Lessons from Western Australia’s Water
Security Strategy
Susan Murphy,
Company Director, the Water Corporation of Western Australia
Our operations
Our operations
3
Source: CSIRO
4
Climate change: enhanced greenhouse
Modelling from the world’s best
9 General Circulation Models
SW WA will be drier than last century
-20% +5% -60% +10%
From long term average
Last 27 years is representative of this change
From long term average
5
Streamflows into Perth’s dams
Looking back
watercorporation.com.au 6
Portfolio of options
7
Demand Management campaign
Campaign approach
Tap in - Engaging the Community
What our customers told us
9
Key points• When both the qualitative and
quantitative elements of the Tap In process were completed, 20 key insights under five themes were uncovered.
• Seven of the insights were overarching insights – they span across many aspects our business, so don’t fit neatly into just one of the four major themes.
• A key learning from this research is that in many areas our strategy is closely aligned to customers expectations.
10
Supporting behaviour change
Partnering with schools
Reducing water use
13
Seawater Desalination
Perth Seawater Desalination
Plant (Kwinana) – 45GL
Southern Seawater
Desalination Plant
(Binningup) – 100GL
15
Groundwater Replenishment2004
GWR identified as a potential source
2005
Commit to a trial following
community feedback
2007
Commence engagement
20010 - 12
Trial GWR technology and recharge
Ongoing community engagement
2013
Community support,
Regulatory and Government approval
2017
Commence recharge from full-scale GWR
scheme – 14 GL
Groundwater replenishment timeline
2004 2006 2007 2008 2009 2010 2012 2013 2014 2016 2017 2018 2019
Engagement
commenced
Wastewater
characterisation Premier’s Collaborative
Research Program (2006-08)
Interagency Working Group
Aquifer characterisation
Baseline groundwater
sampling
Trial plant commissioned
Recharge commenced
Visitors Centre launched
Trial completed
Recharge continues
Final Trial Report and
government decision
Trial plant decommissioned
Stage 1 construction
Stage 1 plant commissioned
Stage 2 announced
Visitors Centre reopenedStage 1 commences operation
Stage 2 construction
Stage 2 commissioning
Stage 2
commences
operation
Community engagement
Pre Tour Survey Results Post Tour Survey Results
1. Start Recharge
2. Complete Trial
3. GWR Stage 11 32