Civil and Geomatics Engineering Laboratory Safety Manual Updated 2019 SEISMIC TABLE Operation in EE185 Seismic Table Safety and Operation The importance of lab safety cannot be emphasized strongly enough. The lab instructor is ultimately responsible for the students' safety. If you practice lab safety, students will be more willing to do so also. In almost every state, instructors—as well as the school—are legally liable for student injuries. In case of an accident, being able to prove that lab safety has been taught, and that safety rules are enforced, becomes your legal protection. Unfortunately the lack of formal safety training and inadequate maintenance procedures could expose you to accidents—and lawsuits. In an effort to help the lab instructor, a safety plan for the above test or experiment has been written below. Although these guidelines carry no legal weight, they can provide instructors with a general overview for lab safety. OVERVIEW During any seismic table testing process, there may be instances when concrete shards or specimen pieces may fall from the structure. In order to reduce exposure to injury for instructor, student and spectators, the following procedures will be in place during the testing procedure. The testing may be stopped at any time if any of the procedures are not followed. WINDOW PROTECTION Some sort of window protection will be required to keep foreign material from penetrating glass in observation decks. This can be either permanent or temporary. CAZ (Controlled Access Zone) The entire main floor of EE185 will be designated as the CAZ. During the testing and immediately afterward, access will be limited only to the MTS operator/Instructor. Only after it has been deemed safe, will observers be allowed in the CAZ.

Upload: others

Post on 20-Jan-2021

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: SEISMIC TABLE Operation in EE185...MTS System Pre-Start Check List 1. Make sure area around seismic table is clear of any obstructions and/or debris. 2. Check for any hydraulic fluid

Civil and Geomatics Engineering Laboratory Safety Manual Updated 2019

SEISMIC TABLE Operation in EE185

Seismic Table Safety and Operation

The importance of lab safety cannot be emphasized strongly enough. The lab instructor is ultimately responsible for the students' safety. If you practice lab safety, students will be more willing to do so also.

In almost every state, instructors—as well as the school—are legally liable for student injuries. In case of an accident, being able to prove that lab safety has been taught, and that safety rules are enforced, becomes your legal protection.

Unfortunately the lack of formal safety training and inadequate maintenance procedures could expose you to accidents—and lawsuits. In an effort to help the lab instructor, a safety plan for the above test or experiment has been written below. Although these guidelines carry no legal weight, they can provide instructors with a general overview for lab safety. OVERVIEW During any seismic table testing process, there may be instances when concrete shards or specimen pieces may fall from the structure. In order to reduce exposure to injury for instructor, student and spectators, the following procedures will be in place during the testing procedure. The testing may be stopped at any time if any of the procedures are not followed. WINDOW PROTECTION Some sort of window protection will be required to keep foreign material from penetrating glass in observation decks. This can be either permanent or temporary. CAZ (Controlled Access Zone) The entire main floor of EE185 will be designated as the CAZ. During the testing and immediately afterward, access will be limited only to the MTS operator/Instructor. Only after it has been deemed safe, will observers be allowed in the CAZ.

Page 2: SEISMIC TABLE Operation in EE185...MTS System Pre-Start Check List 1. Make sure area around seismic table is clear of any obstructions and/or debris. 2. Check for any hydraulic fluid

BARRIER/CAUTION TAPE LOCATION

Barriers or caution tape will be placed at the lab double door to restrict access to the lab from the east. The large rollup door will be opened and used for observation overflow, but caution tape will restrict access to the lab through this door. Access to EE285A, the observation deck, will be via the pedestrian door and up the staircase to the deck. This area will be limited to 20 people, due to egress policies that will be enforced. Once the experiment starts, there should be minimal movement of people to avoid distractions to the operator. When the testing is completed, the instructor will determine if it is safe for access to the main lab floor. EXTENT OF SHAKE Due to the size and weight of the structure under test, the actual shaking will continue until the required frequency and amplitude have been reached. Safety of the students and facility will not be compromised by any additional testing other than the scheduled and predetermined frequency and amplitude. No “shake till it breaks”. EMERGENCY EGRESS In case of a catastrophic failure, the MTS operator/Instructor will have available to him, the emergency abort button for the MTS. After depressing this button, he is to immediately exit area through the west rollup door. There is a reinforced concrete wall for his protection without leaving the general area. NOISE PROTECTION There is no requirement for noise protection; observers will either be out side or behind glass on the second floor observation deck. ADDITIONAL SAFETY PROTECTION The MTS Machine operator/Instructor will be required to have a hard hat and safety glasses on during the testing. Again, observers will be far enough away to not require additional safety measures. AFTER SEISMIC TEST If after the successful test there is visible damage, it will be the responsibility of the MTS Operator/Instructor to determine if the structure is still safe. If it is determined that the structure is unsafe, then the MTS operator/Instructor will make provisions to secure structure until the damaged structure can be safely removed.

Page 3: SEISMIC TABLE Operation in EE185...MTS System Pre-Start Check List 1. Make sure area around seismic table is clear of any obstructions and/or debris. 2. Check for any hydraulic fluid

IN CASE OF CATASTROPHIC FAILURE

• MSDS Sheets are attached to safety plan (See format below) • MTS Operator/Instructor would determine Emergency call to:

o University Police Department 278-2132 o Fresno Fire Department Dial 9-1-1

CLEANUP

Clean up can be accomplished by placing fluid material in a container and sent to an appropriate waste disposal facility • Hydraulic Fluid can be cleaned up with:

o Fire retardant sawdust o Diatomaceous earth o Sand

Material Safety Data Sheet

SECTION I - Material Identity SECTION II - Manufacturer's Information SECTION III - Physical/Chemical Characteristics SECTION IV - Fire and Explosion Hazard Data SECTION V - Reactivity Data SECTION VI - Health Hazard Data SECTION VII - Precautions for Safe Handling and Use SECTION VIII - Control Measures SECTION IX - Label Data SECTION X - Transportation Data SECTION XI - Site Specific/Reporting Information SECTION XII - Ingredients/Identity Information

SECTION I - Material Identity

Item Name Part Number/Trade Name MOBIL DTE 24 National Stock Number 9150L415823F CAGE Code 3U728

Page 4: SEISMIC TABLE Operation in EE185...MTS System Pre-Start Check List 1. Make sure area around seismic table is clear of any obstructions and/or debris. 2. Check for any hydraulic fluid

Part Number Indicator A MSDS Number 189169 HAZ Code B

SECTION II - Manufacturer's Information

Manufacturer Name MOBIL OIL CORP Street 3225 GALLOWS ROAD City FAIRFAX State VA Country US Zip Code 22037-0001 Emergency Phone 800-424-9300 CHEMTREC(609-737-4411) Information Phone 800-662-4245 MSDS Preparer's Information

Date MSDS Prepared/Revised 22FEB00 Date of Technical Review 24AUG95 Active Indicator Y Alternate Vendors

SECTION III - Physical/Chemical Characteristics

Specification Number N/R Specification Type/Grade/Class N/R Hazard Storage Compatibility Code N1 NRC License Number N/R Net Propellant Weight (Ammo) N/R Appearance/Odor AMBER LIQUID WITH MILD ODOR Boiling Point >600F,>316C Melting Point NE Vapor Pressure <0.1 Vapor Density >2.0 Specific Gravity 0.874 Decomposition Temperature UNKNOWN Evaporation Rate NA Solubility in Water NEGLIGIBLE Percent Volatiles by Volume N/K Chemical pH NA Corrosion Rate UNKNOWN Container Pressure Code 1 Temperature Code 4 Product State Code L

Page 5: SEISMIC TABLE Operation in EE185...MTS System Pre-Start Check List 1. Make sure area around seismic table is clear of any obstructions and/or debris. 2. Check for any hydraulic fluid

SECTION IV - Fire and Explosion Hazard Data

Flash Point 396 Lower Explosion Limit NA Upper Explosion Limit NA Extinguishing Media CARBON DIOXIDE, FOAM, DRY CHEMICAL

AND WATER FOG.WATER OR FOAM MAY CAUSE FROTHING. USE WATER TO COOL FIRE EXPOSE CANS

Special Fire Fighting Procedures FOR FIRES IN ENCLOSED AREAS, FIRE FIGHTERS MUST USE SELF-CONTAINED BREATHING APPARATUS. WATER SPRAY MAY BE USED TO FLUSH SPILLS AWAY FROM EXPOSURE

Unusual Fire/Explosion Hazards NOTE: PRESSURIZED MISTS MAY FORM A FLAMMABLE MIXTURE. FLASH POINT:>202C, 396F

SECTION V - Reactivity Data

Stability YES Stability Conditions to Avoid EXTREME HEAT Materials to Avoid STRONG OXIDIZING AGENTS Hazardous Decomposition Products CARBON MONOXIDE, METAL OXIDES,

ELEMENTAL OXIDES Hazardous Polymerization NO Polymerization Conditions to Avoid NONE SPECIFIED BY MANUFACTURER

SECTION VI - Health Hazard Data

Route of Entry: Skin YES Route of Entry: Ingestion YES Route of Entry: Inhalation YES Health Hazards - Acute and Chronic PRODUCT ASSESSED IN ACCORDANCE WITH

OSHA 29 CFR 1910.1200 AND DETERMINED NOT BE TO HAZARDOUS

Carcinogenity: NTP NO Carcinogenity: IARC NO Carcinogenity: OSHA NO Explanation of Carcinogenity NOT CARCINOGENIC Symptoms of Overexposure NO SIGINIFICANT EFFECTS EXPECTED Medical Cond. Aggrevated by Exposure NONE SPECIFIED BY MANUFACTURER Emergency/First Aid Procedures [EYES] FLUSH THOROUGHLY WITH WATER.

IF IRRITATION OCCURS, SEE DOCTOR. [SKIN] WASH WITH SOAP AND WATER. HIGH PRESSURE ACCIDENTAL INJECTION INTO SKIN REQUIRES IMMEDIATE MEDICAL ATTENTION. [INHALATION] NOTEXPECTED TO BE A PROBLEM.

Page 6: SEISMIC TABLE Operation in EE185...MTS System Pre-Start Check List 1. Make sure area around seismic table is clear of any obstructions and/or debris. 2. Check for any hydraulic fluid

[INGESTED] NOT EXPECTED TO BE A PROBLEM. HOWEVER,GIVE 1-2 GLASSES OF WATER & CALL PHYSICIAN. DO NOT INDUCE VOMITING OR GIVEANYTHING TO AN UNCONSCIOUS PERSON

SECTION VII - Precautions for Safe Handling and Use

Steps if Material Released/Spilled ABSORB ON FIRE RETARDENT TREATED SAWDUST, DIATOMECOUS EARTH, ETC. SHOVEL UP & DISPOSE OF AT AN APPROPIATE WASTE DISPOSAL FACILITY IN ACCORDANCE WITH CURRENT APPLICABLE LAWS AND REGULATIONS & PRODUCT CAHRACTERISTICS AT TIME OF DISPOSAL

Neutralizing Agent NONE SPECIFIED BY MANUFACTURER Waste Disposal Method PRODUCT IS SUITABLE FOR BURNING IN

AN ENCLOSED, CONTROLLED BURNER FOR FUEL VALUE OR DISPOSAL BY SUPERVISED INCINERATION. IN ADDITION, THE PRODUCT IS SUITABLE FOR PROCESSING BY AN APPROVED RECYCLING FACILITY

Handling and Storage Precautions DO NOT STORE IN OPEN OR UNLABELED CONTAINERS. STORE AWAY FROM STRONG OXIDIZING AGENTS OR COMBUSTIBLE MATERIAL

Other Precautions HIGH PRESSURE INJECTION UNDER THE SKIN MAY OCCUR DUE TO RUPTURE OF PRESSURIZED LINES. ALWAYS SEEK MEDICAL ATTENTION

SECTION VIII - Control Measures

Respiratory Protection NO SPECIAL REQUIREMENTS UNDER ORDINARY CONDITIONSOF USE AND WITH ADEQUATE VENTILATION

Ventilation NO SPECIAL REQUIREMENTS UNDER ORDINARY CONDITIONS OF USE AND WITH ADEUQATE VENTILATION

Protective Gloves PRACTICE GOOD HYGIENE Eye Protection NORAM INDUSTRIAL EYE PROTECTION Other Protective Equipment NONE NORMALLY REQUIRED Work Hygenic Practices WASH HANDS AFTER USE AND BEFORE

EATING, DRINKING,OR SMOKING. LAUNDER CONTAMINATED CLOTHES BEFORE REUSE

Supplemental Health/Safety Data NOT REGULATED

SECTION IX - Label Data

Page 7: SEISMIC TABLE Operation in EE185...MTS System Pre-Start Check List 1. Make sure area around seismic table is clear of any obstructions and/or debris. 2. Check for any hydraulic fluid

Protect Eye YES Protect Skin YES Protect Respiratory YES Chronic Indicator NO Contact Code SLIGHT Fire Code UNKNOWN Health Code UNKNOWN React Code UNKNOWN Specific Hazard and Precaution NO TARGET ORGANS LISTED FOR CHRONIC

EXPOSURES

SECTION X - Transportation Data

SECTION XI - Site Specific/Reporting Information

Volatile Organic Compounds (P/G) 0 Volatile Organic Compounds (G/L) 0

SECTION XII - Ingredients/Identity Information

Ingredient # 01 Ingredient Name (ZNCPD) ZINC CAS Number 7440666 Proprietary NO Percent 0.1 Ingredient # 02 Ingredient Name (ZNCPD) ZINC DIALKLDITHIOPHOSPHATE

INHIBITOR CAS Number 68649423 Proprietary NO Percent 0.67

Page 8: SEISMIC TABLE Operation in EE185...MTS System Pre-Start Check List 1. Make sure area around seismic table is clear of any obstructions and/or debris. 2. Check for any hydraulic fluid

Also includes

Vickers Pump

Operation !!

MTS Account Information

Site#: 505132

PH #: 800-328-2255

FlexTest SE—4.0D 2008

UPDATED 8-14-16

Page 9: SEISMIC TABLE Operation in EE185...MTS System Pre-Start Check List 1. Make sure area around seismic table is clear of any obstructions and/or debris. 2. Check for any hydraulic fluid

2

EMERGENCY

CONTACT LIST

Lab Custodians for EE 185 (Structures Lab)

Dr. Nazari Lab Custodian 278-6603

Dr. Larralde Associate Dean 278-2566

Dr. Nunna Administrator 278-8111

Steve Scherer Dept Technician 278-7200

University Police Department 278-8400

Page 10: SEISMIC TABLE Operation in EE185...MTS System Pre-Start Check List 1. Make sure area around seismic table is clear of any obstructions and/or debris. 2. Check for any hydraulic fluid

3

CIVIL ENGINEERING

LABORATORY SAFETY PLAN

For

EE-185

STRUCTURES LABORATORY

(Supervising Faculty Member: Dr. Nazari)

Students shall conduct themselves in a safe and orderly manner when using this laboratory facility. Practices, which detract from the normal learning environment, shall be avoided. Dis-ruptive behavior, loud sounds or noises, smoking and any other distraction or unsafe action that disrupts the normal learning process will not be tolerated. Food and drink is allowed only in designated area.

Foot wear, which does not provide adequate protection from dropped objects, should be avoided. Similarly, loose fitting clothing that could become caught in the mechanical compo-nents of the testing equipment should not be worn.

Lubricants (if any) and other necessary maintenance materials shall be used only under the direct supervision of a faculty member or authorized technician.

Avoid heavy lifting or prolonged use of computer monitors. Cease work if a headache develops.

Report all injuries to the supervising faculty member.

All serious injuries shall be reported to the department chair. All such injured personnel shall be escorted to the Student Health Center or call 911 and the Student Health Center.

Page 11: SEISMIC TABLE Operation in EE185...MTS System Pre-Start Check List 1. Make sure area around seismic table is clear of any obstructions and/or debris. 2. Check for any hydraulic fluid

4

MTS System Pre-Start Check List

1. Make sure area around seismic table is clear of

any obstructions and/or debris.

2. Check for any hydraulic fluid leaks at actuator and

accumulator.

3. Insure that there are no abrasions on any of the hy-

draulic lines.

4. Physically verify that the spiral washers (2 sets of

2) are tight and secure and

both yellow lines are still

touching each other.

5. Inspect mechanical connections between the table

and specimen to insure that they are in the proper lo-

cation and secured.

Page 12: SEISMIC TABLE Operation in EE185...MTS System Pre-Start Check List 1. Make sure area around seismic table is clear of any obstructions and/or debris. 2. Check for any hydraulic fluid

5

Vickers Pump Operation and

Start Up Procedures

Page 13: SEISMIC TABLE Operation in EE185...MTS System Pre-Start Check List 1. Make sure area around seismic table is clear of any obstructions and/or debris. 2. Check for any hydraulic fluid

6

BEFORE RUNNING PUMP

Ensure that the “OUTPUT PRESSURE” selector (5-6-7) is in the “LOW” (6) position.

Alternate Pump use by switching between both Pumps, Switch (10-11-12) will change pumps to evenly distribute the use between the two Pumps.

Make sure that all three “EMERGENCY STOP” buttons are in the released state, and ensure the “STOP” button on panel (4) is also released.

EMERGENCY STOP BUTTON LOCATIONS

(One at Panel, One at Vickers Pump, one at Console and one remote portable switch)

TO START PUMP

Make sure “RECIRC PUMP” in the “AUTO” (1) position.

Turn “OUTPUT PRESSURE” to “START” (7), and then turn selector to “LOW” (6) and allow pump to run for about 30 seconds in “LOW” (6), after which time selec-tor can be turned to “HIGH”(5).

To add second pump, turn “PUMP SELECTOR” to “BOTH” (11).

TO TURN OFF PUMP

Turn “OUTPUT PRESSURE” to “LOW” (6).

Press “STOP” (4) button and leave button depressed.

NOTE: If “FILTER DIRTY” (8) light comes on, system can be “RESET” (9), notify Technician if the light comes on just in case the light was caused by something else.

Page 14: SEISMIC TABLE Operation in EE185...MTS System Pre-Start Check List 1. Make sure area around seismic table is clear of any obstructions and/or debris. 2. Check for any hydraulic fluid

7

Starting up System

The login for the computer is “administrator” password is “admin”. There is also a password that is required to load the firmware and for any updates. This is usually done by the MTS Technician or by the Department Technician. This account is used only for upgrades and loading of firmware. The other passwords required to get into Tuning, Configuration, and Calibration will be addressed later.

Do not change any parameters in the “Network Settings”

Do not delete the “MTS_RT Account as this contains all the con-necting information from the computer to the MTS FLEX SE box.

System Loader and Station Manager and

Station Builder Icons

NOTE: PC must be up and running pr ior to starting the MTS FLEX-SE Controller. The On/Off switch for the MTS is on the back of control-ler. (System Loader must be loaded only the first time the computer is turned on.) Then Station Manager should be loaded.

Page 15: SEISMIC TABLE Operation in EE185...MTS System Pre-Start Check List 1. Make sure area around seismic table is clear of any obstructions and/or debris. 2. Check for any hydraulic fluid

8

Open Configuration ( In System Manager)

Under Configuration is a file called ftse.cfg, this is the file that

configures the Table Operation. Choose an existing Parameter Set

to use or to modify, just remember to “Save As” and do not write

over the original Parameter Set.

Page 16: SEISMIC TABLE Operation in EE185...MTS System Pre-Start Check List 1. Make sure area around seismic table is clear of any obstructions and/or debris. 2. Check for any hydraulic fluid

9

Station Manager

You can have the same configuration with different parameters, but each set of parameters must be saved in its own file. Examples are:

Tuned for a specific mass

Tuned for the table only with no mass present.

Windows for a specific Researcher.

Page 17: SEISMIC TABLE Operation in EE185...MTS System Pre-Start Check List 1. Make sure area around seismic table is clear of any obstructions and/or debris. 2. Check for any hydraulic fluid

10

Software Operation

1. Check Box marked “Exclusive Control” , if you do not check it the computer will not have control of the MTS.

2. The system incorporates interlock circuitry that allows for the ces-sation of a test if there is a system malfunction or operator error. Check Box marked “Reset Interlock 1”

3. Observe/Change limits of the Table:

3-1. Display/Station Setup

3-2. Channels

A. Stroke-Displacement limits set to 5”

B. Load-Force limits set to 55kips

3-3. If tuning is required, change from Operation to Tuning (Password “Tuning”), Then select parameters from “Tuning Fork”

Page 18: SEISMIC TABLE Operation in EE185...MTS System Pre-Start Check List 1. Make sure area around seismic table is clear of any obstructions and/or debris. 2. Check for any hydraulic fluid

11

Valve Tuning

4. Check valve response by metering output and spool position.

4-1. Display and Meters

4-2. Pull up Load, Stroke, Output, Spool Position, and

Command as shown below:

4-3. If it is a well-balanced Valve, Spool Position should be at

zero. Note: To get Spool Position to zero, valve tuning is

needed!

4-4. Stroke and Command should be equal, to have the output

(voltage to 5v) = 0.

This is for better performance of the Valve (Error=0).

If Stroke doesn't equal Command, manually match them

by clicking Manual Command on Station Controls.

First Enable then match Stroke and Command, then

Disable, Close Manual Command Box.

Output Spool

Position

Command Stroke

Load

Page 19: SEISMIC TABLE Operation in EE185...MTS System Pre-Start Check List 1. Make sure area around seismic table is clear of any obstructions and/or debris. 2. Check for any hydraulic fluid

12

Valve Tuning (cont’d)

4-5. Click on Function Generator (top cell; left side)

Command: Cyclic

Set Frequency and Amplitude

Display/Scope/Plot Output vs Spool Position

Basic Testware Run

Make sure there is min- imum 0ft set between Output

and Spool Position

NOTE: Contaminated hydraulic fluid may affect this

Valve signal.

Change Amplitude of Cyclic Load to monitor difference,

if any.

Basic Testware Pause

Table Warm-up

5. HSM1 Low (wait for a few seconds) High

This will turn on the table and allow the hydraulic fluid to warm up

to operating temperature.

Table Tuning 6. There are two types of tuning Classic and Earthquake Application 6-1. Classic Tuning Function Generator Command: Cyclic Wave Shape: Squared Taper Amplitude: 0.05 Frequency: 0.1 Hz

Page 20: SEISMIC TABLE Operation in EE185...MTS System Pre-Start Check List 1. Make sure area around seismic table is clear of any obstructions and/or debris. 2. Check for any hydraulic fluid

13

Table Tuning (cont’d) 6-2. Earthquake Application

Function Generator

Command: Random

Wave Shape: Random 1/F2 (for displacement control)

or

Wave Shape: Random Flat and Sm Acc Control

Note: Frequency Range for Tuning: 0.5-25 Hz (smaller

frequency range results in better data)

6-3. Basic Testware Run

6-4. Using either #6-1 or #6-2 then enter:

Display/Scope

Plot Command vs Stroke

(Note: Minimum offset should be observed)

Change Gain Factors (P/J/D/F) for Tuning:

(Display/Stut12 set-up).

(Note: Generally larger P-Gain and smaller D-Gain fac

tors result in sharper response. Also, larger P-Gain fac

tors result in more unstable results.

Table is now Tuned

6-5. Stop

Page 21: SEISMIC TABLE Operation in EE185...MTS System Pre-Start Check List 1. Make sure area around seismic table is clear of any obstructions and/or debris. 2. Check for any hydraulic fluid

14

Table Testing (Apply Eq Record) 7. There are two types of tuning Classic and Earthquake Application

7-1. Application– Multi-Purpose Test

7-2. Procedure Editor–Used to create a New Procedure

7-3. Drag and Drop:

a. Data Acquisition (Table Sensors)

b. Record (Profile Command)

a. Using Timing (For Equalizer Applications)

b. Select Record (Blank Format File)

7-4. Multi-Purpose Test (MPT) for new specimens

7-5. Application/ Profick Editor

a. Open (Find the Eq that was run)

b. Open Graphical Preview

The above a and b used to Plot and see Record

Page 22: SEISMIC TABLE Operation in EE185...MTS System Pre-Start Check List 1. Make sure area around seismic table is clear of any obstructions and/or debris. 2. Check for any hydraulic fluid

15

Page 23: SEISMIC TABLE Operation in EE185...MTS System Pre-Start Check List 1. Make sure area around seismic table is clear of any obstructions and/or debris. 2. Check for any hydraulic fluid

16

FIELD DESCRIPTIONS

Function Generator (A), allows for control of seismic table.

“Initiate Exclusive Control” (C). This allows total control from this location.

Manual Control, Enable Manual Control (B), insure that Control Mode is “Stroke”.

“Reset Interlock 1” (D), this resets all safety Inter locks and Over-rides.

HSM (E) must be ramped up from One Bar to Two Bars to Three Bars in order to get maximum flow from the hydraulic system.

Page 24: SEISMIC TABLE Operation in EE185...MTS System Pre-Start Check List 1. Make sure area around seismic table is clear of any obstructions and/or debris. 2. Check for any hydraulic fluid

17

Amplitude (F), this is the distance that the table will travel, usual-ly start this at ½ inch.

Frequency (G), this will tell the MTS how many cycles per second to operate at, start at about 1 HZ.

Start Triangle on Basic TestWare (H) to star t table, to stop check square.

After stopping test, set both Amplitude and Frequency back to

Page 25: SEISMIC TABLE Operation in EE185...MTS System Pre-Start Check List 1. Make sure area around seismic table is clear of any obstructions and/or debris. 2. Check for any hydraulic fluid

18

Page 26: SEISMIC TABLE Operation in EE185...MTS System Pre-Start Check List 1. Make sure area around seismic table is clear of any obstructions and/or debris. 2. Check for any hydraulic fluid

19

Page 27: SEISMIC TABLE Operation in EE185...MTS System Pre-Start Check List 1. Make sure area around seismic table is clear of any obstructions and/or debris. 2. Check for any hydraulic fluid

20

The hydraulic supply system has a ca-

pacity of delivering 110 gallons per mi-

nute at 55,000 pounds of force, and can

move the 10,000 pound table +/- 5 inches

to simulate an earthquake