senior design project presentation

32
+ PH&J Consultants Project Report Engineer Brock Horsley Engineer Heather Jones Engineer Tyler Puckett

Upload: brock

Post on 13-Apr-2016

15 views

Category:

Documents


0 download

DESCRIPTION

This senior design project conducted the initial design and feasibility study for a water treatment facility that would utilize the Chattahoochee River in supplying the city of Dothan, AL with drinking water.

TRANSCRIPT

Page 1: Senior Design Project Presentation

+

PH&J ConsultantsProject Report

Engineer Brock HorsleyEngineer Heather JonesEngineer Tyler Puckett

Page 2: Senior Design Project Presentation

2

+I. OVERVIEW

Page 3: Senior Design Project Presentation

3

+Objective:Design Water Treatment FacilityOur firm has conducted the initial design and feasibility study for a water treatment facility that would utilize the Chattahoochee River in supplying the city of Dothan with drinking water.

Page 4: Senior Design Project Presentation

+

Overview of ProcessSurface Water Treatment

Page 5: Senior Design Project Presentation

+ Project Schedule

Weekly Tasks for PH&J Consultants

PH&J Consultants Schedule:WEEK: AGENDA:

#1 12-Jan-14 Analysis Job and Acceptance Memo#2 19-Jan-14 Reference Research#3 26-Jan-14 Research Jobsite & Organize Approach

#4 2-Feb-14Intake Analysis, Recharge Rate, Expected Growth, Average Life,

Pipes, & TOPO#5 9-Feb-14 Plant Layout, Design Basis, & Develop Assumptions#6 16-Feb-14 Chemical Reactions & Mass Balanaces#7 23-Feb-14 Check Progress, Calculations, Assumptions, & Design#8 2-Mar-14 Innovation#9 9-Mar-14 Cost Analysis

#10 16-Mar-14 Plant Drawing#11 23-Mar-14 Check Calculations, Assumptions, & Design#12 30-Mar-14 Develop Conclusion & Recommendations#13 6-Apr-14 Develop References & Appendies#14 13-Apr-14 Complete Project Folder#15 20-Apr-14 Check All Work & Submit

✔✔✔✔

5

✔✔✔✔✔✔✔✔✔✔✔

Page 6: Senior Design Project Presentation

6

+II. Location

Page 7: Senior Design Project Presentation

+

Site of Facility- Total Size: 12 acres

- Within City Limits

- Time to furthest serviceable area:

- 55min @ flow of 5ft/s

Page 8: Senior Design Project Presentation

8

+

Intake to Facility:

Page 9: Senior Design Project Presentation

9

+III. Plant Study

Page 10: Senior Design Project Presentation

10

+

Plant Design:

Page 11: Senior Design Project Presentation

+

Flow Rate:Design Life: 25 years (EPA, 2014)

3 Day Peak Selected

Page 12: Senior Design Project Presentation

+

Screens:• Concord Screen Airburst

Assembly D-72 • 2 screens are needed• Equipped with air compressors

that periodically clean the screens, eliminating maintenance costs

Page 13: Senior Design Project Presentation

+ 13

Pumps

Pioneer Pump SC108S17

Specifications: Max flow 6500gpm Variable speed (7 gear) Can handle up to 3.5” solids Operates at 80% power

efficiency

- 4 pumps needed

While the peak flow rate in 2040 is projected to be 35 MGD, the rate for 2015 is projected to be as low as 16 MGD (Polyengineering, 2012).

Page 14: Senior Design Project Presentation

14+Pipes:Transfer Piping• Ductile Iron Pipe • Expected Life: 100 years • 2 pipe lines are needed• 36 in pipe diameter• Velocity: 3.9 ft/s • Length: 81,000 ft per pipe line

• 0.1 ft of headloss per 100 ft of pipe: 89 ft per pipeline

Yard Piping• Accounts for 10% of total cost• High-density polyethylene material will be used• Corrosion resistant • Commonly used for water transmission • Expected Life: 50 years • Color coding for water treatment plants set by Ten States

Standards

Page 15: Senior Design Project Presentation

+

Coagulant:

Aluminum Sulfate, Al2(SO4)3 easily accessible cost effective

Dosage: 20 mg/L 5,843 lb/day $0.07 / lb Year’s supply of Alum, 213,850 lb,

would cost $145,500 Inject by: Dry Alum Feeder

Page 16: Senior Design Project Presentation

+ 16

Rapid Mix:

Detention Time: 45 seconds Needed Volume: 2500 ft3

#tanks = 10 (5 per train)

Vtank = 250 ft3

Velocity Gradient: 900 fps/ft to minimize detention

time

Page 17: Senior Design Project Presentation

+Flocculation:Detention Time: 30 minutesVolume Needed: 49,000 ft3

• Depth: 16 ft• Width: 32 ft• Length: 96 ft

Three chambers in each tank• 1st: G= 80 s-1 • 2nd: G = 50 s-1 • 3rd: G = 20 s-1

Napier Reid Flocculator • Expected life: 10 years

Page 18: Senior Design Project Presentation

18

+

Sedimentation:

Depth: 15 ftWidth: 100 ftLength: 260 ft• Velocity: 0.018 ft/s• Detention Time: 4

hours

Sludge Removal: 52,000 gal of sludge/dayCosts:$4.80 per 1000 gallons & an additional $240 per 50,000 gallons Totaling: $490/day

Page 19: Senior Design Project Presentation

+ 19

Filtration: Granular Rapid FiltrationArea per filter bed: 450ft2

99% removal

Detention Time: 7.5 hrs

Backwash Cycle: 15 min

Filter-to-waste: 10 min

Total Cycle: 8 hours

Recommend using 4 filters

Page 20: Senior Design Project Presentation

20+ Disinfection

Ozonation• Best at removal of bacteria, viruses, etc. when

compared to chlorine and UV- No THMs- Only byproduct is bromate

- Only a problem in areas with high concentrations of bromine- Delivery system system: LOX- Recommended Initial Concentrations:

- Use 1.5 mg/L for effluent 0.5 mg/L- Daily LOX: 470 gal / day

- 1 Horizontal tank for Storage: 10,000 gal- Weekly use: 3300 gal LOX- Storage for 3 weeks

Page 21: Senior Design Project Presentation

+ 21

Disinfectant continued:

Contact Chamber Design:

Volume Required: 243000 gal ( 3250 cf)

For HDT of 10 min

Height: 20 ft

Floor: 13 ft x 13 ft

10 chambers

Total volume: 3380 cf

Page 22: Senior Design Project Presentation

+ 22

Disinfectant continued:

Ozone Generator:

Produces up to 1320 lb ozone / day

Dimensions:- Depth: 7.38 ft- Width: 6.23 ft- Height: 7.08 ft

Floor Space: 46 sf

Page 23: Senior Design Project Presentation

+ 23

Disinfectant continued:- Residual Disinfectant:

- Ozone does not leave a residual

Needed for microbial growth in pipes

Suggested: 0.01 mg/L residual disinfectant

Chlorine Gas0.5 mg/L initial concentration

Need 150 lb chlorine gas / day

<< EPA maximum residual goal of 4 mg/L- Three week supply can be stored in 21 tanks

Page 24: Senior Design Project Presentation

+FluoridationSodium fluorosilicate:• Easy to store• Safer than alternatives

• fluorosilicic acidEPA MCL: 4mg/LEPA secondary MCL: 2mg/L

For areas with high naturally-occurring fluoride

Make 2mg/L target value• 980 lb fluorosilicate / day

Page 25: Senior Design Project Presentation

+

Clear Well:Storage: 25% of Daily flow 9 MGDCST Industries offers construction of ANSI and AWWA approved clearwell storage tanks

Page 26: Senior Design Project Presentation

26

+

Plant Design:

Page 27: Senior Design Project Presentation

27

+IV. INNOVATION

Page 28: Senior Design Project Presentation

+SOLAR PANELS:

Monthly Power used by pumps: 382,500 kWhMonthly Power cost: $5640

Monthly Power supplied by 1 SolarWorld Panel unit: 190 kWh

Number of Units to combat pump power consumption: 3478 units

One-time cost of panels: $272/unit $815,900

Time to payoff: 12 years25 year savings: $815,900

Total acreage required: 0.85 acres << 12acres

Page 29: Senior Design Project Presentation

29

+V. COSTS

Page 30: Senior Design Project Presentation

30

+

Cost Analysis:

Page 31: Senior Design Project Presentation

+ 31

Overall Bill: $24,699.52Due: May 15th

projected: $29,206.73

Budget Used:85%

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15$0.00

$5,000.00

$10,000.00

$15,000.00

$20,000.00

$25,000.00

$30,000.00

$35,000.00

PH&J Consultants' Cost Progress

Projected CostsActual Costs

Week

Cost

($)

Page 32: Senior Design Project Presentation

+ANY QUESTIONS

32