Selected Past Projects Juraj Danko [email protected] Project number : 01 Project title : Implementation of marine environmental monitoring system – Sultanate of Oman Date : 2011 – ongoing Short description : Delivery of complex marine monitoring system, server hardware, software, and services Ordered / cooperated by : PACA, Sultanate of Oman Position in team : Project Manager, Senior Technical Consultant Processed work part in details : Site survey, specification and analysis, quotation, project management Operating system : Linux Used languages, software, tools and technologies : Nortek AWAC, Fujitsu servers, Java, Flash, Oracle, solar powering Project number : 02 Project title : Integrated Monitoring System Date : 2013 – 2016 Short description : Delivery of complex monitoring system, server hardware, software, numerical models, web portal, and mobile applications Ordered / cooperated by : Dubai Municipality, Dubai, UAE Position in team : Project Manager, Senior Technical Consultant Processed work part in details : Specification and analysis, quotation, project management, technical consulting, further business development / account manager Operating system : Linux Used languages, software, tools and technologies : iOS mobile application, Android mobile application, Java, Flash, Oracle, proprietary HW, third-party sensors, solar powering

Upload: juraj-danko

Post on 23-Feb-2017

214 views

Category:

Career


0 download

TRANSCRIPT

Selected Past Projects Juraj Danko

[email protected]

Project number : 01

Project title : Implementation of marine environmental monitoring system –

Sultanate of Oman

Date : 2011 – ongoing

Short description : Delivery of complex marine monitoring system, server

hardware, software, and services

Ordered / cooperated by : PACA, Sultanate of Oman

Position in team : Project Manager, Senior Technical Consultant

Processed work part in

details

: Site survey, specification and analysis, quotation, project

management

Operating system : Linux

Used languages,

software, tools and

technologies

: Nortek AWAC, Fujitsu servers, Java, Flash, Oracle, solar

powering

Project number : 02

Project title : Integrated Monitoring System

Date : 2013 – 2016

Short description : Delivery of complex monitoring system, server hardware,

software, numerical models, web portal, and mobile applications

Ordered / cooperated by : Dubai Municipality, Dubai, UAE

Position in team : Project Manager, Senior Technical Consultant

Processed work part in

details

: Specification and analysis, quotation, project management,

technical consulting, further business development / account

manager

Operating system : Linux

Used languages,

software, tools and

technologies

: iOS mobile application, Android mobile application, Java, Flash,

Oracle, proprietary HW, third-party sensors, solar powering

Project number : 03

Project title : ISO 27001 certification

Date : 2014

Short description : Certification of a company according to ISO 27001

Ordered / cooperated by : MicroStep-MIS

Position in team : Internal auditor, information security manager

Processed work part in

details

: Extension of existing ISO 9001 quality management system with

ISO 27001, auditing, documentation, risk analysis

Operating system : -

Used languages,

software, tools and

technologies

: MS Office, internal tools

Project number : 04

Project title : Data Protection and Information Security auditing and

management, Banská Bystrica Self-Governing Region

Date : 2013-2014

Short description : Auditing, documentation, risk analysis

Ordered / cooperated by : Banská Bystrica Self-Governing Region

Position in team : Auditor, consultant, information security expert

Processed work part in

details

: Auditing, documentation, risk analysis, project management

Operating system : -

Used languages,

software, tools and

technologies

: MS Office, VBA, VSTO

Project number : 05

Project title : Information Security Management, Ministry of Foreign and

European Affairs of the Slovak Republic

Date : 2014

Short description : ISM consulting and development, risk analysis, documentation

Ordered / cooperated by : Ministry of Foreign and European Affairs of the Slovak

Republic

Position in team : Auditor, consultant, information security expert

Processed work part in

details

: Auditing, documentation, risk analysis, project management

Operating system : -

Used languages,

software, tools and

technologies

: MS Office, VBA, VSTO

Project number : 06

Project title : Information Security and Data Protection Auditing,

Documentation and Related Works @ Košice Self-Governing

Region

Date : 2014

Short description : Auditing, documentation, risk analysis

Ordered / cooperated by : Košice Self-Governing Region

Position in team : Auditor, consultant, information security expert

Processed work part in

details

: Auditing of Information Security, Physical Security, and Data

Protection at 50+ organizations in the regions of Košice Self-

Governing Region, Slovak republic. Development of the

respective documentation in accordance with the Information

Security and Personal Data Protection law.

Operating system : -

Used languages,

software, tools and

technologies

: MS Office, VBA, VSTO

Project number : 07

Project title : Information Security and Data Protection Auditing,

Documentation and Related Works @ Trnava Self-Governing

Region

Date : 2014-2015

Short description : Auditing, documentation, risk analysis

Ordered / cooperated by : Trnava Self-Governing Region

Position in team : Auditor, consultant, information security expert

Processed work part in

details

: Auditing of Information Security, Physical Security, and Data

Protection at 20+ organizations in the regions of Trnava Self-

Governing Region, Slovak republic. Development of the

respective documentation in accordance with the Information

Security and Personal Data Protection law.

Operating system : -

Used languages,

software, tools and

technologies

: MS Office, VBA, VSTO

Project number : 08

Project title : BlameItOnTheFish.com

Date : 2012

Short description : Startup

Ordered / cooperated by : Startup

Position in team : Co-founder, CEO

Processed work part in

details

: I participated in this project as an idea-maker and business

developer with influence in product development and marketing.

After more than a year since the launch, we decided to

temporarily discontinue the project for time reasons.

Operating system : -

Used languages,

software, tools and

technologies

: -

Project number : 09

Project title : Meteorological Radar

Date : 2016

Short description : Delivery and installation of a meteorological radar

Ordered / cooperated by : Dubai Municipality, Dubai, UAE

Position in team : Project Manager, Senior Technical Consultant

Processed work part in

details

: Communication with the purchaser, project management,

management of the delivery, installation, and commissioning,

training, services

Operating system : Linux

Used languages,

software, tools and

technologies

: Java, Flash

Project number : 10

Project title : Upgrade of Central System

Date : 2016 - ongoing

Short description : Upgrade of the data acquisition and data propagation system for

an environmental monitoring system

Ordered / cooperated by : National Center of Meteorology & Seismology (NCMS),

Abu Dhabi, UAE

Position in team : Project Manager, Senior Technical Consultant

Processed work part in

details

: Communication with the purchaser, technical consulting, project

management, management of the delivery, installation, and

commissioning, training, services

Operating system : Linux

Used languages,

software, tools and

technologies

: Java, Flash

Project number : 11

Project title : Extension of the monitoring network

Date : 2016

Short description : Extension of the existing environmental monitoring system

Ordered / cooperated by : National Center of Meteorology & Seismology (NCMS),

Abu Dhabi, UAE

Position in team : Project Manager

Processed work part in

details

: Communication with the purchaser, technical consulting, project

management

Operating system : -

Used languages,

software, tools and

technologies

: Proprietary hardware, third-party sensors

Project number : 12

Project title : Extension of the monitoring network

Date : 2013

Short description : Extension of the existing environmental monitoring system

Ordered / cooperated by : Saudi Arabia

Position in team : Project Manager

Processed work part in

details

: Communication with the purchaser, technical consulting, project

management

Operating system : -

Used languages,

software, tools and

technologies

: Proprietary hardware, third-party sensors, software upgrade

Project number : 13

Project title : Media Planning Automation System

Date : 2014 – 2016

Short description : Automation of media planning – radio, print, TV

Ordered / cooperated by : GroupM Slovakia / MEC Slovakia

Position in team : Project Manager, developer

Processed work part in

details

: Managing of the team, development of the system

Operating system : Windows

Used languages,

software, tools and

technologies

: VBA, MS Office, MS SQL

Project number : 14

Project title : Weather Monitoring System

Date : 2012

Short description : Automatic weather stations, central system, software, services

Ordered / cooperated by : Royal Court – Sultanate of Oman

Position in team : Project Manager

Processed work part in

details

: Specification, project management, quotation, purchasing

Operating system : Linux

Used languages,

software, tools and

technologies

: Proprietary HW, third-party sensors, Java, Flash

Project number : 15

Project title : Reorganization of Marketing and PR Department

Date : 2011-2013

Short description : Complete reorganization of the department, marketing & PR

strategy

Ordered / cooperated by : MicroStep-MIS

Position in team : Executive

Processed work part in

details

: Process analysis, HR, marketing and PR strategy consulting,

strategy for exhibitions and conferences, propagation materials

strategy

Operating system : -

Used languages,

software, tools and

technologies

: -

Project number : 16

Project title : Warning and Notification System

Date : 2011-2013

Short description : Implementation of an internal warning and notification system

for a nuclear power plant

Ordered / cooperated by : Jadrová a vyraďovacia spoločnosť, a.s. (JAVYS), Slovakia

Position in team : Project Manager, Trainer

Processed work part in

details

: Project management, documentation, trainings

Operating system : QNX

Used languages,

software, tools and

technologies

: C++, proprietary HW, sirens, bacons

Project number : 17

Project title : Airport Weather Observation System

Date : 2012

Short description : Airport Weather Observation System implementation

Ordered / cooperated by : Oil&Gas, Sultanate of Oman

Position in team : Project Manager

Processed work part in

details

: Project management, documentation, quotation

Operating system : Linux

Used languages,

software, tools and

technologies

: Java, Flash, proprietary HW, third-party sensors