senior thesis ryan e. sickman april 16, 2003
DESCRIPTION
Senior Thesis Ryan E. Sickman April 16, 2003. The New Jacksonville Arena Jacksonville, Florida. The Pennsylvania State University Architectural Engineering. Outline. Background Raker Investigation Structural Change (Breadth Study) Value Engineering of Building Skin 3D – 4D Survey - PowerPoint PPT PresentationTRANSCRIPT
Senior ThesisRyan E. Sickman
April 16, 2003
The New Jacksonville ArenaJacksonville, Florida
The Pennsylvania State UniversityArchitectural Engineering
Outline Background Raker Investigation Structural Change (Breadth Study) Value Engineering of Building Skin 3D – 4D Survey Conclusions and Overall Effects of Changes Gratuities Questions
Background Arena
Owned by The City of Jacksonville
Uses NCAA Basketball Games ECHL Hockey Games Concerts Wrestling Ice Capades / Skating Competitions
Features Home & Away Locker Rooms for
Both Hockey & Basketball Club Level 28 Executive Suites Florida Accessibility Code Accepted
(ADA)
Background
Owner The City of Jacksonville
Architect HOK Sport+Venue+Event
CM Turner Construction Orlando
Structural Engineer Bliss & Nyitray, Inc.
Civil Engineer Bessent Hammock & Ruckman, Inc.
Special Systems M-E Engineers, Inc.
Seating Capacities: Hockey: 13,669 Basketball: 15,009 End Stage Concert: 13,854 WWF (center stage): 15,975
General Info Ground Breaking: June 1, 2002 Occupancy: Nov. 1, 2003 (originally Oct. 1) Project Cost: $100,500,000.00 Arena Size: 452,058 sq. ft.
Background
Goals Quicker & cheaper method of constructing raker
beams Quicker & cheaper method of constructing structure
(Breadth Area) Switch from Concrete to Steel Change from Brick Façade to Brick Panels 3-D/4-D Survey Analysis Results From the Industry
Outline Background Raker Investigation Structural Change (Breadth Study) Value Engineering of Building Skin 3D – 4D Survey Conclusions and Overall Effects of Changes Gratuities Questions
Raker Investigation
68 Raker Locations in Lower Bowl
Raker Investigation
Existing Raker Construction MethodPre-Cast
Long Lead Time Two More Subs to Manage (production & installation)
Coordination with Concrete Sub for Installation 70 Days to Fabricate and Install
$500,000
Raker Investigation
Proposed Raker Construction MethodCast-in-Place
Short or No Lead Time (produce concrete) Concrete Sub to Handle Work
Concrete Sub Can Produce Rakers in Line with Rest of Structure
30 Days to Set, Pour, Finish, Strip Utilize EFCO Formwork
$260,926
Raker Investigation
EFCO Formwork
Self Supporting
Self Spanning
High Quality Form
Heavy Gauge Steel Web Doubles as Form Face
Easily Changeable Sections to Adjust Size of Form
Steel Ribs Distribute Forces from Concrete to Flanges
Unlimited Uses
Raker Investigation
Current Design 68 Rakers of 4 different Sizes Pre-cast Lead Time of 10 weeks Another 4 weeks to install all of
them $500,000 total cost
Proposed Design Exact same raker beams Cast-in-place No Lead Time 30 Days to pour raker
beams $260,926 total cost
Choose
C.I.P.
Outline Background Raker Investigation Structural Change (Breadth Study) Value Engineering of Building Skin 3D – 4D Survey Conclusions and Overall Effects of Changes Gratuities Questions
Structural Change
Existing Design Cast-in-place Concrete Structure until the roof truss supports
Poured decks constructed with shoring Beams are 48” Deep
Columns are 43” Wide Slabs are on average 8” Deep
Designed loads are: 100 psf live load, wind load 115 mph
Issues: Can the structure be constructed quicker? Will the structure cost more or less money?
Structural ChangeProposed Design Steel Structure
Smaller Slab Depth (4”) Metal Decking (3” LOK)
Designed for Moment Connections in the interior to deal with lateral loading
Shear Studs
Advantages Smaller Beams
Smaller Slab Depth Quicker Erection
No Shoring Required
Structural Change
Results of CalculationsNote: I kept the heights of the columns the same as the existing
structure so as not to change the facade of the structure Beams were smaller 35” Deep
More beams to account for the spans of metal decking Columns were smaller 30” Wide
Smaller Slab Thickness 7” (including decking) 1,776 pieces or lifts 2,160 shear studs
1,326 Tons of Steel
Structural Change
Comparison of Structural Choices
MaterialCeiling-to-
Floor Height
Extra Space Erection Time Time
Saved Total Cost Savings
Cast-in-place 56” 0200 Days
(8 Months)0 Days $8,500,000 0
Steel 42” 14”60 Days
(2.5 Months)140 Days $7,080,628 $1,419,372
*All figures include material, labor, and equipment
Choose
Steel
Outline Background Raker Investigation Structural Change (Breadth Study) Value Engineering of Building Skin 3D – 4D Survey Conclusions and Overall Effects of Changes Gratuities Questions
VE of Building Skin
Original Brick Façade Design
Upper WallsBrick Cavity Wall
Batt InsulationMetal Studs
Drywall
Lower WallsBrick Cavity Wall
Backed up by 8” CMU BlocksInsulation Panels
•Both include anArchitectural Precast Elementin addition to the brick work
VE of Building Skin
Proposed Nova-brik Design Mortarless Technology
Attached with furring strips on structure No transportation of mortar or installation time required with
applying mortar Less cost due to lack of mortar
Advantages:Less Cost (no mortar)Less Time (no mortar)
VE of Building Skin
All-inclusive Product Architectural Pre-cast Concrete (Designed Look)
Thermaguard Anchor Light Gauge Steel Studs
Gives a brick like look on the pre-cast element Can include the precast banding in the designed look
Product can be delivered including:Exterior Look (bricks & pre-cast band)
Metal Studs for interiorDrywall AttachedInsulation Panels
(Insulation is not included if batt insulation)
Advantages:•One lift installs all products
•Less Time due to size of panels•Reduced Shipping Costs
(Lightweight Panels so more can be shipped)•Reduced Heating and Cooling Costs•Thermaguard Anchor and air space
reduces heat transfer by 25%•At 28 lbs/ sq ft these panels
40-60% lighter than conventional pre-cast panels
Proposed Slenderwall Product
VE of Building Skin
Façade ComparisonFaçade System
R-Value Time Time Saved
Cost Yes/No
Brick & Precast
21.92 36 Days
O Days
$1,614,110 NO
Novabrik & Precast
21.92 25 Days
11 Days
$1,329,996 NO
Slenderwall 23.63 14 Days
4+ Weeks
$2,117,451 YES
1 Extra Month of Events at $150,000 / event, you would only need to hold 7 events before the cost was made up
Choose
Slenderwall
Outline Background Raker Investigation Structural Change (Breadth Study) Value Engineering of Building Skin 3D – 4D Survey Conclusions and Overall Effects of Changes Gratuities Questions
Survey Results
Initial Thoughts for Survey•The original purpose of this survey was to see how prevalent companies and persons out in the construction industry find 3-D and 4-D CAD systems to be.•If implemented early on, coordination with the different trades will be better as they will be able to see better where other trades work is, and the timing of each trade going into the project.
What I Wanted to Get Out of the Survey•A representation of where we are as an industry with regards to the usage of newer technologies•How willing companies would be to implementing these newer technologies
Survey Results
Responses 64% are using a type of CAD currently
Only 24% are utilizing the 3-D or 4-D aspects of the program 100% said they had someone in the office who could use CAD
Of those who are using this system already they estimate a savings of$15-50,000 / project
88% of the GC’s thought that a 4-D model would help in coordination issues with subs
Uses are distributed in the table below:
Visualization Design Coordination
Estimating Marketing DrawingProduction
FieldPlanning
Superintendent issues or other
4 11 6 8 14 3 8
Survey Results
Responses 16% said they would try this proposed system
12% said they would not And 72% said that they would if proof was shown in another company
that it worked The majority or 64% said they would give the system 2-4 projects to
prove itself While 76% said that the system would have to save over 1 month time
Survey Results
The system will have to prove itself in the big companies first Basically every company has a CAD proficient employee Most companies feel that this might help in some of their
coordination issues as it will allow them to better layout processes
This system which was not used on my project would have allowed for better coordination of the trades, and possibly
allowed the GC to make up the lost time at the beginning of the project.
But they did try and use a bit of technology in the early stages as they published drawings in .PDF format on the internet so
subs could take advantage of that, but nowhere near what could have been used.
Conclusions to Survey
Outline Background Raker Investigation Structural Change (Breadth Study) Value Engineering of Building Skin 3D – 4D Survey Conclusions and Overall Effects of Changes Gratuities Questions
Summary of Findings Raker Investigation
Choose Cast-in-place w/ EFCO Formwork $239,074 Savings and 40 Days Saved
Façade Change Value Engineering Choose Slenderwall System $503, 341 more expensive 20+ Days Saved
Structural Change Choose Steel Structure $1,419,372 Saved and 140 Days Saved
Survey It is going to take some of the bigger companies to take the
chance and prove to the rest of the industry that this system does indeed help and produce results
Summary of Findings
Total Time and Money Saved
$1,155,105 Saved200 Days SavedWhere Other Trades Can Get Started
*This number can not be indicative of the project finishing 200 days early, but it will give the GC the ability to complete the project some time earlier than expected
Outline Background Raker Investigation Structural Change (Breadth Study) Value Engineering of Building Skin 3D – 4D Survey Conclusions and Overall Effects of Changes Gratuities Questions
Gratuities
A Thank You To:The Penn State AE Staff
My Friends and Family
And the People Who Helped Me From the Companies Below As Well As Smith-Midland, and Vulcraft.
Outline Background Raker Investigation Structural Change (Breadth Study) Value Engineering of Building Skin 3D – 4D Survey Conclusions and Overall Effects of Changes Gratuities Questions?Any Questions?