and

amended by these Contract Documents.

3. Valve boxes used for locate wire terminals (material specification 479-03-06-02)

shall have lid furnished with the word "STORM" on the cover to indicate the use

of the locate wire system for stormwater.

4. Provided hereinafter is the Geotechnical Report for the project site as provided

by Geo-Technologies, Inc. (Geo-Tech) dated September 19, 2014, Project No. 14-

4583.15.1 Rev. A.

SECTION 3200-3 CONCRETE

1. Refer to SECTION 3200-1 for Concrete Specifications.

SECTION 3300-3 EARTHWORK

1. Refer to SECTION 3300-1 for Earthwork Specification.

SECTION 3400-3 STRUCTURAL STEEL, MISCELLANEOUS METALS, AND GRATINGS

1. Refer to SECTION 3400-1 for Structural Steel, Miscellaneous Metals, and Gratings

Specifications.

2. Section 9. Access Hatches shall be replaced as stated below:

Access hatches shall be provided for all openings in the top slab for the wet well.

Each hatch shall include an access frame complete with hinge and slide bar

equipped covers. Hatch shall include lockable, hinged protective grating panel.

Grating panel shall be powder coated the color "safety orange". Each wet well

Page 66: SECTION 03000-1 - Tech Specs 05-29-2015

hatch frame and cover shall be constructed of aluminum and designed for a live

load of 300 pounds per square foot. Hatches shall be watertight. Hatch doors

shall be of aluminum check plate with reinforcing ribs to meet design criteria. All

hardware shall be stainless steel. Hatches shall be as manufactured by Halliday

Products, Bilco Company, or equal.

SECTION 3500-3 ALUMINUM FENCING

1. Refer to SECTION 3500-1 for Aluminum Fencing Specifications.

SECTION 3620-3 SUBMERSIBLE SEWAGE PUMPS

1. General

Requirements for submersible sewage pumps shall be in accordance with

specifications within the City of Ocala "Standard Specifications for Water and

Sewer Construction", Volume III, latest edition.

2. Revisions to Standard Specifications for Water and Sewer Construction

Section 493.5.5 Manufacturer shall be amended as written below:

Approved manufacturers of submersible pumps shall be ABS or Flygt.

Section 493.5.9.3.14 Pump Performance Requirements shall be amended as

written below:

The pumps furnished shall meet the Performance Criteria written below. The

pump discharge bases and rail systems furnished shall be capable of supporting

pumps for installation and removal. Rail systems shall be sized as recommended

by pump manufacturer.

Performance Criteria:

Listed below are the minimum performance requirements for the submersible

pumps. Pumps selected by contractor not able to meet the flow rates listed shall

be rejected for use. The Horsepower listed is a maximum which may be provided

by the emergency power generator. Pumps requiring additional horsepower

shall be rejected for use.

Page 67: SECTION 03000-1 - Tech Specs 05-29-2015

Pump 1 shall operate with the following design conditions:

GPM 2500

HP 30

RPM 1750

Total Dynamic Head 25'

Pumps 2 and 3 shall each operate with the following design conditions:

GPM 5000

HP 70

RPM 1750

Total Dynamic Head 38'

3. Pump Placement

Pump 1 shall be placed in the middle of the wet well as indicated on the

drawings. Pump 2 shall be placed on the left side viewing the station from NE 7th

Lane (Northeast). Pump 3 shall be placed on the right side viewing the station

from NE 7th Lane (Southwest). All controls in the control panel shall reflect

operation for this pump placement orientation.

Page 68: SECTION 03000-1 - Tech Specs 05-29-2015

SECTION 3700-3 BASIC ELECTRICAL MATERIALS AND METHODS

1. PART ONE - GENERAL:

1.1 SECTION INCLUDES

A. Raceways, Conduit and fittings, Conduit supports and assembly hardware.B. Wires and CablesC. BoxesD. Wiring devicesE. Cabinets and EnclosuresF. Wire connectors G. PanelboardsH. Overcurrent Protective DevicesI. TransformersJ. Secondary GroundingK. Light Fixtures

1.2 SCOPE:

A. The work to be governed by this section shall include furnishing all labor, material, equipment andservices to construct and install all electrical system(s) as shown on the accompanying plans andattached specifications.

B. Includes But Not Limited To1. General electrical system requirements and procedures.2. Perform excavating and backfilling work required by work of this Division as described in

Contract Documents.3. Make electrical connections to equipment provided under other Sections.

C. Products Supplied But Not Installed Under This Section1. Anchor bolts and templates for equipment bases only.

1.3 RELATED DOCUMENTS:

A. These specifications are supplemental to the City of Ocala Water & Sewer Construction Manual.B. All other Sections 3700-3 and 3800-3 series.C. The other Contract Documents complement the requirements of this Section.

1.4 REFERENCES:

A. Codes and Standards: Work shall be performed in accordance with all Local, State and FederalCodes adopted by the State of Florida and the Local authority having jurisdiction over this project,include as a minimum:1. Florida Building Code - Building, 2010 Edition W\ 2012 Supplements.2. Florida Building Code - Test Protocols for High Velocity Hurricane Zones, 2010 Edition.3. Florida Building Code - Accessibility, 2010 Edition W\ 2012 Supplements.4. Florida Building Code - Energy Conservation, 2010 Edition W\ 2012 Supplements.5. Florida Building Code - Plumbing, 2010 Edition.6. Florida Building Code - Mechanical, 2010 Edition.7. Florida Fire Prevention Code (FFPC), 2014 Edition.8. National Electric Code - NFPA 70, 2008 Edition.

3700-3-1

Page 69: SECTION 03000-1 - Tech Specs 05-29-2015

1.5 SUBMITTALS:

A. Submit Shop Drawings and Manufacturer’s Product Data in compliance with the GeneralConditions and the following, for all Electrical Sections. Data to be provided to the Prime Engineerfor review by the MEP Engineer within thirty (30) working days after the signing of the GeneralContract with the Owner. All electrical submittal data shall be reviewed and accepted prior toapproval of the General Contractor's first draw request.

B. Submittal data may be provided in hard copy paper form or in Digital form. If the contractorchooses to supply Digital Data the Format and Organization requirements described insubparagraphs D & E below, apply with the following:1. Digital Submittals shall be assembled into a single generic PDF format file that is viewable

by multiple platforms. PDF File shall be a PDF/X, PDF/A or PDF/E (PDF 1.7) format free ofall Adobe XML Forms Architecture and Java Script. PDF 2.0 files are not acceptable.

2. Digital Submittals shall meet all the same requirements for organization and presentation ashard copy bound submittals.

3. Provided Manufacturer’s Product Data and Shop Drawings for each specification section asa single complete, indexed section in the submittal. Partial submittals will not be acceptedbut will count as a billable review.

4. Digital files may be transferred via e-mail or FTP Site and the contractor is required toprovide a CD or DVD disk as a hard copy back-up.

5. Digital submittals will be organized in the same manner as bound copy submittals, contractor is to review and incorporate all bound copy instructions in to the digital submittal.

6. Scanned images may be incorporated into the submittal, however; they shall be clear,completely and legible. Pages shall be oriented within not more than 2 degrees ofmisalignment. Illegible submittals will be rejected and count as a billable review.

C. Each submittal package shall be in an individual vinyl-covered 3-ring binder (or CD). Each sectionof the submittal shall correspond with the Specification Sections and shall be separated with tabbeddividers. Failure to follow this procedure will likely delay processing of submittals. Binders shallbe provided with cover page listing the following information:1. Project Name2. Verrando Engineering Co., Inc. Project number as listed on the drawings.3. Name, address, phone no. and FAX no. of General Contractor4. G.C.'s Superintendent on this project and job site phone no.5. Name, address, phone no. and FAX no. of Electrical/Power System Contractor6. Electrical/Power System Contractor's Foreman on this project and job site phone no. (if any)7. List of Exceptions to and Deviations from the Contract Documents.8. The Electrical Contractor shall identify equipment and indicate the lead time (time required

from date of order to date of delivery) required by the manufacture for any electricalequipment requiring a lead time of greater than four weeks. If all electrical equipment for thisproject has a lead time of less than four weeks the Electrical Contractor shall note it with aone sentence statement on this page.

D. Shop Drawings:1. Shop drawings shall be submitted on all major pieces of electrical equipment including Motor

Control Panels, Panelboards and Transformers. Indicate precise equipment to be used,including all options specified. Indicate wording and format of nameplates where applicable.

2. Where shop drawings are called for, drawings shall be drawn to ANSI standards and includeproduct dimensions, schematics and all information to convey operation of the electricalequipment.

E. Manufacturer’s Product Data: Where product data is called for, provide 8-1/2" x 11" sheets ofstandard product literature. This literature shall include as a minimum; catalog ordering number(with all options clearly listed), weight, dimensions, installation instructions, maintenanceinstructions, special instructions, and other pertinent data as necessary for a complete descriptionof each item of equipment. Specific data requirements listed in the sections to be included.

3700-3-2

Page 70: SECTION 03000-1 - Tech Specs 05-29-2015

1. Where product data sheets include more than one item and were items not being submittedare shown, each item being submitted is to be clearly identified by an arrow, high lighter orbox. Where data sheets include items not germane to the project have not been marked,the submittal will be rejected and count as a billable review.

2. Provide specific information listed in each Section for each item of equipment in that Section. Generally provide the following:a. Catalog Sheets.b. Assembly details or dimension drawings.c. Installation instructions.d. Manufacturer's name and catalog numbere. Name of local supplier.

F. Submit manufacturer's product data for the following items under this Section.1. Raceways2. Conduit and fittings: PVC, Rigid Metal, I.M.C., E.M.T. - PVC Coated RMC and Aluminum3. Conduit supports, Unistrut and assembly hardware.4. Wires and Cables5. Boxes6. Wiring devices7. Cabinets and Enclosures8. Wire connectors9. Panelboards (include panel schedule with bill of materials)10. Transformers11. Surge Protection Devices (SPD)12. Circuit Breakers13. Fuses14. Light Fixtures

G. Maintenance Manuals: Provide one (1) set for review at submittal time and two (2) final sets withcomments incorporated at job completion. Manuals shall be bound with a 3-ring binder (as aminimum) with index and thumb-tab markers and shall incorporate all sections into one commonbinder. Label binder with "OPERATION AND MAINTENANCE MANUAL", the name of the project,the name of the Contractor, and the contract number. 1. Include the names, addresses, and telephone numbers of each subcontractor installing the

equipment. 2. Include a table of contents and assemble to conform to the Project Manual (Specifications)

with tab sheets before instructions covering the subject. Instructions shall be legible andeasily read.

3. Include wiring and control diagrams, detailed explanation of operation and control of eachitem of equipment, description of the function equipment, installation instructions,maintenance instructions, lubrication schedules (including type, grade, temperature rangeand frequency, safety precautions, diagrams and illustrations, test procedures, performancedata and parts lists.

1.6 QUALITY ASSURANCE:

A. Qualifications:1. The Electrical Contractor shall have had experience of at least the same size and scope as

this project, on at least two other projects within the last five (5) years in order to be qualifiedto bid this project. This qualification shall also apply to his subcontractors.

2. Workmen shall be experienced in their respective trade. All work performed shall becompleted in a professional manner and of premium quality, as judged by the Engineer. Substandard work shall be removed and replaced at the Electrical Contractor's expense.

3700-3-3

Page 71: SECTION 03000-1 - Tech Specs 05-29-2015

B. Warranty:1. Contractor shall and does hereby warrant all materials and equipment furnished under this

Electrical of the specifications to be free from defects and to function or operate satisfactorilyfor a period of one year after final acceptance of the work and that any items not meeting thisrequirement will be made good by him without cost to the Owner, provided such defects orfailures are not due to abuse, neglect or lack of reasonable and ordinary maintenance.

2. All equipment (unless otherwise specified), material and labor shall be guaranteed for aperiod of 12 months from the date of final completion and acceptance, unless specifiedotherwise in other Sections. Any defects arising within this period shall be repaired and/orreplaced at no cost to the Owner.

C. Storage Of Materials:1. Special care shall be taken for the protection of equipment furnished. Equipment and

material shall be completely protected from weather elements, painting, plaster, etc., until theproject is completed. Damage from rust, paint, scratches, etc., shall be repaired as requiredto restore equipment to original condition.

2. Where the installation or connection of equipment requires work in areas previously finishedby other Contractors, the area shall be protected and not marred, soiled or otherwisedamaged during the course of such work. Contractor shall arrange with other Contractorsfor repairing and refinishing of such areas which may be damaged.

D. Record Drawings:1. The Contractor shall maintain one set of “red lined” construction documents in the field office

as a record of as-built conditions. Maintain records daily using colored pencil or pens,indicating: all changes from drawings, actual field measurements of other services affectingelectrical work, location and field measurements of electrical services (conduit andprovisions) and equipment and any other information pertinent to electrical work beingperformed. At completion of construction, contractor will be provide all as-built informationto the Engineer for inclusion on Record Documents for the Project.

2. Show as-built information to scale using standard symbols listed in the legend. As aminimum requirement, indicate as-built information including, but not limited to, the following:a. Locations of stub-outs, dimensioned from permanent building lines.b. Locations and depth of under-slab and in-slab raceways.c. All routing of raceways.d. Corrected panelboard and equipment schedules.e. Corrected circuit numbers as appearing on Directory.f. Corrected motor horsepower of FLA Data.g. All underground conduit, pipes, and wires discovered or installed during construction,

that are to remain.

2. PART TWO - PRODUCTS:

2.1 RACEWAYS:

A. Electrical contractor shall provide complete and separate raceway system(s) for all electricalsystems, as specified herein, shown on the plans and/or implied in any other sections of thespecifications. Unless otherwise noted, raceway systems shall be constructed of conduit. Unlessotherwise noted, raceway systems shall be continuous throughout.

B. Raceways shall be of ample size to permit the ready insertion and withdrawal of conductors, wiresor cables without abrasion or restriction.

C. PVC Coated Rigid Metal Conduit: PVC coated galvanized rigid steel conduit shall meet thedimensions, weight and welding requirements of the ASA standards and UL 6 (E2314); UL 6A(E98405). Conduit shall be coated with a 40 mil grey PVC coating on the exterior and a 2 mil red

3700-3-4

Page 72: SECTION 03000-1 - Tech Specs 05-29-2015

urethane interior coating. Conduit shall be manufactured by Calpipe Industries, Inc. (Calbond),Robroy Industries, Inc. (Plasti-Bond), Thomas & Betts, or approved substitution.1. Joints and Fittings: shall be PVC coated galvanized rigid steel threaded type fittings all with

U.L. label. Fittings to be manufactured by the same firm as the conduit sections.2. Elbows: Provide standard radius (unless otherwise noted on Drawings) factory fabricated

PVC coated elbows, field bending is not acceptable. Acceptable manufacturers: Same asconduit.

D. PVC Conduit: 1. Below Grade: Schedule 40, TC-2, Gray, and shall be UV stabilized. PVC conduit shall be

U.L.. Listed for direct burial.2. Above Grade in Exterior Locations: Schedule 80, TC-2, Gray, and shall be UV stabilized.

PVC conduit shall be U.L.. Listed for direct burial.3. Elbows:

a. 2-1/2 Inch and Larger - 24 inch Long Radius, Schedule 80, TC-2, Gray, and shall beUV stabilized. PVC conduit shall be U.L.. Listed for direct burial.

b. 2 Inch and Smaller - Standard Radius, Schedule 40, TC-2, Gray, and shall be UVstabilized. PVC conduit shall be U.L.. Listed for direct burial.

E. Flexible Liquid Tight Conduit: shall consist of a moisture and oil proof jacket extruded over agalvanized steel flexible conduit as manufactured by Sealtite.1. Connectors-rain-tight: Meyers or approved equal.2. Water tight flex connectors: Efcor, Raco, or Midwest liquid tight, with insulated throat.

F. Conduit clamps and supports: Shall be manufactured by Efcor, Steel City, or G.A. Tinnerman.

G. Sleeves: passing through walls or floors on or below grade or in moist areas shall be constructedof galvanized steel, schedule 40 pipe and shall be designed with suitable flange in the center toform a water proof passage. After the conduit has been installed in the sleeves, the void spacearound the conduit shall be caulked or water proof.

2.2 CONDUCTORS, WIRES, AND CABLES:

A. The Electrical Contractor shall provide and install a complete wiring system as shown on the plansand/or specified herein.

B. The wire shall be delivered to the site in its original unbroken packaging, plainly marked or taggedas follows:1. Size, kind and insulation of the wire.2. Underwriter's labels3. Name of the manufacturing company and trade name of the wire.

C. Manufacturers: Provide wire and cable manufactured by Cyprus, General Electric, Okonite,Triangle, Phelps-Dodge, Anaconda, General Cable, Beldon or approved equal.

D. Materials and Insulation: Provide conductors made from 98% copper. Insulation types shall beas follows for the location of installation.1. Interior wiring, above slab in conduit & dry locations: THHN, THWN, THW2. Interior wiring, below slab in conduit: THWN3. Exterior wiring, in conduit or damp locations: THWN4. Exterior wiring, exposed RHW5. Overhead Service Conductors: THW6. Underground Service Conductors: THWN

E. General use: #12 and #10 AWG, solid or stranded copper conductors with nylon jacketed, PVCinsulation type THHN or THWN. No wiring less than #12 AWG to be used for lighting or receptaclecircuits. If distance from electrical panel to first fixture exceeds 70 feet, use #10 AWG.

3700-3-5

Page 73: SECTION 03000-1 - Tech Specs 05-29-2015

F. Conductors Type: Provide stranded copper conductors for all sizes no. 8 and larger.

G. Vibrating equipment: Stranded with nylon jacketed, PVC insulation type MTW -90 degrees C.

H. Control wire: #14 AWG, 19 strand copper conductor, with .015 Inch polyvinyl chloride insulation,.004 Inch nylon jacket, type THHN, rated 90 degrees C, full color range.

I. Analog Signal Cable: 16 AWG - Twisted Shielded Pair (2 Str, Cu, W\ Overall Shield), for UG Inst,300 Volt Rated, Overall Cable Diameter 0.328'' Nom. West Penn - AQ294, or Belden - 5240F1.

2.3 BOXES:

A. Exterior work: 1. Above Grade Exterior Locations:

a. 1-1/4 Inch and Larger - Molded Nonmetallic Junction Boxes, NEMA 6P, UV stabilizedPVC, Gray w\ PVC cover, weather seal and Stainless Steel Screws.

b. 1 Inch and Smaller - Standard single or two gang, Type FS, UV stabilized PVC, Gray.2. Below Grade: Direct Burial Enclosures made from Polymer concrete sized for one full size

larger than code minimum with traffic rated cover, unless otherwise note on plan.

2.4 PULL BOXES AND HANDHOLES:

A. Precast Concrete Handholes: Provide precast handholes formed out of 28 day concrete with acompression 4500 PSI. Handholes shall be provided with steel 1/4 inch thick traffic covers, openbottom. Covers shall have beaded weld lettering identifying the system enclosed. Refer toDrawings for box sizes, Special Configurations, Loading Requirements and other installationcriteria. Provide products by Del Zotto Products of Florida, Mack Concrete Industries, OldcastlePrecast, Southern Precast, Pre Cast Specialties or approved substitution.

B. Polymer Concrete (PC) Handholes: Where specified provide pull boxes and handholes may bemanufactured from Polymer concrete made from selectively-graded aggregates in combination witha polymer resin system, combined through a process of mixing, molding and curing. Precastpolymer concrete is to be reinforced with fiberglass for exceptional strength and rigidity. Enclosures, boxes and covers are required to conform to all test provisions of the most currentANSI/SCTE 77 “Specification For Underground Enclosure Integrity” for the appropriateapplications. Handholes shall be provided with steel 1/4 inch thick traffic covers, open bottom. Covers shall have beaded weld lettering identifying the system enclosed. Refer to Drawings forbox sizes, Special Configurations, Loading Requirements and other installation criteria. Provideproducts by Hubbell (Quazite), Communications Products and Services, Inc, Armorcast ProductsCorporation, Oldcastle Precast or approved substitution.

2.5 DEVICES:

A. General: Provide receptacles and wall switches with cover plates as shown on the plans and/orspecified herein. Unless otherwise noted, device grades shall be industrial specification grade.

B. Manufacturers: Devices shall be provided by Hubbell, Leviton, Arrow Hart or Bryant.

C. Cover plates: Cover plates shall be of one piece construction, no sectional plates shall be allowed.

D. Switches: Provide switches of the type and in locations as shown on the plans. Switches shall berated for 120-277 volts, 20 amps as a minimum unless otherwise specified on the plans. Allswitches shall be of the silent type and U.L. Tested for compliance with Federal Specification W-S-896F (50,000 on-off cycles).

E. Receptacles, General Duty: Provide receptacles as shown on the plans or specified herein. 1. Receptacles, Water Proof: Provide 120 VAC, 20 Amp Ground Fault Circuit Interrupter type

3700-3-6

Page 74: SECTION 03000-1 - Tech Specs 05-29-2015

receptacle with Zinc die-cast covers at all outside receptacle locations and where shown onthe plans.

2. Receptacles, GFI:a. Unless otherwise noted or approved, provide 120 VAC, 20 Amp, GFI receptacles:

1) In residential garages.2) At accessible interior locations within (6) feet of a water source or water

containment area.3) In areas subject to high concentrations of moisture.4) Where specified herein or shown on the plans.

b. The practice of using a GFI receptacle to protect an entire circuit is not acceptable inthis project.

2.6 CABINETS AND ENCLOSURES:

A. Provide cabinets, enclosures and electrical support racks as required, specified or shown on plans.

B. All cabinets and enclosures shall be NEMA-3R or 4X, Stainless Steel (no substitutions).

2.7 SUPPORTING DEVICES:

A. Conduit Hangers and Supports: Conduit throughout the project shall be securely and rigidlysupported to the building structure in a neat and workman-like manner and wherever possible,parallel runs of horizontal conduit shall be grouped together on adjustable trapeze hangers.Suspended support spacing shall not exceed (8) feet.1. All conduit and electrical equipment supports shall be 316 stainless steel, supported by one-

hole malleable straps, two-hole straps, suitable beam clamps or split-ring conduit hangerswith support rod. All materials fittings and supports to be made from stainless steel,galvanized steel is not acceptable.

2. Single conduit 1-1/4 inches and larger run concealed horizontally shall be supported bysuitable beam clamps or split-ring conduit hangers with support rod. Multiple runs of conduitshall be grouped together on trapeze hangers where possible. Vertical runs shall besupported by steel riser clamps spaced at (6) feet (minimum).

3. Conduit one inch and smaller run concealed above a ceiling may be supported directly to thebuilding structure with strap hangers or No. 14 Ga. galvanized straps, provided the supportspacing does not exceed (4) feet.

B. Stainless Steel Conduit Hangers and Supports: Provide stainless steel strut designed for theframework and support for conduit systems, with slotted hole configuration for attachment atvarious points without drilling. Provide with fittings as required for the installation. Unless otherwisenoted on Drawings, strut shall be 1-5/8” x 1-5/8” (deep) x 12 Gauge strut, Type 316 SS. Strut shallbe manufactured by Gibson Stainless & Specialty, Inc., All Fasteners USA, Eaton B-Line, Anvil, orapproved substitution.

2.8 CLASSIFIED AREAS:

A. Devices and equipment installed in classified areas shall be U.L. Listed for use in hazardous areas.Devices shall meet all the requirements of the division, class and group of the classified area(s).

B. All wiring, conduit and electrical equipment in classified areas must conform to applicable articlesof the National Electric Code (NEC).

C. Each conduit run leaving a Class I, Division 2 hazardous area must have a seal fitting installed. The seal fitting should be within six inches of the boundary between the hazardous and nonhazardous area. Seal offs should be located in the hazardous area whenever possible. Verticalseal offs are preferred. No union, coupling, box or fitting in the conduit shall be permitted betweensealing fittings and point where the conduit leaves the hazardous location. Seal offs shall beinstalled following manufacturer’s recommendations.

3700-3-7

Page 75: SECTION 03000-1 - Tech Specs 05-29-2015

2.9 ELECTRICAL IDENTIFICATION:

A. Provide Identification Placards on all major pieces of electrical equipment including: panelboards,branch breakers on Main Distribution Panels, lighting contactors, time clocks, transfer switches anddisconnect switches. Placards shall be engraved, rigid laminated plastic type with adhesive back. Unless otherwise noted, color shall be black with 3/16 inch, white letters. Placard dimensions andconfigurations shall be per the details shown on the plans.

2.10 PANELBOARDS:

A. General: Provide and install panelboards as specified on the panel schedules and in the locationsshown on the plans. Panelboards shall be equipped with thermal-magnetic molded case circuitbreakers with frame and trip ratings as shown on the schedule. 1. All panelboards shall be NEMA-3R with stainless steel enclosures.2. The Engineer reserves the right to change the trip amp rating, number of breaker poles and

location of circuit breakers on panelboards during the submittal process. These changesshall be accomplished at no additional cost provided the trip amp rating does not exceed theframe rating of the breaker and that the number of breaker poles equal the number ofspecified poles spaces (three single pole breakers are the same as one three pole breaker).

3. Panelboards that are series-rated shall have circuit breakers installed that are UL Listed assuitable for use in combination with the series-rated panel board assembly and shall belabeled on the panel board. The panelboard shall be clearly labeled indicating its AIC rating.

B. Acceptable Manufacturers: Provide all components of the electrical power distribution system asspecified under this sections, from only one of the following:1. Square-D Company2. Seimens3. General Electric

C. Branch Circuit Panelboards:1. General: Provide Square-D, Type QO panels with plug-on circuit breakers in all locations

where the feeder voltage is 240 volts or less.2. Main Circuit Breaker: Where specified provide main circuit breakers of the size listed on the

panel schedule. Provide thermal-magnetic molded case circuit breakers with a minimumampere interrupting capacity of 22,000 RMS symmetrical amps.

3. Circuit Breakers: Provide plug-on thermal magnetic, molded case circuit breakers with aminimum A.I.C. rating of 10,000 RMS symmetrical amperes.

2.11 TRANSFORMERS:

A. General: Provide and install, dry-type transformers of the KVA rating, primary and secondaryvoltage ratings indicated on the electrical plans.1. Transformers shall be 480 volt single phase primary, 240/120 volts single phase secondary,

dry type with NEMA 3R stainless steel enclosure. Transformers shall have multiple fullcapacity taps for voltage adjustment.

2. Transformers 10 KVA and above shall be rated for operation at 150 deg C temperature riseabove 40 deg C ambient. All insulating materials to be in accordance with NEMA ST20Standard for 220 deg C UL component recognized insulation system.

3. The core of the transformer shall be visibly grounded to the enclosure by means of a flexiblegrounding conductor sized in accordance with applicable NEMA, IEEE and ANSI standards.

2.12 SURGE PROTECTION DEVICES (SPD):

A. Provide Surge Protection Devices (SPD) of the type and rating as listed on the drawings. Surgesuppressors shall be installed per the manufacturer's instructions and this specification and beprovided with the following:1. SPD shall be UL labeled with 200kA Short Circuit Current Rating (SCCR). Fuse ratings shall

3700-3-8

Page 76: SECTION 03000-1 - Tech Specs 05-29-2015

not be considered in lieu of demonstrated withstand testing of SPD, per NEC 285.6. 2. SPD shall be UL labeled as Type 1 (verifiable at UL.com), intended for use without need for

external or supplemental overcurrent controls. Every suppression component of every mode,including N-G, shall be protected by internal overcurrent and thermal over temperaturecontrols. SPDs relying upon external or supplementary installed safety disconnects do notmeet the intent of this specification.

3. SPD shall be UL labeled with 20kA I-nominal (I-n) (verifiable at UL.com) for compliance toUL 96A Lightning Protection Master Label and NFPA 780.

4. Suppression components shall be heavy duty 'large block' MOVs, each exceeding 30mmdiameter.

5. SPD shall provide surge current paths for all modes of protection: L-N, L-G, L-L and N-G forWye systems; L-L, L-G in Delta and impedance grounded Wye systems.

6. UL 1449 Listed Voltage Protection Ratings (VPRs) shall not exceed the following:System Voltage L-N L-G L-L N-G480Y/277 1200V 1200V 1800V 1200V

(Mode VPRs verifiable at UL.com. Numerically lower is allowed/preferred; old-styleSuppressed Voltage Ratings (SVRs) shall not be submitted, nor evaluated due to outdatedless-strenuous testing)

7. UL 1449 Listed Maximum Continuous Operating Voltage (MCOV) (verifiable at UL.com):8. System Voltage Allowable System Voltage Fluctuation (%) MCOV

480Y/277 15% 320V9. SPD shall include a serviceable, replaceable module (excluding Branch). 10. SPD shall have UL 1283 EMI/RFI filtering with minimum attenuation of -50dB at 100kHz.11. SPD shall include visual LED diagnostics including a minimum of one green LED indicator

per phase, and one red service LED. SPD shall include an audible alarm with on/off silencefunction and diagnostic test function (excluding branch).

12. NEMA enclosure listed on drawings13. Acceptable Manufacturers:

a. Square-D Companyb. Seimensc. Advanced Protection Technologies (APT)d. MCG Electronics Inc.e. L.E.A. Dynatech

B. Main and Pump Control Panels rated 250 Amps and greater:1. Minimum surge current capability (single pulse rated) per phase shall be: 100kA2. Basis of Design: 480Y/277 - Square D Model: TVS4HWA10X.

C. Branch Panels rated less than 100 Amps:1. Minimum surge current capability (single pulse rated) per shall be: 100kA2. Basis of Design: 120/240 - Square D Model: TVS120XR50S.

2.13 LIGHT FIXTURES:

A. Lighting fixtures listed on the Light Fixture Schedule are the basis of design. Substitutions will beconsidered if proposed substitute fixtures are submitted for review 10 days prior to bid and areequivalent to specified items in all respects.

B. Surface Mounted LED Fixtures: Provide commercial grade surface mounted LED, fixturesconstructed of fiber-reinforced plastic (FRP) or fiberglass housing with stainless steel hardware andUV stabilized polycarbonate lens, unless otherwise specified. LED characteristics as specified onthe Light Fixture Schedule.

C. Pole Mounted Luminaries: Provide commercial grade pole mounted fixtures as indicated on the Light Fixture Schedule. Luminaries to have IES distribution, lumen output, color rendition andphotometric characteristics to match the specified items. 1. Luminaries shall be constructed of die-cast aluminum housing, stainless steel external

3700-3-9

Page 77: SECTION 03000-1 - Tech Specs 05-29-2015

hardware and UV stabilized polycarbonate reflector, color as specified.2. Luminaries shall be equipped with LED light source.3. Fixtures shall be UL Listed suitable for wet locations unless otherwise noted. 4. All pole and luminary combinations shall be designed to withstand wind loads listed on the

Drawings.5. Provide mounting arms, mounting hardware, trim, and all miscellaneous materials to provide

a proper installation. 6. Mounting height shall be as listed on the Drawings or as determined by the Engineer.

D. Concrete Poles: Provide concrete poles of the Type, Size, Shape, Structural Class as listed on theLight Fixture Schedule. Concrete poles shall be All Concrete poles shall be:1. Pre-stressed Cast Concrete, with a 4" x 6" handhole located 18" above finished grade.2. Constructed with two PVC Conduit inside, one for electrical power to the Luminaries and one

for the Lightning Down Conductor.3. Provide with a stainless steel handhole cover, fastened with stainless steel tamper resistant

screws, and bonded to ground with flexible braid copper of the same size as theequipment-grounding conductor.

4. Natural concrete color, unless specified otherwise.5. Manufactured by: Stresscrete Group, Traditional Concrete, Inc. Pre-Cast Specialties, Inc.,

or Seminole Pole, Inc.

E. Submit certified calculations for all pole and luminary combinations to demonstrate compliance withflorida building code wind load criteria specified on the Drawings. Certified calculations to beprovided bearing the signature and seal of a florida registered structural engineer and per ASCE7 – 2010 Edition with the minimum required design wind load criteria shown on the Drawings. These calculations are to be accepted by the Engineer as complying with the specifiedrequirements for the installation prior to placement of any orders.

3. PART THREE - EXECUTION:

3.1 LOCATION CHECKING:

A. This contractor shall coordinate his work with all trades involved so that exact locations may beobtained for all outlets, apparatus, appliances and wiring.

B. The location of outlets are diagrammatic and shall be considered as approximate. It shall be theresponsibility of this contractor, before installing outlet boxes, to study all pertinent drawings andobtain precise information from the architectural schedules, scale drawings, large scale and detailof finished rooms, approved shop drawings of other trades or from the engineer.

C. It shall be understood that any device (at the request of the Engineer) may be relocated a distancenot to exceed twenty (20) feet from the location shown on the drawings.

D. This contractor shall make any necessary adjustment of his work to fit conditions for recessedfixtures and for outlets occurring in glazed tile, block, terra cotta, marble, wood paneling or otherspecial finish material in order that all boxes may register flush with finish and shall be centeredproperly.

E. Connections to equipment incorrectly located shall be properly relocated at the contractor'sexpense.

F. Local switches which are shown near doors shall be located at the strike side of the door as hung,regardless of swing on the drawings.

G. Any relocation of devices resulting from failure to follow this procedure shall be performed by thecontractor at no additional cost to the owner.

3.2 INSTALLATION OR CONNECTION OF ELECTRICAL EQUIPMENT:

A. The Electrical Contractor shall provide and install all conduit, wire, devices and/or miscellaneouselectrical materials for electrically powered or controlled equipment, whether installed by thisContractor or not. The installation and/or connection of the Equipment shall be complete, adhering

3700-3-10

Page 78: SECTION 03000-1 - Tech Specs 05-29-2015

to all applicable Electrical specifications, manufacturer’s instructions, equipment nameplate data,and as required by governing codes.

B. The Electrical Contractor shall receive and properly store the equipment and material associatedwith his/her scope of work. The equipment shall be tightly covered and protected against dirt,water, chemical or mechanical damage, and theft. The manufacturer's directions shall be followedcompletely in the delivery, storage, protection, and installation of all equipment and materials.

C. It shall be the responsibility of the Electrical Contractor to clean electrical equipment, makenecessary adjustments and place the equipment into operation before turning equipment over tothe Owner. Any paint that was scratched during shipping or erection shall be "touched-up" with"factory-color" paint to the satisfaction of the Architect. Any items that are damaged beyond repairduring shipment or erection shall be replaced.

3.3 CONCRETE PADS, SUPPORTS AND ENCASEMENT:

A. The Electrical Contractor shall be responsible for all concrete pads, supports, piers, bases,foundations and encasements required for the installation of electrical equipment and conduit. Concrete pads shall be six (6) inches larger all around than the base of the equipment and aminimum of six inches thick unless specifically indicated otherwise. The pad shall have a one inchchamfer on all exposed edges. The pad shall be sloped three inches per one hundred feet toprevent water accumulation. The pad shall be reinforced with six inch square wire reinforcingmesh.

B. Unless otherwise noted or approved, transformer pads shall be surrounded by a ring of crushedstone ( approximately ½" in diameter) 18" wide and 3-1/2" deep, contained by a concrete curb 4"wx 8"h, raised 3-1/2" above final grade. Curb corners shall be chamfered one inch.

C. All concrete work is subject to the Engineer’s approval, unacceptable work shall be corrected orreplaced.

3.4 ELECTRICAL SYSTEM IDENTIFICATION:

A. General: All electrical systems shall be identified either through color coding with placards or bothas specified. All wiring shall be color coded for phasing as described in Section 3700-3, andlabeled for circuit number corresponding to circuiting on shop drawings.

B. Equipment Placards: Provide on all disconnect switches, panelboards, motor starters, controlpanels, each component of switchboards and other items of electrical supply equipment, includingspare equipment, engraved UV stabilized placards per Section 3700-3 of this specification.

C. Circuit labels: Identify all connected circuits with a typed panel schedule attached to the inside dooron all electrical panels. Circuit numbers shall be provided on the cover panel of the board adjacentto the corresponding breaker. If no such numbers have been embossed into the steel cover, thiscontractor shall provide engraved or printed labels to accomplish same. Spare circuits shall belabeled as such.

D. Raceways shall be marked at all junction points (boxes or panels), indicating the system(s) that isenclosed. Unless otherwise noted, system identification text may be made using a blackpermanent ink magic marker. All text shall be easily read from a distance of ten feet or greater.

E. Control panels: all control panels shall have a laminated schematic diagram and a laminatedequipment list (listing the manufacturer and model of all electrical components housed within thecontrol panel) attached to the inside surface of the front door. A typed directory indicatingequipment controlled and/or monitored by the panel, electrician that installed the panel, electricianthat assembled the panel and the date the panel was installed shall be attached to the insidesurface of the front door.

3700-3-11

Page 79: SECTION 03000-1 - Tech Specs 05-29-2015

3.5 INSTALLATION OF RACEWAYS:

A. General: Unless otherwise noted or approved, All conduit shall be concealed in walls, aboveceiling, in slab or underground. Underground conduit runs for receptacles and major power loadsare preferable to overhead runs. Conduit materials specified herein are minimum requirements,the electrical contractor may substitute materials of a higher quality without prior approval, IE; RigidMetal conduit for PVC, I.M.C. for E.M.T.

B. Unless otherwise noted or approved, metallic raceway systems shall be mechanically andelectrically continuous. Non-metallic raceways shall be mechanically continuous.

C. Exposed Conduit: Shall be run to or at right angles with the lines of the building. Schedule 80 PVCor Aluminum Rigid Metal Conduit shall be used above grade on the exterior of structures, storagetanks, and well pumps installations. Aluminum Rigid Metal conduit shall be used where exposedand where there exists a possibility of mechanical damage, such as; Shop and MaintenanceFacilities, Loading Docks and Parking Areas. Exposed conduit runs shall be parallel and/or at rightangles to building walls and/or partitions.

D. A No. 14 Ga. galvanized steel fish wire or 1/4 inch nylon rope shall be left in all conduit in whichpermanent wiring is not installed. Unoccupied conduit shall be capped with an approvedmanufactured conduit seal and labeled to indicate the destination, size and application (system)of the conduit.

E. During construction, conduit shall be capped with approved conduit seals as soon as installed andkept capped until ready for use.

F. Conduit shall be securely fastened to all sheet metal outlets, junction and pull boxes withgalvanized lock-nuts and bushings, care being observed to see that the full number threads projectthrough to permit the bushings to be drawn tight against the end of conduit after which the lock-nutshall be made sufficiently tight to draw the bushings into firm electrical contact with the box.

G. PVC Coated Rigid Metal Conduit:1. Penetrations through concrete floor slabs.2. Load side of all Variable Frequency Drives (unless otherwise noted on Drawings).

H. PVC Conduit: Unless indicated on the plans or specified otherwise, PVC Conduit may be permittedfor use as follows:1. For feeders, run below grade / slab elevation in light duty areas. 2. For exterior underground.

I. Flexible conduit:1. Flexible conduit shall be sealtite.2. Flexible conduit shall not exceed (6) feet in length.3. Flexible conduit shall be trimmed to avoid unnecessary or excessive slack. 4. Flexible conduit shall have a code sized insulated ground run within the conduit.5. Flexible conduit shall not be used as a means of support for electrical equipment.6. Flexible conduit shall be supported to avoid strain or tension on the conduit.7. Flexible conduit installed exterior shall be liquid tight, immune to the effects of sunlight and

connected with liquid tight fittings.

J. Metal conduit in direct contact with concrete shall be coated to inhibit the corrosive effects of theconcrete on the conduit.

K. Box Connections, Interior: Where Rigid and/or I.M.C. Conduits enter boxes, they shall be securedin place by approved lock nuts and bushings. Where E.M.T. enters boxes, they shall be securedin place with approved fittings.

3700-3-12

Page 80: SECTION 03000-1 - Tech Specs 05-29-2015

L. Box Connections, Exterior: Watertight conduit connectors shall be used on sheet metal cabinetsor enclosures subject to water intrusion.

M. Conduit Attachment: Fasten conduit securely in place by means of approved conduit clamps,hangers, supports and fastenings. Arrangements and methods of fastening all conduit shall besubject to Engineer's direction and approval. Galvanized wire may not be used to support conduit.

N. PVC Coated RMC:1. Fittings shall be PVC coating over listed galvanized steel conduit. PVC-coated raceways shall

be installed as a system, where the fittings, conduit bodies, straps, hangers, boxes, etc., areall coated or stainless steel.

2. Use tools specially designed for PVC-coated conduit. 3. Cutting shall be performed with a band saw. Perform threading per manufacturer’s

instructions and coat threads with an approved electrically-conductive, corrosion resistantcompound.

4. Provide factory fabricated elbows for all 45 and 90 degree bends in conduit, avoid fieldbending where ever possible.

5. Bending PVC - Coated Conduit: As a minimum, use an EMT bender one trade size largerthan the conduit being bent, to avoid damaging the coating. A bender with shoes madespecifically to bend PVC-coated conduit is preferred. Trade sizes 2 and larger should bebent with a hydraulic bender. Do not use lubricants on bending shoes.

3.6 SECURING OF BOXES, EQUIPMENT OR PANELS:

A. All equipment, boxes, or panels shall be securely mounted using approved methods and withapproved screws, bolts, and/or fasteners. Devices smaller than 50 cubic inches and weighing lessthan five pounds shall have a minimum of two mounting fasteners per device. Devices larger than50 cubic inches and/or weighing greater than five pounds shall have a minimum of four mountingscrews, bolts or fasteners per device.

3.7 INSTALLATION OF BOXES:

A. Openings made in masonry for the installation of boxes shall be saw cut.

B. Exterior Boxes: Outside boxes for switches, receptacles and devices shown on exterior of buildingwalls shall be installed in surface mounted boxes provided with weatherproof gasket flush covers.

C. Receptacle outlet boxes: 1. When the receptacle is mounted in a masonry wall, the bottom of the outlet box shall be in

line with the bottom of the masonry unit. 2. Receptacle outlet boxes shall be equipped with a grounding conductor which shall be

connected to the grounding terminal of the device and the grounding terminal of the boxunless the receptacle is designated as an isolated ground receptacle. In this case discreteinsulated ground conductors shall be run to the device ground terminal and the box groundterminal separately.

D. Surface fixture outlet boxes shall be set so edge of cover comes flush with finished surface. Surface fixture outlet boxes shall be secured to the supporting surface with a minimum of twomounting screws or bolts.

E. There shall be no more knockouts opened in any outlet box than are actually required.

F. Boxes shall be sealed during construction.

G. Provide junction boxes where shown on the drawings and as required to facilitate installation ofconductors. Such boxes shall be "code" sized unless required to be larger by the plans or othersections of this specification. All junction boxes shall be accessible.

3700-3-13

Page 81: SECTION 03000-1 - Tech Specs 05-29-2015

H. Boxes to be imbedded in concrete shall be properly leveled and anchored in place before theconcrete is poured. Install floor boxes per the manufacturer's instructions and recommendations.

I. Boxes shall be properly protected during construction and shall be cleaned of all foreign matterbefore conductors are installed.

3.8 SWITCH INSTALLATION:

A. Shall be checked by the contractor against the engineer’s plans and shop drawings to be certainthat switches are on the strike side of the door regardless of swing shown on drawings. Ensurethat a minimum of one inch clearance is maintained between trim(s) and face plates. Switchesshall be relocated as required and at no additional cost to the owner.

3.9 SURGE PROTECTION DEVICE:

A. The Electrical Contractor shall provide Surge Protection Devices where shown if specified herein.

B. The Electrical Contractor shall provide approved surge protection on all Data, Communication, FireAlarm, Programmable Logic Controls (PLC), Supervisory Control And Data Acquisition (SCADA)or miscellaneous systems with metallic conductors, that are subject to the effects of lighting orvoltage spikes. As a minimum this shall include but is not limited to all wires entering or leavingeach building and/or facility and each Main Control Panel.

3.10 INSTALLATION OF CONDUCTORS:

A. On wire #10 and smaller copper connections shall be made with T & B STA-KON wire joints, PTseries, complete with insulating caps and installed with WT161 tool or WT2000 tool, Ideal super-nuts (not wire nuts), Ideal wing nuts, or Buchanan elect. Products B cap or series 2000 pressureconnectors complete with nylon snap-on insulators and installed with C24 pressure tool.

B. On wire larger than #10, connection shall be made with approved solder-less connectors andcovered with Scotch #33 electrical tape so that insulation is equal to conductor insulation.

C. No power wiring conductor shall be smaller than #12 except where so designated on the drawingsor specified herein.

D. A common neutral shall not be used for return current of ungrounded conductors of the samephase.

E. Neutral conductors in raceways containing more than one circuit shall be marked at each splice,connection or junction box, to prevent the "crossing" of circuits.

F. No splices shall be pulled into conduit.

G. Both conductors and conduits shall be continuous from outlet to outlet.

H. No conductor shall be pulled until the raceway is clean of all foreign matter.

I. No lubricant other than powdered soapstone or approved pulling compound shall be used to pullconductors.

J. When installing parallel conductors, it is mandatory that all conductors be the same length, thesame size, the same type of conductor with the same insulation and terminated in the samemanner. Each set of conductors making up a phase or neutral must be bonded together at boththe load and supply end.

K. Circuits and branch circuits: outlets shall be connected to branch circuits as indicated on drawings

3700-3-14

Page 82: SECTION 03000-1 - Tech Specs 05-29-2015

by circuit number adjacent to outlet symbols. No more outlets than are indicated shall beconnected to a circuit.

L. Unless otherwise noted, underground electrical conductors shall be buried in conduit (24) inchesbelow final grade, primary conductors shall be buried in conduit (36) inches below final grade. Cover underground conductors with a (6) inch wide tape buried (12) inches below finished grade. The tape shall be red or orange with black lettering "CAUTION BURIED ELECTRICAL CABLESBELOW".

M. All underground conductors, wire, or cable shall be installed in conduit.

N. Non-ferrous identifying tags or pressure sensitive labels shall be securely fastened to all cables,feeders and power circuits in vaults, pull boxes, manholes, switchboards, panels, starters,terminations of cables, etc. Tags or labels shall be labeled to correspond with panel and circuitnumber, so the feeder or cable can be readily identified.

O. A color coding system as listed below shall be followed throughout the power conductor system. All ungrounded conductors sized #10 AWG and less and all grounded conductors sized #6 AWGand less shall be provided with colored insulation as specified by the color code. All otherconductors shall be provided with 3/4" wide marking bands of the appropriate color code, on blackinsulation. Marking bands shall be provided at all pull boxes, junction boxes, wiring troughs andterminations.

208/120 VOLT 480/277 VOLT 120/240 VOLTPHASE A - BLACK PHASE A - BROWN PHASE A - BLACKPHASE B - RED PHASE B - ORANGE PHASE B - ORANGEPHASE C - BLUE PHASE C - YELLOW PHASE C - BLUENEUTRAL - WHITE NEUTRAL - GRAY NEUTRAL - WHITEGROUND - GREEN GROUND - GREEN GROUND - GREEN

P. Control conductors: shall be color coded by use of color coded "tracers." No color circuit shallcontain two identical conductors.

3.11 INSTALLATION OF CONTROL DEVICES:

A. Furnishing equipment: Unless otherwise noted, motor starters for all pumping equipment shall beprovided by the manufacturer of the pump control panel. All control wiring for pump controlequipment shall be provided by the Electrical Contractor per the Pump Control Manufacturer’sShop/Coordination Drawings.

3.12 INSTALLATION OF PIPE SLEEVES:

A. Install pipe sleeves at all locations where pipes pass through wet well walls or ceilings.

B. Where subject to moisture or weather, seal sleeves with watertight sealant.

C. Install conduit sleeves under paved areas.

3.13 FEEDER AND BRANCH CIRCUITS:

A. Connection of equipment: connection of all items using electrical power shall be included underthis section of the specifications, including necessary wire, conduit, circuit protection, disconnectsand all accessories. Securing of rough-in drawings and connection information for equipmentinvolved shall also be included. All branch and feeder circuits shall be connected exactly as shownon the drawings, unless specific permission is requested to alter the arrangements shown.

3700-3-15

Page 83: SECTION 03000-1 - Tech Specs 05-29-2015

3.14 GROUNDING:

A. General: This contractor shall provide a complete electrical service grounding system that ensures all metallic components in the building including foundation and structural steel, electrical conduitand raceways, metallic pipe and metal equipment are maintained at ground potential levels not toexceed 5 Ohms to ground. All grounding and bonding methods shall be in accordance with theNational Electric Code and these specifications.

B. Electrical Systems Grounding: The electrical system shall be completely and effectively groundedas required by the NEC and local codes as specified herein or detailed on the Drawings.1. Metallic raceways are not to be utilized as the circuit ground conductors. Contractor is to

provide copper wire ground conductors in all metallic raceways. All other connections ofmetallic raceways to the grounding system is for bonding purposes only.

2. All metallic raceways shall be mechanically and electrically secure at all joints and all boxes,cabinets, fittings and equipment. Metallic raceways shall be bonded to the grounding systemand shall be electrically continuous throughout the entire system.

3. Equipment connected to the conduit system by a section of flexible conduit shall have a fullsize, but not larger than No. 3/0, Grounding shunt installed.

4. The equipment shall be connected to the conduit system by means of a short section (18"minimum) of flexible conduit unless otherwise indicated.

5. Grounding conductor shall be provided in all PVC raceways which contain power conductors.6. Equipment grounding wire shall be bonded to each panel board and to each metallic

enclosure of frame.7. Refer to Section 3790 for Ground Testing Requirements.

3.15 EQUIPMENT IDENTIFICATION:

A. Placards: Provide on all disconnect switches, panelboards, motor starters, each component ofswitchboards and other items of electrical supply equipment, including spares, engraved placardsper Section 3700-3 of this specification.

B. Circuit labels: Identify all connected circuits with a typed panel schedule attached to the inside dooron all electrical panels. Circuit numbers shall be provided on the cover panel of the board, adjacentto the corresponding breaker. If no such numbers have been embossed into the steel cover, thiscontractor shall provide engraved or printed labels to accomplish same. Spare circuits shall benoted as such.

C. Directory: for panelboards, mount a typewritten directory showing the actual circuit numbers, typeof load and room name. Room names used shall be the actual names used, not necessarily thoseshown on the drawings. Submit a typical directory for approval.

3.16 PHASING:

A. General: Phasing of the complete electrical installation shall be connected and maintaineduniformly throughout the power distribution system. Where the project is an addition ormodification to an existing facility, the electrical distribution system phasing shall be made the sameas the existing installation. All switch-gear, safety switches, motor starters, plug-in type bus duct,lighting and power panels and power receptacles shall have the same phase arrangementsthroughout the facility.1. Color Coding Conductors: Wire and cable for feeders and branch circuits shall be identified

with a visual color code as specified in Section 3700-3 of this specification. 2. Grounding Conductors: Provide insulated green copper ground wires for all system ground

conductors. 3. Motor Controls: Power from the motor starter to the motor or similar equipment shall be color

coded black. Control wiring shall be color coded red for the hot (ungrounded) conductorsand white for the grounded conductor. Direct current control conductors shall be color codedblue.

3700-3-16

Page 84: SECTION 03000-1 - Tech Specs 05-29-2015

3.17 INSTALLATION OF CIRCUIT PROTECTIVE DEVICES:

A. Unless otherwise indicated protective devices shall be mounted with top of cabinet or enclosure6'-6" above finished floor, properly aligned and adequately supported independently of theconnecting raceways. All steel shapes, etc, necessary for the support of the equipment shall befurnished and installed by the contractor where the building structure is not suitable for mountingthe equipment directly thereon.

3.18 ENERGIZING PANELBOARDS: Refer to Testing - Section 3790.

3.19 LIGHTING INSTALLATION:

A. Pole Mounted Fixtures:1. Coordinate with other electrical work as necessary to properly interface installation of

roadway and parking area lighting with other work. 2. Use belt slings or rope (not chain or cable) to raise and set finished poles and standards to

protect finishes. 3. Set poles and standards plumb. Support adequately during backfilling, or anchoring to

foundations. 4. Provide sufficient space encompassing hand access and cable entrance holes for installation

of underground cabling where indicated5. Install under ground conduit coordinated to run up through the center of pole / pole base,

exterior conduit connections are not acceptable.6. Provide a 10' copper-clad dedicated secondary ground electrode at each pole location. Bond

all metal components of lighting fixture to secondary ground electrode and building groundvia # 10 AWG (Min.) green wire ground in conduit.

7. All conduit entering light fixtures from under ground shall be sealed using ductseal orequivalent.

B. Lighting Quality Control: 1. Upon completion of installation of lighting fixtures, and after energizing branch supply

circuitry, apply electrical energy to lighting fixtures to demonstrate capability and compliancewith requirements. Where possible, correct malfunctioning units at site, then retest todemonstrate compliance; otherwise, remove and replace with new units, and proceed withretesting.

2. Replace defective and burned-out lamps at the time of Substantial Completion.

END OF SECTION

3700-3-17

Page 85: SECTION 03000-1 - Tech Specs 05-29-2015

SECTION 3760-3 LIGHTNING PROTECTION SYSTEMS

1. PART ONE - GENERAL:

1.1 SECTION INCLUDES

A. Air TerminalsB. Ground RodsC. Down ConductorsD. Ground RingsE. Pipe Bonding of all Metal Piping Systems

1.2 SCOPE:

A. The work to be provided under these specifications shall include furnishing and installing acomplete lightning protection system. The work shall consist of the following:1. Installation of a complete system of air terminals, down conductors and ground rods

in accordance with the guidelines of NFPA 780 or UL Master Label.2. Provide a lightning protection system using Class II Materials per NFPA-780.3. Bonding and Grounding of all Metal Piping Systems.4. Inspection and Testing5. All associated material, hardware, and wiring necessary for a completely installed and

operating system.

1.3 RELATED DOCUMENTS:

A. Division 1. - General requirements.

1.4 REFERENCES:

A. ANSI/NFPA 70, 2008 Edition - National Electric Code.B. ANSI/NFPA 780, 2004 Edition - Lightning Protection Code.C. ANSI/IEEE Std 142-2007 - IEEE Recommended Practice for Grounding of Industrial and

Commercial Power Systems.

1.5 SUBMITTALS:

A. Refer to the Submittals Section in General Requirements and Section 3700-3 for completedescription of submittal data requirements.

B. Submit Manufacturer’s Product Data for the following items:1. Air Terminals and Mounting Bases2. Ground Rods3. Main Down Conductors and Bonding Conductors4. Cable Clamps5. Straps and Fasteners6. Through Roof Assemblies7. Structural Metal Connectors8. Exothermic Welding Materials and Methods

C. Prepare a complete set of working drawings showing plan view locations of all Air Terminals,Bonding Conductors, Main Conductors (Both Down Conductors and Cross-Run Conductors),and Ground Rods; and details of installation for each type. Submit these drawings to theEngineer for review and receive comments, prior to ordering materials.

1.6 WARRANTY:

3760-3-1

Page 86: SECTION 03000-1 - Tech Specs 05-29-2015

A. All labor and material supplied by the Lightning Protection Contractor shall be warranted fora period of one year after acceptance.

2. PART TWO - PRODUCTS:

2.1 ACCEPTABLE MANUFACTURERS:

A. Lightning protection equipment provided under this Section shall be from only one of thefollowing manufacturers:1. Advanced Lightning Technology, Inc. (ALT)2. Alltec Corp3. Erico Inc, Solon, OHwww.erico.com4. Kuefler Lightning Protection, Inc (KLP)5. Independent Protection Company (IPC), Goshen, IN www.ipclp.com6. Robbins Lightning Protection Company, Maryville, MOwww.robbins-lightning.com7. Thompson Lightning Protection, St Paul, MNwww.tlpinc.com

2.2 LIGHTNING PROTECTION SYSTEM:

A. Materials shall be in compliance with the following standards1. UL96A. 2. NEC. 3. NFPA No. 780.

B. General Requirements:1. All materials used for the system installation shall comply in size, composition and

weight to all requirements of NFPA and UL for the class of system in which they areinstalled. All materials shall be labeled or listed by UL for use in master labeledsystems

2. Materials:a. Aluminum - Above grade where mounted on finished metal building surfaces,

galvanized steel surfaces, concrete surfaces and pole mounted lighting fixturesand antennas.

b. Copper - Above grade where mounted on structural steel surfaces (red iron),metal piping systems and finished metal equipment (generators, pumpsequipment structures).

3. Compatibility: All portions of the system shall be galvanically compatible to the buildingmaterial to which they are to be attached. Connections between copper and aluminumportions of the system shall be made with appropriate bimetallic coupling devices. Inall areas, the conductor shall be supported to maintain clearance from all galvanicallyincompatible materials or shall be of the same material.

4. All system components shall be, to the maximum extent possible, the product of asingle manufacturer. All components shall be Class I as required by NFPA 780.All airterminal bases shall be securely mounted to the building structure by bases securedby hard setting epoxy adhesive.

C. Air Terminals:1. Air terminals shall be aluminum or copper as required to match the material / building

system to which they are attached. Air terminals shall protrude a minimum of 10 inchesabove the object to be protected. Center roof terminals shall be 24" high. Air terminalpoints shall be blunt with the radius of curvature equal to the rod diameter.

2. Each air terminal shall be equipped with the correct type of base for the location.3. Air terminals and interconnecting cable shall be provided for all roof mounted

equipment subject to a direct strike as required by NFPA 780.

D. Conductors:

3760-3-2

Page 87: SECTION 03000-1 - Tech Specs 05-29-2015

1. Main roof conductors shall be aluminum and shall provide a two-way patch from eachair terminal horizontally or downward to connections with down conductors. Conductorsshall be free of excessive splices and bends. No bend of a conductor shall form anincluded angle of less than 90 degrees nor have a radius of bend of less than 8 inches.Conductors shall be secured to the structure at intervals not exceeding 3 feet withapproved fasteners.

2. Down conductors shall be aluminum where attached to the building structure and shallbe concealed in the exterior wall construction. Where run in or on reinforced concretecolumns, bond down conductor to the re-bar at top and bottom of column. Downconductors shall be spaced at intervals averaging not more than 100 feet around theperimeter of the structure.

3. Thru-roof penetrations of down conductors are not allowed.4. Down conductors shall be copper where installed below the roof on structure and

routed to the ground grid.5. Main Down Conductors:

a. Aluminum - Class 1 Main Conductor, Ropelay Woven Cable, 28 Strand, 14Gauge Wire, 98,640 Circular Mils, 1/2" Dia, per NFPA 780.

b. Copper - Class 1 Main Conductor, Ropelay Woven Cable, 28 Strand, 16 GaugeWire, 72,258 Circular Mils, 3/8" Dia, per NFPA 780.

6. Bonding Conductors: a. Aluminum - Class 1 Bonding Conductor, Bare Solid Soft Drawn, 4 Gauge Wire,

41,700 Circular Mils, 1/5" Dia, per NFPA 780.b. Copper - Class 1 Bonding Conductor, Bare Solid Soft Drawn, 6 Gauge Wire,

26,250 Circular Mils, 1/6" Dia, per NFPA 780.

E. Fittings:1. Conductor fasteners shall be manufactured of a material which is compatible with the

type of conductor being supported. Fasteners shall be of sufficient strength to properlysupport each conductor or terminal base, etc.

F. Connection Materials:1. Cable-to-cable, cable-to-rod and cable-to-steel connection shall be exothermic-type

welding process or compression-type connectors. 2. Cable-to-Equipment Ground Lugs:

a. Copper alloy terminal with twin clamping element. b. Bolt to equipment housing and hatch doors with silicon bronze bolts and

lockwashers.c. Down Conductor Guards: Guards shall be of self-extinguishing high-impact

polyvinyl chloride or polyethylene.

2.3 GROUND GRID SYSTEM:

A. Wire and Cable:1. Bare Copper Ground Cable:

a. Type BC-2 (Medium Hardness) - 2/0 AWG, 19 Strand, 0.0837 Dia Wire, 133,108Circular Mils, 0.419 Dia, unless otherwise noted on plan.

B. Ground Rods: 1. Solid Copper or Stainless Steel sectional-type rods.2. One end pointed to facilitate driving.3. 5/8-inch diameter and furnished in 10-foot sections with diameter and total length

stamped near top of rod.

C. Ground Test Well:1. Junction box with cover.2. Molded body with high density polymer concrete ring.3. Manufactured by Synertech catalog #S1212B18FA for box and catalog

3760-3-3

Page 88: SECTION 03000-1 - Tech Specs 05-29-2015

#S1212HFAOA01 for cover or approved equal.

D. Connection Materials:1. Cable-to-cable, cable-to-rod, cable-to-steel/iron pipe and cable-to-steel connections

of exothermic-type welding process.

E. Mastic:1. Sonneborn-Sonoshield Mastics. 2. W.R. Meadows-Sealmastic.

2.4 EXOTHERMIC WELDING:

A. Provide appropriately sized molds for exothermic welding of copper cable-to-cable,cable-to-rod, cable-to-steel/iron pipe and cable-to-structural steel sections. All molds to besized for the materials being welded to and all molds to be from the same manufacturer.Contractor may use exothermic welding to attach bonding conductors to vertical or horizontalstructural steel, horizontal steel or cast iron pipe, cable to lugs, cable to cable, and cable toground rods.

3. PART THREE - EXECUTION:

3.1 GENERAL:

A. Install in conformance with the following standards:1. NFPA No. 780.2. UL 96A. 3. NFPA 70 (NEC).

B. Underwriters Laboratories Inc. (UL) Master Label:1. There are five applicable Listing Marks which are used for the Master Label:

a. Air Terminal: Attached to the air terminal near the base.b. Conductor: Attached at 10-foot (3-m) intervals.c. Listed Fittings: UL symbol die-stamped, cast, rolled, or molded into the product

or a permanently secured label.d. Ground Electrode: Rod and pipe electrodes are covered under the Standard for

Grounding and Bonding Equipment, UL 467.In addition to bearing the ListingMark, they shall also comply with the size requirements of Standard UL 96A,Section 8.

e. Master Label: For attachment to the protected structure as evidence that listedlightning protection materials are installed in accordance with Standard UL96A.The location shall be adjacent to the installer's nameplate.

2. Listing Mark Items "a" through "e" are applied to listed components at the factory bythe listed component manufacturer. Listing Marks Item "e" is issued to the structureowner through the listed installer for the protected structures.

3. The Master Label shall only be issued for a lightning protection system that complieswith Standard UL 96A and the applicable specifications.

4. The Master Label may be issued for a system on a structure that is connected to anunprotected structure if the only connection is a walkway which is located in a zone ofprotection and is at least 6 feet (1.8 m) long.

C. Do not install copper lightning protection materials on aluminum roofing, siding material, orother aluminum surfaces. On aluminum surfaces, use aluminum lightning protectionmaterials.

3760-3-4

Page 89: SECTION 03000-1 - Tech Specs 05-29-2015

3.2 LIGHTNING PROTECTION SYSTEM:

A. Install lightning protection systems as indicated, in accordance with equipmentmanufacturer's written instructions, and in compliance with applicable installation standards.Suitably protect cable and air terminals from damage during construction.

B. Air Terminals: 1. Structures not exceeding 75 feet in height: Use Class I materials.2. Air terminals shall be installed within 2 feet of all ends, edges, and corners of the

building.

C. Conductors:1. General:

a. Install conductor with tin-plating in areas subject to corrosion.b. Protect down conductors from physical damage and displacement by installing

guards.2. Structures not exceeding 75 feet in height: Use Class I materials.3. Install conductor with direct paths from air terminals to ground connections avoiding

sharp bends. Where required for protection, run conductors in nonmetallic PVCraceway Schedule 80 with a minimum elbow radius of 8 inches.

D. Bonding: Install in accordance with UL96A.

E. Structure Reinforcing Steel: Reinforcing steel shall be electrically continuous and bonded tothe lightning protection system at both the top and the bottom of the structure.

F. Provide bimetallic connectors when joining copper to aluminum conductors.

3.3 LIGHTNING PROTECTION GROUND GRID SYSTEM:

A. Wire and Cable:1. General:

a. Install using as few joints as possible.b. Protect against unraveling, caging, and abrasion by several wrappings of plastic

tape on all ends. c. Install so as not to be entirely encircled or closely encircled by magnetic material. d. Suitably protect against damage during construction. Replace or repair cable at

if cable is damaged by anyone before final acceptance.e. Protect cable at all points where cable leaves concrete by wrapping rubber tape

on 2 inches either side of the plane formed by the finished concrete surface.2. Buried Installations:

a. Install at locations and depths as specified or indicated. Otherwise install at least18 inches below finished grade or deeper if necessary in order to be in contactwith earth. Install outside of foundation or wall at a distance of not less than 2feet.

b. Maintain clearance of at least three feet from all underground metal piping orstructures where possible, otherwise tape all ground conductors within thisclearance.

c. Backfill with excavated earth free from rocks or stones. Thoroughly compactbackfill

B. Ground Rods:1. Install rods where indicated by driving and not by drilling or jetting.2. Drive rods into unexcavated portion of the earth where possible.3. Where rods must be installed in excavation areas, drive rods into earth after

compaction of backfill is completed.4. Drive to a depth such that top of rods will be approximately 18 inches below final

3760-3-5

Page 90: SECTION 03000-1 - Tech Specs 05-29-2015

grade, or subgrade, and connect to the buried grid ground conductors.

C. Ground Test Well:1. Install at locations indicated on drawings.

D. Connections:1. Conform to manufacturer's instructions2. Chemically degrease and dry completely before welding or applying compression-type

connectors.3. Apply coating to all exothermic-welded connections to be buried, at 15 mils dry film

thickness, after checking of connections by Engineer.4. Make up bolted connections clean and tight.5. Low-resistance connections with resistance drop not exceeding 1 ohm.6. Do not cover up connections before they are checked by Engineer.

3.4 CORROSION PROTECTION:

A. Use no combination of materials that may form an electrolytic couple of such nature thatcorrosion is accelerated in the presence of moisture, unless moisture is permanentlyexcluded from the junction of such metals. Where unusual conditions exist that would causedeterioration or corrosion of conductors, use conductors with suitable protective coatings.

3.5 INSPECTION AND MAINTENANCE:

A. Inspection of Lightning Protection Systems1. Frequency of Inspections. All new lightning protection systems must be inspected

following completion of their installation. The system should be inspected wheneverany alterations or repairs are made to a protected structure; also, following any knownlightning discharge to the system. The system should be inspected semi-annually.

2. Visual Inspection. Visual inspections are made to ascertain the following:a. The system is in good repair.b. There are no loose connections which might result in high resistance joints.c. No part of the system has been weakened by corrosion or vibration.d. All down conductors and ground terminals are intact (non-severed).e. All conductors and system components are securely fastened to their mounting

surfaces and are protected against accidental mechanical displacement asrequired.

f. There have not been additions or alterations to the protected structure whichwould require additional protection.

g. There has been no visual indication of damage to surge suppression (overvoltage) devices.

h. The system complies in all respects with the current edition of the LightningProtection Code.

3. Provide UL inspection and delivery of UL Master Label to Owner.

B. Maintenance of Lightning Protection Systems1. Maintenance Procedures: Lightning protection system maintenance procedures should

be established and become a part of the overall maintenance program for the structurewhich it protects.

2. A maintenance program should contain a list of more or less routine items that mayserve as a check list so that a definite maintenance procedure can be followedregularly. It is the repeatability of the procedures that enhance the effectiveness of agood maintenance program.

3. A good maintenance program should contain provisions for the following:a. Inspection of all conductors and system components.b. Tightening of all clamps and splicers.c. Measurement of lightning protection system resistance.

3760-3-6

Page 91: SECTION 03000-1 - Tech Specs 05-29-2015

d. Measurement of resistance of ground terminals.e. Inspection of and/or testing of surge protection devices to determine their

effectiveness compared with similar new devices.f. Refastening and tightening of components and conductors as required.g. Inspection and testing as required to determine if the effectiveness of the

lightning protection system has been altered due to additions to, or changes in,the structure.

4. Maintenance Records - Complete records shall be kept of all maintenance proceduresand routines and shall include corrective actions that have been or will be taken.Records provide a means of evaluating system components and their installation. Theyalso serve as a basis for reviewing maintenance procedures as well as updatingpreventative maintenance programs.

END OF SECTION

3760-3-7

Page 92: SECTION 03000-1 - Tech Specs 05-29-2015

SECTION 3790-3 ELECTRICAL TESTING

1. PART ONE - GENERAL:

1.1 SCOPE:

A. Tests specified in this section are to be performed in accordance with the requirements of START-UP Section in the General Conditions and the applicable requirements of other Electrical Sections.

B. The work to be performed under this section includes all labor, materials, equipment and servicesnecessary to bring the complete electrical system to a state of substantial completion, as shownon the drawings and as specified.

1.2 REFERENCES:

A. ANSI/NFPA 70 - 2008 - National Electric Code.B. ANSI/NFPA 780 - 2011 - Standard for the Installation of Lightning Protection Systems.C. ANSI/IEEE Std 142 - 2007 - IEEE Recommended Practice for Grounding of Industrial and

Commercial Power Systems.D. International Electrical Testing Association (NETA) - ATS, Acceptance Testing Specifications for

Electrical Power Distribution Equipment and Systems.

1.3 SUBMITTALS:

A. Administrative Submittals - Submit 30 days prior to performing inspections or tests: 1. Schedule for performing inspection and tests. 2. List of references to be used for each test. 3. Sample copy of equipment and materials inspection form(s). 4. Sample copy of individual device test form. 5. Sample copy of individual system test form.

B. Test / Inspection Reports - Submit within 30 days after completion of test:1. Test or inspection reports and certificates for each electrical item tested. 2. The following test shall be performed on instrumentation and control system cables. All tests

shall be end-to-end test of installed cables with the ends supported in free air, not adjacentto any ground object. All test data shall be recorded on forms acceptable to the Engineer. Complete records of all tests shall be made and delivered to the Engineer. a. Continuity tests shall be performed by measuring wire/shield loop resistance of signal

cable as the wires, taken one at a time, are shorted to the channel shield. No loopresistance measurement shall carry by more than +2 ohms from the calculatedaverage loop resistance value.

b. Insulation resistance tests shall be performed by using a 500 volt megohmeter tomeasure the insulation resistance between each channel wire, between each channelwire and channel shield, between individual channel shields in a multi-channel cable,between each individual channel and the overall cable shield in multi-channel cable,between each wire and ground, and between each shield and ground. Values ofresistance less than 10 megohms shall be unacceptable.

C. Contract Closeout Submittals: 1. Operation and Maintenance Data: After test or inspection reports and certificates have been

reviewed by Engineer and returned, insert a copy of each in operation and maintenancemanual.

3790-3-1

Page 93: SECTION 03000-1 - Tech Specs 05-29-2015

1.4 QUALITY ASSURANCE

A. Testing Firm Qualifications: 1. Corporately and financially independent organization functioning as an unbiased testing

authority. 2. Professionally independent of manufacturers, suppliers, and installers, of electrical

equipment and systems being tested. 3. Employer of engineers and technicians regularly engaged in testing and inspecting of

electrical equipment, installations, and systems. 4. Technicians certified by NICET or NETA. 5. Assistants and apprentices assigned to project at ratio not to exceed two certified to one

non-certified assistant or apprentice. 6. In compliance with OSHA Title 29, Part 1907 criteria for accreditation of testing laboratories

or a full Member Company of International Electrical Testing Association.

B. Test equipment shall have an operating accuracy equal to, or greater than, requirementsestablished by NETA ATS.

C. Test instrument calibration shall be in accordance with NETA ATS.

1.5 SEQUENCING AND SCHEDULING

A. Perform inspection and electrical tests after equipment has been installed.

B. Perform tests with apparatus de-energized whenever feasible.

C. Inspection and electrical tests on energized equipment are to be: 1. Scheduled with Engineer prior to de-energization. 2. Minimized to avoid extended period of interruption to the operating plant equipment.

D. Notify Engineer at least 24 hours prior to performing tests on energized electrical equipment.

2. PART TWO - PRODUCTS:

2.1 GENERAL:

A. The Electrical Contractor shall furnish all equipment necessary to perform any test ordemonstration specified or required. Equipment and personnel required to perform tests anddemonstrations shall be included in the Electrical Contractors basic proposal.

B. Furnish completed checklist and or reports of commissioning procedures and inspections asdirected by the Engineer or required in this section.

3. PART THREE - EXECUTION:

3.1 GENERAL:

A. Tests and inspection shall establish that:1. Electrical equipment is operational within industry and manufacturer’s tolerances. 2. Installation operates properly. 3. Equipment is suitable for energization. 4. Installation conforms to requirements of Contract Documents and NFPA 70, and ANSI C2.

B. Perform inspection and testing in accordance with NETA ATS, industry standards, andmanufacturer's recommendations, including the following:

3790-3-2

Page 94: SECTION 03000-1 - Tech Specs 05-29-2015

1. Set, test, and calibrate protective relays, circuit breakers, fuses, and other applicable devicesin accordance with values established by the short circuit and coordination study or asdirected by the Engineer.

2. Adjust mechanisms and moving parts for free mechanical movement. 3. Adjust adjustable relays and sensors to correspond to operating conditions, or as

recommended by manufacturer. 4. Verify nameplate data for conformance to Contract Documents. 5. Realign equipment not properly aligned and shim into level condition. 6. Properly anchor electrical equipment found to be inadequately anchored. 7. Tighten accessible bolted connections, including wiring connections, with calibrated torque

wrench to manufacturer's recommendations, or as otherwise specified. 8. Clean contaminated surfaces with cleaning solvents as recommended by manufacturer. 9. Provide proper lubrication of applicable moving parts. 10. Inform Engineer of working clearances not in accordance with NFPA 70. 11. Investigate and repair or replace:

a. Electrical items that fail tests. b. Active components not operating in accordance with manufacturer's instructions. c. Damaged electrical equipment.

12. Electrical Enclosures: a. Remove foreign material and moisture from enclosure interior. b. Vacuum and wipe clean enclosure interior. c. Remove corrosion found on metal surfaces. d. Repair or replace, as determined by Engineer, door and panel sections having dented

surfaces.e. Repair or replace, as determined by Engineer, poor fitting doors and panel sections. f. Repair or replace improperly operating latching, locking, or interlocking devices. g. Replace missing or damaged hardware. h. Provide matching paint and touch up scratches and mars. i. If required due to extensive damage, as determined by Engineer, refinish the entire

assembly. 13. Replace fuses and circuit breakers that do not conform to size and type required by the

Contract Documents.

3.2 METERING

A. Visual and Mechanical Inspection: 1. Verify meter connections in accordance with appropriate diagrams. 2. Verify meter multipliers. 3. Verify that meter types and scales conform to Contract Documents. 4. Check calibration of meters at cardinal points. 5. Check calibration of electrical transducers.

3.3 PANELBOARDS & PUMP CONTROL PANELS:

A. Visual and Mechanical Inspection: 1. Insulator damage and contaminated surfaces. 2. Proper operation of indicating devices. 3. Check Door and Device Interlocking System By:

a. Closure attempt of device when door is in OFF or OPEN position. b. Opening attempt of door when device is in ON or CLOSED position.

4. Check Key Interlocking Systems For: a. Key captivity when device is in ON or CLOSED position. b. Key removal when device is in ON or CLOSED position. c. Closure attempt of device when key has been removed. d. Correct number of keys in relationship to number of lock cylinders. e. Existence of other keys capable of operating lock cylinders. Destroy duplicate sets of

keys.

3790-3-3

Page 95: SECTION 03000-1 - Tech Specs 05-29-2015

5. Check Nameplates for Proper Identification Of: a. Equipment title and tag number with latest one-line diagram. b. Pushbutton. c. Control switch. d. Pilot light. e. Control relay. f. Circuit breaker. g. Indicating meter.

6. Verify that fuse and circuit breaker ratings, sizes, and types conform to those specified, 7. Check bus and cable connections for high resistance by thermographic survey, low

resistance ohmmeter and calibrated torque wrench applied to bolted joints. a. Ohmic value to be zero. b. Bolt torque level in accordance with NETA ATS, Table 10. 1, unless otherwise specified

by manufacturer. c. Thermographic survey temperature gradient of 2 degrees C, or less.

8. Check Operation and Sequencing of Electrical and Mechanical Interlock Systems By: a. Closure attempt for locked open devices. b. Opening attempt for locked closed devices. c. Key exchange to operate devices in OFF-NORMAL positions.

9. Verify performance of each control device and feature. 10. Control Wiring:

a. Compare wiring to local and remote control and protective devices with elementarydiagrams.

b. Proper conductor lacing and bundling.c. Proper conductor identification. d. Proper conductor logs and connections.

11. Exercise active components. 12. Perform phasing check on double-ended equipment to ensure proper bus phasing from each

source.

B. Electrical Tests: 1. Insulation Resistance Tests:

a. Applied megohmeter dc voltage in accordance with NETA ATS, Table 7.1.1. b. Each phase of each bus section. c. Phase-to-phase and phase-to-ground for 1 minute. d. With switches and breakers open. e. With switches and breakers closed. f. Control wiring except that connected to solid state components. g. Insulation resistance values equal to, or greater than, Ohmic values established by

manufacturer. 2. Overpotential Tests:

a. Applied AC or DC voltage and test procedure in accordance with ANSI C37.20.3 andNEMA PB 2.

b. Each phase of each bus section. c. Phase-to-phase and phase-to-ground for 1 minute. d. Test results evaluated on a pass/fail basis.

3. Current Injection Tests: a. For entire current circuit in each section. b. Secondary injection for current flow of 1 ampere. c. Test current at each device.

4. Control Wiring: a. Apply secondary voltage to control power and potential circuits. b. Check voltage levels at each point on terminal boards and each device terminal.

5. Operational Test: a. Initiate control devices. b. Check proper operation of control system in each section.

3790-3-4

Page 96: SECTION 03000-1 - Tech Specs 05-29-2015

3.4 MOLDED AND INSULATED CASE CIRCUIT BREAKERS

A. General: Inspection and testing limited to circuit breakers rated 70 amperes and larger and tomotor circuit protector breakers rated 50 amperes and larger.

B. Visual and Mechanical Inspection: 1. Proper mounting. 2. Proper conductor size. 3. Feeder designation according to nameplate and one-line diagram. 4. Cracked casings. 5. Connection bolt torque level in accordance with NETA ATS, Table 10.1. 6. Operate breaker to verify smooth operation. 7. Compare frame size and trip setting with circuit breaker schedules or one-line diagram. 8. Verify that terminals are suitable for 75 degrees C rated insulated conductors.

C. Electrical Tests: 1. Insulation Resistance Tests:

a. Utilize 1,000-volt dc megohmeter for 480- and 600-volt circuit breakers and 500-volt dcmegohmeter for 240-volt circuit breakers.

b. Pole-to-pole and pole-to-ground with breaker contacts opened for 1 minute. c. Pole-to-pole and pole-to-ground with breaker contacts closed for 1 minute. d. Test values to comply with NETA ATS, Table 10.2.

2. Contact Resistance Tests: a. Contact resistance in microhms across each pole. b. Investigate deviation of 50 percent or more from adjacent poles and similar breakers.

3. Primary Current Injection Test to Verify: a. Long-time minimum pickup and delay. b. Short-time pickup and delay. c. Ground fault pickup and delay. d. Instantaneous pickup by run-up or pulse method. e. Trip characteristics of adjustable trip breakers shall be within manufacturer's published

time-current characteristic tolerance band, including adjustment factors. Trip timesshall be within limits established by NEMA AB 4, Table 5-3.

f. Instantaneous pickup value shall be within values established by NEMA AB 4, Table5-4.

3.5 DRY TYPE TRANSFORMERS

A. Visual and Mechanical Inspection: 1. Physical and insulator damage. 2. Proper winding connections. 3. Bolt torque level in accordance with NETA ATS, Table 10.1, unless otherwise specified by

manufacturer. 4. Defective wiring. 5. Proper operation of fans, indicators, and auxiliary devices. 6. Removal of shipping brackets, fixtures, or bracing. 7. Free and properly installed resilient mounts. 8. Cleanliness and improper blockage of ventilation passages. 9. Verify that tap-changer is set at correct ratio for rated output voltage under normal operating

conditions. 10. Verify proper secondary voltage phase-to-phase and phase-to-ground after energization and

prior to loading.

B. Electrical Tests: 1. Insulation Resistance Tests:

a. Applied megohmeter dc voltage in accordance with NETA ATS, Table 7.2.3 for each: 1) Winding-to-winding.

3790-3-5

Page 97: SECTION 03000-1 - Tech Specs 05-29-2015

2) Winding-to-ground, b. l0-minute test duration with resistances tabulated at 30 seconds, 1 minute, and 10

minutes. c. Results temperature corrected in accordance with NETA ATS, Table 7.2.4. d. Temperature corrected insulation resistance values equal to, or greater than, Ohmic

values established by manufacturer. e. Insulation resistance test results to compare within 1 percent of adjacent windings.

2. Perform tests and adjustments for fans, controls, and alarm functions as suggested bymanufacturer.

3.6 LOW VOLTAGE CABLES, 600 VOLTS MAXIMUM

A. Visual and Mechanical Inspection: 1. Inspect Each Individual Exposed Power Cable No. 6 and Larger For:

a. Physical damage. b. Proper connections in accordance with single-line diagram. c. Cable bends not in conformance with manufacturer's minimum allowable bending

radius where applicable. d. Color coding conformance with specifications. e. Proper circuit identification.

2. Mechanical Connections For: a. Proper lug type for conductor material. b. Proper lug installation. c. Bolt torque level in accordance with NETA ATS, Table 10. 1, unless otherwise specified

by manufacturer. 3. Shielded Instrumentation Cables For:

a. Proper shield grounding. b. Proper terminations. c. Proper circuit identification.

4. Control Cables For: a. Proper termination. b. Proper circuit identification.

5. Cables Terminated Through Window Type CT's: Verify that neutrals and grounds areterminated for correct operation of protective devices.

B. Electrical Tests for Conductors No. 6 and Larger: 1. Insulation Resistance Tests:

a. Test each conductor with respect to ground and to adjacent conductors per IEEE 118procedures for 1 minute.

b. Evaluate Ohmic values by comparison with conductors of same length and type. c. Investigate values less than 50 megohms. d. Utilize 1,000VDC megohmeter for 600V insulated conductors.

2. Continuity test by ohmmeter method to ensure proper cable connections.

3.7 INSTRUMENT/CONTROL TRANSFORMERS

A. Visual and Mechanical Inspection: 1. Visually Check Current, Potential, and Control Transformers For:

a. Cracked insulation. b. Broken leads or defective wiring. c. Proper connections. d. Adequate clearances between primary and secondary circuit wiring.

2. Verify Mechanically That: a. Grounding and shorting connections have good contact. b. Withdrawal mechanism and grounding operation, when applicable, operate properly.

3. Verify proper primary and secondary fuse sizes for potential transformers.

3790-3-6

Page 98: SECTION 03000-1 - Tech Specs 05-29-2015

B. Electrical Tests: 1. Current Transformer Tests:

a. Insulation resistance test of transformer and wiring-to-ground at 1,000 volts dc for 30seconds.

b. Polarity test. 2. Potential Transformer Tests:

a. Insulation resistance test at test voltages in accordance with NETA ATS, Table 7.1.1for 1 minute on: 1) Winding-to-winding. 2) Winding-to-ground.

b. Polarity test to verify polarity marks or H1-X1 relationship as applicable. 3. Insulation resistance measurement on instrument transformer shall not be less than that

shown in NETA ATS, Table 7.1.1.

3.8 GROUNDING SYSTEMS:

A. Visual and Mechanical Inspection: 1. Equipment and circuit grounds in motor control centers, panelboards, switchboards, and

switchgear assemblies for proper connection and tightness. 2. Ground bus connections in motor control centers, panelboards, switchboards, and switchgear

assemblies for proper termination and tightness, 3. Effective transformer core and equipment grounding. 4. Accessible connections to grounding electrodes for proper fit and tightness. 5. Accessible exothermic-weld grounding connections to verify that molds were fully filled and

proper bonding was obtained.

B. Electrical Testing:1. Fall-Of-Potential Test:

a. In accordance with IEEE 81, Section 8.2.1.5 for measurement of main groundsystem's resistance.

b. Main ground electrode system resistance to ground to be no greater than 5 ohms.2. Two-Point Direct Method Test:

a. In accordance with IEEE 81, Section 8.2. 1.1 for measurement of ground resistancebetween main ground system, equipment frames, and system neutral and derivedneutral points.

b. Equipment ground resistance shall not exceed main ground system resistance by 0.50ohm.

C. Reducing Resistance to Ground of an Electrode may be accomplished as follows:a. Install longer ground rods: Long ground rods made in sections coupled together are

very effective where there is considerable depth of dry sand and good moist soil ismany feet underground.

b. Install additional ground rods: Install two, three, or more rods in parallel spaced aminimum of six feet apart. Bond ground rods with a continuous code sized groundconductor.

c. Chemical treatment of the soil: This method of reducing ground resistance may beperformed only with the expressed written approval by the Engineer. The Contractorshall submit proposed methods and chemical for review if this technique is requested.

3.9 GROUND FAULT SYSTEMS

A. Inspection and Testing Limited To: Test all Ground Fault Isolated receptacles.

3.10 AC INDUCTION MOTORS

A. General: Inspection and testing limited to motors rated 5 horsepower and larger.

3790-3-7

Page 99: SECTION 03000-1 - Tech Specs 05-29-2015

B. Visual and Mechanical Inspection: 1. Proper electrical and grounding connections. 2. Shaft alignment. 3. Blockage of ventilating air passageways. 4. Operate Motor and Check For:

a. Excessive mechanical and electrical noise. b. Overheating. c. Correct rotation. d. Check vibration detectors, resistance temperature detectors, or motor inherent

protectors for functionality and proper operation. e. Excessive vibration.

5. Check operation of space heaters.

C. Electrical Tests: 1. Insulation Resistance Tests:

a. In accordance with IEEE 43 at test voltages established by NETA ATS, Table 10.2 for: 1) Motors above 200 horsepower for l0-minute duration with resistances tabulated

at 30 seconds, 1 minute, and 10 minutes. 2) Motors 200 horsepower and less for 1-minute duration with resistances tabulated

at 30 and 60 seconds. b. Insulation resistance values equal to, or greater than, Ohmic values established by

manufacturers. 2. Calculate polarization index ratios for motors above 200 horsepower. Investigate index ratios

less than 1.5 for Class A insulation and 2.0 for Class B insulation. 3. Insulation resistance test on insulated bearings in accordance with manufacturer's

instructions. 4. Measure running current and voltage, and evaluate relative to load conditions and nameplate

full-load amperes. 5. Overpotential Tests:

a. Applied dc voltage in accordance with IEEE 95. b. Limited to 4,000-volt motors rated 1,000 horsepower and greater. c. Test results evaluated on pass/fail basis.

3.11 LOW VOLTAGE MOTOR CONTROL

A. Visual and Mechanical Inspection: 1. Proper barrier and shutter installation and operation. 2. Proper operation of indicating and monitoring devices. 3. Proper overload protection for each motor. 4. Improper blockage of air cooling passages. 5. Proper operation of draw out elements. 6. Integrity and contamination of bus insulation system. 7. Check Door and Device Interlocking System By:

a. Closure attempt of device when door is in OFF or OPEN position. b. Opening attempt of door when device is in ON or CLOSED position.

8. Check Key Interlocking Systems For: a. Key captivity when device is in ON or CLOSED position. b. Key removal when device is in OFF or OPEN position. c. Closure attempt of device when key has been removed. d. Correct number of keys in relationship to number of lock cylinders. e. Existence of other keys capable of operating lock cylinders; destroy duplicate sets of

keys. 9. Check Nameplates for Proper Identification Of:

a. Equipment title and tag number with latest one-line diagram. b. Pushbuttons. c. Control switches. d. Pilot lights.

3790-3-8

Page 100: SECTION 03000-1 - Tech Specs 05-29-2015

e. Control relays. f. Circuit breakers. g. Indicating meters.

10. Verify that fuse and circuit breaker sizes and types conform to Contract Documents. 11. Verify that current and potential transformer ratios conform to Contract Documents. 12. Check Bus Connections for High Resistance by Low Resistance Ohmmeter and

Thermographic Survey: a. Ohmic value to be zero. b. Bolt torque level in accordance with NETA ATS, Table 10.1, unless otherwise specified

by manufacturer. c. Thermographic survey temperature gradient of 2 degrees C, or less.

13. Check Operation and Sequencing of Electrical and Mechanical Interlock Systems By: a. Closure attempt for locked open devices. b. Opening attempt for locked closed devices. c. Key exchange to operate devices in OFF-NORMAL positions.

14. Verify performance of each control device and feature furnished as part of the motor controlcenter.

15. Control Wiring: a. Compare wiring to local and remote control, and protective devices with elementary

diagrams. b. Check for proper conductor lacing and bundling. c. Check for proper conductor identification. d. Check for proper conductor lugs and connections.

16. Exercise active components. 17. Inspect Contactors For:

a. Correct mechanical operations. b. Correct contact gap, wipe, alignment, and pressure. c. Correct torque of all connections.

18. Compare overload heater rating with full-load current for proper size. 19. Compare motor protector and circuit breaker with motor characteristics and power factor

correction capacitors for proper size. 20. Perform phasing check on double-ended motor control centers to ensure proper bus phasing

from each source.

B. Electrical Tests: 1. Insulation Resistance Tests:

a. Applied megohmeter dc voltage in accordance with NETA ATS, Table 10.2. b. Bus section phase-to-phase and phase-to-ground for 1 minute on each phase. c. Contactor phase-to-ground and across open contacts for 1 minute on each phase. d. Starter section phase-to-phase and phase-to-ground on each phase with starter

contacts closed and protective devices open. e. Test values to comply with NETA ATS, Table 10.2.

2. Overpotential Tests: a. Maximum applied ac or dc voltage in accordance with NETA ATS, Table 7.1.2. b. Phase-to-phase and phase-to-ground for 1 minute for each phase of each bus section. c. Test results evaluated on pass/fail basis.

3. Current Injection through Overload Unit at 300 Percent of Motor Full-Load Current andMonitor Trip Time: a. Trip time in accordance with manufacturer's published data. b. Investigate values in excess of 120 seconds.

4. Control Wiring Tests: a. Apply secondary voltage to control power and potential circuits. b. Check voltage levels at each point on terminal boards and each device terminal. c. Insulation resistance test at 1,000 volts dc on control wiring except that connected to

solid state components. 1) Insulation resistance to be 1 megohms minimum.

5. Operational test by initiating control devices to affect proper operation.

3790-3-9

Page 101: SECTION 03000-1 - Tech Specs 05-29-2015

3.12 STANDBY GENERATOR SYSTEMS

A. Visual and Mechanical Inspection: 1. Proper grounding. 2. Blockage of ventilating passageways. 3. Proper operation of jack water heaters. 4. Integrity of engine cooling and fuel supply systems. 5. Excessive mechanical and electrical noise. 6. Overheating of engine or generator. 7. Proper installation of vibration isolators. 8. Proper cooling liquid type and level. 9. Operate Engine-Generator and Check For:

a. Excessive mechanical and electrical noise. b. Overheating. c. Correct rotation. d. Check resistance temperature detectors or generator inherent thermal protectors for

functionality and proper operation. e. Excessive vibration.

10. Verify that voltage regulator and governor operation will cause unit speed and output voltageto stabilize at proper values within reasonable length of time.

11. Proper operation of meters and instruments. 12. Compare generator nameplate rating and connection with one-line diagram. 13. Verify engine-generator operation with adjustable frequency drives energized and operating

under normal load conditions.

B. Electrical and Mechanical Tests: 1. Cold start test by interrupting normal power source with test load consisting of connected

building load to verify: a. Transfer switch operation. b. Automatic starting operation. c. Operating ability of engine-generator. d. Overcurrent devices capability to withstand inrush currents.

2. Phase rotation tests. 3. Test Engine Protective Shutdown Features For:

a. Low oil pressure. b. Overtemperature. c. Overspeed.

4. Vibration base-line test on generator sets rated above 250 kW; levels in accordance withmanufacturer's recommendations.

5. Load bank test with reactors and resistors adjusted to 80 percent power factor for each loadstep. Record voltage, frequency, load current, oil pressure, and engine coolant temperatureat 15-minute intervals: a. 25 percent applied load for 30 minutes. b. 50 percent applied load for 30 minutes. c. 75 percent applied load for 30 minutes. d. 100 percent applied load for 3 hours. e. Load test results to demonstrate ability of unit to deliver rated load for test period.

6. One-Step Rated kW Load Pickup Test: a. Perform test immediately after performing load bank test. b. Apply rated load, minus largest rated horsepower motor, to generator. c. Start largest rated horsepower motor and record voltage drop for 20 cycles minimum

with high-speed chart recorder or digital storage oscilloscope. d. Compare voltage drop with maximum allowable voltage dip for specified starting

situation.

3790-3-10

Page 102: SECTION 03000-1 - Tech Specs 05-29-2015

3.13 THERMOGRAPHIC SURVEY

A. Provide a thermographic survey of connections associated with incoming service conductors, buswork, and branch feeder conductors No. 2 and larger at each: 1. Medium voltage switchgear and transformer. 2. Low voltage switchgear and switchboard. 3. Low voltage motor control center. 4. Panelboard.

B. Provide a thermographic survey of feeder conductors No. 2 and larger terminating at: 1. Motors rated 30 horsepower and larger. 2. Medium and low voltage disconnect switches. 3. Transfer switches. 4. Engine-generators.

C. Remove necessary enclosure metal panels and covers prior to performing survey.

D. Perform with equipment energized during periods of maximum possible loading.

E. Do not perform survey on equipment operating at less than 20 percent of rated connectedoperating load.

F. Utilize Thermographic Equipment Capable of: 1. Detecting emitted radiation. 2. Converting detected radiation to visual signal. 3. Detecting 1 degree C temperature difference between subject area and reference point of

30 degrees C.

G. Temperature Gradients Of: 1. 3 degrees C to 7 degrees C indicates possible deficiency that warrants investigation. 2. 7 degrees C to 15 degrees C indicates deficiency that is to be corrected as time permits. 3. 16 degrees C and above indicates deficiency that is to be corrected immediately.

H. Provide Written Report Of: 1. Areas surveyed and the resultant temperature gradients. 2. Locations of areas having temperature gradients of 3 degrees C or greater. 3. Cause of heat rise and actions taken to correct the cause of heat rise. 4. Detected phase unbalance.

END OF SECTION

3790-3-11

Page 103: SECTION 03000-1 - Tech Specs 05-29-2015

SECTION 3800-3 ENGINE GENERATOR SYSTEM

1. PART ONE - GENERAL:

1.1 SECTION INCLUDES:

A. Engine - GeneratorB. MufflerC. Base Mounted Fuel TankD. Sound Attenuating EnclosureF. Access CatwalksE. Controls & Interface

1.2 SCOPE:

A. Provide complete factory assembled generator set with digital electronic controls, including:Residential Grade Muffler, Base Mounted Fuel Tank, Sound Attenuating Enclosure, AccessCatwalks, Factory Test, Startup by a supplier authorized by the manufacturer, and on-sitetesting of the system.

B. These Specifications are intended to provide a general description of the requirements, but donot identify all details which vary with the requirements of equipment offered.

1.3 CODES AND STANDARDS:

A. The generator set and its installation and on-site testing shall conform to the requirements ofthe following codes and standards:1. FCC Part 15, Subpart B.2. NEMA ICS10 - AC Generator sets. 3. NFPA70 - National Electrical Code, 2008 Edition.4. NFPA110 - Emergency and Standby Power Systems. The generator set shall meet all

requirements for Standby Power System.5. UL508 - The entire control system of the generator set shall be UL508 listed and labeled.6. UL2200 - The genset shall be listed to UL2200 or submit to an independent third party

certification process to verify compliance as installed.7. UL142 - Steel Aboveground Tanks for Flammable and Combustible Liquids8. Florida Building Code - Building, 2010 Edition W\ 2012 Supplements.9. Florida Building Code - Test Protocols for High Velocity Hurricane Zones, 2010 Edition.10. Florida Building Code - Energy Conservation, 2010 Edition W\ 2012 Supplements.11. Florida Fire Prevention Code (FFPC), 2014 Edition.12. National Electric Code - NFPA 70, 2008 Edition.

B. The generator set manufacturer shall be certified to ISO 9001 International Quality Standardand shall have third party certification verifying quality assurance in design/development,production, installation, and service, in accordance with ISO 9001.

1.4 SUBMITTALS:

A. Submit Shop Drawings and Manufacturer’s Product Data. Data to be provided to the PrimeEngineer for review by the MEP Engineer within fifteen (15) working days after receipt ofpurchase order from the Owner. All generator submittal data shall be reviewed and acceptedprior to placement of the factory work order.

B. All Generator submittal data is to be provided at one time, in a complete package to the PrimeEngineer with sufficient time to provide 15 working days to review of this material.

C. Submittal data may be provided in hard copy paper form or in Digital form. If the contractorchooses to supply Digital Data, the Format and Organization requirements described below,apply with the following:1. Digital Submittals shall be assembled into a single generic PDF format file that is viewable

by multiple platforms. PDF File shall be a PDF/X, PDF/A or PDF/E (PDF 1.7) format freeof all Adobe XML Forms Architecture and Java Script. PDF 2.0 files are not acceptable.

3800-3-1

Page 104: SECTION 03000-1 - Tech Specs 05-29-2015

2. Digital Submittals shall meet all the same requirements for organization and presentationas hard copy bound submittals.

3. Provided Manufacturer’s Product Data and Shop Drawings for each specification sectionas a single complete, indexed section in the submittal. Partial submittals will not beaccepted but will count as a billable review.

4. Digital files may be transferred via e-mail or FTP Site and the contractor is required toprovide a CD or DVD disk as a hard copy back-up.

5. Digital submittals will be organized in the same manner as bound copy submittals,contractor is to review and incorporate all bound copy instructions in to the digitalsubmittal.

6. Scanned images may be incorporated into the submittal, however; they shall be clear,completely and legible. Pages shall be oriented within not more than 2 degrees ofmisalignment. Illegible submittals will be rejected and count as a billable review.

D. Where product data sheets include more than one item and were items not being submitted areshown, each item being submitted is to be clearly identified by an arrow, high lighter or box. Where data sheets include items not germane to the project that have not been marked, thesubmittal will be rejected and count as a billable review.

E. Submit manufacturer's shop drawings for the following items:1. Engine Generator Set.2. Remote Annunciator(s)3. Sound Attenuating Enclosure.4. Base Mounted Fuel Storage Tank.5. Access Catwalks6. All Generator Connections (Power and Communications).

F. Submit manufacturer's product data for the following items.1. Circuit Breakers2. Switch Contacts3. Switch Enclosure4. Remote Annunciator(s)5. Exhaust/Muffler6. Engine7. Generator8. Controls9. Batteries & Battery Charger

G. Shop drawings to include; all installation drawings, schematics, and wiring diagrams whichshow details of installation and connections to the work of other sections, including foundationdrawing showing location and size of foundation bolts for the spring type vibration isolators andbrochures covering each item of equipment.

H. Engine Data to include but not limited to; Manufacturer, Model. Make and model anddescriptive literature of electric governor (where required), Fuel consumption rate curves atvarious loads, Engine continuous pump drive duty rating (without fan) Rated HP.

I. Generator Data to include but not limited to; Manufacturer, Model, Rated KVA, Rated kW,Voltage, Temperature rise above 40 degree C ambient, Stator by thermometer, Field byresistance, Class of insulation, Generator efficiency including excitation losses and at 80percent power factor (at full load, 3/4 load & ½ load).

J. Generator unit Control Data to include but not be limited to; electrical diagrams andinterconnection wiring diagrams for all equipment to be provided, legends for all devices ondiagrams and sequence of operation explanations for all portions of all schematic wiringdiagrams.

3800-3-2

Page 105: SECTION 03000-1 - Tech Specs 05-29-2015

K. Operating & Maintenance (O&M) Instructions:1. Three copies of the operating and maintenance manuals shall be furnished. The

manuals shall be prepared specifically for this installation and shall include all requiredcuts, drawings, equipment lists, descriptions, etc. that are required to instruct operatingand maintenance personnel unfamiliar with such equipment.

2. A factory representative who has complete knowledge of proper operation andmaintenance shall be provided for one (1) day after completion of all training to instructrepresentatives of the Owner on proper operation and maintenance.

1.5 QUALITY ASSURANCE:

A. Acceptable Generator Set Manufacturers: The Generator Set Manufacturer shall maintain andstaff engineering service and repair shops through the United States, including the State ofFlorida, trained to do start up service, emergency service calls, repair work, service contractsand training of customer personnel. Generator Sets by one of the following manufacturers' maybe incorporated in the work:1. Cummins-Onan Company2. Caterpillar, Inc.3. Detroit Diesel.

B. Automatic Transfer Switch: The automatic transfer switch specified in SECTION 3850-3 shallbe supplied by the generator set manufacturer in order to establish and maintain a singlesource of system responsibility and coordination.

C. Warranty:1. The generator set manufacturer shall warrant all equipment provided under this section,

whether or not is manufactured by the generator set manufacturer, so that there is onesource for warranty and product service.

2. Provide under base bid: The manufacturer's standard warranty for a period of two (2)years from date of initial start-up of the system and shall include repair parts, labor,reasonable travel expense necessary for repairs at the job site, and expendables(lubricating oil, filters, antifreeze, and other service items made unusable by the defect)used during the course of repair. Running hours shall be limited to 500 hours annually forthe system warranty by both the manufacturer and servicing distributor.

3. Provide a supplemental price for a 5-year parts and labor warranty, where the Owner isnot responsible for any warranty costs including travel, labor, parts, or other costs for five(5) years from the date of initial start-up of the system.

D. Delivery, Storage and Handling:1. Deliver units with factory installed shipping skids and lifting lugs; pack components in

factory-fabricated protective containers.2. Handle units carefully to avoid damage to components, enclosures and finish. Do not

install damaged components; replace and return damaged components to drivemanufacturer.

3. Store units in clean dry location and protect from the elements and construction traffic.

E. Spare Parts: Provide generator set with the following:1. Radiator and Alternator fan belts2. Fuel Filter3. Oil Filter4. Fuses and Relays5. Touch-up paint for the enclosures

F. Start-up: Coordinate all start-up and testing activities with the Engineer and Owner. Afterinstallation is complete and normal power is available, the manufacturer's local dealer shallperform the following:1. Perform a four (4) hour load bank test at a 1.0 PF at full nameplate rating. Loadbank,

cables and other equipment required for this test to be supplied by the genset supplier.2. Provide two (2) hours of on-site training to instruct the owner's personnel in the proper

operation and maintenance of the equipment. Review operation and maintenancemanuals, parts manuals, and emergency service procedures.

3800-3-3

Page 106: SECTION 03000-1 - Tech Specs 05-29-2015

2. PART TWO - PRODUCTS:

2.1 GENERATOR SET:

A. Ratings:1. The generator set shall operate at 1800 rpm and at a voltage of: 480Y/277, Three phase,

Four-wire, 60 hertz.2. The generator set shall be Standby Duty rated at 175 kW, 218.8 kVA at 0.8 PF, including

radiator fan and all parasitic loads. 3. Generator set shall be sized to operate at the specified load at a maximum ambient of

95F (35.0C) and altitude of 250.0 feet.4. Operating Loads - Generator shall be selected to operate as a minimum, the following

loads and with the listed steps:a. Step 1 - 10 KVA @ 0.8 PF, General Electrical Load.b. Step 2 - Start and run P1 - 30 Hp on Reduced Voltage Solid State Motor Starter

(RVSS).c. Step 3 - Start and run P2 - 75 Hp (on RVSS).d. Step 4 - Start and run P3 - 75 Hp (on RVSS).

B. Engine:1. Diesel fueled, four (4) cycle, water-cooled with nominal speed not exceeding 1800 RPM.

The engine will meet applicable EPA non-road mobile regulations and/or the EPA NSPSrule for stationary reciprocating compression ignition engines and all State Emissionregulations at the time of installation/commissioning. Utilization of the "TransitionProgram for Equipment Manufacturers" (also known as "Flex Credits") to achieve EPAcertification is not acceptable.

2. Engine Governing: The engine governor shall be a electronic Engine Control Module(ECM) with 24-volt DC Electric Actuator. The ECM shall be enclosed in anenvironmentally sealed, aluminum housing which isolates and protects electroniccomponents from moisture and dirt contamination. Speed droop shall be adjustable from0 (isochronous) to 10%, from no load to full rated load. Steady state frequency regulationshall be +/- 6 RPM. A provision for remote speed adjustment shall be included.

C. Generator:1. The synchronous three phase generator shall be a single bearing, self-ventilated,

drip-proof design in accordance with NEMA MG 1 and directly connected to the engineflywheel housing with a flex coupling. The generator shall meet performance class G2 ofISO 8528. The excitation system shall enable the alternator to sustain 300% of ratedcurrent based on the 125C (Class H) or 105C (Class F) rise rating for ten seconds duringa fault condition and shall improve the immunity of the voltage regulator to non-lineardistorting loads. The generator shall be a permanent magnetic type unit.

2. Digital Voltage Regulator: Provide microprocessor based voltage regulator with fullyprogrammable operating and protection characteristics. The regulator shall maintaingenerator output voltage within +/- 0.25% for any constant load between no load and fullload. The regulator shall be capable of sensing true RMS in three phases of alternatoroutput voltage, or operating in single phase sensing mode.

D. Circuit Breaker: Provide a generator mounted 100% rated circuit breaker, molded case, 400amp w/adjustable trip, 3 pole, NEMA 1/IP22. Breaker shall utilize a solid state trip unit. Thebreaker shall be UL/CSA Listed and connected to engine/generator safety shutdowns. Breaker shall be housed in an extension terminal box which is isolated from vibrations inducedby the generator set. Mechanical type lugs, sized for the circuit breaker feeders shown ondrawing, shall be supplied on the load side of breaker.

E. Cooling System: Engine-driven radiator with blower fan and all accessories. The coolingsystem shall be sized to operate at full load conditions and 110 Deg F ambient air entering theenclosure. The generator set supplier is responsible for providing a properly sized coolingsystem based on the enclosure static pressure restriction.

F. Fuel System: The fuel system shall be integral with the engine. In addition to the standard fuelfilters provided by the engine manufacturer, there shall also be a primary fuel filter/water

3800-3-4

Page 107: SECTION 03000-1 - Tech Specs 05-29-2015

separator installed in the fuel inlet line to the engine. All fuel piping shall be black iron or flexiblefuel hose rated 300 degrees F and 100 psi.

G. Silencer: A residential grade silencer, companion flanges, and flexible stainless steel exhaustfitting properly sized shall be furnished and installed in the assembly by the manufacturer. Thesilencer shall be mounted so that its weight is not supported by the engine nor will exhaustsystem growth due to thermal expansion be imposed on the engine. Exhaust pipe size shall besufficient to ensure that exhaust backpressure does not exceed the maximum limitationsspecified by the engine manufacturer.

H. Starting Motor: A DC electric starting system with positive engagement shall be furnished. Themotor voltage shall be as recommended by the engine manufacturer.

I. Jacket Water Heater: Jacket water heater shall be provided and shall be sized to insure thatgenset will start within the specified time period and ambient conditions. Heater to be 120/ 240Volt Single Phase, 2000 Watt @ 240 VAC rated and provided a dedicated power circuit fromthe Generator Bus, refer to Drawings.

J. Batteries: Batteries - A lead-acid storage battery set of the heavy-duty diesel starting type shallbe provided. Battery voltage shall be compatible with the starting system.

K. Battery Charger: Provide a current limiting battery charger to automatically recharge batteries. The charger shall be dual charge rate with automatic switching to the boost rate when required. The battery charger shall be mounted on the genset package or inside the genset enclosure. Charger to be 120 volt, 10 Amp rated and provided a dedicated power circuit from theGenerator Bus, refer to Drawings.

2.2 DOUBLE WALL SUB-BASE FUEL STORAGE TANK:

A. Provide a double wall sub-base tank constructed to meet all local codes and requirements. Tank shall have not greater than 510 gallon but not less than 500 gallon capacity and beprovided as an integral part of the enclosure. It shall contain a rupture basin with 110%capacity of the tank. The tank shall meet UL142 standards. A locking fill cap, a mechanicalreading fuel level gauge and the following fuel level & leak sensors:1. High fuel switch2. Low fuel switch3. Interstitial (rupture basin) leak switch 4. Mechanical fuel level gauge, visible from fuel fill and wired to genset control panel for

alarms.

B. Fuel - It is the intent of this specification to provide the Owner with a complete and fullyoperable standby generator system at the time of substantial completion. This Contractor willprovide the generator with sufficient fuel to perform all acceptance testing and start-upoperations prior to acceptance by the Owner. The Contractor will provide fresh fuel to top-offand completely fill the tank after all testing and demonstration and just prior to acceptance bythe Owner. Fuel is not to be more than 14 Days old at the time of acceptance.

2.3 OUTDOOR WEATHER PROTECTIVE SOUND ATTENUATING ENCLOSURE:

A. The generator set shall be provided with a sound-attenuated housing which allows thegenerator set to operate at full rated load in the ambient conditions previously specified. Theenclosure shall provide a 25 dBa reduction in sound level measured at 7 meters from thegenerator set in a free field environment. Housing configuration and materials used shall meet150 mph Florida Hurricane wind load w\ certifications. Acoustical materials used shall be oiland water resistant. Enclosure shall include the following:1. The enclosure shall include hinged doors for access to both sides of the engine and

alternator, and the control equipment. Key-locking and padlockable door latches shall beprovided for all doors. Door hinges shall be stainless steel.

2. The enclosure shall be provided with an exhaust silencer which is mounted inside of theenclosure, and allows the generator set package to meet specified sound levelrequirements. Silencer and exhaust shall include a raincap and rainshield.

3800-3-5

Page 108: SECTION 03000-1 - Tech Specs 05-29-2015

3. All sheet metal shall be primed for corrosion protection and finish painted with themanufacturers standard color. All surfaces of all metal parts shall be primed and painted.

4. Painting of hoses, clamps, wiring harnesses, and other non-metallic service parts is notacceptable. Fasteners used shall be corrosion resistant, and designed to minimizemarring of the painted surface when removed for normal installation or service work.

B. Certification: Submit certified calculations for all pole, enclosure and luminary combinations todemonstrate compliance with florida building code wind load criteria specified on the Drawings. Certified calculations to be provided bearing the signature and seal of a florida registeredstructural engineer and per ASCE 7 – 2010 Edition with the minimum required design wind loadcriteria shown on the Drawings. These calculations are to be accepted by the Engineer ascomplying with the specified requirements for the installation prior to placement of any orders.

2.4 ACCESS CATWALKS:

A. Provide a 42” wide Free Standing Stair Package using aluminum construction, with 42" tallhandrail (affixed on the side opposite of the fuel tank) in a u-shaped platform to extend length ofengine room on both sides and width of enclosure on the rear. Provide with two (2) sets ofstairs to access platform, as shown on the Drawings and per the following:1. Platform may be manufactured as a single U shaped assembly or as 3 separate units that

are field assembled with bolts to provide a single structure forming a U around thegenerator.

2. Platform elevation shall not be taller than the maximum height of the fuel tank.3. Platform to extend the full length of the generator enclosure with steps at the control end.4. Provide a 42" high handrail along the full length of the platform not mated along the

generator enclosure and on the stairs. The hand rail is measured from the top surface ofthe platform.

5. Shall be designed so as not to interfere with the access or full opening of any doors orpanels and the shall provide full and unobstructed access to the fuel tank refueling port.

6. Provision shall be made to bolt the catwalks to the concrete pad as well as anyattachment to the generator, that the manufacturer may recommend.

2.5 GENERATOR SET MOUNTED CONTROL:

A. Provide a fully solid-state, microprocessor based, generator set control. The control panel shallbe designed and built by the engine manufacturer. Communications to support Modbus RTU(RS-485 Half Duplex) data links. The control shall provide all operating, monitoring, and controlfunctions for the generator set.

B. Environmental: The generator set control shall be tested and certified to the followingenvironmental conditions:1. -40°C to +70°C Operating Range2. 100% condensing humidity, 30°C to 60°C3. IP22 protection for rear of controller; IP55 when installed in control panel4. 5% salt spray, 48 hours, +38°C, 36.8V system voltage5. Sinusoidal vibration 4.3G's RMS, 24-1000Hz6. Electromagnetic Capability (89/336/EEC, 91/368/EEC, 93/44/EEC, 93/68/EEC, BS EN

50081-2, 50082-2)7. Shock: withstand 15G

C. Functional Requirements: The following functionality shall be integral to the control panel: 1. The control shall include a 33 x 132 pixel, 24mm x 95mm, positive image, transflective

LCD display with text based alarm/event descriptions.2. Audible horn for alarm and shutdown with horn silence switch3. Standard ISO labeling4. Multiple language capability5. Remote start/stop control6. Local run/off/auto control integral to system microprocessor7. Cooldown timer8. Lamp test9. Emergency stop push button

3800-3-6

Page 109: SECTION 03000-1 - Tech Specs 05-29-2015

D. Digital Monitoring Capability: The controls shall provide the following digital readouts for theengine and generator. All readings shall be indicated in either metric or English units.1. Engine:

a. Engine oil pressureb. Engine coolant temperaturec. Engine RPMd. Battery volts

2. Generator:a. Generator AC volts (Line to Line, Line to Neutral and Average)b. Generator AC current (Per phase and Average)c. Generator AC Frequency

E. Alarms and Shutdowns: The control shall monitor and provide alarm indication and subsequentshutdown for the following minimum conditions. All alarms and shutdowns are accompanied byan engine hour stamp that is stored by the control panel for first and last occurrence. DuringConstruction, the Owner will designate those alarm conditions monitored by the digital enginecontroller that are to be output via SCADA communication using one of the six I/O outputs orvia Modbus.1. Engine Alarm/Shutdown:

a. Low oil pressure alarm/shutdown . . . . . . . . . . . . . . . . . . . . . . . . . . . . SCADA Alarmb. High coolant temperature alarm/shutdown . . . . . . . . . . . . . . . . . . . . . SCADA Alarmc. Loss of coolant shutdown . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . SCADA Alarmd. Overspeed shutdown . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . SCADA Alarme. Overcrank shutdown . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . SCADA Alarmf. Emergency stop shutdowng. Low coolant temperature alarm

2. Generator Alarm/Shutdown: . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . SCADA Alarm (any)a. Generator phase sequenceb. Generator over voltagec. Generator under voltaged. Generator over frequencye. Generator under frequency

F. Inputs and Outputs:1. Dedicated Digital Inputs: Two (2)2. Programmable Digital Inputs: Six (6)3. Programmable Input/Outputs: Six (6) - Form A (Normally Open) Dry Contacts.4. Programmable Input/Outputs: Two (2) - Form C (SPDT) Dry Contacts.5. Digital Outputs: Two (2)

G. Maintenance: All engine, voltage regulator, control panel and accessory units shall beaccessible through a single electronic service tool. The following maintenance functionalityshall be integral to the generator set control:

a. Engine running hours displayb. 40 events are stored in control panel memory

2.6 AUTOMATIC LOAD TRANSFER SWITCH: REFER TO SECTION 3850.

3. PART THREE - EXECUTION:

3.1 INSTALLATION:

A. Equipment shall be installed by the contractor in accordance with final submittals and contractdocuments. Installation shall comply with applicable state and local codes as required by theauthority having jurisdiction. Install equipment in accordance with manufacturer's instructionsand instructions included in the listing or labeling of UL listed products and the following:1. Installation of equipment shall include furnishing and installing all interconnecting wiring

between equipment provided for the on-site power system. The contractor shall alsoperform interconnecting wiring between equipment sections (when required), under the

3800-3-7

Page 110: SECTION 03000-1 - Tech Specs 05-29-2015

supervision of the equipment supplier.2. Equipment shall be installed on concrete housekeeping pads. Equipment shall be

permanently fastened to the pad in accordance with manufacturer's instructions andseismic requirements of the site.

3. All equipment shall be physically inspected for damage. Scratches and other installationdamage shall be repaired prior to final system testing. Equipment shall be thoroughlycleaned to remove all dirt and construction debris prior to final testing of the system.

4. The Contractor shall install suitable jacket water additives, including antifreeze, asfurnished by the engine manufacturer and approved by the Engineer, for prevention ofboth scale formation and corrosion in the water jackets and cooling system componentswhich are in contact with the engine jacket water. These additives shall be added to thecooling system prior to running the field acceptable test.

3.2 WIRING AND CONNECTIONS:

A. All conduit, wire, cables, interconnections, etc., entering or exiting the generator enclosure shallbe furnished and installed by the installing contractor. All wiring shall be in conduit sized inaccordance with the NEC. All power wiring shall be THWN copper and all control wiring shallbe stranded type THHN-THWN copper. All power and control wiring shall be installed for acomplete and operating system.

B. Installation and connection of the remote annunciator shall be performed by the electricalcontractor and inspected by the generator supplier.

C. The basis of design has been configured for separate power circuits feeding generator utilities. The Contractor may substitute this configuration with a Generator that has pre-terminatedpower utilities in a common power panel, provided all costs for powering and feeding the singlepoint connection on the generator are included in the base bid. Contractor is to clearly identifyproposed configuration in submittal data.

3.3 SEQUENCE OF OPERATION:

A. Generator set shall start on receipt of a start signal from ATS. The start signal shall be viahardwired connection to the generator set control and a redundant signal over the requirednetwork connection. The generator set shall complete a time delay start period as programmedinto the control.

B. The generator set control shall initiate the starting sequence for the generator set. The startingsequence shall include the following functions:1. The control system shall verify that the engine is rotating when the starter is signaled to

operate. If the engine does not rotate after two attempts, the control system shall shutdown and lock out the generator set, and indicate "fail to crank" shutdown.

2. The engine shall fire and accelerate as quickly as practical to start disconnect speed. Ifthe engine does not start, it shall complete a cycle cranking process as describedelsewhere in this specification. If the engine has not started by the completion of thecycle cranking sequence, it shall be shut down and locked out, and the control systemshall indicate "fail to start".

3. The engine shall accelerate to rated speed and the alternator to rated voltage. Excitationshall be disabled until the engine has exceeded programmed idle speed, and regulated toprevent over voltage conditions and oscillation as the engine accelerates and thealternator builds to rated voltage.

C. On reaching rated speed and voltage, the generator set shall operate as dictated by the controlsystem in isochronous, synchronize, load share, load demand, or load govern state.

D. When all start signals have been removed from the generator set, it shall complete a time delaystop sequence. The duration of the time delay stop period shall be adjustable by the operator.

E. On completion of the time delay stop period, the generator set control shall switch off theexcitation system and shall shut down.

F. Any start signal received after the time stop sequence has begun shall immediately terminatethe stopping sequence and return the generator set to isochronous operation.

3800-3-8

Page 111: SECTION 03000-1 - Tech Specs 05-29-2015

3.4 TESTING:

A. Factory Testing:1. The generator set supplier shall perform a complete operational test on the generator set

prior to shipping from the factory. A certified test report shall be provided. Equipmentsupplied shall be fully tested at the factory for function and performance.

2. Generator set factory tests on the equipment shall be performed at rated load and ratedpower factor. Generator sets that have not been factory tested at rated power factor willnot be acceptable. Tests shall include: run at full load, maximum power, voltageregulation, transient and steady-state governing, single step load pickup, and function ofsafety shutdowns.

B. Site Testing:1. The complete installation shall be tested for compliance with the specification following

completion of all site work. Testing shall be conducted by representatives of themanufacturer, with required fuel supplied by Contractor. The Engineer shall be notified inadvance and shall have the option to witness the tests.

2. Installation acceptance tests to be conducted on-site shall include a "cold start" test, aPerform a four (4) hour load bank test at a 1.0 PF at full nameplate rating, and a one steprated load pickup test in accordance with NFPA 110. Provide a resistive load bank andmake temporary connections for full load test, if necessary.

3. Perform a power failure test on the entire installed system. This test shall be conductedby opening the power supply from the utility service, and observing proper operation of thesystem for at least 2 hours. Coordinate timing and obtain approval for start of test withsite personnel.

3.5 TRAINING:

A. The equipment supplier shall provide two (2) hours of on-site training for the facility operatingpersonnel covering operation and maintenance of the equipment provided. The training classsize shall be limited to 5 persons. Training date shall be coordinated with the facility Owner.

3.6 SERVICE AND SUPPORT:

A. The manufacturer of the generator set shall maintain service parts inventory at a centrallocation which is accessible to the service location 24 hours per day, 365 days per year.

B. The generator set shall be serviced by a local service organization that is trained and factorycertified in generator set service. The supplier shall maintain an inventory of criticalreplacement parts at the local service organization, and in service vehicles. The serviceorganization shall be on call 24 hours per day, 365 days per year.

C. The manufacturer shall maintain model and serial number records of each generator setprovided for at least 20 years.

END OF SECTION

3800-3-9

Page 112: SECTION 03000-1 - Tech Specs 05-29-2015

SECTION 3850-3 AUTOMATIC TRANSFER SWITCHES

1. PART ONE - GENERAL

1.1 SCOPE:

A. Provide complete operational service entrance rated automatic transfer switch(s) with Amp, Volt,Phase, Hz Ratings and Number of Poles listed on the Electrical Drawings. Units shall be factoryassembled with electronic controls designed for fully automatic open transition(break-before-make) transfer operation and including; surge voltage isolation, voltage sensors onall phases of the normal source and one phase of the emergency source, positive mechanical andelectrical interlocking to prevent the utility and generator supplies from being interconnected.

1.2 RELATED DOCUMENTS:

A. Section 3800-3 - Engine Generator SystemsB. The other Contract Documents complement the requirements of this Section.

1.3 CODES AND STANDARDS:

A. The automatic transfer switch shall conform to the requirements of the following:1. UL 1008 - Automatic Transfer Switches for Use in Emergency Systems2. National Electric Code - NFPA 70, 2008 Edition.3. NFPA 110 - Emergency and Standby Power Systems4. IEEE Standard 446 - IEEE Recommended Practice for Emergency and Standby Power

Systems for Commercial and Industrial Applications5. NEMA Standard ICS10-1993 - AC Automatic Transfer Switches6. UL 508 - Industrial Control Equipment

B. The transfer switch manufacturer shall be certified to ISO 9001 International Quality Standard.

1.4 SUBMITTALS:

A. Submit shop drawings and product data under the provisions of Section 3800-3 - Engine GeneratorSystem for the Automatic Transfer Switch(s) including all optional features.

B. Shop drawings to include; all installation drawings, schematics, and wiring diagrams which showdetails of installation and connections to the work of other sections.

C. Product Data Sheets to include Equipment Ratings.

D. Control Data to include; electrical diagrams and interconnection wiring diagrams for all equipmentprovided, legends for all devices on diagrams and sequence of operation, explanations for allportions of all schematic wiring diagrams.

1.5 QUALITY ASSURANCE:

A. Acceptable Manufacturers: The Automatic Transfer Switch manufacturer shall maintain and staffengineering service and repair shops through the United States, including the State of Florida,trained to do start up service, emergency service calls, repair work, service contracts and trainingof customer personnel. Automatic Transfer Switch(s) by one of the following manufacturers' maybe incorporated in the work:1. Asco2. Square-D3. Caterpillar CTE

3850-1

Page 113: SECTION 03000-1 - Tech Specs 05-29-2015

B. Warranty:1. Provide units with a 5-year parts and labor warranty, where the Owner is not responsible for

any warranty costs including travel, labor, parts, or other costs for five (5) years from the dateof installation of the ATS.

C. Delivery, Storage and Handling:1. Deliver units with factory installed shipping skids and lifting lugs; pack components in factory-

fabricated protective containers.2. Handle units carefully to avoid damage to components, enclosures and finish. Do not install

damaged components; replace and return damaged components to ATS manufacturer.3. Store units in clean dry location and protect from the elements and construction traffic.

D. Start-up: A factory-authorized service technician shall perform start-up on each ATS. ("Start up"shall not include installation or termination of either power or control wiring). Start-up costsprovided with the bid shall include time and travel for the estimated number of visits required, butshall not be less than at least one half-day with travel. Additional labor or return trips to the siteshall be billed at the ATS supplier's published straight-time rates. The rates shall be submitted withthe ATS shop drawings. Upon completion, a start-up service report shall be provided.

2. PART TWO - PRODUCTS:

2.1 POWER TRANSFER SWITCH

A. Ratings:1. Basis of Design: ASCO Model No: 3AUS03400N1XH-11BG-14AA-44G-480V / 60HZ,

Service Duty Rated, 277Y/480 Volt 3 Phase, 400 Amp, 3 Pole, Solid Neutral, NEMA 4XEnclosure, with Programmable Engine Exerciser, Auxiliary Contacts and Strip Heater andThermostat with a 300 Amp Trip rating on the Main Breaker.

2. Transfer switches shall be rated to carry 100 percent of rated current continuously in theenclosure supplied, in ambient temperatures of -15 to +50 degrees Celsius, relative humidityfrom 0 to 95% (non-condensing), and altitudes up to 10,000 feet (3000M).

3. Transfer switch shall have fault withstand current rating of the complete assembly of 35,000amps RMS minimum. The interrupting and closing rating shall be equal to or exceed therequired withstand rating and shall be greater than the available fault current shown on thedrawings. The transfer switch and its upstream protection shall be coordinated. The transferswitch shall be UL 1008 listed and labeled for use.

4. Disconnecting and Overcurrent Protection Device: The normal connection shall be providedwith a thermal magnetic rated molded case circuit breaker with current ratings as listed. Itshall have a thermal magnetic trip unit.

B. Mechanically Held Transfer Switch:1. The transfer switch unit shall be electrically operated and mechanically held. The electrical

operator shall be a single-solenoid mechanism, momentarily energized. The switch shall bemechanically interlocked to ensure only one of two possible positions, normal or emergency.

2. The switch shall be positively locked and unaffected by momentary outages.3. All main contacts shall be silver composition.4. Inspection of all contacts shall be possible from the front of the switch without disassembly

of operating linkages and without disconnection of power conductors. A manual operatinghandle shall be provided for maintenance purposes. The handle shall permit the operatorto manually stop the contacts at any point throughout their entire travel to inspect and servicethe contacts when required.

5. Where neutral conductors are to be solidly connected, a neutral terminal plate with fully-ratedAL-CU pressure connectors shall be provided.

C. Connections:1. Field control connections shall be made on a common terminal block that is clearly and

3850-2

Page 114: SECTION 03000-1 - Tech Specs 05-29-2015

permanently labeled.2. Transfer switch shall be provided with AL/CU mechanical lugs sized to accept the full output

rating of the generator set.

2.2 TRANSFER SWITCH CONTROL:

A. The controller shall direct the operation of the transfer switch. The controller's sensing and logicshall be controlled by a built-in microprocessor for maximum reliability, minimum maintenance, andinherent serial communications capability. The controller shall be connected to the transfer switchby an interconnecting wiring harness. The harness shall include a keyed disconnect plug to enablethe controller to be disconnected from the transfer switch for routine maintenance.

B. The controller shall be enclosed with a protective cover and be mounted separate from the transferswitch unit for safety and ease of maintenance. Sensing and control logic shall be provided onprinted circuit boards. Interfacing relays shall be industrial grade plug-in type with dust covers.

C. Voltage and Frequency Sensing:1. The voltage of each phase of the normal source shall be monitored, with pickup adjustable

to 95% of nominal and dropout adjustable from 70% to 90% of pickup setting.2. Single-phase voltage and frequency sensing of the emergency source shall be provided.

D. Time Delays - Adjustable time delays shall be provided for the following:1. Override momentary normal source outages and delay all transfer and engine starting

signals.2. Transfer to standby, adjustable from 0 to 5 minutes for controlled timing of transfer of loads

to generator.3. Retransfer to normal, adjustable to 30 minutes. Time delay shall be automatically bypassed

if emergency source fails and normal source is acceptable.4. 5-minute cooldown time delay shall be provided on shutdown of engine generator.5. All adjustable time delays shall be field adjustable without the use of tools.

E. Additional Features:1. Set of contacts rated 10 amps, 32 VDC shall be provided for a low-voltage engine start

signal. The start signal shall prevent dry cranking of the engine by requiring the generatorset to reach proper output, and run for the duration of the cool down setting, regardless ofwhether the normal source restores before the load is transferred.

2. Push-button type test switch shall be provided to simulate a normal source failure.3. Push-button type switch to bypass the time delay on transfer to emergency, the engine

exerciser period on the retransfer to normal time delay whichever delay is active at the timethe push-button is activated.

4. Auxiliary contacts, rated 10 amps, 250 VAC shall be provided consisting of one contact,closed when the ATS is connected to the normal source and one contact, closed, when theATS is connected to the generator.

5. Indicating lights shall be provided, one to indicate when the ATS is connected to the normalsource (green) and one to indicate when the ATS is connected to the emergency source(red). Also provide indicating lights for both normal and emergency source availability.

6. Terminals shall be provided to indicate actual availability of the normal and emergencysources, as determined by the voltage sensing pickup and dropout settings for each source.

7. Engine Exerciser - An engine generator exercising timer shall be provided, including aselector switch to select exercise with or without load transfer.

8. Inphase Monitor shall be inherently built into the controls. The monitor shall control transferso that motor load inrush currents do not exceed normal starting currents, and shall notrequire external control of power sources.

9. Selective Load Disconnect - A double throw contact shall be provided to operate after a timedelay, adjustable to 20 seconds prior to transfer and reset 0 to 20 seconds after transfer. This contact can be used to selectively disconnect specific load(s) when the transfer switchis transferred. Output contacts shall be rated 6 amps at 28 VDC or 120 VAC.

3850-3

Page 115: SECTION 03000-1 - Tech Specs 05-29-2015

2.3 ENCLOSURE:

A. The ATS shall be furnished in a NEMA Type 4X - Stainless Steel enclosure with the following:1. Provide strip heater with thermostat for Type 3R/4X enclosure requirements.2. Controller shall be flush-mounted display with LED indicators for switch position and source

availability. It shall also include test and time delay bypass switches.3. Control wiring shall be rated for 600 volt, UL 1015. Wires shall be placed in wire duct or

harnessed, and shall be supported to prevent sagging or breakage from weight or vibration.All wiring to hinged doors shall be run through door terminal blocks or connection plugs.

2.4 OPTIONAL ACCESSORIES:

A. Communications Interface - Serial Module to allow local or remote communications with ATS communication software. To connect Automatic Transfer Switches, and ATS Annunciators to theserial network via an RS485 interface.

B. Programmable Engine Exerciser - A seven or fourteen day programmable engine exerciser withdigital readout display. Shall include one form C contact for availability of normal and emergency.Include "with or without" load control switch for exerciser period. The exerciser shall be backedup by a permanent battery.

C. Enclosure Heater - A 125 watt enclosure heater with transformer and thermostat (adjustable from30 Deg to 140 Deg F).

3. PART THREE - EXECUTION:

3.1 INSTALLATION:

A. Install the transfer switch as shown on Drawings. Make installation in accordance withmanufacturer's instructions.

B. Start-up and Inspection: On completion of the installation, start-up shall be performed by a factorytrained, authorized dealer service representative. Operation of each voltage, frequency, and timing device shall be checked for proper operation and initial setting.

C. Training: Provide the services of a factory authorized dealer representative to conduct a minimumof two one-hour training sessions in the operation and maintenance the installed transfer switchingequipment. Training sessions shall be conducted at the installation site and shall be held at timeand place designated by the Architect.

D. Before, during and after the installation up to the date of substantial completion, the ATS equipmentshall be protected from site contaminants, including but not limited to; concrete, mortar, drywall jointcompound, paint, grinder and drill debris.

E. Interior of cabinets to be free of all; drill debris, wire clippings, wire insulation, concrete dust, loosemanuals, shipping documents and any other foreign materials not indigenous with the equipmentand as identified by the Engineer.

F. Restore factory finish, marred, and damaged surfaces.

3.2 FUNCTIONAL REQUIREMENTS:

A. The service entrance rated automatic transfer switch shall automatically transfer the load to thegenerator supply in the event of a utility supply failure and return the load to the utility supply uponrestoration. The transfer switch shall incorporate an isolating mechanism and over currentprotection on the utility supply to allow operation as the main service disconnect in accordance with

3850-4

Page 116: SECTION 03000-1 - Tech Specs 05-29-2015

NEC requirements. The transfer switch power switching devices shall be mechanically andelectrically interlocked to prevent the utility and generator supplies from being interconnected.

B. Open Transition Sequence of Operations:1. When the voltage on any phase of the utility supply is below preset levels of rated voltage for

a preset time delay, a contact shall close to initiate starting of the generator set.2. The load shall transfer to the generator supply when the generator voltage and frequency

have reached acceptable preset levels and the warm-up time delay has expired.3. When the utility supply is restored to above preset levels of rated voltage on all phases, load

transfer from generator to utility supply shall be initiated following expiry of the utility returntimer.

4. Once the transfer mechanism operates and opens the generator power switching device, thetransfer mechanism shall stop in the neutral position (i.e. with both power switching devicesopen) for the duration of the neutral delay timer setting to allow load voltage to decay priorto re-connecting the utility supply.

5. The load shall be re-connected to the utility supply once the neutral delay timer expires andthe transfer mechanism continues operation and closes the utility power switching device.

6. The load shall immediately retransfer to the utility supply (if within acceptable limits) shouldthe generator supply fail prior to expiry of the utility transfer delay.

7. The generator set shall continue to operate following a load transfer for a cooldown delayperiod, and then a contact shall open to stop the generator set.

8. An "on load" test mode may be initiated which shall cause a simulated utility failure conditionand transfer the load to the generator set. The transfer sequence shall be the same as fora utility power failure except a neutral delay sequence shall occur when transferring fromutility to a generator source.

9. The load shall immediately retransfer to the utility supply (if within acceptable limits) shouldthe generator supply fail during an "on load" test mode.

3.3 FACTORY TESTING:

A. The transfer switch supplier shall perform a complete operational test on the transfer switch priorto shipping from the factory. A certified test report shall be provided with delivery of equipment. Test process shall include calibration of voltage sensors.

3.4 FIELD TESTING/COMMISSIONING:

A. The automatic transfer switch shall be tested once installed at the project site to confirm properoperation of the system. Schedule and witness testing activities shall be coordinated with theproject engineer, site contractor, and owner as required in advance of the testing. Qualified localfactory-trained field service representatives shall conduct the following tests:

B. Visual Inspection: Electrical and Mechanical inspection to verify the installation is correct asrecommended by the transfer switch manufacturer and as per NEC/CEC requirements.

C. Mechanical Tests: As a minimum, the following mechanical tests shall be performed on the transferswitch:1. Power Conductor Torque Verification2. Verification of Mechanical Interlock3. Manual ATS Mechanism Operation4. All Mechanical Fasteners/Wire Connections Tight5. Confirmation of correct transfer switch voltage, current and withstand ratings as is required

for the application.

D. Electrical Tests: As a minimum, the following electrical tests shall be performed on the transferswitch:1. Megger Testing the Power Cabling to the transfer Switch2. Verification of correct power cabling phasing and phase rotation, prior to energization.

3850-5

Page 117: SECTION 03000-1 - Tech Specs 05-29-2015

3. Confirmation of settings for all Timers & Voltage Sensors4. Full Function Test-Normal Operation-3 Complete Cycles of failing the utility supply, and

transfer load to/from the generator set.5. Verification of all Test Modes operate correctly

E. Qualified factory-trained field service personnel shall provide four (4) copies of field test reportsnoting any deficiencies that require corrective action.

F. The manufacturer of the transfer switch shall maintain service parts inventory at a central locationwhich is accessible to the service location 24 hours per day, 365 days per year.

G. The transfer switch shall be serviced by a local service organization that is trained and factorycertified in both generator set and transfer switch service. The supplier shall maintain an inventoryof critical replacement parts at the local service organization, and in service vehicles. The serviceorganization shall be on call 24 hours per day, 365 days per year.

H. The manufacturer shall maintain model and serial number records of each transfer switch providedfor at least 20 years.

END OF SECTION

3850-6

Page 118: SECTION 03000-1 - Tech Specs 05-29-2015

SECTION 3900-3 LEVEL CONTROL

1. GENERAL

A. Refer to the City of Ocala Water and Sewer Construction Manual

Specification Section 495.5.14 for Level Control System Specifications.

B. Specification Section 495.2.6 Level Controls shall be omitted and

replaced with information contained within this specification. Level

control set points shall be as indicated on the drawings.

2. REVISIONS TO STANDARD SPECIFICATIONS

A. 493.5.14.2 Type shall be amended as written below.

The level control system shall be air bubbler type complete with

air supply, air piping, and pressure transducer. Air bubbler level

control system shall send 4-20 mA signal to the SC2000 station

controller with change in wet well liquid level. Air supply shall be

continuous to the wet well and may require periodic tube purges

in order to maintain clean air tubing. Products for the bubbler

system shall be as shown on the drawings.

B. 493.5.14.3 Sequence of Operation shall be amended as written below.

The pump operation shall be completely controlled by the pump

controller shown on the drawings. The pump controller shall

receive signal from the level control system upon wet well fluid

level rise and fall. A second signal may be received from the NE

28th Avenue Recirculation Simplex Pump Station upon reaching

high level in the stormwater pond. If this signal is received, no

pumps at the Cameo Pond Pump Station shall be able to operate

unless manually started. Upon initial rise, first level set point shall

start Pump 1. Upon additional level rise to second level set point,

Pump 1 shall turn off and Pump 2, alternating with Pump 3 for

each pump run sequence, shall start. Upon further wet well level

rise, Pump 3, alternating with Pump 2, in addition to continued

operation of Pump 2, alternating with Pump 3 for each sequence,

shall start. Upon further level rise, Pump 1 shall start in addition

to operation of Pumps 2 and 3. With further wet well level rise,

high level float shall be activated and redundant signal shall be

sent for all pumps to run. Upon level fall, Pumps 2 and 3 shall be

turned off when reaching the pump off set point. Pump 1 shall

remain running until the wet well level reaches the Pump 1 off

Page 119: SECTION 03000-1 - Tech Specs 05-29-2015

level. Low level float is installed for redundancy. When low level

float is activated, all pumps shall be off.

C. 493.5.14.4 Automatic Pump Alternation shall be amended as written

below.

The pump controller shall automatically alternate operation of

Pumps 2 and 3 after each respective pump has run. Alternation

shall occur at the end of a pumping cycle.

D. 493.5.14.6 Pressure Sensor shall be amended as written below.

The pressure sensor shall be a strain gauge transducer and shall

receive an input pressure from the air bubbler tubing. The

transducer shall convert the input to a proportional electrical

signal for distribution to the display and electronic comparators.

The transducer output shall be filtered to prevent control

response to level pulsations or surges. Transducer over-pressure

rating shall be three times full scale. Transducer is mounted in the

air bubbler system panel, separate from pump controller.

3. MATERIALS

A. Air compressor shall be furnished to deliver free air at a rate of

approximately 5 cubic feet per hour and a pressure not to exceed 10 psi.

Air compressor shall be furnished with an intake air filter. Air compressor

shall come with corrosion resistant aluminum panel mounting bracket

fitting within the enclosure. Air compressor shall be model no. HR10WB3

as manufactured by Ingram Products, Inc.

B. A back check valve shall be included in the air bubbler piping to prevent

fluid from entering the compressor upon air piping purge or power

outage. Valve shall be model no. AP19CV0012NL as manufactured by

Ingram Products, Inc.

C. A fixed orifice choke shall be included in the system to reduce air flow

produced from the compressor. Orifice shall be model no. IM- .016 as

manufactured by Ingram Products, Inc.

D. A discharge air filter shall be installed directly downstream of back check

valve. Air filter shall be model no. AP19FV0012P1L as manufactured by

Ingram Products, Inc.

Page 120: SECTION 03000-1 - Tech Specs 05-29-2015

E. An air flow indicator gauge shall be provided and connected to the air

bubbler piping to provide a visual indication of rate of flow in standard

cubic feet per hour.

F. Pressure transducer shall be connected to the air bubbler piping.

Transducer shall measure air pressure in the piping and convert to 4-20

mA signal. Transducer shall be two-wire system connected to pump

controller receiving 20 VDC and sending 4-20 mA signal, indicating wet

well level. Transducer shall be model no. S-10 as manufactured by WIKA

Instrument Corporation.

G. Air bubbler piping shall be 1/2" stainless steel. Piping shall be installed

from bubbler system panel to junction box at wet well slab then proceed

down in to the wet well as shown on the drawings.

H. Air bubbler drop piping shall be secured in the wet well with a minimum

of two (2) stainless steel eye bolts.

I. Panel shall be sized to fit all components of the air bubbler system and

shall be located within 25 feet of wet well or as shown on the drawings.

Enclosure shall be rated NEMA 4X stainless steel.

4. INSTALLATION

A. Air bubbler enclosure shall be installed in location as shown on plans.

B. Air bubbler piping shall be installed below grade and cast into top slab.

C. Pump manufacturer shall be responsible to demonstrate at start-up that

level control system is compatible with pump controller and pumps.

SECTION 4000-3 PUMP CONTROL PANEL

1. GENERAL

A. Refer to the City of Ocala Water and Sewer Construction Manual

Specification Section 495.5.13 for Pump Control Panel Specifications.

Specifications below shall be supplemental to, and in some instances

in place of, those specifications provided in Section 495.5.13.

B. Pump Control Panel shall be located as indicated on the drawings.

Page 121: SECTION 03000-1 - Tech Specs 05-29-2015

C. Pump control panel shall be delivered to site completely assembled

with all components as indicated on the drawings. All components

factory assembled shall be tested and approved prior to shipping to

job site.

D. All components submitted on the Bill Of Material (BOM) during the

shop drawing phase will be subject to Owner preferences to maintain

commonality of components.

2. REVISIONS TO STANDARD SPECIFICATIONS

A. 495.5.13.1 Panel Enclosure shall be revised as written below.

The electrical components and control equipment shall be

mounted within NEMA 3R, dead front type control enclosures

fabricated of stainless steel. Enclosure doors shall be gasketed

with neoprene, hinged, and equipped with captive closing

hardware. Control compartments shall incorporate removable

back panels on which control components shall be mounted. Back

panel shall be secured to enclosures with collar studs. Panels shall

be mounted as shown on the drawings.

B. 495.5.13.6 Variable Frequency Drives shall be omitted. No variable

frequency drives will be required for this project.

C. 495.5.13.9 Emergency Disconnect Breaker shall be revised as written

below.

Provide automatic transfer switch breaker to switch to generator

power. No generator receptacle shall be required. Provisions shall

be made so main and emergency breakers from being on at the

same time. See Specification Section 03850-3 Automatic Transfer

Switches for additional requirements.

D. 495.5.13.14 Warning Light and Horn shall be omitted. No warning

light and horn shall be required for this project.

E. 495.5.13.15 GFI Receptacle shall be revised as written below.

A weatherproof duplex ground fault indicating utility receptacle

providing 115 volts, 60Hz, single-phase current, shall be mounted

on the front of the main panel. Receptacle circuit shall be

protected by a 20 ampere thermal-magnetic circuit breaker. This

receptacle shall be intended for programming and diagnostic use

Page 122: SECTION 03000-1 - Tech Specs 05-29-2015

only. Maximum of 5 amperes. There shall be a separate GFI

receptacle mounted externally from the control panel as shown

on the drawings for site equipment use.

F. 495.5.13.18 Pump Mode Selection shall be revised as written below.

Pump Mode Selection: Pump mode selector switches shall be

connected to permit manual start and stop of each pump

individually, and to select automatic operation of each pump

under control of the level control system. Manual operation shall

override all shutdown systems, but not the motor overload relays.

Selector switches shall be toggle switches meeting Military

Standards (MS) for quality. Switch contacts shall be rated 15

amperes minimum at 120 volts non-inductive.

A rotary type 3 position selector switch for hand-off-automatic

operation and a run pilot light for each pump shall be on the inner

door.

G. 495.5.13.21 Wiring shall be revised as written below.

Wiring: The pump station as furnished by the manufacturer shall

be completely wired except for the power feeder lines to the

branch circuit breakers and final connections to remote alarm

devices. All wiring, workmanship, and schematic wiring diagrams

shall be in compliance with applicable standards and

specifications set forth by the National Electric Code (NEC).

Control wiring from the wetwell shall enter the panel in a manner

to prevent the possible entry of gases from the wetwell. Conduit

shall enter the wet well and terminate with a fiber bushing. No

splices will be allowed in the wet well or conduit. All control and

motor cords shall be continuous to the control cabinet.

3. MATERIALS

3.1. Mounting Support

A. Electrical component cabinets shall be installed on three (3) 6-

inch square by 10 feet precast concrete poles with two (2)

number four reinforcing steel bars for support structure. Electrical

cabinets shall include but may not be limited to pump control

panel, air bubbler system panel, automatic transfer switch, CT

cabinet, meter, transformer, and main breaker panel.

Page 123: SECTION 03000-1 - Tech Specs 05-29-2015

B. Panels shall be physically mounted to equipment rack attached to

support poles.

3.2. Pump Control Panel Accessories

A. General

A. This section shall provide supplemental information to the City

of Ocala Water and Sewer Construction Manual Specification

Section 493.5 Pump Equipment for items required to be

installed within the pump control panel.

B. Pump Controller

1. The SC2000-34 Controller is to be manufactured by Motor

Protection Electronics of Apopka, Florida, (407) 299-3825.

2. The controller shall control up to four pumps to perform liquid

level control. The device must be capable of controlling any

mix of constant speed and variable speed pumps. The

controller shall be capable of alternating the pumps, and shall

provide lag pump delays and high and low level alarms.

3. The controller shall be standard “off the shelf” equipment

with published literature and fully tested hardware and

operating program. The controller shall be field configurable

from the front of the unit, and require no special tools or

software to set-up or operate.

4. The controller shall be a microprocessor-based device and not

require a battery to maintain the operating program. All set-

up values shall be stored in non-volatile memory.

5. The controller shall be UL listed as Industrial Control

Equipment, UL 508.

6. A numerical level display shall be provided on the front of the

unit. The display shall have a 3 digit, 7 segment LED display and

show levels in feet and tenths of feet.

7. The controller shall not require an external power supply or any

external I/O modules to be a fully functioning unit. An analog

input (4-20mA) with zero and span adjustments shall be

provided for the wet-well level input.

Page 124: SECTION 03000-1 - Tech Specs 05-29-2015

8. Relay outputs shall be provided as standard for high and low

level alarms and for the control of up to four pumps. Up to four

isolated analog outputs (4-20mA) shall be available as an option,

for VFD speed control when needed. Up to four isolated analog

inputs (4-20mA) inputs shall also be available as an option, for

use when needed as telemetry inputs.

9. All electrical connections, for power or I/O, shall be by quick-

disconnect, phoenix style connectors.

10. The controller shall have a minimum of 18 discrete inputs.

The inputs shall be transient protected and be programmable

for the following functions:

• Pump disable with HOA in OFF, or pump fault

• External Alternator Selector Switch

• All pump disable – for connection to Phase Monitor

• Limit number of pumps, called to run, while on

emergency power

• Alternation by External Time Clock

• Freeze wet well level during a bubbler tube purge

• Call pump last – for connection to VFD/Bypass logic

• Pump disable upon low level – for connection to low

level float switch

• Float switch backup

11. Troubleshooting features shall include a fault indicator on the

front of the unit and retrievable fault codes.

12. Status of the discrete inputs shall be viewable from the front

of the unit.

13. A level simulation feature shall be available from the front of the

unit. The controller shall automatically return to monitoring the

wetwell level after sixty seconds if left in the simulation mode.

14. Menu selectable First-On/First-Off or First-On/Last-Off

alternation sequences shall be available.

15. Menu selectable alternation modes shall include:

• Standard Alternation

Page 125: SECTION 03000-1 - Tech Specs 05-29-2015

• Jockey pump (Pump 1 stays on when other pumps turn

on)

• Jockey Pump (Pump 1 turns off when other pumps turn

on)

• Split alternation (Pumps 1&2, Pumps 3&4)

• Fixed sequence (Pump 1 always lead)

• Stepped on/off (Only one pump runs at a time)

16. Pump disable discrete inputs shall cause the alternator to skip

over disabled pumps.

17. The controller shall remember which pump was in the lead

position during a power outage.

18. An RS232 serial port with Modbus RTU protocol shall be

provided for SCADA.

19. Programming shall be in place to collect and transmit the station

status, and to allow for the remote control of the pumps.

20. The pump On/Off levels, high level alarm, low level alarm setup,

and VFD speed values shall be viewable and changeable from a

remote location.

21. Pump elapsed time meters shall be viewable and resettable

from a remote location and shall be stored in non-volatile

memory during a power outage.

22. For VFD operation, the controller shall have menu selectable

parameters to form a linear wet-well level versus pump speed

curve. This pump speed curve shall include the parameters VFD

Minimum Speed, Level at Minimum Speed, and Level at 100%

speed.

23. Typical operation for Controller operating on VFD shall be:

• As the level rises to a PUMP ON LEVEL, a Pump/VFD is

called for, and ramps up to 100% speed as the level

increases. As additional pumps are called for, they are

started and ramped to 100 % speed. As the level

decreases below the 100 % speed point, the speed of

the VFD(s) is ramped down. When the level drops to a

PUMP OFF LEVEL, the pump/VFD is turned off.

Page 126: SECTION 03000-1 - Tech Specs 05-29-2015

24. The controller shall contain inputs for Bypass logic. These

inputs shall cause the controller to favor pumps with

operational VFDs over pumps that have VFDs in the Bypass

Mode.

25. The controller shall contain a discrete input for connection to

an external time clock to force pump alternation.

26. The controller shall be capable of accepting four additional

analog input signals, as well as the input level signal. These

additional analog input signals are used for telemetry

purposes only, and this information shall be re-transmitted by

the controller via ModBus communication protocol.

27. The controller shall have a parameter setting to allow the

analog input level to be a 4-20mA signal from a transducer or

an input from a conductance level probe. The controller shall

also have a parameter that will allow the level probe to be

used as a back-up level measurement device to the analog

transducer input.

28. The controller must have a level probe connection capable of

interfacing to a conductance level probe with ten sensor

points.

29. The controller shall have a parameter to select the level probe

type by the distance between the electrodes.

30. The controller shall have a choice of impedance settings for

use with a conductance probe.

31. The controller shall have a level offset parameter to enable

the transducer or conductance level probe to be placed off the

bottom of the wetwell, while maintaining an accurate

representation of the wetwell depth.

32. The controller shall be able to perform float back-up using

from 2 to 7 floats.

C. Wireless Radio Receiver

A. General Operation: Radio receiver shall receive 900 MHz RF

signal from NE 28th Avenue Drainage Retention Area Simplex

Page 127: SECTION 03000-1 - Tech Specs 05-29-2015

Pump Station sent by Wireless Radio Transmitter for high level

alarm. Upon receiving signal, radio receiver shall convert the

analog signals and switch status to a 4/20 mA signal and send

to the pump controller to prevent any pumps from operating.

B. Wireless radio receiver shall be model DR9021 as

manufactured by Wilkerson Instrument Company, Inc.

Wireless radio transmitter shall be model DR9011 as

manufactured by Wilkerson Instrument Company, Inc.

C. Wireless radio units shall be capable of operation up to three

miles.

D. Wireless radio receiver shall indicate that it is receiving a

signal by LED light on the front of the unit.

E. Wireless radio receiver shall mount to DIN rails within the

main control panel.

F. Warranty: Product shall have a minimum five-year warranty

from manufacturer.

D. Remote Terminal Unit

1. Radio transmitter shall utilize 400 MHz frequency and shall be

model SD4 as manufactured by General Electric Company, Inc.

or engineered approved substitution. Frequency to be used is

452.900 MHz as designated by the Owner.

2. Transmitter shall receive input signal from Pump Controller via

RS-232 Serial Port.

3. Transmitter shall have coaxial cable port to connect with

antenna.

E. Antenna

1. Antenna shall have broadcast frequency of 452.900 MHz as

designated by the owner.

2. Antenna shall have minimum 20 MHz operating bandwidth.

3. Antenna shall be constructed of grade 6061-T6 seamless

aluminum with stainless steel hardware.

Page 128: SECTION 03000-1 - Tech Specs 05-29-2015

4. Antenna shall be Laird Yagi or engineer approved substitution.

Page 129: SECTION 03000-1 - Tech Specs 05-29-2015

SECTION 03000-4 CAMEO POND STORM DRAIN

COMPONENT PROJECT - PART 4

SECTION 3100-4 GENERAL

1. This section covers supplemental technical specifications not covered in thestandard specifications.

2. The City of Ocala "General Conditions for Construction", Volume I and“Standard Specifications for Water and Sewer Construction”, Volume III, alongwith FDOT Standard Specifications for Road and Bridge Construction, latestedition, Divisions II and III shall govern the execution of this ComponentProject - Part 4 as specified and amended by these Contract Documents.

3. The contractor will be required to submit Traffic Control Plans (signed andsealed by a licensed engineer) to be approved by FDOT, City of Ocala and theConsultant.