senior design project presentation
DESCRIPTION
This senior design project conducted the initial design and feasibility study for a water treatment facility that would utilize the Chattahoochee River in supplying the city of Dothan, AL with drinking water.TRANSCRIPT
+
PH&J ConsultantsProject Report
Engineer Brock HorsleyEngineer Heather JonesEngineer Tyler Puckett
2
+I. OVERVIEW
3
+Objective:Design Water Treatment FacilityOur firm has conducted the initial design and feasibility study for a water treatment facility that would utilize the Chattahoochee River in supplying the city of Dothan with drinking water.
+
Overview of ProcessSurface Water Treatment
+ Project Schedule
Weekly Tasks for PH&J Consultants
PH&J Consultants Schedule:WEEK: AGENDA:
#1 12-Jan-14 Analysis Job and Acceptance Memo#2 19-Jan-14 Reference Research#3 26-Jan-14 Research Jobsite & Organize Approach
#4 2-Feb-14Intake Analysis, Recharge Rate, Expected Growth, Average Life,
Pipes, & TOPO#5 9-Feb-14 Plant Layout, Design Basis, & Develop Assumptions#6 16-Feb-14 Chemical Reactions & Mass Balanaces#7 23-Feb-14 Check Progress, Calculations, Assumptions, & Design#8 2-Mar-14 Innovation#9 9-Mar-14 Cost Analysis
#10 16-Mar-14 Plant Drawing#11 23-Mar-14 Check Calculations, Assumptions, & Design#12 30-Mar-14 Develop Conclusion & Recommendations#13 6-Apr-14 Develop References & Appendies#14 13-Apr-14 Complete Project Folder#15 20-Apr-14 Check All Work & Submit
✔✔✔✔
5
✔✔✔✔✔✔✔✔✔✔✔
6
+II. Location
+
Site of Facility- Total Size: 12 acres
- Within City Limits
- Time to furthest serviceable area:
- 55min @ flow of 5ft/s
8
+
Intake to Facility:
9
+III. Plant Study
10
+
Plant Design:
+
Flow Rate:Design Life: 25 years (EPA, 2014)
3 Day Peak Selected
+
Screens:• Concord Screen Airburst
Assembly D-72 • 2 screens are needed• Equipped with air compressors
that periodically clean the screens, eliminating maintenance costs
+ 13
Pumps
Pioneer Pump SC108S17
Specifications: Max flow 6500gpm Variable speed (7 gear) Can handle up to 3.5” solids Operates at 80% power
efficiency
- 4 pumps needed
While the peak flow rate in 2040 is projected to be 35 MGD, the rate for 2015 is projected to be as low as 16 MGD (Polyengineering, 2012).
14+Pipes:Transfer Piping• Ductile Iron Pipe • Expected Life: 100 years • 2 pipe lines are needed• 36 in pipe diameter• Velocity: 3.9 ft/s • Length: 81,000 ft per pipe line
• 0.1 ft of headloss per 100 ft of pipe: 89 ft per pipeline
Yard Piping• Accounts for 10% of total cost• High-density polyethylene material will be used• Corrosion resistant • Commonly used for water transmission • Expected Life: 50 years • Color coding for water treatment plants set by Ten States
Standards
+
Coagulant:
Aluminum Sulfate, Al2(SO4)3 easily accessible cost effective
Dosage: 20 mg/L 5,843 lb/day $0.07 / lb Year’s supply of Alum, 213,850 lb,
would cost $145,500 Inject by: Dry Alum Feeder
+ 16
Rapid Mix:
Detention Time: 45 seconds Needed Volume: 2500 ft3
#tanks = 10 (5 per train)
Vtank = 250 ft3
Velocity Gradient: 900 fps/ft to minimize detention
time
+Flocculation:Detention Time: 30 minutesVolume Needed: 49,000 ft3
• Depth: 16 ft• Width: 32 ft• Length: 96 ft
Three chambers in each tank• 1st: G= 80 s-1 • 2nd: G = 50 s-1 • 3rd: G = 20 s-1
Napier Reid Flocculator • Expected life: 10 years
18
+
Sedimentation:
Depth: 15 ftWidth: 100 ftLength: 260 ft• Velocity: 0.018 ft/s• Detention Time: 4
hours
Sludge Removal: 52,000 gal of sludge/dayCosts:$4.80 per 1000 gallons & an additional $240 per 50,000 gallons Totaling: $490/day
+ 19
Filtration: Granular Rapid FiltrationArea per filter bed: 450ft2
99% removal
Detention Time: 7.5 hrs
Backwash Cycle: 15 min
Filter-to-waste: 10 min
Total Cycle: 8 hours
Recommend using 4 filters
20+ Disinfection
Ozonation• Best at removal of bacteria, viruses, etc. when
compared to chlorine and UV- No THMs- Only byproduct is bromate
- Only a problem in areas with high concentrations of bromine- Delivery system system: LOX- Recommended Initial Concentrations:
- Use 1.5 mg/L for effluent 0.5 mg/L- Daily LOX: 470 gal / day
- 1 Horizontal tank for Storage: 10,000 gal- Weekly use: 3300 gal LOX- Storage for 3 weeks
+ 21
Disinfectant continued:
Contact Chamber Design:
Volume Required: 243000 gal ( 3250 cf)
For HDT of 10 min
Height: 20 ft
Floor: 13 ft x 13 ft
10 chambers
Total volume: 3380 cf
+ 22
Disinfectant continued:
Ozone Generator:
Produces up to 1320 lb ozone / day
Dimensions:- Depth: 7.38 ft- Width: 6.23 ft- Height: 7.08 ft
Floor Space: 46 sf
+ 23
Disinfectant continued:- Residual Disinfectant:
- Ozone does not leave a residual
Needed for microbial growth in pipes
Suggested: 0.01 mg/L residual disinfectant
Chlorine Gas0.5 mg/L initial concentration
Need 150 lb chlorine gas / day
<< EPA maximum residual goal of 4 mg/L- Three week supply can be stored in 21 tanks
+FluoridationSodium fluorosilicate:• Easy to store• Safer than alternatives
• fluorosilicic acidEPA MCL: 4mg/LEPA secondary MCL: 2mg/L
For areas with high naturally-occurring fluoride
Make 2mg/L target value• 980 lb fluorosilicate / day
+
Clear Well:Storage: 25% of Daily flow 9 MGDCST Industries offers construction of ANSI and AWWA approved clearwell storage tanks
26
+
Plant Design:
27
+IV. INNOVATION
+SOLAR PANELS:
Monthly Power used by pumps: 382,500 kWhMonthly Power cost: $5640
Monthly Power supplied by 1 SolarWorld Panel unit: 190 kWh
Number of Units to combat pump power consumption: 3478 units
One-time cost of panels: $272/unit $815,900
Time to payoff: 12 years25 year savings: $815,900
Total acreage required: 0.85 acres << 12acres
29
+V. COSTS
30
+
Cost Analysis:
+ 31
Overall Bill: $24,699.52Due: May 15th
projected: $29,206.73
Budget Used:85%
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15$0.00
$5,000.00
$10,000.00
$15,000.00
$20,000.00
$25,000.00
$30,000.00
$35,000.00
PH&J Consultants' Cost Progress
Projected CostsActual Costs
Week
Cost
($)
+ANY QUESTIONS
32